CADANGAN PEMBINAAN

KOMPLEKS PANGKALAN KASTAM


BAHAGIAN PENCEGAHAN DAN
PERUMAHAN DI TG. DAWAI,
MERBOK, KEDAH

25 OKTOBER 2011
AGENSI PELAKSANA :

JABATAN KERJA RAYA MALAYSIA


CAWANGAN PANGKALAN UDARA DAN
MARITIM

PELANGGAN :

KEMENTERIAN KEWANGAN MALAYSIA

PENGGUNA :

JABATAN KASTAM DIRAJA MALAYSIA

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

KANDUNGAN LAPORAN
MAKLUMAT KONTRAK
STATUS KEMAJUAN FIZIKAL & KEWANGAN - SEHINGGA 25
OKTOBER 2011
S-CURVE FIZIKAL
S-CURVE KEWANGAN
KEMAJUAN KERJA SEHINGGA 25 OKTOBER 2011
KEMAJUAN KERJA SEHINGGA AKHIR OKTOBER 2011
BUTIRAN BAYARAN KEMAJUAN KEPADA KONTRAKTOR
ISU / MASALAH & CADANGAN TINDAKAN PENYELESAIAN

KOS KERUGIAN & BAYARAN TAMBAHAN DISEBABKAN LANJUTAN


MASA (EOT)
GAMBAR KEMAJUAN

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

MAKLUMAT KONTRAK
NAMA KONTRAKTOR

WIDAD BUILDERS SDN. BHD.

KELAS KONTRAKTOR

KELAS A (BUMIPUTERA)

HARGA KONTRAK ASAL

RM 12,137,667.00

HARGA KONTRAK TERKINI

RM 11,853,377.70

TARIKH MILIK TAPAK

12 APRIL 2010

TARIKH SIAP KERJA

06 JUN 2011

TARIKH SIAP SEMASA

04 MAC 2012

TEMPOH LM NO. 2

13 MINGGU (90 hari)


[Klausa 43.1 (e) Kelewatan memberi
sebahagian milik Tapak Bina kepada
kontraktor]

TEMPOH KONTRAK

99 MINGGU

TEMPOH LIABILITI
KECACATAN

12 BULAN

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
3
KEDAH

STATUS KEMAJUAN SEHINGGA 25 OKTOBER 2011


(Berdasarkan Revised CPM-EOT No.2)

KEMAJUAN FIZIKAL (KONTRAKTOR)

Jadual

52 %

Sebenar

55%

Kemajuan

+3%

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

S-CURVE FIZIKAL
PEMBINAAN KOMPLEKS PENGKALAN KASTAM, TANJUNG DAWAI
Physical S - Curve
100%
90%
80%

Percentage (%)

70%
60%

50%
40%
30%
20%
10%
0%

April

Mei

Jun

Julai

Ogos

Sep

Okt

Nov

Dis

Jan

Feb

Mac

April

Mei

Jun

Julai

Ogos

Sept

Okt

Nov

Dis

Jan

Feb

March

Kemajuan Jadual

0%

2%

4%

6%

8%

11%

13%

14%

16%

19%

21%

24%

26%

30%

33%

37%

42%

47%

54%

63%

78%

93%

99%

100%

Kemajuan Sebenar

0%

1%

2%

3%

3%

4%

6%

8%

11%

12%

16%

17%

20%

23%

27%

36%

43%

53%

Time/Month

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,

S-CURVE KEWANGAN
PEMBINAAN KOMPLEKS PANGKALAN KASTAM , TANJUNG DAWAI
FINANCIAL S-CURVE
14,000,000.00
12,137,667.00
12,124,029.20
12,000,000.00
10,793,524.97
10,000,000.00

COST (RM)

8,409,877.32
8,000,000.00
6,645,541.76
5,954,523.99
6,000,000.00

4,000,000.00

2,000,000.00

Kemajuan
Jadual
Kemajuan
Sebenar

5,172,354.58
5,568,215.08
4,768,216.07
4,752,397.79
3,994,612.86
4,030,559.49
2,962,872.50
2,766,522.86
2,633,381.01
2,575,800.78
3,224,489.49
2,518,587.60
2,461,613.70
2,398,950.63
2,257,141.23
2,047,837.68
1,513,170.25
2,137,380.30
1,862,070.30
1,835,070.30
1,829,220.30
1,821,920.30
1,815,020.30
1,802,420.30
923,532.07
481,844.47
1,042,220.30
264,891.44
- 91,594.59
649,320.30
462,320.00
227,920.00
159,420.30
4
5 85,820.00
6
7
8
9
10
11
12
1
2
3
4
5
6
7
8
9
-

10

11

12

91,59 264,8 481,8 923,5 1,513 2,047 2,257 2,398 2,461 2,518 2,575 2,633 2,766 2,962 3,994 4,768 5,172 5,954 6,645 8,409 10,79 12,12 12,13
85,82 159,4 227,9 462,3 649,3 1,042 1,802 1,815 1,821 1,829 1,835 1,862 2,137 3,224 4,030 4,752 5,568
TIME (MONTHS)

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

KEMAJUAN KERJA SEHINGGA 27 OKTOBER 2011


% Jadual
(CPM)

% Sebenar

52%

55%

Kerja Cerucuk (Bangunan)


Bangunan Pentadbiran
TNB Sub station
Rumah Pam
Pondok Keselamatan

100%
100%
100%
100%
100%

100%
100%
100%
100%
100%

Kerja Bangunan
Bangunan Pentadbiran
TNB Sub station
Rumah Pam
Pondok Keselamatan

26%
21%
64%
30%
0%

25%
20%
62%
34%
1%

Jeti
Jambatan Penghubung
Kepala Jeti
Production of Precast Component

69%
46%
26%
100%

71%
65%
22%
100%

Aktiviti

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

KEMAJUAN KERJA SEHINGGA 27 OKTOBER 2011


% Jadual
(CPM)

% Sebenar

55%

52%

Revetment

22%

30%

Kerja Luar
Surface water drainage
Sewerage
External Water Reticulation
Roads and Car Park
Underground Fuel Tank
Turfing
Fencing and Gates

6%
14%
0%
0%
0%
17%
0%
8%

18%
32%
27%
0%
0%
13%
15%
25%

Provisional Sum
Prime Cost Sum

0%
1%

0%
8%

Aktiviti

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

KEMAJUAN KERJA SEHINGGA 31 OKTOBER 2011


% Jadual
(CPM)

% Sasaran

54%

56%

Kerja Cerucuk (Bangunan)


Bangunan Pentadbiran
TNB Sub station
Rumah Pam
Pondok Keselamatan

100%
100%
100%
100%
100%

100%
100%
100%
100%
100%

Kerja Bangunan
Bangunan Pentadbiran
TNB Sub station
Rumah Pam
Pondok Keselamatan

29%
22%
76%
34%
4%

35%
22%
80%
50%
9%

Jeti
Jambatan Penghubung
Kepala Jeti
Production of Precast Component

71%
51%
28%
100%

75%
70%
36%
100%

Aktiviti

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

KEMAJUAN KERJA SEHINGGA 31 OKTOBER 2011


% Jadual
(CPM)

% Sasaran

54%

56%

Revetment

25%

50%

Kerja Luar
Surface water drainage
Sewerage
External Water Reticulation
Roads and Car Park
Underground Fuel Tank
Turfing
Fencing and Gates

8%
14%
0%
0%
0%
30%
0%
12%

19%
30%
27%
0%
0%
55%
13%
23%

Provisional Sum
Prime Cost Sum

0%
2%

0%
9%

Aktiviti

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

BUTIRAN BAYARAN KEMAJUAN KEPADA KONTRAKTOR


No

Tarikh

Interim

Penilaian

Nilai Kerja Yang Dilaksanakan (RM)


Nilai Kerja
Dilaksanakan

Nilai Kerja
Dilaksanakan

Bayaran
Pendahuluan

Yang Perlu Dibayar Semasa Kumulatif


(RM)
(RM)
(RM)

(RM)

LAD

Disyorkan

(RM)

Amaun Yang Diperakui

Bayaran

(RM)

Wang Tahanan 10%


Semasa
Kumulatif
(RM)

(RM)

Kontraktor

(RM)

NSC

etc.

Bayaran

Bayaran

Date &

Bayaran

Yang
Diperakukan

Diperakukan
(Kumulatif)

Voucher No

Diterima

(RM)

(RM)

14.7.2010

77,238.27

27.5.2010

85,820.30 0.41%

85,820.30

85,820.30

8,582.03 8,582.03

77,238.27

85,820.30

85,820.30

21.6.2010

159,516.00 0.77%

82,277.73

73,695.70

7,360.00 15,942.03

66,240.00

73,600.00

159,420.30

17.7.2010 66,240.00

27.7.2010

227,957.90 1.10%

84,479.63

68,537.60

6,850.00 22,792.03

61,650.00

68,500.00

227,920.30

4.3.2010

61,650.00

9.8.2010

338,247.26

1.63%

133,118.99

110,326.96

11,030.00 33,822.03

99,270.00

110,300.00

338,220.30

1.9.2010

99,270.00

23.8.2010

473,404.01

2.29%

157,975.74

124,153.71

12,410.00 46,232.03

111,690.00

124,100.00

462,320.30

7.9.2010

111,690.00

27.9.2010

672,859.70

3.25%

245,741.43

199,509.40

18,700.00 64,932.03

168,300.00

187,000.00

649,320.30

15.10.2010

168,300.00

25.10.2010

1,053,329.14

5.09%

468,940.87

404,008.84

39,290.00 104,222.03

353,610.00

392,900.00

1,042,220.30

18.11.2010

353,610.00

14.11.2010

1,473,580.58

7.12%

535,582.31

431,360.28

43,130.00 147,352.03

388,170.00

431,300.00

1,473,520.30

1.12.2010

388,170.00

24.11.2010

1,802,512.58

8.71%

476,344.31

328,992.28

32,890.00 180,242.03

296,010.00

328,900.00

1,802,420.30

9.12.2010

296,010.00

10

22.12.2010

1,815,084.02

8.77%

192,905.75

12,663.72

1,260.00 181,502.03

11,340.00

12,600.00

1,815,020.30

26.1.2011

11,340.00

11

24.1.2011

1,821,985.46

8.80%

188,467.19

6,965.16

690.00 182,192.03

6,210.00

6,900.00

1,821,920.30

17.03.2011

6,210.00

12

22.2.2011

1,829,306.90

8.84%

189,578.63

7,386.60

730.00 182,922.03

6,570.00

7,300.00

1,829,220.30

17.3.2011

6,570.00

13

25.3.2011

1,881,590.09

9.09%

235,291.82

52,369.79

650.00 183,572.03

5,850.00

6,500.00

1,835,720.30

25.4.2011

5,850.00

14

21.4.2011

1,996,032.59

9.64%

343,884.32

160,312.29

3,000.00

186,572.03

27,000.00

30,000.00

1,865,720.30

04.05.2011

27,000.00

15

23.5.2011

2,171,669.35

10.49%

492,521.08

305,949.05

30,590.00

217,162.03

275,310.00

305,900.00

2,171,620.30

15.04.2011

275,310.00

16

20.06.2011

2,557,403.90 12.35%

602,945.63

385,783.60

38,570.00

255,732.03

347,130.00

385,700.00

2,557,320.30

11.07.2011

347,130.00

17

06.07.2011

3,229,962.88 15.60%

928,374.61

672,642.58

67,260.00

322,992.03

605,340.00

672,600.00

3,229,920.30

19.07.2011

605,340.00

18

27.07.2011

19.50%

1,129,142.82

806,150.79

80,610.00

403,602.03

725,490.00

806,100.00

4,036,020.30

08.08.2011

725,490.00

19

15.08.2011

4,752,397.79 22.96%

1,119,979.52

716,377.49

71,630.00

475,232.03

644,670.00

716,300.00

4,752,320.30

25.08.2011

644,670.00

20

26.09.2011

1,291,126.81

815,894.78

81,580.00

734,220.00

815,800.00

5,568,120.30

12.10.2011

734,220.00

4,036,071.09

5,568,215.08

26.90%

556,812.03

556,812.03

5,011,308.27

5,568,120.30

5,011,308.27

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

ISU & MASALAH


Kelewatan Pemilikan Sepenuhnya
Tapak Bina (Pemindahan Jeti
Nelayan)
Terdapat sembilan (9) buah jeti
nelayan sedia ada di tapak
cadangan jeti yang menghalang
kerja pembinaan
Pembayaran Pampasan kepada
pemilik jeti nelayan diselesaikan
pada bulan April 2011. Namun
terdapat sebuah jeti yang tetap
tidak memindahkan operasi.
Pemindahan
sepenuhnya
jeti
nelayan hanya berlaku dalam bulan
Jun 2011.
Kerja kerja jeti dan revetment
hanya dapat dimulakan pada bulan
Jun 2011. Jadual sebenar (LM 01)
kerja tersebut bermula pada 24 Feb.
2011

TINDAKAN/
PENYELESAIAN
Perakuan Kelambatan dan
Lanjutan Masa

Lanjutan masa 01 telah diberikan


selama 182 hari dan lanjutan
masa 02 selama 90 hari
berdasarkan klausa 43.1(e).

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

KOS KERUGIAN & BAYARAN TAMBAHAN DISEBABKAN


LANJUTAN MASA (EOT)
JKR Kedah (P.P) telah terima Notis Niat Menuntut
Kos Kerugian dan Bayaran (Claim for Loss and
Expenses) dari pihak kontraktor dan tuntutan
tersebut di dalam semakan Bahagian Kontrak dan
Ukur Bahan JKR Negeri Kedah.

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

GAMBAR KEMAJUAN

BANGUNAN
PENTADBIRAN

12 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
14
KEDAH

GAMBAR KEMAJUAN

TNB SUB STATION

07 SEPTEMBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
KEDAH

GAMBAR KEMAJUAN

RUMAH PAM

13 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
16
KEDAH

GAMBAR KEMAJUAN

JETI

10 SEPTEMBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
17
KEDAH

GAMBAR KEMAJUAN

LONGKANG

01 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI ,
MERBOK, KEDAH

18

GAMBAR KEMAJUAN

DETENTION
PONDS

12 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI ,
MERBOK, KEDAH

19

GAMBAR KEMAJUAN

SEWERAGE

12 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI ,
MERBOK, KEDAH

20

GAMBAR KEMAJUAN

FENCING
& GATES

12 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI ,
MERBOK, KEDAH

21

GAMBAR KEMAJUAN

FUEL
DISPENSER

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI ,
MERBOK, KEDAH

22

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
23
KEDAH