Construction of Transformer Foundation & Pedestal


Cost Proposal for Installation and Fabrication of structure
July 9, 2013

scope of works

General Requirements
1.1 Mobilization/Demobilization
1.2 Power & Water Consumption
1.3 Haul of Debris & delivery of Material
1.4 Consumables(Uniform,id,etc)
1.5 Temfacil
Sub-total
Foundation and Pedestal
2.1 Staking and Layout
2.2 Gravel Bedding 3/4"
2.3 Rebar Works
2.4 Form Works
2.5 Concreting Works
2.6 Backfilling & Compaction
2.7 25mm dia A305 Anchor Bolt - 1700mm

qty

2.8 Restoration Works

1.00
1.00
1.00
1.00
1.00

1.00
1.00
1,553.00
9.00
8.01
23.30
12.00

unit
lot
lot
lot
lot
lot

lot
cu.m
kgs
sq.mtr
cu.m
cu.m

labor

unit cost

by Owner

320.00
10.00
450.00
500.00
80.00
720.00

1,000.00
320.00
10.00
450.00
500.00
80.00
720.00
4,500.00

1.00

sets
lot

1.00
1.00
1.00

lot
lot
lot

32,700.00
7,000.00
by Owner

Sub-total
3

Steel Structure
3.1 Fabrication and Installation of Steel
Structure of Scafoldings
3.2 Installation
3.3 Consumables, by Others
Sub-total
Total

Contingency, O&M
Profit
Total
Terms and Condition:
1.0 Terms of Payment: 50% Downpayment; Balance Upon Completion
2.0 Project Duration: 21 Calendar Days
3.0 Price Validity: 15 Days
4.0 Amount in Php
5.0 Vat Excluded

Prepared by & Submitted by:

Bonifacio C. Iringan Jr

total amount

2,500.00
1,500.00
3,000.00
3,000.00
7,000.00
1,000.00
320.00
15,530.00
4,050.00
4,006.25
1,864.00
8,640.00
4,500.00
39,910.25
32,700.00
7,000.00
39,700.00
86,610.25
8,661.03
8,661.03
103,932.30