You are on page 1of 1

aAgenda of the Meeting

1. Introductions and sign-in of attendees


2. Un priced PO review
3. ITP review
4. Shop/Plant walk-through
5. Engineering status
6. Drawings, codes and specifications
7. Review of sub-orders
8. Main supplier/Sub-supplier QC responsibilities
9. Shop/Plant safety and accessibility controls
10. Primary/Sub-supplier manufacturing, production, and testing milestones
11. Material traceability control
12. Welding procedures and operator qualification controls
13. NDE procedures and operator qualification controls
14. Control of nonconforming product/material
15. Welding repairs
16. Protective coatings, linings, and painting
17. Control of inspection, measuring, and test equipment
18. Tagging, marking, and packing requirements -
19. Exceptions taken and concessions granted
20. Action points