You are on page 1of 21

Levelling

Principle operation required in the determination of heights of points on the surface of the Earth

Elementary Land Surveying

ELS_Levelling05_06: 1

Equipment
1. Level with tripod (device to gives a truly horizontal line) 2. Levelling staff (a suitably graduated staff for reading vertical heights) 3. Chain/Tape (to enable the points leveled to be located relative to each other on a map) 4. Change plate (staff base plate) 5. Staff bubble
Elementary Land Surveying ELS_Levelling05_06: 2

Elements of Surveyors Level


1. Telescope  Diaphragm plane glass on which a series of line is etched (cross-hairs)  Parallax in focusing the real image formed by the objective lens is made to lie in the same plane as diaphragm Procedure of focusing: a) Adjusting eyepiece to bring diaphragm into sharp focus b) Adjust focusing screw until no parallax

Elementary Land Surveying

ELS_Levelling05_06: 3

Elements of Surveyors Level


2. Compensating Device in Automatic Level  The telescope need only be approximately levelled and then a compensating device corrects for the residual mislevelment

Elementary Land Surveying

ELS_Levelling05_06: 4

Levelling Staff
1. Sectional and assembled by slotting onto one another vertically 2. Made of aluminium alloy 3. E-shaped graduation (reading to 1mm for ordinary levelling)

Elementary Land Surveying

ELS_Levelling05_06: 5

Precision Levelling Staff


1. Used for more accurate work (accuracy to 0.1mm in use with precise level) 2. Spring-mounted at the top 3. Made of invar alloy (iron + nickel) which has a lower coefficient of expansion unaffected by temperature effects

Elementary Land Surveying

ELS_Levelling05_06: 6

Levelling Terminology
1. Level line is a surface which is at a constant height relative to Mean Sea Level (MSL) and is a curved line 2. Horizontal line is tangential to the level line at any particular point and is perpendicular to the direction of gravity. Over short distance, the 2 lines are taken to coincide

Elementary Land Surveying

ELS_Levelling05_06: 7

Levelling Terminology (cont)


3. Datum  A level line is chosen in which the elevation of all points is referred a) Mean Sea Level (MSL) is the mean of tidal height over a period of time (> 19 years) b) Principal Datum Hong Kong (PDHK) most of the works in HK refer to this. It is 1.230m below MSL (revised in June 1984) c) Chart Datum (CD) is a tidal datum for marine works and navigation

Elementary Land Surveying

ELS_Levelling05_06: 8

Relationship among different datums (Source: Lands Department, No Date)

Elementary Land Surveying

ELS_Levelling05_06: 9

Levelling Terminology (cont)


4) Bench Marks  Points of known elevation above PDHK a) Bench Mark (BM) established on vertical surfaces such as walls of buildings or substantial structures

Elementary Land Surveying

ELS_Levelling05_06: 10

Levelling Terminology (cont)


4. Bench Marks (cont) b) Temporary Bench Marks (TBM) constructed at locations on site or off site, where the level of the mark is calculated from PDHK 5. Reduced Level (RL) the height of a point relative to PDHK 6. Height of Collimation is the height of collimation above PDHK
Elementary Land Surveying

+5.00

TBM +10.00

ELS_Levelling05_06: 11

Levelling Terminology (cont)


7. Backsight (BS) 1st sight taken after the level has been set up. It is also a sight taken to a point whose height above HKPD is known 8. Foresight (FS) last sight taken before moving the level. It is also a sight taken to a point whose height is required to carry on the line of levels 9. Intermediate Sight (IS) other staff readings taken between BS and FS 10. Change Point (CP) the staff position at which a FS and then a BS readings are taken

BS CP
Elementary Land Surveying

FS

IS

ELS_Levelling05_06: 12

Levelling Terminology (cont)

FS BS FS IS BS IS

Elementary Land Surveying

ELS_Levelling05_06: 13

Field Procedure

1. The level is set up at P where BM may be observed and readings taken at points A, B, C and D
a) The 1st reading (BS) made with the staff on a point of known RL b) The staff is now held at points A, B and C (ISs) in turn, and record the readings c) A change point (CP) is chosen at D, owing to the nature of the ground and take the reading (FS)
Elementary Land Surveying ELS_Levelling05_06: 14

Field Procedure (cont)

2. The staff remains at point D. The level is moved to Q, set up and levelled
a) Taking the reading on the staff at the change point D (BS) b) Followed by IS with the staff on E, F and G until a further change becomes necessary

3. This procedure is repeated until all the required levels have been obtained 4. The final staff position is at a point of known RL
Elementary Land Surveying ELS_Levelling05_06: 15

Procedure in Levelling

1. Height of Collimation Method


1st find the height of the line of collimation above the datum Height of collimation (HC) = 128.480 + 3.222 = 131.702m PD a) level at B (rise from A to B) = height of collimation reading at B = 131.702 1.414 = 130.288m PD b) level at B (rise from A to B) = height of collimation reading at B = 131.702 3.484 = 128.218m PD
Elementary Land Surveying ELS_Levelling05_06: 16

Procedure in Levelling

2. Rise and Fall Method Rise 2nd reading < 1st reading Fall - 2nd reading > 1st reading b) from A to B a) from A to B 1st reading 2nd reading = 3.222 1.414 = 1.808 (rise) level at B (rise from A to B) = level at A + rise = 128.480 + 1.808 = 130.288mPD
Elementary Land Surveying

1st reading 2nd reading = 3.222 3.484 = -0.262 (fall) level at B (fall from A to B) = level at A - fall = 128.480 + 0.262 = 128.218mPD
ELS_Levelling05_06: 17

Booking and Calculation


1) Rise and Fall Method each reading is entered on a different line in the appropriate column, except at a change point, where a FS and BS occupy the same line. To check, BS - FS = Rise - Fall = Last RL First RL

BS 0.663

IS 1.946 1.008 1.153

FS

Rise

Fall 1.283

RL 98.760 97.477 98.415 98.270 97.838 98.355 99.407 99.979

Remarks BM A B C D (CP) E F G

0.938 0.145 1.585 0.432 0.517 1.052 0.646 0.572 3.079 1.860 1.219 1.860 2.231

2.787 2.270 1.218 3.450 2.231 1.219


Elementary Land Surveying

99.979 98.760 1.219


ELS_Levelling05_06: 18

Booking and Calculation (cont)


2) Height of Collimation Method the collimation height is obtained by adding the staff reading, which must be a BS, to the known RL of the point on which the staff stands. To check, BS - FS = Last RL First RL BS 0.663 1.946 1.008 1.153 2.787 2.270 1.218 0.646 3.450 2.231 1.219
Elementary Land Surveying

IS

FS

Collimation 99.423

RL 98.760 97.477 98.415 98.270

Remarks BM A B C D (CP) E F G

1.585

100.625

97.838 98.355 99.407 99.979 99.979 98.760 1.219

2.231

ELS_Levelling05_06: 19

Comparison
Rise and Fall Method
More accurate More calculation Intermediate RLs are known

Height of Collimation Method


Quicker Good for a lot of ISs

Elementary Land Surveying

ELS_Levelling05_06: 20

10

Accuracy in Levelling
For normal engineering works and site surveys
Allowable misclosure = 5 n mm where n = no. of instrument positions

OR
Allowable misclosure = 12 k mm where k = length of levelling circuit in km

If actual misclosure > allowable misclosure, levelling should be repeated If actual misclosure < allowable misclosure, misclosure should be equally distributed equally between the instrument positions
Elementary Land Surveying ELS_Levelling05_06: 21

Summary of Levelling Fieldwork


 For levelling fieldwork, the following practice should be adhered to in order to improve the accuracy of the levelling works. 1. Levelling should always start and finish at points of known RL so that misclosure can be detected 2. Where possible, all sight lengths should be below 60 m 3. The staff must be held vertically by suitable use of a bracket bubble 4. BS FS Lengths 5. Reading should be booked immediately after they are observed. Important readings, particularly readings at change points, should be checked 6. The rise and fall method of reduction should be used if possible, especially for control works
Elementary Land Surveying ELS_Levelling05_06: 22

11

Collimation Error
 if level is set up, levelled and the line of sight or collimation is not truly horizontal, it will sweep out a cone as it is rotated.  this cone will be either above or below the horizontal plane
Staff Horizontal Line Level

Line of Sight

Elementary Land Surveying

ELS_Levelling05_06: 23

Permanent Adjustment Two Peg Test


1. On fairly level ground, set 2 points A and B, a maximum of 60m apart. Let this distance be L metres 2. Set up the level exactly midway between the points at point C and level carefully 3. Place a levelling staff at each peg in turn and obtain readings S1 and S2

S1 S2 = (S1 + x ) (S2 + x) = S1 S2 = true difference on height between A and B X is the error due to collimation error (inclination of the collimation line by angle

Elementary Land Surveying

ELS_Levelling05_06: 24

12

Permanent Adjustment Two Peg Test


4. Move the level so that it is L/10 metres from point B at D. Take readings S3 and S4
Apparent difference in height between A and B = S3 S4 If there is any difference between the apparent and true value, e = (S1 S2) (S3 S4) m per L metres (e should be less than 0.5mm per 10 m for average precision)

Elementary Land Surveying

ELS_Levelling05_06: 25

Permanent Adjustment Two Peg Test


5. Any error e of the level should be adjusted using the adjusting screw with the collimation line altered to the correct staff reading For example, to adjust the level with instrument at D and staff at A, S4 = S4 e(L/10 + L) / L 6. The test should be repeated to ensure that the adjustment has been successful

Elementary Land Surveying

ELS_Levelling05_06: 26

13

Two Peg Test - Example


 The reading obtained from a two-peg test carried out on an automatic level with a single levelling staff set up alternately at 2 pegs A and B placed 60m apart are as follows: 1. With the level midway between A and B
Staff reading at A = 1.283m Staff reading at B = 0.860m

2. With the level positioned 5 m from peg B on the line produced from AB
Staff reading at A = 1.612m Staff reading at B = 1.219m

Find the collimation error (e) and corrected staff reading (S4)?
Elementary Land Surveying ELS_Levelling05_06: 27

Errors in Levelling
 Errors in Equipment 1. Collimation Error
Keep sight distance roughly equal Check by two peg test regularly Move eye with respect to eyepiece, see if any relative movement between target & cross-hairs, if so adjust eyepiece Zero error, check by tape, does not affect height difference if one staff is used 3-section staff should be properly extended Robust, properly tightened On soft ground, force it firmly into the ground
ELS_Levelling05_06: 28

2. Parallax Error 3. Defects of Staff


4. Tripod

Elementary Land Surveying

14

Errors in Levelling (cont)


 Field Errors 1. Staff not vertical
Staff is held vertical with aid of a bracket bubble A change plate should be used Ensure that the circular bubble is centered before and after a reading is taken Avoid windy condition Avoid line of collimation close to the ground in hot weather Start and finish at points of known height Run a loop
ELS_Levelling05_06: 29

2. Unstable ground 3. Instrument not level 4. Weather condition


5. Checking

Elementary Land Surveying

Errors in Levelling (cont)


 Reading and Booking Errors 1. Misreading of the staff graduation
Keep sight distance < 60 m, otherwise it becomes impossible to take accurate readings Carefully entered the reading into the fieldbook always read the staff, book the observation and then check that the recorded entry agrees with a second reading through the telescope.

2. Erroneous Booking

Elementary Land Surveying

ELS_Levelling05_06: 30

15

Error adjustments in levelling calculations

Elementary Land Surveying

ELS_Levelling05_06: 31

Error adjustments in levelling calculations


1. Rise and Fall Method
BS 1.944 1.691 2.009 0.367 1.223 1.347 2.114 0.775 0.816 4.425 4.433 -0.008
Elementary Land Surveying

IS

FS

Rise

Fall

Provisional RL 32.640

Correction 0.003 0.003 0.003 0.005 0.005 0.005 0.008

Corrected RL 32.640 32.896 32.578 31.745 30.891 30.767 31.339 32.640

Remarks BM CH0 CH20 CH40 CH60 CH80 CH100 BM

0.253 0.318 2.842 0.833 0.856 0.124 0.572 1.298 2.123 2.131 -0.008 2.131

32.893 32.575 31.742 30.886 30.762 31.334 32.632 32.632 32.640 -0.008

4.433

ELS_Levelling05_06: 32

16

Error adjustments in levelling calculations


2. Height of Collimation Method
BS 1.944 1.691 2.009 0.367 1.223 1.347 2.114 0.775 0.816 4.425 4.433 -0.008
Elementary Land Surveying

IS

FS

Collimation 34.584

Provisional RL 32.640 32.893 32.575

Correction 0.003 0.003 0.003 0.005 0.005 0.005 0.008

Corrected RL 32.640 32.896 32.578 31.745 30.891 30.767 31.339 32.640

Remarks BM CH0 CH20 CH40 CH60 CH80 CH100 BM

2.842

32.109

31.742 30.886 30.762

33.448

31.334 32.632 32.632 32.640 -0.008

4.433

ELS_Levelling05_06: 33

Error adjustments in levelling calculations


Note:
Misclosures = -0.008m No. of instrument station = 3 Correction is +0.0027m and is added to the RL found from each instrument station No adjustment is applied to the initial BM, since this level cannot be altered.

Elementary Land Surveying

ELS_Levelling05_06: 34

17

Additional Levelling Methods


1. Inverted Staff
Used to determine the RL of points, such as the soffit of a bridge, underpass or canopy The inverted staff reading is booked with a negative sign
BS 1.750 -3.100 1.490 -4.210 -2.460 1.640 -4.100 -2.560 4.200 1.640 8.900 13.000 -4.100 4.050 8.410 13.000 4.850 4.590 IS FS Rise Fall RL 72.300 77.150 72.560 76.610 68.200 68.200 72.300 -4.100 Remarks BM A) Frame (lift-shaft) B) Floor Level C) Canopy D) Kerb

Elementary Land Surveying

ELS_Levelling05_06: 35

Example
BS 1.432 -0.874 -1.107 1.383 0.558 0.148 0.410 BS 1.432 -0.874 -1.107 1.383 0.558 0.148 0.410
Elementary Land Surveying

IS

FS

Collimation 31.432

RL 30.000 32.667 32.900 30.410 30.410 30.000 0.410

Remarks TBM A Top of wall Arch soffit B

-1.235

31.793

0.148

IS

FS

Rise

Fall

RL 30.000

Remarks TBM A Top of wall Arch soffit B

-1.235

2.667 0.233 2.490 2.900 2.490 0.410 2.490

32.667 32.900 30.410 30.410 30.000 0.410

0.148

ELS_Levelling05_06: 36

18

Additional Levelling Methods


2. Reciprocal Levelling
By means of reciprocal levelling, the need for applying curvature and refraction corrections may be avoided 2 similar instruments in correct adjustment are required H = ((a1 b1) + (a2 b2)) / 2

Elementary Land Surveying

ELS_Levelling05_06: 37

Example
In levelling across a river, reciprocal levelling observations gave the following results for staffs held vertically at X and Y from level stations A and B on each bank respectively:
Staff Staff Staff Staff reading reading reading reading of of of of X X Y Y from from from from A B A B = = = = 1.753m 2.080m 2.550m 2.895m

If the RL of X is 90.370m PD, calculate the RL of station Y.


(note: Y is lower than X)
Elementary Land Surveying ELS_Levelling05_06: 38

19

Effects of Earths Curvature and Atmospheric Refraction A. Earths Curvature In , L2 + R2 = (R + c)2 L2 = (R + c)2 - R2 L2 = 2cR + c2 L2 2cR c L2 / 2R (km) = 0.0785 L2 (m) where radius of the Earth, R 6370 km and L in km

Elementary Land Surveying

ELS_Levelling05_06: 39

Effects of Earths Curvature and Atmospheric Refraction

Refraction
Line of sight is not really horizontal and bent downwards towards the Earth Value not constant, affected by pressure, temperature, latitude, humidity etc. Usually taken as 1/7 and opposite of the correction of curvature Combined correction = 0.0785 L2 * (6/7) = 0.0673 L2 (m) where L in km If L = 120m, c = -0.00097m 0.001m 1mm The effect is negligible for ordinary levelling
Elementary Land Surveying ELS_Levelling05_06: 40

20

Example
A staff is held at a distance of 200m from a level and a reading of 2.758m obtained. Calculate the reading corrected for curvature and refraction.

Elementary Land Surveying

ELS_Levelling05_06: 41

21

You might also like