Guidelines for Erection of Trussed Structure

1
1.1

Unloading trussed structures


When a delivery of trussed structure arrives on site the contractor(s) involved should be prepared and have already allocated sufficient and suitable resources to ensure the trussed structures are unloaded safely and in a manner so as not to overstress or damage the trusses. This operation will have been subjected to a Contractors General Risk Assessment and then detailed in a safe working method statement that has been approved by the principal contractor or the person responsible for health and safety on site. Normally, trussed structures will be deliverd/shifted in tight bundles using bindings. This is often require mechanical handling equipment, such as a forklift or crane, to enable the safe manoeuvring of these large units. The safe working methos statement should accommodate any special handling instructions or hazards specified by the designer in his risk assessment for the truss design.

1.2

1.3

2
2.1

Site Storage of trussed structures


Trussed structures can be safely stored vertically or horzontally at ground level or any other properely designed temporary storage platform above ground level. Whichever mehod and location is chosen the temporary support should be set out to ensure that the units don't make direct contact with the ground or any vegitation and be so arranged so as to prevent any distortion. The delivery of trussed structures should, wherever possible, be organised to minimise site storage time; however, where longer periods of storage are anticipated then the trusses should be protected with covers.

2.2

Erection Procedure for Trussed Structure


1 2 3 Mark off position of trusses along both ends. Either mechanically or manually lift the first truss upto the roof holding it in a vertical plane , as far as possible, at all times. Erect the first truss in such a way that it coincides with the position of the end of the walls. Temporary brace the first truss to both wall plates(or as specified in approved drawing). After erection of 1st truss we have to check the top elevation of the truss by water level, column to column distance 4 5 6 7 Erect second truss ensuring that its production face matches the first truss as indicate by the labels or markings affix to the truss. After finishing of two trusses erection, we have to check the straightness, dimensions between two trusses and make the final weld with embedded plates which is placed in civil column. After doing the final weld we have to place the tie bracing such as top chord, bottom chord, purlin and make that to do bolting or welding or both. Like that we have erect and chack the water level, straightness of each and every truss with the reference to the last truss. Important : Trusses must never be cut or adjusted in any way without prior consultation with the roof truss designers. If site circumstances make modification unavoidable then changes shouls only ever be made with prior knowledge and consent of the trussed structures design.

You might also like