1. Production 2. Production Rate 3. Production Efficiency 4. Availability 5. Utility 6. Capacity 7. Rated Capacity 8. Swell Factor 9. Bucket Fill Factor 10. Cycle
1. Determine required production 2. Determine reach or haul path 3. Calculate cycle time 4. Calculate capacity 5. Iterate to improve productivity 6. Calculate fleet size 7. Iterate to reduce owning and operating costs
Type of Mineral: Copper Porphyry Copper Grade: 1% Gold Grade: 1 gram per tonne Ore Reserve: 1,000,000,000 tonnes
1,000,000,000 tonnes Design Mine Life: 50 years Ore Production Per Annum: 20,000,000 tonnes Stripping Ratio: 2:1 Waste Material Moved: 40,000,000 tonnes per annum Monthly Rates:
Ore: 1,666,667 tonnes Waste: 3,333,333 tonnes
Daily
Ore: 555,555 tonnes Waste: 1,111,111 tonnes
Hourly
Ore: 23,148 tonnes Waste: 46,296 tonnes
Power Shovels
30 cubic meters 20 cubic meters
Dump Trucks
350 tonnes 300 tonnes 250 tonnes
Determinants
Cycle Time Bucket Size
Sample
Assume cycle time: 60 seconds Calculations:
Hauling
Trip to dumpsite Return trip to minesite