You are on page 1of 7

PROCESS FMEA CHECK SHEET

PFMEA NO.: CES/FM/NS/024-00


STATUS S.No CHECK POINTS OK Past Trouble Data(PTD),Drg,Failure Mode on process and Product, Data for Process & Product charactertics, Similar part comparision,(Detection & prevention mechanisim, Assembly Fitments etc. Was the Process FMEA is prepared using based on FMEA Procedure? NOT OK DOCUMENT REFERENCE Comment & Action Required

Doc No. : CES/ENG/F/25 Rev No 0

Responsibility

Target Date

Have all operations affecting customer requirements including fit, functions, durability,governmental regulations and safety been identified and listed sequentially? Were similar part/process FMEAs considered?

Have appropriate corrective actions been planned or taken for high risk priority numbers?

Have appropriate corrective actions been planned or taken high severity number?

Were risk priorities numbers revised when corrective action was completed?

Were high severity numbers revised when design change was completed? Do the effects consider the customer in terms of the subsequent operation, assembly and product? Were customer plant problems used as an aid in developing the Process FMEA?

10

11

Have the cause been described in terms of something that can be corrected or controlled? Where detection is the major factor, have provision been made to control the cause proir to the next operation? Past Trouble Data base considered, feedback ratio occurance matrix Was the Process FMEA prepared by a cross functional team? Has the team taken into account all customer specific requirements,including FMEA methodlogies as show in the current edition of FMEA? Have all operations including subcontracted, or outsourced processes and services been considered? Have historical campaign and warranty data been reviewed and used in the analysis?

12

13

14

15

16

17

Have you applied the appropriate controls to address all of the identified failure modes? Have provisions been made to control the cause of the failure mode prior to subsequent or the next operations?

18

PREPARED BY

APPROVED BY

POTENTIAL FAILURE MODE AND EFFECTS ANALYSIS (PROCESS FMEA)


Part Name BRKT-RR DOOR GUARD FR RH / LH Part No/ Issue 82182 / 3 - 3BB0A Customer/Model NISSAN/X02B Core Team S.Pandiyan -Engg ,K.Rajesh - Engg ,P.Kumar - QA, S.Arun Kumar - QA, V.Kumar - Press Shop, Ramesh-Weld Shop
RPN(SxOxD) Occur (O) Sever (S)

Process Responsibility: Mfg-Press Shop Approval / Date : Key Date: 7/6/2011

Document Number Date (Org.) Revision No. Date (Rev.)

CES/FM/NS/036 4/4/2010 1 17/02/2011


Action Results

Detect

Occur

Operation Number & Name

Sevr

Prevention

Detection

Action Taken

Correct Chemical / mechanical properties 1.5A. Part receiving at store. Dimensions as per drawing

Chemical & Mechanical properties variation

Next Opn Customer End User Next Opn

Part cannot be used (8) Nil Nil Part cannot be used Nil Nil Crack will develop(7) Low Performance the Vehicle(7) Nil Crack will develop(7) Low Performance the Vehicle(7) Nil Nil Poor appearance (4) 4 Causes Poor Appearance, Does Not Have Impact on Vehicle function, Sorting & Scraping(4) Nil Poor appearance (4) Nil Nil Poor appearance (4) Nil Cant locate properly(5) Nil Nil Nil 5 5 4 4 7 7 8 -8 --

Supplier process variation 2

Material TC verification

Incoming Sample inspection

4 64 -

Supplier process variation 2

Supplier Inspection report

Incoming inspection(Test certificate)

4 64 -

Dimensional Variation.

Customer End User Next Opn

High cushion pressure Clearance on the die & Punch 5

Operating Procedure

No Crack

Crack

Customer End User

First off / Patrol/Last Off Inspection - Set up Preventive maintenance of verification. the tool

Engg & QA Process to be stabilised 175 and to be validated & Jul-10 tools to be fine tuned

84

Thinning( Up to 0.3T )minimum Thickness should be 0.8 mm.

Next Opn Thinning Exceeds the Limit Customer ( Thickness less than 0.8 mm) End User Next Opn Customer

High cushion pressure Clearance on the die & Punch 4

Operating procedure Preventive maintenance of the Tool

First off / Patrol/Last Off Inspection - Set up verification.

Engg & QA Process to be stabilised 140 and to be validated & Jul-10 tools to be fine tuned

84

Low Cushion Presure Operating Procedure High Cushion Pressure 4 Improper holding of component( Beading & Blank holder to be checked) Tool set up not done properly( Setting block ) Die and punch clearance. 4 Preventive maintenance of the Tools Operating Procedure Preventive maintenance of the Tools

First off / Patrol/Last Off Inspection Set up Verification 5 80 -

With out Waviness Waviness PTD End User 10.Draw Next Opn No Double Folding Double Folding Customer End User Next Opn No Air Bubbles Air Bubbles Presence Customer
PTD

First off / Patrol/Last Off Inspection 5 80 -

In draw operation air vent hole blocked 3

Preventive maintenance of First off / Patrol/Last Off the Tools Inspection 5 60 -

End User Next Opn With Bottoming Mark(To Ensure Draw Depth) No Bottoming Mark Customer End User Next Opn No Short Trim Short Trim

Tool set up not done properly( Setting block ) Bottoming Mark Insert Worn out 3

Operating Procedure Preventive maintenance Of the Tools

First off / Patrol/Last Off Inspection Set up Verification 5 75 -

First off / Patrol/Last Off Inspection

Proper Location tobe 100 done & Pin Provided to avoid Mis Location

Engg & Die Maint

60

20.Trim
Prepared By Checked By Page 2 of 10

RPN

Operation / Process Function Requirements

Potential Failure Mode

Potential Effect(s) of Failure

Potential Cause(s) / Mechanism (s) of Failure

Det(D)

Class

Current Process Control

Recommended Action(s)

Respons. And Target Date

POTENTIAL FAILURE MODE AND EFFECTS ANALYSIS (PROCESS FMEA)


Part Name BRKT-RR DOOR GUARD FR RH / LH Part No/ Issue 82182 / 3 - 3BB0A Customer/Model NISSAN/X02B Core Team S.Pandiyan -Engg ,K.Rajesh - Engg ,P.Kumar - QA, S.Arun Kumar - QA, V.Kumar - Press Shop, Ramesh-Weld Shop
RPN(SxOxD) Occur (O) Sever (S)

Process Responsibility: Mfg-Press Shop Approval / Date : Key Date: 7/6/2011

Document Number Date (Org.) Revision No. Date (Rev.)

CES/FM/NS/036 4/4/2010 1 17/02/2011


Action Results

Detect

Occur

Operation Number & Name

Sevr

Prevention

Detection

Action Taken

No Short Trim

Short Trim

Customer End User

Low Performance the Vehicle (5) Nil Nil Dissatisfaction( No functional impact(4) Nil Nil Will reduce the vehicle perormance.(6) Nil Cant rework, 100% to be scraped if all found to be Exceeds Thinning(7) Crack will develop and low performance the Vehicle.(7) Nil Cant locate next operation & Welding Assembly welding at customer not possible. Nil Cant locate next operation & Welding Assembly welding at customer not possible. Nil Cant locate next operation & Welding Cant Locate in Assy. Nil Cant locate next operation & Welding Assembly welding at customer not possible.Nil Nil Poor appearance (4) Nil

Mis location Of the component

Operating Procedure

First off / Patrol/Last Off Inspection

Proper Location tobe 100 done & Pin Provided to avoid Mis Location

Jul-10

20.Trim Next Opn Burr with in the Limit(Max=0.2mm) Burr Exceeds the limit Customer End User Next Opn Flanging as per Drawing. 30.Flange & Restrike Thinning( Up to 0.3T )minimum Thickness should be 0.8 mm. Flanging not as per drawing. Customer End User Next Opn Thinning Exceeds Customer the Limit End User Next Opn Hole Missing Customer End User Next Opn All hole Open Hole Not Open
PTD

Punch & Die worn Out 4 Improper clearence between punch & die 3 Preventive maintenance of the Tools First off / Patrol/last off Inspection 5 60 -

Tool set up not done properly( Setting block ) 6 Mislocation of component Improper staking in packing High cushion pressure 7 Clearance on the die & Punch 4 3

Operating Procedure Operator training Packing standard. Operating Procedure

First off / Patrol Inspection 5 PDI Inspection. Engg & QA Process to be stabilised 140 and to be validated & Jul-10 tools to be fine tuned 7 4 3 84 90 -

Preventive maintenance of First off / Patrol/Last Off Inspection the tool

No hole( Datum & Customer Fitment )missing

Punch Broken 8 Punch hight variation. Tool set up not done properly( Setting block ) Punch Broken 8 Punch hight variation. Tool set up not done properly( Setting block ) Improper Location 8 3 3 3

Preventive maintenance of First off / Patrol/Last Off the Tools Inspection.

120

Pin to be provided to locate hole in Next Engineeringoperation and Assembly July -2010 operation

72

Customer End User

Preventive maintenance of First off / Patrol/Last Off the Tools Inspection.

120

Pin to be provided to locate hole in Next Engineeringoperation and Assembly July -2010 operation

72

Next Opn No hole( Datum & Customer Fitment ) Hole position shift. Customer position shift. PTD End User Next Opn 40. Pierce & Separation No hole missing Hole Missing Customer End User Next Opn No Double Piercing Double Piercing Customer End User

Preventive maintenance of the Tools.

First off / Patrol/Last Off Inspection.

Pin to be provided to locate hole in Next Engineering120 operation and Assembly July -2010 operation

72

Punch Broken 6 Punch hight variation. Tool set up not done properly( Setting block ) Part location/locator improper 4 3 3

Preventive maintenance of First off / Patrol/Last Off the Tools Inspection.

90

First off / Patrol/Last Off Inspection Preventive maintenance of the Tools. 5 60 -

Prepared By

Checked By Page 3 of 10

RPN

Operation / Process Function Requirements

Potential Failure Mode

Potential Effect(s) of Failure

Potential Cause(s) / Mechanism (s) of Failure

Det(D)

Class

Current Process Control

Recommended Action(s)

Respons. And Target Date

POTENTIAL FAILURE MODE AND EFFECTS ANALYSIS (PROCESS FMEA)


Part Name BRKT-RR DOOR GUARD FR RH / LH Part No/ Issue 82182 / 3 - 3BB0A
40. Pierce & Customer/Model NISSAN/X02B Separation

Process Responsibility: Mfg-Press Shop Approval / Date : Key Date: 7/6/2011

Document Number Date (Org.) Revision No. Date (Rev.)


RPN(SxOxD)

CES/FM/NS/036 4/4/2010 1 17/02/2011


Action Results

Core Team S.Pandiyan -Engg ,K.Rajesh - Engg ,P.Kumar - QA, S.Arun Kumar - QA, V.Kumar - Press Shop, Ramesh-Weld Shop
Occur (O) Sever (S)

Detect

Occur

Operation Number & Name

Sevr

Prevention

Detection

Action Taken

Next Opn No Scrap Impression Scrap Impression Customer End User Next Opn Burr with in the Burr Exceeds the Limit(Max=0.15mm) limit
PTD PTD

Nil Poor appearance (4) Nil Nil Dissatisfaction( No functional impact(4) Nil
Poke-Yoke

Improper Sie Insert Cleareance , Die Design 4 4 Preventive maintenance of the Tools.

First off / Patrol/Last Off Inspection 5 80 -

Punch & Die worn Out 4 Improper clearence between punch & die 3 Preventive maintenance of the Tools First off / Patrol/last off Inspection 5 60 -

Customer End User

A Critical Characterisitics

PTD

Past Trouble Data

Significant Characterisitics

Recommended Action : If RPN 100 & Severity is 1 to 7 If RPN 80 & Severity is 8 & 9 If RPN > 10 & Severity is 10

Prepared By

Checked By Page 4 of 10

RPN

Operation / Process Function Requirements

Potential Failure Mode

Potential Effect(s) of Failure

Potential Cause(s) / Mechanism (s) of Failure

Det(D)

Class

Current Process Control

Recommended Action(s)

Respons. And Target Date

POTENTIAL FAILURE MODE AND EFFECTS ANALYSIS (PROCESS FMEA)


Part Name BRKT-RR DOOR GUARD FR RH / LH Part No/ Issue 82184 / 5 - 3BB0A Customer/Model NISSAN/X02B Core Team S.Pandiyan -Engg ,K.Rajesh - Engg ,P.Kumar - QA, S.Arun Kumar - QA, V.Kumar - Press Shop, Ramesh-Weld Shop
RPN(SxOxD) Occur (O) Sever (S)

Process Responsibility: Mfg-Press Shop Approval / Date : Key Date: 7/6/2011

Document Number Date (Org.) Revision No. Date (Rev.)

CES/FM/NS/036 4/4/2010 1 17/02/2011


Action Results

Detect

Occur

Operation Number & Name

Sevr

Prevention

Detection

Action Taken

Correct Chemical / mechanical properties 1.5A. Part receiving at store. Dimensions as per drawing

Chemical & Mechanical properties variation

Next Opn Customer End User Next Opn

Part cannot be used (8) Nil Nil Part cannot be used Nil Nil Nil Low Performance the Vehicle (5) Nil Nil Dissatisfaction( No functional impact(4) Nil Nil Matching Part Fouling or Difficult to Assemble (4) Nil Nil Poor appearance (4) Nil Nil Poor appearance (4) Nil Cant rework, 100% to be scraped if all found to be Exceeds Thinning(7) Crack will develop and low performance the Vehicle.(7) Nil Nil Will reduce the vehicle perormance.(6) 6 4 4 4 4 5 8 -8 --

Supplier process variation 2

Material TC verification

Incoming Sample inspection

4 64 -

Supplier process variation 2

Supplier Inspection report

Incoming inspection(Test certificate)

4 64 -

Dimensional Variation.

Customer End User Next Opn

No Blank-out(Blank Blank out Profile Cut) 10.Blank

Customer End User Next Opn

Mis location Of the component

Operating Procedure

First off / Patrol/Last Off Inspection

75

Punch & Die worn Out Improper clearence between punch & die 3 Preventive maintenance of the Tools First off / Patrol/last off Inspection 5 60 -

Burr with in the Burr Exceeds the Limit(Max=0.15mm) limit

Customer End User Next Opn

No Uneven Forming ( Forming Height Variation )

Tool set up not done properly( Setting block ) Mis location Of the component 4

Operating Procedure Additional Location Pin Provided to Ensure Proper Position First off / Patrol/Last Off Inspection 5 80 -

Un Even Forming

Customer End User Next Opn

Improper Hole Locating Pin 3 Preventive maintenance of the Tools & Punch Clearance Checking

First off / Patrol/Last Off Inspection. 5 Check Point Added in PDI First off / Patrol/Last Off Inspection. 5 Check Point Added in PDI 80 60 -

No Hole Oblong

No Hole Oblong

Customer End User

20.Forming Next Opn No Damages Damages Customer End User


PTD PTD

Lack of operator awarness in loading & Unloading 4

Operator Tranning

Thinning( Up to 0.3T )minimum Thickness should be 0.8 mm.

Next Opn Thinning Exceeds Customer the Limit End User Next Opn

High cushion pressure 7 Clearance on the die & Punch 4

Operating Procedure Preventive maintenance of First off / Patrol/Last Off Inspection the tool 5

Engg & QA Process to be stabilised 140 and to be validated & Jul-10 tools to be fine tuned

84

Tool set up not done properly( Setting block ) Mislocation of component 3

Operating Procedure Operator training

First off / Patrol Inspection 5 90 -

Flanging as per Drawing. 30.Flange & Restrike

Flanging not as per drawing.

Customer

Prepared By

Checked By Page 5 of 10

RPN

Operation / Process Function Requirements

Potential Failure Mode

Potential Effect(s) of Failure

Potential Cause(s) / Mechanism (s) of Failure

Det(D)

Class

Current Process Control

Recommended Action(s)

Respons. And Target Date

POTENTIAL FAILURE MODE AND EFFECTS ANALYSIS (PROCESS FMEA)


Part Name BRKT-RR DOOR GUARD FR RH / LH Part No/ Issue 82184 / 5 - 3BB0A Customer/Model NISSAN/X02B Core Team S.Pandiyan -Engg ,K.Rajesh - Engg ,P.Kumar - QA, S.Arun Kumar - QA, V.Kumar - Press Shop, Ramesh-Weld Shop
RPN(SxOxD) Occur (O) Sever (S)

Process Responsibility: Mfg-Press Shop Approval / Date : Key Date: 7/6/2011

Document Number Date (Org.) Revision No. Date (Rev.)

CES/FM/NS/036 4/4/2010 1 17/02/2011


Action Results

Detect

Occur

Operation Number & Name

Sevr

Flanging as per Drawing. 30.Flange & Restrike Thinning( Up to 0.3T )minimum Thickness should be 0.8 mm.

Flanging not as per drawing. End User Next Opn Thinning Exceeds Customer the Limit End User Next Opn Hole Missing Customer End User Next Opn Nil Cant rework, 100% to be scraped if all found to be Exceeds Thinning(7) Crack will develop and low performance the Vehicle.(7) Nil Cant locate next operation & Welding Assembly welding at customer not possible. Nil Cant locate next operation & Welding Assembly welding at customer not possible. Nil Cant locate next operation & Welding Cant Locate in Assy. Nil Cant locate next operation & Welding Assembly welding at customer not possible.Nil Nil Poor appearance (4) Nil Nil Poor appearance (4) Nil Nil Dissatisfaction( No functional impact) Nil
Poke-Yoke

6 Improper staking in packing High cushion pressure 7 Clearance on the die & Punch

Prevention

Detection

90

Action Taken

Packing standard. Operating Procedure 4

PDI Inspection. Engg & QA Process to be stabilised 140 and to be validated & Jul-10 tools to be fine tuned 7 4 3 84

Preventive maintenance of First off / Patrol/Last Off Inspection the tool

No hole( Datum & Customer Fitment )missing

Punch Broken 8 Punch hight variation. Tool set up not done properly( Setting block ) Punch Broken 8 Punch hight variation. Tool set up not done properly( Setting block ) Improper Location 8 3 3 3

Preventive maintenance of First off / Patrol/Last Off the Tools Inspection.

120

Pin to be provided to locate hole in Next Engineeringoperation and Assembly July -2010 operation

72

All hole Open

Hole Not Open


PTD

Customer End User

Preventive maintenance of First off / Patrol/Last Off the Tools Inspection.

120

Pin to be provided to locate hole in Next Engineeringoperation and Assembly July -2010 operation

72

Next Opn No hole( Datum & Customer Fitment ) Hole position shift. Customer position shift. PTD End User Next Opn 40.Pierce & Separation No hole( missing Hole Missing Customer End User Next Opn No Double Piercing Double Piercing Customer End User Next Opn No Scrap Impression Scrap Impression Customer End User Next Opn Burr with in the Limit(Max=0.2mm) Burr Exceeds the limit Customer End User
A Critical Characterisitics

Preventive maintenance of the Tools.

First off / Patrol/Last Off Inspection.

Pin to be provided to locate hole in Next Engineering120 operation and Assembly July -2010 operation

72

Punch Broken 6 Punch hight variation. Tool set up not done properly( Setting block ) Part location/locator improper 4 3 3

Preventive maintenance of First off / Patrol/Last Off the Tools Inspection.

90

First off / Patrol/Last Off Inspection Preventive maintenance of the Tools. 5 60 -

Improper Sie Insert Cleareance , Die Design 4 4 Preventive maintenance of the Tools.

First off / Patrol/Last Off Inspection 5 80 -

Punch & Die worn Out 4 Improper clearence between punch & die 3 Preventive maintenance of the Tools First off / Patrol/last off Inspection 5 60 -

PTD

Past Trouble Data

Significant Characterisitics

Recommended Action : If RPN 100 & Severity is 1 to 7 If RPN 80 & Severity is 8 & 9 If RPN > 10 & Severity is 10

Prepared By

Checked By Page 6 of 10

RPN

Operation / Process Function Requirements

Potential Failure Mode

Potential Effect(s) of Failure

Potential Cause(s) / Mechanism (s) of Failure

Det(D)

Class

Current Process Control

Recommended Action(s)

Respons. And Target Date

POTENTIAL FAILURE MODE AND EFFECTS ANALYSIS (PROCESS FMEA)


Part Name BRKT-RR DOOR GUARD FR RH / LH Part No/ Issue 82184 / 5 - 3BB0A Customer/Model NISSAN/X02B Core Team S.Pandiyan -Engg ,K.Rajesh - Engg ,P.Kumar - QA, S.Arun Kumar - QA, V.Kumar - Press Shop, Ramesh-Weld Shop
RPN(SxOxD) Occur (O) Sever (S)

Process Responsibility: Mfg-Press Shop Approval / Date : Key Date: 7/6/2011

Document Number Date (Org.) Revision No. Date (Rev.)

CES/FM/NS/036 4/4/2010 1 17/02/2011


Action Results

Detect

Occur

Operation Number & Name

Sevr

Prevention

Detection

Action Taken

Prepared By

Checked By Page 7 of 10

RPN

Operation / Process Function Requirements

Potential Failure Mode

Potential Effect(s) of Failure

Potential Cause(s) / Mechanism (s) of Failure

Det(D)

Class

Current Process Control

Recommended Action(s)

Respons. And Target Date

You might also like