APPENDIX 1 PREVENTIVE MAINTENANCE CHECKLIST EMERGENCY STANDBY GENERATORS/SWITCHES/CONTROLS

Agency Representative: ________________________


(Print Name)

_________________________________
(Signature)

Location: ___________________________ Time: _____________


Hour Meter: _________________________ Unit Mfg. ______________________ Engine Mfg: ______________________ Model: ______________ Model: ______________

Date: _____________________

S/N:______________________ S/N:____________________ S/N:____________________

Gen. Mfg. ______________________ Model:_______________

SECTION A COOLING SYSTEM 1. 2. 3. 4. Engine coolant level Radiator core/heat exchanger Coolant lines/connections/hoses & connections Water jacket heater(s)

SAT.

UNSAT.

(check one)

Note: Contractor is responsible for replenishing of necessary fluids where there is an unsatisfactory rating. SECTION B D.C. ELECTRICAL SYSTEM 1. 2. 3. 4. 5. 6. Battery(s) electrolyte level/specific gravity Battery compartment/heater cooperation Battery connections/cables/casing Shutdown mechanisms Electrical starter/alternator generator Electrical system, accessories & components SAT. UNSAT.

(check one)

Note: Contractor is responsible for indicator lights, indicator lamps, gauges, switches, relays, contactors, solenoids, coils, voltage regulators, sensors, fuses, pressure sensing switches, transformers, power supplies, battery cables and connections. SECTION C A.C. ELECTRICAL SYSTEM 1. 2. 3. 4. 5. A.C. wiring Battery charger Control panel/switchgear A.C. generator voltage regulator Electrical system accessories & components SAT.
(check one)

UNSAT.

Note: Contractor is responsible for the same components listed under Section B-D.C. Electrical System.

T1399 7/12/07

APPENDIX 1 PREVENTIVE MAINTENANCE CHECKLIST EMERGENCY STANDBY GENERATORS/SWITCHES/CONTROLS


SECTION D AIR INDUCTION & EXHAUST SYSTEM 1. 2. 3. 4. Air cleaner units/oil bath and dry type Air induction piping and connections Turbocharger/blower Exhaust manifold/piping/connections SAT. UNSAT.
(check one)

Note: Contractor is responsible for replacing air cleaners, all types. SECTION E POWER UNIT 1. Generator structure 2. Clutch assembly (power take off) 3. Coupling(s) SECTION F LUBRICATION SYSTEM 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. Engine oil level Engine oil change Engine oil filter change Engine oil sample for analysis Crankcase pressure Crankcase breather Oil leaks (hoses, connectors) Engine governor oil level/linkage (UG8) Fan drive bearings Generator bearings Engine starter oiler (air type only) Gauges and safety mechanism Accessory drives SAT. UNSAT. SAT. UNSAT.

(check one)

(check one)

Note: Contractor is responsible for replacing any and all engine oil, lubricant, filters and/or belts. SECTION G FUEL SYSTEM 1. 2. 3. 4. 5. Fuel tank/day tank Fuel filters-primary/secondary Fuel system components/hoses/piping Gauges and Safety mechanism Condensation/water in fuel SAT. UNSAT.

(check one)

Note: Contractor is responsible for replacing all fuel filters (primary and secondary) REMARKS:

Technician: __________________________________________________
T1399 7/12/07