Crash The Project by 4 Days: Act. Imed. Pred. Time

You might also like

You are on page 1of 3

Act.

Imed. Pred. Time

None

B,C

E,F

Crash the project by 4 days

B(3)

F(4)
G(5)

D(5)

A(7)

C(4)

E(2)
1

Time Cost Analysis


Crashing the Project (Crash 4 days)
Activity

Normal
Time

Crash
Time

Normal
Cost

Crash
Cost

Cost/Day

$7,000

$8,000

$1,000

5,000

7,000

2,000

9,000

10,200

1,200

3,000

4,500

1,500

2,000

3,000

1,000

4,000

7,000

1,500

5,000

8,000

3,000
2

Action
Path

Length

ABDFG
ABDEG
ACDFG
ACDEG

24
22
25
23

Action

Crash A Crash C Crash F


(or D)
23
23
22
21
21
21
24
23
22
22
21
21

Marginal
Cost
Crash A $1,000
Crash C $1,200
Crash F $1,500
Crash F $1,500

Total Cost
$1,000
$2,200
$3,700
$5,200

Crash F
(or D)
21
21
21
21