Did BP take shortcuts?

A congressional investigation into the April 20 oil well blowout


shows BP made risky decisions to save time and money.

Under the gun


Oil well was 43 days behind schedule
BP spent about $500,000 a day to lease rig

Centralizer Cement bond log


Time 10 hours Time 9-12 hours
April 15 BP decides to use only six April 20 BP cancels acoustic
centralizers to keep casing in center test to make sure cement has
of the borehole during cementing; bonded to casing and wellbore
21 centralizers were recommended Cost More than $118,000*

Mud circulation
Time 12 hours
April 20 BP conducts only
partial circulation of drilling
Cost 15 centralizers mud, a way to check for gas
pockets before cementing well
Cost N/A
Well design
Time At least 3 days Lockdown sleeve
April 19 BP chooses riskier well casing Time N/A
(steel tube) design with only one gas April 20 BP did not
flow barrier if well cementing failed install device to prevent
Cost $7-10 million well seal from being blown
out from below
2010 MCT Cost N/A
Source: House Subcommittee
on Oversight and Investigations *BP paid $10,000 cancellation fee
Graphic: Judy Treible, Lee Hulteng