Professional Documents
Culture Documents
Duration, week Cost, Tk. “000” Duration, week Cost, Tk. “000”
Activity Pred. Normal Crash 1st wk 2nd & Activity Pred. Normal Crash 1st wk 2nd &
on on
A 5 5 30 45 F C, D 4 4 75 100
B 7 4 50 65 G C, D 5 3 25 40
C A 4 3 50 60 H E 4 3 100 130
D B 8 4 60 80 I G, H 3 1 100 150
E B 5 4 70 100 J E 6 3 40 60
2. The following data and network are obtained from a project. Durations are in weeks and costs are in
thousand taka.
F
C
A G H
D J
B
E
Find:
a) Which activities would be crashed to meet a project deadline of 11 days at a minimum additional cost.
b) Calculate the additional cost.
d) The least possible time to complete the project.
e) Minimum cost to complete the project in the least possible time?