2 CAR GARAGE CONSTRUCTION SCHEDULE Class Assignment 1

ACTIVITY ID

DESCRIPTION

DURATION

5 10 15 20 25 30 35 40 50 60 70 80 90 100

Construction Permit Grading Trench Foundations Form, Rebar, Place Foundation Cure Foundations Place Garage Slab Install Frame Order Roof Trusses Fabricate & Deliver Trusses Install Trusses Install Roofing Install Siding Complete Landscaping Garage Ready

1 Day 2 Days 1 Day 3 Days 5 Days 2 Days 2 Days 1 Day 20 Days 2 Days 2 Days 2 Days 1 Day 1 Day

DEPENDS ON COMPLETION OF ACTIVITY 5 10 15 20 25 30 5 40 35 & 50 60 70 80 90

Draw a Barchart and determine the project duration in working days.

2. TABLE : Precedence Relations and Durations for a Nine Activity Project Example Activity Description Predecessors Duration A B C D E F G H I Site clearing Removal of trees General excavation Grading general area Excavation for trenches Placing formwork and reinforcement for concrete Installing sewer lines Installing other utilities Pouring concrete ----A A B, C B, C D, E D, E F, G 4 3 8 7 9 12 2 5 6

Buat CPM pada aktivitas proyek seperti table diatas, dan tentukan berapa total durasi proyek dan jalur kritis nya !!! Kerjakan sendiri-sendir dan dikumpulkan