EQUIPMENT TRANSPORTATION STATUS

S. No. 1 2 3 4 5 6 7 8 9 10 11 12 Contractor Abdullah Abdullah Abdullah Abdullah Abdullah Site ID 1765 1856 868 2335 2163 Transported YES YES YES YES YES Date 7-May-13 7-May-13 7-May-13 9-May-13 9-May-13 Crane NO NO NO NO NO Amount

10000 6000 5000

NT TRANSPORTATION STATUS
Remarks As per Contactors Rate 5000 for each site (Green Field) & 6000 for each site (Roof Top 1 to 2nd Floor) if space is available in stairs but for first time he give us 5000 concession to check his work & proper feedback & equipment transported on time 6000 is claiming because Outdoor Cabinet will be installed at Roof Top(3rd floor). 5000 is claiming because this is green field site & per site cost is 5000