Date:
scope of works
General Requirements
1.1 Mobilization/Demobilization
1.2 Power & Water Consumption
1.3 Haul of Debris & delivery of Material
1.4 Consumables(Uniform,id,etc)
1.5 Temfacil
Sub-total
Foundation and Pedestal
2.1 Staking and Layout
2.2 Gravel Bedding 3/4"
2.3 Rebar Works
2.4 Form Works
2.5 Concreting Works
2.6 Backfilling & Compaction
2.7 25mm dia A305 Anchor Bolt - 1700mm
qty
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1,553.00
9.00
8.01
23.30
12.00
unit
lot
lot
lot
lot
lot
lot
cu.m
kgs
sq.mtr
cu.m
cu.m
labor
unit cost
by Owner
320.00
10.00
450.00
500.00
80.00
720.00
1,000.00
320.00
10.00
450.00
500.00
80.00
720.00
4,500.00
1.00
sets
lot
1.00
1.00
1.00
lot
lot
lot
32,700.00
7,000.00
by Owner
Sub-total
3
Steel Structure
3.1 Fabrication and Installation of Steel
Structure of Scafoldings
3.2 Installation
3.3 Consumables, by Others
Sub-total
Total
Contingency, O&M
Profit
Total
Terms and Condition:
1.0 Terms of Payment: 50% Downpayment; Balance Upon Completion
2.0 Project Duration: 21 Calendar Days
3.0 Price Validity: 15 Days
4.0 Amount in Php
5.0 Vat Excluded
Bonifacio C. Iringan Jr
total amount
2,500.00
1,500.00
3,000.00
3,000.00
7,000.00
1,000.00
320.00
15,530.00
4,050.00
4,006.25
1,864.00
8,640.00
4,500.00
39,910.25
32,700.00
7,000.00
39,700.00
86,610.25
8,661.03
8,661.03
103,932.30