Professional Documents
Culture Documents
Magalang, Pampanga
COLLEGE OF ENGINEERING AND COMPUTER STUDIES
Leveling
Prepared by: Khiel S. Yumul
Submitted to: Engr. Genesis A. Casiño
• Definition of leveling
Leveling is the most widely used method for obtaining the elevations of ground
points relative to a reference datum and is usually carried out as a separate
procedure from that used for fixing planimetric position. The basic concept of leveling
involves the measurement of vertical distance relative to a horizontal line of sight.
Hence it requires a graduated staff for the vertical measurements and an instrument
that will provide a horizontal line of sight. A host of definitions have been made by
different authors, and the following are listed:
2. Level Line
A level line is a curved line in a level surface all points of which are normal to the
direction of gravity and equidistant from the center of the earth.
3. Horizontal Surfaces
5. Vertical Line
For a particular point, its elevation is the vertical distance above or below mean
sea level or any other selected datum. Points on or near the surface of the earth
have either positive or negative elevations, depending if the point is above or below
mean sea level.
7. Datum
Datum is any convenient level surface coincident or parallel with mean sea level
to which elevations of a particular area are referred. Any surface may be used as a
datum when relative elevations over a limited area needs to be established. It is
done by assigning an assumed elevation to a reference point and determining the
elevation of other points in the vicinity with regard to this value.
8. Difference in Elevation
The difference in elevation between two points is the vertical distance between
the two level surfaces in which the points lie.
9. Mean Sea Level
HI = Elev BMa + BS
Elev TP1 = HI - FS
Sample Problem:
Prepare and complete the differential level notes for the information shown in the
accompanying illustration below. Include the customary arithmetic check.
Sample Problem:
Prepare and complete the differential level notes for the information shown in the
accompanying illustration below. Include the customary arithmetic check.
Solution:
c) Arithmetic Check:
2. Double Rodded Leveling
Complete the following differential level notes for a double-rodded line from BM1
to BM2 .
Solutions:
a)
b)
3. Three-Wire Leveling
The main difference between these two methods of leveling lies in the number of
foresights taken from each setup of the instrument. In differential leveling only one
foresight is necessary whereas in profile leveling any number of foresights can be
taken. In profile leveling, a series of bench marks intended for use at a later date are
also set up.
Sample Problem:
Another method of carrying out a leveling operation is by the rise and fall
method which is popularly adapted by the British. It is a very simple method and
may serve as an alternate method for profile or differential leveling or it may also be
used to check a completed set of level notes.
The rise and fall method is based on the principle that two consecutive readings
from the same instrument position gives the difference in elevation of the two points
sighted. In this method the actual height of instrument has no real significance other
than being the line to which vertical distances are conveniently measured from
various points on the ground. The method relies upon the difference in elevation
between successive points such that each point is considered in relation to the point
immediately preceding it and whose computed elevation (or reduced level, RL) is
either known or has just been calculated.
Sample Problem:
The figure below shows a schematic arrangement of lines in a level route. The
reduced level of the beginning benchmark (BM #2I5l) is 203. 113m and oil values
indicated represents either a backsight, intermediate foresight, or a foresight
reading taken on stations along the route. Prepare and complete on appropriate
format of level notes for the portrayed information using the rise and fall method
of leveling.
Solutions:
c) Arithmetic Check
6. Reciprocal Leveling:
Where,
TDE= True Difference in Elevation
Sample Problem:
In leveling across a deep and wide river, reciprocal level readings were taken
between two points, X and Y, as follows:
a. With instrument set up near X, the rod readings on X are 1.283 and l.285 meters;
on the distant point Y, the rod readings are 2.618, 2.619, 2.621, and 2.622 meters.
b. With instrument set up near Y, the rod readings on Y are 3.478 and 3.476 meters;
on the distant point X, the rod readings are 2.143, 2.140, 2.146, and 2.144 meters.
Determine the true difference in elevation between the two points and the
elevation of Y if the known elevation of X is 290.082 meters.
Solutions:
Let A be a point of elevation 130.48m above datum, and let B and C be points of
unknown elevation. By means of on instrument set 1.22 m above B, vertical
angles are observed, that to A being -14°45’ and that to C being +8°32'. If the
horizontal distance AB is 547 .20m and the horizontal distance BC is 923.95m,
determine the elevations of B and C, making due allowance for earth's curvature
and atmospheric refraction.
Solutions:
a) Determining Difference in Elevation b) Determining Difference in Elevation
between A and B between A and B
The two principal methods by which altimeter surveys may be conducted are:
the single-base method and the two-base method.
1. Single-Base Method.
In this method, two altimeters and two thermometers are employed. One
altimeter remains at a reference base whose elevation is known while the other
altimeter, which is referred to as the roving altimeter, is taken to other points ,or
field stations whose elevations are to be determined. It is necessary to record the
readings of the altimeters and thermometers at regular intervals of time.
2. Two-Base Method
The two-base method was designed to eliminate the need to apply correctness
for the effects of temperature and relative humidity. The method also improves the
accuracy in determining differences in elevation between field stations and
reference bases.
Barometric Leveling (Altimeter Surveys)
Two-Base Method
Since similar triangles are formed, the
difference in elevation between the low base
and the field station (line S'L') can be
determined by .proportion as follows:
Given the following data gathered from an altimeter survey: Elevation of the high
base, 518m; elevation of the low base, 122 m, altimeter reading at the high base,
5964; and altimeter reading at the low base, 2708. If the altimeter , reading at a
field station is 4150:, determine the elevation of the station.
Solutions:
a) Determining Difference in Elevation and Altimeter Readings
By similarity of Triangles:
9. Inverse Leveling
In the conventional method of differential leveling we normally see
to it that the line of sight of the instrument is always higher than any
point on which the leveling rod is held . However, this is not always
the case. It is sometimes necessary to determine the elevation of a
point located higher than the telescope of the instrument.
When an obstruction such as a concrete wall is encountered along
a level route, the usual procedure is to get around it. This may be a
way to go about it, however, it could be time consuming or may not
be possible at all. In such a situation, inverse leveling should solve the
problem. The illustrated example given on the next sample problem
should explain the simple principle of inverse leveling.
Sample Problem:
■ A tall concrete wall is an obstruction along a level route between points A and B.
To proceed with the leveling work, an inverse method of leveling is executed at
the vicinity of the obstruction where rod readings were taken with the rod heId
upside down as shown in figure below. From the observed data portrayed in the
figure, determine the elevation of point. B.
(Leveling over an obstruction)
Solutions:
a)
b) Arithmetic Check
10. Cross-Section Leveling
Cross-sections are short profiles taken perpendicular to the centerline of projects
such as a highway, railroad, irrigation canal, or sewer line. They may also be taken
for borrow-pits and excavations required for buildings, structures, and quarries.
Cross-sections provide the necessary data needed for estimating quantities of
earthwork and for other related purposes.
• Roadway Cross-Sections
This type of cross-section is required for most route projects such as roads and
railroads. The sections are taken at regular intervals usually at full and some plus
stations and where there are abrupt changes in the profile of a centerline.
• Borrow-Pit Cross-Sections
Cross-sections are also employed in the construction of structures and buildings,
and in the excavation of borrow pits. A borrow pit is an open area which is usually
adjacent to a construction project where suitable fill material is excavated.
• Adjustment of Level Circuits
A level circuit (or loop) is a line of levels which begins and ends at the same point
or is run 6etween points of precisely known elevations. In running a closed loop, it
will always be expected that the observed elevations (as computed from the level
notes) will not agree with the known elevations of previously established points
within the loop. The difference between the observed and known elevations of the
initial point, or bench mark, is referred to as' the error of closure.
When a line of levels closes back on the bench mark at the beginning of the
survey, the observed elevation of the initial bench mark will not be equal to its
known (or accepted) elevation. Apparently, there will always be an error of closure.
Several lines of levels are run over different routes from BM1 in order to establish
the elevation of BM2 . The lengths of these routes and the value of the elevations
determined are shown in the accompanying tabulation. Determine the most probable
elevation of BM2.