List tool and equipment for Precom/Com CALM BUOY Project

No. Description Tool & equipment for leaktest 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Air Compressor Helium cylinder in pallets Helium Detector hand helds Nitrogen cylinder in pallets Booster Pump HP Flexible Hose 1/2 NPT - 6000psi Flexible Hose 3/8" - 20 bar Injection Fittings and accessories Pressure Gauge Chart Recorder Pressure Switch Instrument Pressure Safety Valve HP regulator Manifold Testing manifold Tape Hand tools Tool & equipment for testing SDV 1 2 3 HPU + hose Hyraulic Oil Shell Teslus T32 24DC Power Unit Output 10000 PSI T32 24DC Tool & equipment for Pre/com Navigation Aid system 1 2 3 Mutimetter Fulke 726 Digital Clamp Metter Kyoritsu 2017 Kyoritsu 3005A-Megger Digital Insulation Tester 1 Unit 1 Unit 1 Unit 1 Unit 50 Lite 2 Unit 50m 500 PSI, 3000 PSI, 5000PSI, 10000PSI 150PSI, 1000 PSI, 5000 PSI, 10000PSI Adjustable (1-700bar) Adjustable (1-700bar) 0-200 Bar 50 litres, 150 Bar Output 10000 PSI 6000 psi 20 bar 50 litres, 200 Bar 1 set 12 cylinders 2 Unit 36 Cylinders 1 Unit 100m 50m 1 Unit 3 Unit 2 Unit 1 Unit 1 Unit 2 Unit 3 Unit 4 Unit 50 Unit 1 set Specification Quantity

List manpower for Precom/Com CALM BUOY Project


No. Description Manpower for leaktest 1 2 3 Piping & Mechanical Engineer Piping Technican Booster Pump Operator 7 Day (1 Day = 8h) 7 Day (1 Day = 8h) 7 Day (1 Day = 8h) Manpower for testing SDV 1 2 E&I Engineer E&I Technican 2 Day (1 Day = 8h) 3 Day (1 Day = 8h) Manpower for Pre/com Navigation Aid system 1 2 Commissioning Engineer E&I Technican 7 Day (1 Day = 8h) 8 Day (1 Day = 8h) 1 3 1 3 1 6 1 Time Quantity

You might also like