Professional Documents
Culture Documents
1
Definition of Leveling:
Leveling is an approach for determining elevation
difference between two points.
2
Importance of Leveling
Mainly leveling is important to:
3
3.1 Definitions and terms used in leveling
Datum: is a reference point usually mean sea level (MSL)
to which elevations of other points or benchmarks are
referred.
4
Elevation: is the relative magnitude for the height of the
point above or below the datum, which is believed to
having zero elevation.
5
Elevation difference: is the difference or change in
vertical distance between the two points in reference of
the datum or benchmark.
Back sight (BS): the 1st staff reading taken from a point
of known or assumed elevation
6
Vertical line
7
Fore sight (FS): The last staff reading taken from a
point of unknown elevation or a point its elevation to be
determined.
8
Turning point: is an intermediate point where both
fore sight and back sight readings are taken.
9
In order to calculate the elevation difference, BS and
FS readings should be taken from the staff reading
when the “middle cross hair” cuts the leveling rod.
10
During determining elevation difference of given points,
there should be benchmark with known or assumed
elevation.
HI = Ele.BM + BS
11
General Procedures of leveling
12
1. First, set the instrument between the two points, say
point A and B.
2. Set the instrument (stadia) in between the points (A and
B).
3. Held the leveling rod at point A, which is the B.M with
assumed elevation.
4. Take BS reading from point A and determine HI by
adding BS reading to Elevation of point A (BM).
13
5. Held the leveling rod at point B and turn the head of the
stadia to point B and take FS reading from point B (which is
the point its elevation to be determined).
6. Finally, calculate elevation of point B by subtracting FS
from HI.
14
Example
Point B
Elevation = 103.22 ft
Starting point
Point A (BM elevation 100.00 ft)
What is the difference in level between A & B ?
16
Cont..
17
Cont.…
18
The difference in level between F&G is 3.2222 – 3.484
= -0.262m
19
CON…
= 1281.808 m a.s.l
20
3.2 Types of leveling
Based on the type of instruments and nature of the
lands to be surveyed, there are different methods of
leveling. However, among those, the following
leveling types are to de described:
»Simple leveling
»Differential leveling
»Profile leveling
21
3.2.1 Simple leveling:
22
Example of simple leveling
Ele.B = HI - FS
HI = Ele. A + BS
FS (-)= 0.895 m
BS (+) = 1.037 m
Answer:
24
3.3.2 Differential leveling:
26
Materials required for differential leveling:-
Engineer’s level
Leveling rod
Plumb bob
Measuring tape
Field note book
Duty of survey members
Instrument man
Rod man
Note keeper
Members 27
28
1) First, locate two points BM1 and final point (M).
29
5) With bubble at the center (full instrument setup),
take BS reading from the rod held at BM1. and
record.
12. And shift the rod to other turning point (TP2) and
take FS reading from the level rod held in TP2.
32
14. Set up the level (instrument) at “position -C” and
take BS reading from the level rod held at point
(M).
33
Differential Leveling
Example
1.055m 1.451m
0.927m 1.295m
S1
S1’
BM1 (elev. S2 0.713m 1.835m
134.685m) A S2 ’
TP1
B S3
TP2 S3 ’
HI @ A C
Ele TP1
HI @ B
Ele TP2 M
HI @ C
34
Ele M
Since any differential leveling operation is not
complete with out closing it (turning to the start
point), a return check measurement must be
done to reduce error.
36
Differential Leveling Field
NoteBook
37
Points Dist (m) BS(+) HI FS(-) Elev.
BM1 1.055 134.685 (Given)
55 135.740
TP 1 0.927 1.451 134.289
38 135.216
TP 2 0.713 1.295 133.921
45 134.634
M 1.756 1.835 132.799
66 134.555
TP 3 1.533 0.917 133.638
77 135.171
TP 4 1.384 0.841 134.330
82 135.714
BM1 1.022 134.692
363 7.368 -7.361 134.685
Check
Error 0.007 0.007 38
Arithmetic check by closing a loop
ΣBS- ΣFS = Last Elevation BM-1 – First (given) Elevation BM-1
Last Elev. BM-1 – First Elev. BM-1 = 134.692m – 134.685m = 0.007m = 7mm
Therefore, the
operation is:
39
Q: What if arithmetically is not checked?
So, what…..??
40
Calculate allowable error of closure:
Allowable C D
• Where:
• ε – Allowable error of closure in (mm)
• D – total distance in (km)
• C – constant which is 24 for ordinary surveying
Allowable error of closure = ± 240.363km = 14.46 mm
Allowable error of closure > error of closure,
14.46mm > 7mm
accepted and apply correction.
41
Distribute the error of closure over each point
(applying correction)
Si
General formula is: vi *
S
S1 55
v1 * v1 * 0.007 0.001
S 363
42
S1 S2 55 38
v2 * v2 * 0.007 0.002
S 363
55 38 45 66 77 82
v6 * 0.007 0.007
363
43
Point Dist (m) BS(+) HI FS(-) Elev. Corec.Ele.
BM1 1.055 134.685 (given) 134.685
55 135.740
TP 1 0.927 1.451 134.289 134.288
38 135.216
TP 2 0.713 1.295 133.921 133.919
45 134.634
M 1.756 1.835 132.799 132.796
66 134.555
TP 3 1.533 0.917 133.638 133.634
77 135.171
TP 4 1.384 0.841 134.330 134.325
82 135.714
BM1 1.022 134.692 134.685
363 7.368 -7.361 134.685 134.685
Ditch (channel)
Road or
0+00,0+20….1+00….
46
Importance of profile leveling:
When planning the design and construction of buildings,
engineers must first consider the existing conditions of the
site.
Because, the given site may not be level and suitable for the
proposed work.
47
Therefore, :
Initially, slope of the natural ground should
be displayed.
48
So, profile leveling:
49
Materials required for profile leveling:-
Engineer’s level
Leveling rod
Plumb bob
Measuring tape
Peg and mallet
Field note book
Duty of survey members
Instrument man
Rod man
Note keeper
Members
50
Procedures of profile Leveling
51
1) Determine the proposed surveying line and fix a
BM1.
53
Legend:
In the next slide, we will use these colors to represent
the respective staff readings.
TP-1
BM-1
0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 4+80 5+00 5+50 6+00 6+35
Station Hor. Dist BS IS FS HI Elevation
BM-1 3.81 103.81 100.00
0+00 0 9.42 94.39
Therefore,
the work is:
57
• If arithmetically is not checked, something
goes wrong.
So, what…..??
58
Plotting a profile
Profile leveling shows the cross section of the
ground surface on a paper using convenient scale.
100
99
Elevation in Meter
98
97
96
95
94
0 100 200 300 400 500 600 700
Horizontal Distance in Meter 60
Question:
Ele.0 00 97.5m 62
Profile of the proposed irrigation canal
101
100
99
Elevation in Meter
98
97
96
95
94
0 100 200 300 400 500 600 700
Horizontal Distance in Meter 63
Cut and fill areas of the proposed irrigation canal
101
100 Cut
99
Elevation in Meter
98
97
Fill
96
95
94
0 100 200 300 400 500 600 700
Horizontal Distance in Meter 64
HI-2 @ P-1
HI-2 @ P-2
TP-1
BM-1
0+00 0+10 0+20 0+30 0+40 0+50 0+60 0+70 0+80 0+90 1+00
The End
66
This +0.004 value indicates the error is +ve error
or increase value from the assumed, so it should be
subtracted from each point elevation.
To distribute error of closure equally over all
points use the formula below the same, as using in
differential leveling.
Si
vi *
S
Not necessary 67
68