You are on page 1of 420

FTS-Rev

ITD CEMENTATION INDIA LIMITED


PROJECT TITLE :
Tender no. Div 2/044/13 Revision- R2 Date: 16-Sep-13
COMBINED SECTION % of
ITEM FINAL TENDER SUMMARY OFFSHORE ONSHORE TOTALS GRAND
Rs. Lakhs Rs. Lakhs Rs. Lakhs Rs. Lakhs TOTAL
A INDIRECT COSTS
01. STAFF - i) CONSTRUCTION * INDIAN 576.15 576.15 1.78%
ii) OTHERS * INDIAN 642.73 642.73 1.99%
02. STAFF - i) CONSTRUCTION * EXPAT 0.00 0.00%
ii) OTHERS * EXPAT 0.00 0.00 0.00%
03. INDIRECT LABOUR - i) CONSTRUCTION * (added in B 05.) 0.00 0.00 0.00%
ii) OTHERS * 208.86 208.86 0.65%
04. SITE ESTABLISHMENT 697.78 697.78 2.16%
05. INSURANCE 355.71 355.71 1.10%
06. BONDS 183.18 183.18 0.57%
07. INTEREST ON ADVANCE - Interest bearing 0.00 0.00 0.00%
08. BANK CHARGES - Interest on External borrowing 0.00 0.00 0.00%
09. TAXES 2496.00 2,496.00 7.72%
10. DESIGN & PROFESSIONAL SERVICES 0.00 0.00%
SUB TOTAL 5,160.42 5,160.42 15.96%
B DIRECT COSTS
01. LOCAL MATERIALS ( DM )
i) CEMENT 417.43 417.43 5.80%
ii) REBAR & HT STRAND 480.68 480.68 12.78%
iii) STRUCTURAL STEEL 36.64 36.64 1.37%
iv) BITUMEN 0.00 0.00 0.00%
v) OTHERS 1- AGREGATES 197.07 197.07 3.87%
vi) OTHERS 2 Sand 73.39 73.39 0.76%
vii) OTHERS 3 0.00 0.00%
viii) REMAINING OTHERS 1175.54 1,175.54 8.50%
02. IMPORTED MATERIALS 0.00 0.00 0.00%
03. ENABLING WORKS 58.13 58.13 0.18%
04. SHUTTERING & STAGING MATERIAL 335.18 335.18 1.97%
05. LABOUR & LABOUR CONTRACT (PRW) 589.72 589.72 4.95%
06. a. SUB-CONTRACT 3363.13 3,363.13 22.11%
b. Div-III -PILING 0.00 0.00 0.00%
07. PLANT HIRE 1009.29 1,009.29 3.12%
08. POL 421.77 421.77 1.37%
09. PLANT WEAR PARTS 65.37 65.37 0.20%
10. PLANT MOB & DE-MOB 50.15 50.15 0.16%
11. PLANT LABOUR/OPERATOR 64.08 64.08 0.20%
SUB TOTAL 8,337.56 26,926.95 83.30%
C OTHER COSTS
01. i) GTE on (CV-Sub Con Value) 323.25 323.25 1.00%
ii) MISC.ISSUE / CONSUMABLE IDM 0.00 0.00%
02. LABOUR CESS 1% 323.25 323.25 1.00%
03. PRICE INFLATION 2% 646.51 646.51 2.00%
04. RISK & BENEFIT COSTS 0.00 0.00%
05. DLP PROVISION 0.20% 64.65 64.65 0.20%
06. PROVISIONAL SUMS 0.00 0.00%
07. OTHERS (SPECIFY) 0.00 0.00%
SUB TOTAL 1,357.66 28,284.61 87.50%
D CONTINGENCIES
01. PROJECT CONTINGENCY 0.50% ON T.O. 161.63 161.63 0.50%
02. ADDITIONAL CONTINGENCY 2.00% ON T.O. 646.51 646.51 2.00%
SUB TOTAL 808.13 29,092.74 90.00%
E TENDER ADJUSTMENTS 0.00 0.00%
SUB TOTAL 0.00 29,092.74 90.00%
F OVERHEAD & MARGIN
01. OVERHEAD -ITD CEM 4.00% ON T.O. 0.00 0.00 4.00%
02. ITD FEE ON T.O. 0.00 0.00 0.00%
03. FINANCING CHARGES 3.00% ON T.O. 0.00 969.76 3.00%
04. MARGIN excl Sub Con 3.00% ON T.O. 0.00 755.35 2.34%
04.a. MARGIN on Sub Con 3.00% ON Sub Con 100.89 100.89 0.66%
05. MARGIN ON FREE ISSUE MATERIALS 0.00% Mat= 7,142.0 0.00 0.00 0.00%
SUB TOTAL 0.00 0.00 100.00%
G OTHER DIVISION'S WORK (SPECIFY) 0.00 0.00%
H GRAND TOTAL Rs. Lakhs 0.00 0.00 100.00%
I NEGOTIATION MARGIN 3.00% ON G.Total 969.76 969.76 3.00%
J QUOTE AMOUNT Rs. Lakhs 969.76 103.00%
K CURRENCY SPLIT
L CAPITAL PURCHASE 149.05
M RESIDUAL VALUE 85.85
CURRENCY SPLIT
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
Page 1 of 430
FTS-Rev
For Internal Assessment:
` Lacs %
1. Direct Cost 23,215.47 100%
[Incl.Sttaff-Construction, Indir.Lab-Construction, Client Estimate
Design Fee, Inflation, Risk, DLP & Proj.Conting.] % above #DIV/0!
2. Indirect cost
2(i) Type I
Insurrance & Bond 538.89
Interest & Bank Charges 0.00
Taxes 2,496.00
GTE & Cess 646.51
Addnl.Contingency 646.51
4,327.90 18.64%
2(ii) Type II 1,549.37 6.67%
3. Site Margin 3,232.53 13.92%
Total Price 32,325.27 1.39
Page 2 of 430
1
2
345678
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
A B C D G H I J K L M N
Markup==> 4.0636
SASAN
Rate Amount Rate Amount Rate Amount
PP1 EARTHWORK
PP2 Earthwork in excavation in the all types of soil including bailing / pumping out anywater accumulating inside the excavation if required strutting, shoring / sheet piling, dressing and transporting the excavated soil up to 1.0 KM lead and filling / stacking selectively as directed by the Engineer, all complete as per drawing & specification.
- 1.53
PP3 Up to 2.0 mdepth fromGround level Cu.M 24828.74 68 1,685,072 1.53 99 1,970,578 108
PP4 Between 2.0mto 4.0mdepth fromground level Cu.M 12664.31 78 986,142 1.53 114 2,277,326 164
PP5 Between 4.0mto 6.0mdepth fromground level Cu.M 2151 65 140,281 1.53 180 72,078 180
PP6 Between 6.0mto 8.0mdepth fromground level Cu.M 0.001 85 0 1.53 211 - 196
PP7 Between 8.0mto 10.0mdepth fromground level Cu.M 0.001 225 0 1.53 426 - 348
PP8 Earthwork in excavation belowground level in hard rock byanymechanical means without blasting & wedging, without damaging the existing structures, including setting out, clearing & grubbing, removal of debris, dewatering if required, strutting & shoring if required, dressing the sides, leveling to grade and stacking / disposal of surplus excavated material within a lead of 1.0 KM etc as directed by the Engineer, all complete as per drawing & specification.
- 1.53 -
PP9 Up to 2.0 mdepth fromGround level Cu.M 0.001 15793170883 15,793,171 1.53 33,786,600 390
PP10 Between 2.0mto 4.0mdepth fromground level Cu.M 0.001 15793170913 15,793,171 1.53 609 30,456,108 624
PP11 Between 4.0mto 6.0mdepth fromground level Cu.M 0.001 301339012 301,339 1.53 677 1,693,746 781
PP12 Between 6.0mto 8.0mdepth fromground level Cu.M 0.001 301339042 301,339 1.53 724 217,053 937
PP13 Between 8.0mto 10.0mdepth fromground level Cu.M 0.001 301339082 301,339 1.53 785 78,486 1447
PP14 Earthwork in excavation belowground level in hard rock by means of controlled blasting including provision of sensor to assess the impact of blast on the adjacent structures, without damaging the existing structures, including setting out, clearing & grubbing, removal of debris, dewatering if required, strutting & shoring if required, dressing the sides, leveling to grade and stacking / disposal of surplus excavated material within a lead of 1.0 KM etc as directed by the Engineer, all complete as per drawing & specification.
- 1.53 - NA
PP15 Up to 2.0 mdepth fromGround level Cu.M 0.001 361607308 361,607 1.53 1063 4,145,526 NA
PP16 Between 2.0mto 4.0mdepth fromground level Cu.M 0.001 361607338 361,607 1.53 1109 14,305,680 NA
PP17 Between 4.0mto 6.0mdepth fromground level Cu.M 0.001 241071826 241,072 1.53 1228 7,365,232 NA
PP18 Between 6.0mto 8.0mdepth fromground level Cu.M 0.001 241071856 241,072 1.53 1274 2,547,102 NA
PP19 Between 8.0mto 10.0mdepth fromground level Cu.M 0.001 241071906 241,072 1.53 1350 1,350,238 NA
PP20 Disposal of surplus excavated earth beyond a lead of 4.0 KM but anywhere within plant boundaryas directed bythe Engineer dumping and leveling the area from where the dumped earth is to be transported complete with all lifts as specified and directed byEngineer.
Cu.M 13705.682 415 5,682,896 1.53 - 81
PP21 Earthworkin Backfilling around foundations in plinths etc to proper grade and level with selected material within a lead of 1.0 KM from available excavated soil includingre- excavating loose thickness watering and ramming in layers with proper compaction as per specification and direction of Engineer.
Cu.M 30746.17 305 9,382,448 1.53 142 17,001,135 152
PP22 Supplyand Laying sand under floor, foundations & Plinths including cost of sand, transporting for all leads, loading, unloading & spreading in layers of 250 mmthickness at all depths, watering, compaction complete as per specification and direction of Engineer.
Cu.M 0.001 645 1 1.53 663,740 496
PP23 Providing and Laying rubble soiling with specified sizes of approved qualityhard rockrubble or hard broken hard metal of sizes ranging from100 mmto 230 mmbelowfinished ground floor level, belowfoundation hand packing, filling in interstices with sand including watering thoroughlycompacting the layer all complete as per drawings and direction of Engineer.
Cu.M 661.206 1620 1,071,153 1.53 2485 19,877,255 1365
PP24 Providing & laying of approved qualityhard crushed stone metal size 40 mmaverage thickness in transformer yard, stacker area and in other places where required as per drawing including loading,unloading & transportation spreading, compacting, all labour, materials complete.
Cu.M 0.001 1510 2 1.53 2316 2,315,946 1365
PP25 Providing & laying of approved qualityhard crushed stone metal size 10 mmaverage thickness in transformer yard, stacker area and in other places where required as per drawing including loading, unloading & transportation complete.
Cu.M 0.001 1668 2 1.53 2558 6,393,774 NA
PP26 PLAIN AND REINFORCED CEMENT CONCRETE - 1.53 -
PP27 The following items shall be read along with General Notes. - 1.53 -
PP28 Supplying and laying in position plain cement concrete of following nominal mix (by volume) using graded crushed stone (20 mmdown) as coarse aggregate including mixing, conveying, laying, compacting and curing etc. complete as per drawings specification and directions of Engineer.
- 1.53 -
PP29 M-10 Cu.M 1287.332 6013 7,741,249 1.53 5774 42,147,569 5245
PP30 Supplying, laying, finishing and curing of following screed concrete with 10 mmdowngraded crushed stone over RCC roof and trenches etc. including cleaning and backing of surface before laying as per drawings and specification.
- 1.53 -
PP31 M-15 Cu.M 3762 6304 23,717,105 1.53 6220 621,993 5554
PP32 Supplying and laying in position design mix cement concrete of following grades for reinforced concrete work in foundation and substructure in all kinds of workusing graded crushed stone (20 mmdown) as coarse aggregate including mixing, conveying, laying, compacting and curing etc. complete as per drawings, specifications and directions of the Engineer.
- 1.53 -
PP33 M - 20 Cu.M 0.001 65616 66 1.53 7389 3,694,597 5408
PP34 M - 25 Cu.M 472.49635 65759 31,070,713 1.53 7608 383,433,947 5275
PP35 Extra over above item(12-a-ii) above for supplying and using special admixtures / plasticizers for producing Self Compacting Concrete (SCC) with a Slump value of 660 mmto 750 mmand Passing abilityof 60 mmto 80 mm. Admixtures shall be of M/s. BASF / Sunandha Chemicals or equivalent make, for small column and thin walled section concreting including additional precaution to ensure leakproof shuttering with smooth surface.
Cu.M 0.001 1088 1 1.53 1669 834,354 NA
PP36 Supplying and laying in position design mix cement concrete of following grades for reinforced concrete work in superstructure in all kinds of workusing graded crushed stone (20 mmdown) as coarse aggregate including mixing, conveying, laying, compacting and curing etc. complete as per drawings, specifications and directions of the Engineer.
- 1.53 -
PP37 M - 25 Cu.M 0.001 6514000870 6,514,001 1.53 7927 143,477,982 5469
PP38 Extra over above item (12-b-i) above for supplying andusing special admixtures / plasticizers for producing Self Compacting Concrete (SCC) with a Slump value of 660 mmto 750 mmand Passing abilityof 60 mmto 80 mm. Admixtures shall be of M/s. BASF / Sunandha Chemicals or equivalent make, for small column and thin walled section concreting including additional precaution to ensure leak proof shuttering with smooth surface.
Cu.M 0.001 1088 1 1.53 1669 1,168,095 NA
PP39 Supplying and laying in position design mix cement concrete of following grades for reinforced concrete works in T.G. Foundation using graded crushed stone (20 mm down) as coarse aggregate including mixing, conveying, laying, compacting and curing of concrete bythe application of a membrane curing compound to all concrete surfaces. The compound shall conformto ASTM C 309, Type I with white pigmentation and shall be applied bya sprayer. etc. complete as per drawings, specifications and directions of the Engineer.
- 1.53 -
PP40 M - 30 Cu.M 9192.296 8063 74,117,032 1.53 10216 20,432,425 6401
PP41 M - 35 Cu.M 0.001 8464 8 1.53 10831 21,661,817 6499 M40 rate
PP42 Extra over above item(12-c-i & ii) above for supplying and using special admixtures / plasticizers for producing Self Compacting Concrete (SCC) with a Slump value of 660 mmto 750 mmand Passing abilityof 60 mmto 80 mm. Admixtures shall be of M/s. BASF / Sunandha Chemicals or equivalent make including additional precaution to ensure leakproof shuttering with smooth surface.
Cu.M 0.001 680 1 1.53 1043 4,171,770
PP43 Carrying our Ultrasonic Pulse Velocity(UPV) testing for top deck of TGcomplete as per specification, drawing and direction of Engineer including labour, machineryand submission of test results complete
LS for each TG
0.001 1300000 1,300 1.53 1993860 1,993,860 1920625
PP44 Supplying and laying in position design mixcement concrete of following grades for reinforced concrete work in Equipment foundations / Block foundations using graded crushed stone (20 mm down) as coarse aggregate including mixing, conveying, laying, compacting and curing of concrete by the application of a membrane curing compound to all concrete surfaces. The compound shall conformto ASTM C 309, Type I with white pigmentation and shall be applied bya sprayer. etc. complete as per drawings, specifications and directions of the Engineer.
- 1.53 -
PP45 M - 35 Cu.M 0.001 66529 67 1.53 8789 30,761,685 6499 M40 rate
PP46 Extra over above item (12-d-i) above for supplying and using special admixtures / plasticizers for producing Self Compacting Concrete (SCC) with a Slump value of 660 mmto 750 mmand Passing abilityof 60 mmto 80 mm. Admixtures shall be of M/s. BASF / Sunandha Chemicals or equivalent make including additional precaution to ensure leakproof shuttering with smooth surface.
Cu.M 0.001 544 1 1.53 834 2,920,239 NA
PP47 Supplying and laying pre cast reinforced cement concrete elements cast at Project site with following grade of concrete at various elevations in all kinds of workincluding supplyof materials, formwork, mixing, laying, compacting and curing, storing, handling, transporting, erection without damage, setting in position with cement sand mortar (1:2 byvolume) grouting/welding etc. complete as per drawings, specification and direction of Engineer.
- 1.53 -
PP48 M - 25 Cu.M 0.001 6514005785 6,514,006 1.53 15466 2,706,585 2102
PP49 Providing and mixing as cement concrete admixtures - super plasticizers (including super plasticizers cum retarder, super plasticizers cum water proofing and super plasticizers cum. pumping aid for concrete), at all levels, for all kinds of works, including all labour, material,equipment, handling, transportation, testing, etc., all complete, as per specifications, drawings and instructions of the Engineer / manufacturers.
MT 0.001 187000 187 1.53 286809 172,085,497 NA
PP50 Dismantling concrete work (both PCC and RCC of all grades), for all types of structures, at all levels, including all labour,equipment, scaffolding,staging,stacking of serviceable material upto a lead of 500 mand disposal of unserviceable material upto a lead of 2 kmbeyond the plant boundaryor as directed bythe Engineer, cutting of reinforcement, propping, shoring, enclosures, including all labour, material, equipment, handling, transportation, etc., all complete, as per specifications, drawings and instructions of the Engineer.
Cu.m 0.001 1500 2 1.53 2301 230,061 8807
PP51 Chipping of Cement Concrete work (both PCC and RCC), for all type of structures, at all levels, for making grooves, removing surface concrete etc., according to shapes, sizes and profiles as shown on the construction drawings, stacking of serviceable material upto a lead of 500 m, disposal of unserviceable material upto a lead of 2.00 km. beyond the plant boundaryor as directed bythe Engineer, cutting of reinforcement, including all labour, equipment, scaffolding, staging, handling, transportation, propping and shoring, enclosures, etc., all complete, as per specifications, drawings and instructions of the Engineer.
Cu.m 0.001 2200 2 337,423 NA
PP52 Making of Circular opening of diameter varying from25 mmto 150 mmand depth upto 450 mmin cement concrete work(both PCC and RCC) of all grades, for all type of structures, at all levels and for all positions, bycoring using diamond bits for pockets / thorough opening according to size as shown on the construction drawings, stacking of serviceable material upto a lead of 500 m, disposal of unserviceable material upto a lead of 2.00 km. beyond the plant boundary or as directed by the Engineer, finishing neatlythe surface area of cement concrete exposed after creation of circular opening including all labour, equipment, scaffolding, staging, handling, transportation, propping and shoring, enclosures, etc., all complete, as per specifications, drawings and instructions of the Engineer.
Sq.m 0.001 7200 7 11043 1,104,292 NA
PP53 Making of slit type opening of rectangular, square and or similar shape of varying size (in plan) and depth upto 450 mmin cement concrete work(both PCC and RCC) of all grades, for all type of structures, at all levels and for all positions, bysawing using wall sawmachine with on the construction drawings, locating the reinforcement before making the opening byuse of rebar detector and obtaining specific clearance fromthe Engineer, if the cutting of the reinforcement bar are involved in the making of the opening, cutting of reinforcement, stacking of serviceable material upto a lead of 500 m, disposal of unserviceable material upto a lead of 2.00 Kms. beyond the plant boundaryor as directed bythe Engineer, finishing neatlythe surface area of cement concrete exposed after creation of opening including all labour,equipment,scaffolding,staging,handling, transportation, propping and shoring, enclosures, etc., all complete, as per specifications, drawings and instructions of the Engineer.
Sq.m 0.001 6000 6 1.53 920,243 NA
PP54 Supplying, fabricating and installing following embedded items in cement concrete, as per drawings and specification including necessarytemplates : (Base rate of structural steel will be applied for this item)
- 1.53 - NA
PP55 Anchor bolt assembly complete with sleeves, nuts, washers, anchor plates, etc. MT 0.001 141105 141 21,089,725 NA
PP56 Insert plates, edge protection angles, pipe sleeves, hangers, conducts and other miscellaneous embedded fixtures of MS, GI, WI, CI, cast steel or other metal items.
MT 1 80811 80,811 14,802,770 NA
PP57 Taking, deliveryand installing following embedded Items in cement concrete, as per drawings and specifications including necessarytemplates :
- -
PP58 Anchor bolt assembly complete with sleeves, nuts, washers, anchor plates, etc. MT 0.001 21705 22 1.53 3,471,104 27300 Free issue material
PP59 Insert plates, edge protection angles, pipe sleeves, hangers, conducts and other miscellaneous embedded fixtures of MS, GI, WI, CI, cast steel or other metal items.
MT 0.001 36105 36 1.53 4,985,467 27300 Free issue material
PP60 Supply, fabrication and fixing of necessary templates against itemno 20-a above, if templates are not supplied byJPL.
MT 0.001 75411 75 1.53 1,652,099 27300 Free issue material
PP61 Forming expansion / isolation j oints in concrete as per drawings and specifications using Bitumen boards / expanded polystyrene boards complete with bitumen sealing compound including supplyof all materials
- 1.53 -
PP62 12 mmThick Sq.M. 8997.168 681 6,127,071 208,895 NA
PP63 25 mmThick Sq.M. 0.001 906 1 1390 277,913 855
PP64 50 mmThick Sq.M. 0.001 1231 1 1888 377,607 NA
PP65 Supplying and filling the expansion j oints of following dimension with bitumen / other j oint sealing compound confirming to IS : 1834 including through cleaning of the joints, as per manufacturer' s specification and as directed bythe Engineer.
- -
PP66 25 mm x25 mm RM 0.001 50 0 1.53 76 19,076 186
PP67 Same as above item(22-a) but with Silica Sealant RM 0.001 775 1 1.53 1189 297,162 71
PP68 Providing vertical expansion j oint with polyurethane foam road of required diameter and sealed with silicon sealant over road including fixing of rod with all materials complete at various elevations as per drawings and specifications similar to C/S Group & McCoyor approved equivalent.
- 1.53 - NA
PP69 25 wide with 25 x12 poly-sulphide including fixing of 25 mm dia rod. R.M. 0.001 1261 1 4.06 1934 290,026 NA
PP70 50 wide with 50 x12 poly-sulphide including fixing of 50 mm dia rod. R.M. 0.001 2607 3 4.06 3999 399,884 NA
PP71 Providing horizontal expansion j oint on roof with polyurethane foamrod and sealed with silicon sealant including fixing of rod complete with all materials joint filler, sealing compound, etc. as per drawing and specifications similar to C/S Group & McCoyor approved equivalent.
- 1.53 - NA
PP72 25 wide with 25 x12 poly-sulphide including fixing of 25 mmdia rod. R.M. 0.001 1042 1 1.53 1597 119,804 NA
PP73 50 wide with 50 x12 poly-sulphide including fixing of 50 mm dia rod. R.M. 0.001 2248 2 1.53 3447 172,354 NA
PP74 Providing & Fixing desired thickness of SIL FIL of Dawn Color, manufactured byThe Supreme Industries Limited or equivalent, thickness built up using minimum10 mmspecifically extruded high performance sheet, minimumdensity30 kg/ cum& compression strength of 0.21 kg/sqm, when tested as per ASTM D-3575, including using double sided adhesive SIL SEAM TAPE(manufactured byThe Supreme Industries Limited) or equivalent of 2 mmx25 mmx 25 mmat four places per sq.mtr to the casted surface to formthe expansion joint. SIL FIL will become one side of the shuttering while the expansion j oint is being created.
Sq.M. 0.001 636 1 1.53 976 195,168 NA
PP75 Supplying and installing ribbed water stops with central bulbs as per relevant Indian Standards, drawings and specification
- 1.53 -
PP76 230 mmx6 mm RM 4834.1 300 1,450,230 1.53 460 46,012 380 230x10mm- 936.98
PP77 230 mmx8 mm RM 0.001 370 0 1.53 567 56,748 NA
PP78 150 mmx6 mm RM 0.001 280 0 1.53 429 42,945 NA
PP79 150 mmx8 mm RM 0.001 300 0 1.53 460 46,012 NA
PP80 Providing and placing in position at ground floor level, building paper (kraft paper) of 250 micron as per IS : 1397 between the concrete surfaces including the cost of all labours, materials etc. complete as per drawings, specifications as directed bythe Engineer in charge.
Sq.M. 0.001 50 0 1.53 77 38,343 39
PP81 Providing, applying and painting 85/25 industrial grade hot bitumen at the rate of 1.2 kg/sqm or 0.4 kg/sqm over concrete surface after cleaning with brushes and finallywith cloth soaked kerosene oil.
- 1.53 -
PP82 1.2 kg/sqm Sq.M. 0.001 116 0 1.53 179 1,071,163 175 1.7kg/sqm
PP83 0.4 kg/sq.m Sq.M. 0.001 59 0 1.53 90 270,552 NA
PP84 Providing, mixing and laying in position and curing ordinary plumconcrete of mix 1:4:8 mixusing size less than 80 mm boulder as coarse aggregate as per drawing and specification and direction of Engineer at all locations for ground filling.
Cu.M 0.001 3898 4 1.53 5979 1,195,779 5573 1:5:10 using 150mm boulder,ceme nt free issue
PP85 Supplying & laying of transformer rail 52 kg/mincluding fixing with guard angle & U-bolts and whatever necessary complete as per approved drawing & direction of Engineer.
MT 0.001 77330 77 1.53 118604 5,930,201 28284 Rail free issue
PP86 Supplying necessarymaterials and grouting under column base using following flowable grout including preparation of concrete surfaces complete as per specification and instruction of Engineer (No formwork to be paid separately)
- 1.53 -
PP87 Ordinarygrout with 1:2 cement : sand mix Cu.M 0.001 6683 7 1.53 10251 51,254 2397 cement free issue
PP88 Non- shrink grout of approved make (Combextra GP1 or equivalent) Cu.M 0.001 86000 86 1.53 131902 21,104,246 45711
PP89 Concrete mix 1:1:2 (1 part Cement : 1 part Sand : 2 parts of 6 mm downgraded stone chips) with non-shrink hand grout using approved admixture.
Cu.M 0.001 6016 6 1.53 9228 230,688 NA
PP90 Taking, delivery of grouting material from store and grouting for equipment foundations including preparation of concrete surfaces for TGlevel and other equipment foundations complete as per specifications and directions of Engineer (No formwork to be paid separately)
Cu.M 0.001 28000 28 1.53 42945 1,717,787 9750
PP91 Same as item no. (32) above except when non-shrink grout of approved make (Combextra GP2 or equivalent) are supplied bycontractor.
Cu.M 0.001 30000 30 1.53 46012 1,840,487 56280
Civil works for 3 x 800 MWGadarawara Power plant, M.P.
Item
No.
Description Unit Qty Quote ITD CEM Quote
Factor
Page 3 of 429
9
10
A B C D G H I J K L M N
SASAN
Rate Amount Rate Amount Rate Amount
Item
No.
Description Unit Qty Quote ITD CEM Quote
Factor
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
PP92 Supplying and providing inj ection of cement mortar with approved waterproofinggroutingcompoundat construction j oints in concrete under pressure through nozzles along the joint including installation of 12 / 18 mm dia threaded nozzles in concrete, grouting, sealing the nozzles etc. all complete as per drawings, specification and direction of Engineer.
Each 0.001 900 1 1.53 1380 69,018 NA
PP93 Providing, applying and fixing in position in line and level MS black medium qualitypipe sleeves with lugs including bends as per drawings of following sizes as embedment in masonryand concrete.
0.001 - 1.53 -
PP94 80 NB RM 0.001 577 1 1.53 885 22,123 693
PP95 100 NB RM 0.001 800 1 1.53 1228 30,693 977
PP96 150 NB RM 0.001 1145 1 1.53 1755 43,886 1457
PP97 200 NB RM 0.001 1766 2 1.53 2708 67,712 2094
PP98 Supplying and laying in position Netlone 300 or equivalent Geo-textile of 3 mm thk. (min.) having tensile stress of 6T/m2 in M/D as shown in design drawing belowcoal stock drainage pipe complete as per drawing.
Sq.M. 0.001 2100 2 1.53 3221 64,417 NA
PP99 Providing and laying as per Manufacturer' s Instruction acrylic based polymer modified cementitious composite coating system"Tapecrete of CICO" or Equivalent waterproofing to underground structure complete as per drawing and direction of Engineer.
Sq.M. 0.001 800 1 1.53 1227 613,496 NA
PP100 FORMWORK - 1.53 -
PP101 Supplying, installing, dismantling and removing following classes / class of formworks for foundation & sub- structure in all kinds of workincluding necessaryrendering of concrete surface after exposure as per drawings, specification and direction of Engineer.
- 1.53 -
PP102 Ordinary Sq.M. 6346.248 935 5,935,138 1.53 718 43,804,471 467
PP103 Plywood Sq.M. 4230.832 1021 4,320,628 1.53 850 51,850,855 439
PP104 Curved / Ornamental Sq.M. 4160.4 1582 6,579,825 1.53 1709 170,939 601
PP105 Supplying, installing, dismantling and removing following classes / class of formwork for superstructures in all kinds of workincluding necessaryrendering of concrete surface after exposure as per drawings, specification and direction of Engineer.
- 1.53 -
PP106 Ordinary Sq.M. 9519.372 833 7,925,466 1.53 1115 7,133,502 536
PP107 Plywood Sq.M. 6346.248 1304 8,276,457 1.53 1838 47,785,458 536
PP108 Curved / Ornamental Sq.M. 6240.6 1869 11,664,468 1.53 2704 1,352,214 601
PP109 Extra over formworkitem38.b for TGdeckslab, columns and beams using leak proof type laminated plywood shuttering, including designing the formworkfor the lateral thrust due to SCC.
Sq.M. 0.001 12870000593 12,870,001 1.53 2722 27,216,420 NA
PP110 Modular shuttering consisting of prefabricated Steel / / Timber beams & formwork modules including necessary fixtures, clips, pins, screws, fittings etc as directed by Engineer-in-Charge.
Sq.M. 0.001 391372457 391,372 1.53 6582 6,581,839 NA
PP111 Fixing in position and removing forms for pockets and openings less than 0.1 sq.mincluding necessaryrendering of concrete surface after exposure.
Each 0.001 400 0 1.53 613 368,097 952
PP112 REINFORCEMENT STEEL - 1.53 -
PP113 Supplying, cutting, bending and binding with 1.6 mmgalvanized annealed soft iron wire and placing in position following types of Jindal Panther TMT / High Yield steel deformed bars, of all diameters in RCC members as per drawings, including preparation of bar bending schedule as per specification and direction of Engineer. (Base rate of reinforcement steel will be applied for this item)
- 1.53 -
PP114 Using straight bar MT 0.001 49892 50 1.53 77395 356,015,238 5937 steel free issue
PP115 Using cut and bent bar MT 1044.02 49264 51,432,225 1.53 76431 321,009,811 4937 steel free issue
PP116 Using welded reinforcement mesh MT 0.001 50618 51 1.53 78508 23,552,341 NA
PP117 Extra over itemno -40-i, for bending of bars at site as per BBS and as directed bythe engineer. MT 0.001 2200 2 1.53 3374 337,423 NA
PP118 STRUCTURAL STEEL WORKS - 1.53 -
PP119 Preparation of fabrication drawing, receiving fabricated material at site, transporting, stacking at store, erecting structural steel works as per specification, drawings, including necessaryloading, stacking, including addition of gussets, base-plate, cap-plates, stiffeners, shimplates, spacers, washers etc. as specified / required and erecting in position byall sorts of mechanical means including suitable type of crane and erection bolts, nuts [shot blasting of steel surfaces to near white metal surface (Sa 2) and applying Inorganic Zinc Silicate primer of minimum75 micron (DFT)] etc. complete.
MT 0.001 19905 20 1.53 25008 410,132,931
PP120 Supplying,fabricatinganderectionincluding transportation, storing etc for Miscellaneous steel work in handrails, sag rods, ladders, platforms and other structures not included above.
MT 75.55 81534 6,159,867 1.53 119530 62,753,358 20899 Str.steel free issue
PP121 Providing and application of synthetic enamel paint of Shalimar make or equivalent and colour in two coats of minimum 50 micron each including surface preparation using wire brush, necessary cleaning and applying two coats of primer with Zinc chromate primer of DFT 25 microns per coat over steel sections alreadyhaving primer coats at all elevations
MT 0.001 7000 7 1.53 10736 2,684,043 3205
PP122 Providing and applying high performance epoxy based Polyamide cured painting systemof approved colour and shade consisting of Zinc silicate primer, intermediate (under) coat, finish coat and final finish coat including shot blast cleaning of steel surfaces to near white metal surface (Sa 2), to steel surfaces of all types, shapes and sizes, at all levels, to achieve an even shade, including all labour,material,consumablesequipment,handling, transportation, protection and cleaning, scaffolding and staging, testing, etc., all complete, as per specifications, drawings and instructions of the Engineer.
- 1.53 - NA
PP123 Blast cleaning byshot blasting of steel surfaces to near white metal surface (Sa 2) and applying Inorganic Zinc Silicate primer of minimum75 micron (DFT), including touch up painting for the damaged surfaces of primer.
MT 0.001 10300 10 1.53 15798 8,293,693 NA
PP124 Applying intermediate (under) coat over inorganic Zinc Silicate primer, (excluding cost of primer), consisting of minimum75 micron DFT epoxybased Titaniumdioxide/ Miscellaneous iron oxide (pigmented) including touch up painting for the damaged surfaces of intermediate paint.
MT 0.001 2500 3 1.53 3834 64,896,324 NA
PP125 Applying finish coat over Intermediate (under) coat, (excluding cost of Intermediate coat), consisting of minimum75 micron DFT Epoxybased colour pigmented finish Polyamide cured paint and Final Finish coat with minimum25 micron DFT Polyurethane colour pigmented finish paint, including final touch up painting for the damaged surfaces of Finish and Final Finish Paint.
MT 16925 4050 68,546,250 1.53 6212 105,132,045 NA
PP126 Dismantling of erected structural steel member at any elevation, lowering of material and carriage of dismantled material up to field fabrication shop or return to owners store, includingtemporarydismantling,cutting,re-welding, supporting and restoring to correct position of all temporarily dismantled members, realignment of adjacent connected members to their correct position (Weight of such temporarily dismantled and adjacent members not to be paid), including all labour, material, equipment, handling, transportation, all complete as per specifications, drawings and Instructions of Engineer.
MT 100 18000 1,800,000 1.53 27607 2,760,730 29355
PP127 Additions to, alterations in and / or modification of "Erection Marks" (of structural steel) either in erected position or in shop, including all labour, material, equipment, handling, transportation, cutting of parts, gouging of welds, cutting, grinding, fabrication, welding, drilling holes, straightening, removal of bends, raising to required levels, primer painting, with Zinc silicate primer, touch up painting, transportation, return of unutilized steel pieces to the Owner' s store, temporarilydismantling, cutting, re-welding, supporting and restoring to correct position of all temporarilydismantled members, realignment of adjacent connected members to their correct position (Weight of such temporarilydismantled and adjacent members not to be paid),.etc, including all labour, material, equipment, handling, transportation, all complete as per specifications, drawings and Instructions of Engineer.
- 1.53 - NA
PP128 In erected Position MT 50 30000 1,500,000 1.53 46012 2,300,608 NA
PP129 In fabrication yard MT 50 25000 1,250,000 1.53 38343 1,917,174 NA
PP130 Re-erection of dismantled fabricated structural steel members requiring addition to, alterations in and / or modification, (dismantling and additions to, alterations in and / or modification to be paid separatelyunder relevant items), includingalllabour,material,equipment,handling, transportation, carriage of modified "Erection Marks" fromthe field fabrication shop to erection site, raising to required levels, aligning in position, tackwelding, final welding, touch up painting, including temporarilydismantling, cutting, re- welding, supporting and restoring to the correct position of all temporarily dismantled members, realignment of adjacent connected members to their correct position (Weight of such temporarily dismantled and adjacent members not to be paid), etc., all complete as per specifications, drawings and Instructions of Engineer.
MT 80 30000 2,400,000 1.53 46012 3,680,973 NA
PP131 Providing,supplying,fabrication,transportation, erection and alignment including installation in position bybolting / welding / screwing of factorymade electro- forged gratings fabricated using mild steel conforming to IS : 2062, at all levels, in floorings, platforms, drain covers trench covers, walk-ways, passages, staircase treads with edge binding strips and anti-skid nosing etc. with all fittings and fixtures, (clips, bolts, self drilling and taping screws, nuts and lockwashers) etc., self drilling and tapping screws, welding, edge preparation, painting byblast cleaning of steel surfaces to near white metal surface (Sa 2 ) and applying high performance painting systemconsisting of zinc silicate primer (minimum 75 micron DFT) followed byintermediate coat (minimum 75 micron DFT) consisting of epoxy based Titaniumdioxide / Micaceous iron oxide and finished with finish coat (minimum 75 micron DFT) consisting of epoxybased coloured pigmented finish including all labour, material, equipment, handling, transportation, preparation of fabrication drawings, etc., all complete, as per specifications, drawings and instructions of Engineer.
MT 130 143705 18,681,663 1.53 214885 27,935,047 104495
PP132 Extra over item47.a above for finishing the fabricated grating unit with hot dipped galvanization @610 g. / Sq. M. over blast / chemicallycleaned steel surfaces, instead of painting with high performance painting system
MT 130 27000 3,510,000 1.53 41411 5,383,423 NA
PP133 Providing and fixing in position at all levels, high strength structural steel bolts (Propertyclass 8.8 ,class 10.9 and product grade C as per IS:1367) conforming to IS : 3757 and high strength structural hardened and tempered nuts (Propertyclass 8 as per IS:1367) conforming to IS : 6623 with hardened and tempered washers as per IS:6649 etc., up to and inclusive of 39 mmdiameter and 300 mm long, installing the same as per IS:4000 for structural steel works including all labour, material, equipment, handling, transportation, testing, all complete, as per specifications, drawings and instruction of Engineer.
MT 250 359705 89,926,276 1.53 546173 136,543,140 NA
PP134 Providing and fixing in position at all level, permanent mild steel bolts (Propertyclass 4.6 as per IS:1367 and MT 50 153705 7,685,255 1.53 230222 11,511,118 NA
PP135 Product grade C as per IS:1363), nuts, washers, etc. up to and inclusive of 39 mm diameter and 300 mm long for structural steel works, including all labour, material, equipment, handling, transportation, testing, all complete, as per specifications, Drawings and Instruction of Engineer.
- 1.53 - NA
PP136 Supplying, Fabricating, transporting, erecting in position at all levels the chequered plates for platformwalkways, stair treads, trenches, etc. Complete as per specification and approved fabrication drawings.
- 1.53 -
PP137 6 o/p chequered plate MT 6 80000 480,000 1.53 122699 3,067,478 21080
PP138 ARCHITECTURAL WORKS - 1.53 -
PP139 Damp Proofing / Protective Layer - 1.53 -
PP140 Supplying and laying 40 mmthick damp proof course with cement concrete (1:1:3 nominal mixbyvolume) with a minimum of 2%admixture of waterproofing compound etc. with all materials complete.
Sq.M. 700 220 153,860 1.53 337 235,981 436 Concerete free issue
PP141 Making plinth protection (minimum 75mm thick and minimum750mmwide) of cement concrete M20 over 75mmbed of drybrick ballast consolidated and grouted with fine sand including finishing the top smooth including shuttering.
Sq.M. 954 698 666,250 1.53 1071 535,562 138 Concerete free issue
PP142 Providing and injecting chemical emulsion for PRE- CONSTRUCTIONAL anti-termite treatment as per IS: 6313 Part (II) - 1981 and creating a chemical barrier under and around the column pits, wall trenches, basement, excavation, top surface of plate filling, junction of wall and floor along the external perimeter of building floor together with plinth protection, expansion joints, surroundings of pipes and conduits etc. complete (plinth area of building at ground floor under action area onlyshall be measured).
- 1.53 -
PP143 Chlorpyriphos emulsifiable concentrate conforming to IS:8944 - 1978 with 1%concentration (The workshall be get executed by an approved specialist agency and the contractor shall furnish 10 years guarantee on non-judicial stamp paper)
Sq.m. 100 220 22,000 1.53 337 33,742 94
PP144 Masonry - 1.53 -
PP145 Supplying and laying in position full brick work (FlyAsh bricks) of class designation minimum75 in foundation and plinth in cement-sand mortar (1:6) including mixing mortar, laying bricks, raking joints, curing etc. with all materials complete as per drawings and specifications.
Cu.M 1000 5865 5,864,659 1.53 8995 8,994,855 777 brick& cement free issue
PP146 Supplying and laying in position full brick work (FlyAsh bricks)ofclassdesignationminimum75in superstructure at various elevations in cement-sand mortar (1:6)
Cu.M 661.165 6164 4,075,125 1.53 9453 18,906,558 894 brick& cement free issue
PP147 Supplying and laying in positionbrickwork of class designation minimum75 in half brick (FlyAsh bricks) thick walls at various elevations in cement-sand mortar (1:4) with HB netting at everyfourth layer including mixing mortar, laying bricks, raking joints curing scaffolding, equipment as required etc. with all materials complete as per drawings and specifications.
Sq.M. 1500 6586 9,878,654 1.53 10101 15,151,275 NA
PP148 Optional for item(54 & 55) above for Laying in position Pre Engineered Non Load bearing light gauge steel (LGS) Structure (byJindal Fab Infra Private Limited or equivalent) constructed using hot dip galvanized (275 gsm) cold rolled C profile sections having tensile strength of 350 Mpa with all necessaryfasteners, fixtures and fittings etc complete.
- 1.53 - NA
PP149 External wall: The external / outer wall shall be Cladded with PPGI Sheet / PPGL Sheets (0.5 thk ) including screwing, and all complete etc.
Sq.M. 4500 1500 6,750,000 1.53 2301 10,352,737 NA
PP150 Internal wall: Internal Surface of the wall shall be cladded with 6mmCP board and 12.5 mmthick GypsumBoard and without paint.
Sq.M. 4500 1400 6,300,000 1.53 2147 9,662,555 NA
PP151 Supplying and fixing 17.5 cm. X 17.5 cmglass bricks in pattern with epoxy mortar match to the bricks as per manufacturer' s manual, drawings and directions of the Engineer in charge.
Sq.M. 200 158 31,500 1.53 242 48,313 NA
PP152 Dismantling of brick work and removal of debris fromthe site as directed byEngineer for all heads and lifts etc. Cu.M 150 800 120,000 1.53 1227 184,049 2202
PP153 Plastering - 1.53 -
PP154 Providing 18 mm thick cement plaster on exterior surfaces in two layers vertical, horizontal or curved up to any elevation and heights under layer 12 mm thick Cement plaster 1:6 (1 cement: 6 coarse sand) finishing with a top layer 6 mmthick cement plaster 1:4 (1 cement: 4 fine sand) including the cost of all materials, equipment, labour, scaffolding, curing, as per specification and the direction of Engineer-in-charge.
Sq.M. 3220.5 295 950,150 1.53 453 10,860,047 86
PP155 12 mm thick (minimum) cement-sand (1:6) plaster to interior faces of walls, beams columns etc. at various elevations including mixing etc., with all materials complete
Sq.M. 54300 194 10,514,255 1.53 297 16,126,122 76
PP156 Extra over plaster for supplying and fixing galvanized chicken wire mesh (gauge-22) at junctions of brickwork and concrete workwith an minimumoverlapping of 150 mmon either side of the junction and as per drawing & instruction of engineer, complete in all respect.
Sq.M. 0.001 250 0 1.53 383 1,533,739 172
PP157 Providing 6 mmthick cement plaster on ceiling wherever directed bythe Engineer in 1:4 (1 cement: 4 sand) mortar including the cost of all materials, equipment, scaffolding, etc. complete.
Sq.M. 1815 156 283,792 1.53 240 1,846,571 86
PP158 Supplying & laying Vineratex or equivalent granular decorative textured coat finish over plaster surfaces at various elevations including mixing, laying, finishing etc. with materials & labour complete as per manufacturers specification and drawing.
Sq.M. 1000 500 500,000 1.53 767 766,869 437
PP159 25 mm x 12 mm Drip course at various elevations to parapet, chajja, windowheads, door heads etc. with all materials at all elevations complete as per drawings and specification.
R.M. 2000 200 400,000 1.53 307 613,496 138
PP160 Flooring, Skirting and Dado - 1.53 -
PP161 40 mm. thick cement concrete floor 1:1.5:3 with top of concrete floor painted with two coats of Epoxypaint as per manufacturer' s specification.
Sq.M. 200 724 144,720 1.53 1110 221,963
PP162 Providing and laying overall 40 mmthick cement concrete flooring with metallic concrete hardener topping (ironite), at various elevations, consisting of under layer 28 mm average thick cement concrete of grade M 20 and top layer 12 mmthick metallic cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 stone aggregate 6 mm nominal size) byvolume (Ironite shall be added in mix @ 1.5 kg / m2) including finishing of joints at maximumtwo (2) metres interval, or anysurface, and including 40 mmwide and 4 mmthick, glass strip placed between the panels including labour, materials and equipment and curing including scouring of surface providing necessaryshape etc. complete in all respects and in accordance with specifications and direction of the Engineer.
Sq.M. 355 404 143,349 1.53 619 22,914,978 256
PP163 Providing and laying overall 40 mmthick cement concrete (grade M25) flooring including cement slurry, finishing of joints at maximumtwo (2) metres interval, or anysurface, and including 40 mmwide and 4 mmthick, glass strip placed between the panels including labour, materials and equipment and curing including scouring of surface providing necessaryshape etc. complete in all respects and in accordance with specifications and direction of Engineer.
Sq.M. 1962.5 368 722,985 1.53 565 5,650 357
PP164 Providing 25 mmthick and 150 mmhigh cement mortar (1:3) skirting finished with a floating coat of neat cement at all elevations including labour, materials and equipment and curing complete in all respects and in accordance with specifications and direction of the Engineer
Sq.M. 2000 326 651,525 1.53 500 999,270 515
PP165 Providing and laying non-skid fullyvitrified 10 mmthick tiles similar to "MARBONITE","FERRASTONE",of "BOSS Profile Ltd." or similar approved laid on 20 mm thick cement mortar (1:4) including grouting the joints with white cement and matching pigments etc., in floors, skirting and dado complete as per manufacturer' s specification . (Base rate of cement will be applied for this item)
- 1.53 -
PP166 600 mmx600 mm(Base rate = Rs. 1500/-) Sq.M. 2500 1963 4,908,125 1.53 3011 7,527,782 1799
PP167 400 mmx400 mm(Base rate = Rs. 1270/-) Sq.M. 1500 1717 2,575,725 1.53 2634 3,950,489 1721
PP168 Supplying & laying 50 mm thick floor with matt finish unglazed ceramic tiles of approved colour and shade and of minimumthickness 7.2-7.5 mmover necessaryunder bed and 15 mmthick cement sand mortar 1:3 including cement slurry and joining with white cement slurry mixed with pigment to match the shade of tile complete with all materials as per specification and drawing. (Base rate = Rs. 1000/-) (Base rate of cement will be applied for this item)
Sq.M. 300 1433 429,825 1.53 2197 659,239 NA
PP169 Same as above item no 70 but with tiles of designer series of Kajaria, Nitco or of approved equivalent manufacturers (Base rate = Rs. 1200/-) (Base rate of cement will be applied for this item)
Sq.M. 100 1717 171,715 1.53 2634 263,366 NA
PP170 Supplying and placing 5 mmthick glazed ceramic tiles of approved make, size in skirting, dado etc on 12 mmthick 1:3 cement mortar in base and jointed with white cement slurry and matching pigments etc, including labour, materials and equipment, cleaning of surfacelaid as per manufacturer' s instruction and direction of Engineer in charge. (Base rate = Rs. 750/-) (Base rate of cement will be applied for this item)
Sq.M. 2600 1433 3,725,150 1.53 2197 5,713,407 NA
Page 4 of 429
9
10
A B C D G H I J K L M N
SASAN
Rate Amount Rate Amount Rate Amount
Item
No.
Description Unit Qty Quote ITD CEM Quote
Factor
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
PP171 Supplying & laying 40 mm thick acid/alkali resistant floor with 20 mmthick unglazed ceramic vitreous acid / alkali resistant tiles laid on potassiumsilicate based under bed mortar as per IS: 4832 (part I) over a primer coat and alkali resistant bituminoustic readymade paint conforming to IS: 158 with 6 mmwide joints in between tiles filled with resin type (epoxy/Furane) mortar conforming to IS- 4832(Part-II) including preparation of surface, acid curing sealing the edges bybituminastic filler etc complete as per specification, drawing and direction of Engineer. (Base rate = Rs. 4450/-)
- 1.53 -
PP172 The tile samples shall be approved by Engineer before execution. Sq.M. 900 1156 1,040,625 1.53 1773 1,596,047 2811
PP173 All as per item(73-a) above but with Acid/Alkali resistant paint over 20 mmthick unglazed ceramic normal tile all as per specification complete.
Sq.M. 400 6331 2,532,500 1.53 9710 3,884,194 NA
PP174 Supplying and laying polished kota stone slab of approved size and 20 mmthick (the tile sample shall be got approved fromthe Engineer) in flooring and skirting laid on 20 mm thick cement mortar 1:4 bedding, cement floated mixed with pigment, all joints well filled on completion, including polishing at site all as per specifications and directions of Engineer. (Base rate = Rs. 350/-) (Base rate of cement will be applied for this item)
Sq.M. 500 964 482,125 1.53 1479 739,454 940
PP175 Providing, supplying and laying 2 mmthick homogeneous flexible heavy duty antistatic PVC tiles of approved manufacture, size and colour on floor, dodo etc using rubber based adhesive of approved manufacture including rolling with light wooden roller weighing about 5 kg, material, labour, equipment etc. complete as per drawing and direction. (Base rate = Rs. 750/-)
Sq.M. 200 1488 297,500 1.53 2281 456,287 1873
PP176 Providing and laying 18 mmthick Polished granite stone (slab) over 20 mmthick base in cement mortar 1:4 (1 cement : 4 coarse sand) including labour materials and equipment and also including scouring of surface providing necessaryshape etc. complete in all respect with standard accordance with specification & direction of engineer. The joints shall be grouted with white cement by mixing & matching colour pigment. (Base rate = Rs. 2750/-) (Base rate of cement will be applied for this item)
Sq.M. 3000 3484 10,452,750 1.53 5344 16,031,789 7217
PP177 Supplying, fitting and fixing Polished granite slabs 12 mm thick in columns, walls, facias, skirting, dado etc. with cement mortar (1:3) including making suitable arrangement to hold the stone properlybybrass/copper hooks including filling the j oints with necessarycement mortar (1 white cement : 2 stone dust) with admixture of pigment matching the shades, all complete including edge molding. (Base rate = Rs. 2000/-) (Base rate of cement will be applied for this item)
Sq.M. 500 2697 1,348,375 1.53 4136 2,068,055 8265
PP178 Providing and laying 18 mmthick Adanga White Marble slab (1.5 mx 0.6 m) flooring over 22 mmthick base in cement mortar 1:4 (1 cement : 4 coarse sand) having 5 mmthick white cement topping, including labour materials and equipment and also including scouring of surface providing necessaryshape etc. Complete in all respect with standard accordance with specification & direction of engineer. The j oints shall be grouted with greycement by mixing & matching colour pigment. (Base rate = Rs. 1600/-) (Base rate of cement will be applied for this item)
Sq.M. 500 2427 1,213,375 1.53 3722 1,861,000 4593
PP179 Providing and laying over-all 40 mm thick granite work with 18 mmthick greygranite in flooring above as per floor pattern indicated in drawing and/or instructed bythe Engineer / Architect. (Base rate = Rs. 2750/-) (Base rate of cement will be applied for this item)
Sq.M. 100 3734 373,425 1.53 5727 572,736 7217
PP180 18 mmthick marble slab skirting or dado matching with floor marble slab as per instruction of engineer. (Base rate = Rs. 1600/-) (Base rate of cement will be applied for this item)
Sq.M. 100 2527 252,675 1.53 3875 387,537 9263
PP181 Supplying and fixing glass mosaic tiles 20 x 20 x 4.5 mm thick in pattern as per drawings and directions of the Engineer in charge.
Sq.M. 25 3077 76,919 - NA
PP182 Supplying & Laying precast cement concrete tiles (minimumsize 600 mmX 600 mm) 20 mm. thick on roof surface including preparation of bed with 15 mmthick sand cement mortar (4:1) to proper slope as per direction of the Engineer - in -charge complete including cost of all labour and materials etc.
Sq.M. 800 2527 2,021,400 1.53 - NA
PP183 Doors, Windows, Ventilators and Rolling Shutters (Rate shall be inclusive of cost of all required hardware) - 1.53 -
PP184 Supplying, fitting & fixing full glazed aluminumdoor with minimum 15 micron colour anodized aluminum frame and shutter of approved colour and make, complete with all fitting and fixtures (e.g. push plate, double actingfloor spring, locks etc.) sealing, grouting frames, rawbolt fixing, etc., as required with all materials complete including 8 mmthick toughened float glass (Vendor' s drawing to be approved by Architect before fabrication).
- 1.53 -
PP185 Single leaf Sq.M. 20 10500 210,000 1.53 16104 563,649 7808
PP186 Double leaf Sq.M. 50 8500 425,000 1.53 13037 651,839 7808
PP187 Supplying and fixing of best quality anodized aluminum windows and ventilators conforming to IS: 1949 & IS: 1948 including supplying and fixing approved glazing including all fixtures and fittings, fixing material such as puttyetc. and all labour complete as per specification, drawing and direction of Engineer. (thickness of aluminumsections is 3 mm)
- 1.53 -
PP188 With 4 mmthickclear float glass Sq.M. 500 4000 2,000,000 1.53 6135 3,067,478 4840
PP189 With 4 mmthickground glass Sq.M. 50 4300 215,000 1.53 6595 329,754 4840
PP190 With 6 mmthickclear toughened glass Sq.M. 29 5000 145,000 1.53 7669 383,435 5660
PP191 With 6 mmthick wired glass Sq.M. 400 4500 1,800,000 1.53 6902 2,760,730 5465
PP192 Fire proof glass (2hr fire rating) Sq.M. 100 7000 700,000 1.53 10736 1,073,617 NA
PP193 Extra for colour anodizing over and above itemno 84 natural colour anodizing Sq.M. 1200 450 540,000 1.53 690 828,219 NA
PP194 Supplying, erecting and fixing heavydutysteel louvers from approved manufacturer at various elevations including frame, louvers fitting including bird screen as per specification and fixture, mastic caulking, grouting the frame, rawl bolt including one coat of primer and two coat of approved synthetic paint with all material, labour, equipment etc. complete .
Sq.M. 200 3800 760,000 1.53 5828 1,165,642 6402
PP195 Supplyingandinstalling partition fromapproved manufacturer at all elevations in 100 mm x 45 mm and bottomframe 200 mmx 45 mmof 3 mmthick Anodized aluminum section of best approved quality frame work including full glazing with 8 mm thick toughened float glass superior qualityfirst grade of Modi float or equivalent approved byEngineer including frame, glazing beds, fittings and fixture, mastic caulking, putty, grouting the frame, rawl bolt, sealing after finishing etc. (glazing to be fixed to the framework with anodized aluminumchannels or angles and rubber beading all around. The itemrate shall include for all works including fixing of partitions to floor and roof and fixing of glass etc. complete as per specification and directions)
Sq.M. 400 5600 2,240,000 1.53 8589 3,435,575 6089
PP196 Providing, erecting and fixing 45 mm thick flush type hollowmetal doors with two outer sheets of 18 G rigidly connected with continuous vertical 20 Gstiffener at the rate of 150 mmcentre to centre and reinforced by18 G pressed steel channel fixed in pressed steel frame as per IS: 4351. Mineral wool insulation is to be provided inside the channel with fixtures, fittings, hold fast and locking arrangements etc. including finishing with two coats of zinc chromate primer and two coats of Synthetic enamel paint.
- 1.53 -
PP197 Single leaf shutters Sq.M. 200 8402 1,680,365 1.53 12886 2,577,241 8744
PP198 Double leaf shutters Sq.M. 250 11024 2,756,124 1.53 16909 4,227,175 8822
PP199 Supplying fitting and fixing fullyglazed frame less door (10 mmthick toughened) fitted with Stainless steel end caps with locating lug and screw. Single extrusion profile for universal frameless glass door rails. Trackshall be extruded hardened aluminumwith a maximumchannel wall thickness of 4.20 mmin 6060-T5 alloy. The weight of the extrusion shall be no less than 5.76 kg per lineal meter length. The rate should include the twin wheel carriage with a stabilizer wheel to prevent free side swing of the slydstakdoor panel, all complete as per manufacturer' s detail, drawing and direction of the Engineer in charge including the cost of glass.
Sq.M. 25 15000 375,000 1.53 23006 575,152 14834
PP200 Supplying and erecting including assembling, fitting and fixing best quality fully glazed openable, fixed or partly openable type steel windows,ventilators with frames fromapproved manufacturer including fabrication, one coat of shop paint, all fittings and fixtures as per Schedule of fixtures, at various elevations, includingglazing beads, frames, shutters, transom, coupling mullions, weather bars, inclusive of supplyof caulking, mastic, puttyetc. including supplying, fitting and fixing 4 mm thick clear float glass as per drawings, specification & windowschedule.
Sq.M. 0.001 3190 3 1.53 4893 978,525 3615
PP201 Extra over item(90) above for providing 5 mmthick clear float glass. Sq.M. 30 3410 102,300 1.53 5230 156,901 NA
PP202 Extra over item(90) above for providing 6 mmthick wired glass. Sq.M. 10 3960 39,600 1.53 6074 60,736 NA
PP203 Providing fitting and fixing fire proof metal doors with mineral wool insulation, conforming to IS: 3614 (Parts I &II) meeting TAC requirements and having a fire rating of two hours (min) at all levels and for all type of work, including all labour, materials workmanship including preparation of working drawings, equipments, handlings, transportation, steel frames ,shutter insulation, fitting, hinges, panic lock, latch, horizontal full width lever, openable on pressing door stoppersholdfasts/expandinganchorboltsbolting arrangements , grouting frames , blast cleaning of steel surfaces to near white metal surfaces applying inorganic zinc silicate primer of minimum 75 micron (DFT) and finish with suitable fire retardant painting systemtesting etc. all complete as per drawings, specification
- 1.53 -
PP204 Single leaf Sq.M. 130 23000 2,990,000 1.53 35276 4,585,879 28106
PP205 Double leaf Sq.M. 100 24000 2,400,000 1.53 36810 3,680,973 28106
PP206 Providing and fixing doors fabricated from roll formed section made of Galvanized steel colour coated with total thickness of 0.6 mm. Coated sections should be painted with 12-16 microns thick polyester paint over a primer coat of Epoxyprimer of 5-7 microns thick. The frame and shutter should be cut and mitre jointed with corner bracket made of CRCA electroplated made of CRCA electroplated EPDM gasket should be used all around glass in shutter,
Sq.M. 10 9000 90,000 1.53 13804 138,036 NA
PP207 between frame and glazed shutter and both sides of fixed glass. The frame along with the shutter should be fixed to brick/concrete masonrybyusing Nylon self expanding caps and driving MS electroplated 80 mmlong screws into the caps through frames similar to NCL ALTECK and Seccolor ltd.
- 1.53 - NA
PP208 Providing and fixing factorymade 38 mmthick solid core flush door fromapproved manufacturer with frame of teak wood and well matched commercial plyveneering wood with vertical grains or cross bands and face veneer on both faces of shutters including providing and fixing lipping with first class wood batten 10 mm thick on all edges of shutters including anodized aluminumtower bolt and mortised lock, with one coat of approved primer and two coats of synthetic enamel paint of approved make and shade, complete in all respect.
Sq.M. 700 13500 9,450,000 1.53 20705 14,493,832 8510
PP209 Same as above item no 93 but low in height as per drawing and direction of the engineer in charge. Sq.M . 50 12500 625,000 1.53 19172 958,587 NA
PP210 Supplying and fixing glazed vision panel (of minimumsize 200 mmX 200 mm) to doors with 6 mmthick glazing of tempered safetyglass or wired glass including fitting and fixture with all material, labour, equipment etc. complete as per the instructions of Engineer. (Actual size of vision panel will be measured and paid)
Sq.M. 5 10000 50,000 1.53 15337 76,687 13273
PP211 Supplying, fitting and fixing in position PVC door upto 1.0 M. wide including PVC frame and shutter of approved colour and make of approved SystemDS-06 or approved equal, complete in all respect including all accessories, complete hardware, grouting, fitting and fixing hardware with necessaryfittings etc. as per manufacturer' s specification, drawing and instruction of Engineer/Architect
Sq.M. 50 6000 300,000 1.53 9202 460,122 NA
PP212 Supplying, erecting and fixing of steel rolling shutter with 18 SWGsteel laths with the provision of manual operation arrangement / mechanical gear operation arrangement, of any size with slide guides, bottomrail brackets, door supervision shaft, housing box at top with all necessaryfittings, fixtures, locking arrangements gear, mechanical device etc. including finishing with 2 coats of Synthetic enamel paint of approved qualityover one shop coat of zinc chromate primer etc. complete as per drawings specification and direction of Engineer including, labour, material equipment etc. complete (Measurement on the basis of opening covered by rolling shutters).
- 1.53 -
PP213 Hand operated Sq.M. 100 4500 450,000 1.53 6902 690,182 4684
PP214 With mechanicallyoperated Sq.M. 18 6000 108,000 1.53 9202 1,380,365 6246
PP215 With electricallyoperated Sq.M. 200 25000 5,000,000 1.53 38343 7,668,694 12492
PP216 Providing and fixing automatic operation systemfor doors (4 nos. sliding opening of openable size 2.4 mx 2.4 m) suitable for door openings consisting of sliding door shutters, opening on opposite sides, complete with solid state controller unit heavydutyreversible associate cabling and circuit etc. so as to provide flawless automatic operation, with all labour, material, equipment, handling, transportation, workmanship, preparation of working drawings, testing etc all complete as per specification, drawings, testing etc all complete as per specification, drawings and instructions of the Engineer. The Electric operating mechanismshall be mounted and concealed within Aluminumheader and the controller unit shall be Micro processor based. The bottom rail of the door shall have security lock. Weather
Sq.M. 25 30000 750,000 1.53 46012 1,150,304 NA
PP217 stripping shall be provided along the edges of sliding door panels. Basic sensor system shall be of active infrared sensor type, header mounted on each side of the door and shall remain active throughout the door opening and closing cycle. Two pulsed infrared photo
- 1.53 - NA
PP218 Glazing - 1.53 -
PP219 Providing and fixing Unitised vertical Structural glazing system with IG unit(insulated double Glass unit) for vision panel and single glass for spandrel panel of approved make having main frame of verticals and horizontals made out of specially designed extruded aluminumsections to withstand wind pressure of 200 kg/sq.m. at a height to the Masonry/RC wall with necessary clamps, brackets and anchor fasteners . All clamps and brackets shall be Mild steel Hot Dip galvanized minimum 80 microns thick and shall conformto IS: 4756-1996 .The extruded aluminumsections shall be anodized as per the approved colour with anodic coating of minimum 20 microns .Extruded section shall be 6063 T5 or T6 alloy conforming to ASTM B 221 or BSH79 conforming to IS: 63400. Anyother fastening straps, clamps, nuts, bolts, rivets, washers etc. shall be stainless steel SS 304 grade or aluminum. All tapes shall be Norton make. Rate shall include providing Column closers, Fire stops at all floor levels. rate shall include to provide column closers , Fire stops (at all elevations. to be done under specific instruction glazing). Rate shall include EPDM gaskets, open cell polythene backer rods etc. The structural glazing sealant shall be DowCorning 983 and weather sealant shall be DowCorning 991H. All sealant shall be blackin colour. Rate shall include to conduct the performance test conforming to ASTM specifications, etc. complete all as directed.
Sq.M. 200 1800 360,000 1.53 2761 552,146 NA
PP220 Supplying bubble free float glass set in puttyand fitted and fixed with nails and puttycomplete in all floors. - 1.53 - NA
PP221 6 mmthickclear glass Sq.M. 15 800 12,000 1.53 1227 18,405 NA
PP222 4 mmthickclear glass Sq.M. 15 700 10,500 1.53 1074 16,104 NA
PP223 10 mmthickclear glass Sq.M. 15 1200 18,000 1.53 1840 27,607 NA
PP224 4 mmthickfigured glass Sq.M. 15 1500 22,500 1.53 2301 34,509 NA
PP225 Supplying and fixing composite double glazing consisting of clear float glass of 6 mmthick on one side and tinted glass of 6 mmthick on other side and are separated by 12 mm air gap hermetically sealed by beading of anodized aluminum.
Sq.M. 200 3500 700,000 1.53 5368 1,073,617 NA
PP226 Extra for 12 mm clear toughened float glass on both sides instead of 6 mmthick glass Sq.M. 200 3200 640,000 1.53 4908 981,593 NA
PP227 Extra for 8 mmclear toughened float glass on both sides instead of 6 mmglass Sq.M. 100 3000 300,000 1.53 4601 460,122 NA
PP228 Supplying and fixing Glaverbal heat reflecting glass of thickness 8 mmof AIS float glass or of approved equivalent Sq.M. 10 5000 50,000 1.53 7669 76,687 NA
PP229 Painting - 1.53 -
PP230 Providing and applying white cement puttyof minimum 2 mm thick (over plaster) at various elevations in interior surfaces with all materials etc. complete as per specifications
Sq.M. 1000 120 120,000 1.53 184 184,049 97
PP231 Providing and applying Oil bound crylic distemper of approved make consisting of a priming coat with approved primer over white cement putty and two (2) finishing coats of paint of approved manufacture and quality approved shades, including labour, materials, equipment and scaffolding etc. complete as per manufacturer' s instructions at all elevations.
Sq.M. 2683 160 429,280 1.53 245 9,815,929 76
PP232 Providing and applying acrylic emulsion paint of approved make consisting of a priming coat with approved primer over white cement puttyand two (2) finishing coats of paint of approved manufacture and qualityapproved shades, including labour, materials, equipment and scaffolding etc. complete as per manufacturer' s instructions at all elevations.
Sq.M. 5500 160 880,000 1.53 245 1,349,690 144
PP233 Providing and applying chemical resistant paint of approved make applied on a clean surface free of oils etc. after applying approved primer coat to seal the surface porosity followed bytwo (2) full coats of the paint, including labour, material, equipment, and scaffolding etc. at all elevations and heights as per manufacturer' s specification and direction of the Engineer.
Sq.M. 1000 320 320,000 1.53 491 490,796 427 acid & alkali resistance paint
PP234 Providing and applying three (3) coats of water proof cement paint of approved manufacturer (Snowcemor equivalent approved bythe Engineer-in-charge) and in approved shades to plastered surfaces including cleaning and preparing the wall surface, curing etc. complete as per specifications and directions of Engineer at all elevations including labour, material, scaffolding etc. complete.
Sq.M. 3755.5 180 675,990 1.53 276 5,245,387 66
PP235 Providing and applying three (3) coats of synthetic plaster composed of synthetic fiber and petroleumbased chemical similar to 'RENOVO' of approved shade to plastered surfaces including cleaning and preparing the wall surface, curing etc. complete as per specifications and directions of Engineer at all elevations including labour, material, scaffolding etc. complete.
Sq.M. 1500 350 525,000 1.53 537 805,213 437
PP236 Providing and application of ready mix two component resin and polymer bonded granular textured coating finish of approved colour and shade for all types plaster and / exposed concrete surfaces in all kinds of workat all levels including preparation of surfaces , preparation of working drawing,labour,materials,equipments,handling, transportation, mixing , laying, applying , finishing, testing, curing, making grooves, scaffolding, staging, etc. all complete as per specifications, drawing and the instruction of the Engineer for the following nominal thickness:
- 1.53 - 437
PP237 1.2 mmpigmented granular for interior application Sq.M. 2500 420 1,050,000 1.53 644 1,610,426 NA
PP238 2.5 mmnatural stone chips for external finish in readymix. Sq.M. 2500 480 1,200,000 1.53 736 1,840,487 NA
PP239 Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved puttyetc. on the surface , if necessary:
- 1.53 -
PP240 On timber or plastered surface: Sq.m. 1000 150 150,000 1.53 230 230,061 211
PP241 False Ceiling - 1.53 -
Page 5 of 429
9
10
A B C D G H I J K L M N
SASAN
Rate Amount Rate Amount Rate Amount
Item
No.
Description Unit Qty Quote ITD CEM Quote
Factor
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296 297
298
PP242 Providing and fixing Glass Reinforced (GRG) false ceiling systemhaving fine texture finish, at all levels for all kind of workwhich includes providing and fixing GI perimeter Channels of size 0.55 mmthickness having one flange of 20 mmand another flange of 30 mmand a web of 27 mmalong with perimeter of ceiling, screwfixed to brickwall / partition with the help of nylon sleeves and screws at 610 mmcenters. Then suspending GI intermediate channels of size 45 mm, 0.9 mmthickwith two flanges of size 45 mm, 0.9 mmthickwith two flanges of size 15 mmeach fromthe soffit at 1200 mm centers with ceiling angle of width 25 mmx25 mmx0.55 mm thickfixed to soffit with GI cleat and steel expansion fastener. Ceiling section of 0.55 mmthickness having knurled web of 51.5 mmand two flanges of 26 mmeach with lips of 10.5 mmare then fixed to the intermediate channel with the help of connecting clips and in direction perpendicular to the intermediate channel at 457 mmcenters. 12 mmthickGRG Board is then fixed to the ceiling sections with 25 mmdrywall screws at 230 mmcenters .The itemto include all labour, material supporting equipments fromRCC, preparation of working drawing, providing openings for AC ducts, return air grill light fixtures, etc all complete as per specifications, drawings and direction of the Engineer in charge.
- 1.53 -
PP243 12 mmthick GRGplaster board, finished seamless. Sq M. 1000 1241 1,240,625 1.53 1903 1,902,795 300
PP244 Providing and fixing insulation of resin bonded mineral wool 25 mmnominal thickness conforming to IS: 8183, having a density of 32 kg/cum for glass wool or 48 kg/cumfor rock wool insulation over false ceiling , at all levels for all kinds of work, handling transportation etc. including all labour, material, scaffolding, equipment, wrapped in polyethylene sheet bags with or without framed strips 25 x 3 mm(minimum) at maximum300 mm. centre to centre spacing to hold the insulation between horizontal sheeting runners, keeping in position with galvanized hexagonal wire netting of 0.3 mmwire diameter and 19 mm mesh size for glass/rock wool as per specifications drawings and instruction of the Engineer .
Sq M 200 525 105,000 1.53 805 161,043 NA
PP245 Providing and fixing insulation of resin bonded mineral wool 50 mmnominal thickness conforming to IS: 8183, having a density of 32 kg/cum for glass wool or 48 kg/cumfor rock wool under deck insulation, at all levels for all kinds of work, handling transportation etc. including all labour ,material, scaffolding, equipment, wrapped in polyethylene sheet bags with or without framed strips 25 x 3 mm (minimum) at maximum300 mm. centre to centre spacing to hold the insulation between horizontal sheeting runners, keeping in position with galvanized hexagonal wire netting of 0.3 mmwire diameter and 19 mmmesh size for glass/rock wool as per specifications drawings and instruction of the Engineer .
SQM 100 709 70,875 1.53 1087 108,704 NA
PP246 Providing and fixing Polyisocyanurate or rigid fenolic foam (fire and non toxic) preformed insulation slab conforming to IS: 12436/ IS: 13204 having 30 mmnominal thickness, having a densityof 32 kg/cumbottomface of the slab laminated with 0.05 mmthick aluminumfoil, as under deck insulation at all levels fixed with adhesive followed by metal expansion fasteners at the spacing not more than 450 center to center including all labour ,material, scaffolding etc. all complete as per specifications drawings and instruction of the Engineer
Sq.m. 3000 1313 3,937,500 1.53 2013 6,039,097 NA
PP247 Preparation of grading underbed with 1:1 1/2:3 concrete of cement: coarse sand: 12 mmdown stone chips (by volume) at various elevations for roof waterproofing works etc. complete including mixing laying, curing etc. with all materials complete as per drawing and specification.
Cu.m . 500 5200 2,600,000 1.53 7975 3,987,721 NA
PP248 Preparation of minimum25 mmto maximum50 mmthick grading underbed with 1:4 cement: coarse sand mortar (by volume) at various elevations for roof waterproofing works including mixing, laying, curing etc. with all materials complete as per drawings and specifications.
Sq.M 11000 210 2,310,000 1.53 322 3,542,937 NA
PP249 Supplying and laying roof insulation with 50 mm thick expanded polystyrene Blocks similar to Supreme or similar approved make at various elevations including preparation of surface, laying blocks, pointing etc. as per manufacturers specification with al materials etc. complete as per drawings and specifications.
Sq.M 200 680 136,000 1.53 1043 208,588 NA
PP250 Supplying and laying 150 mmx 150 mmfillets at j unction of roof and parapet wall with Expanded Polystyrene Blocks at various elevations etc. complete similar to Item above.
Rm 5 120 600 1.53 184 920 NA
PP251 Roof water proofing treatment for buildings and structure shall be provided using high solid content liquid elastomeric water proofing membrane with separate wearing course as per ASTM C-898. Thickness of the membrane shall be 1.5 mm. This treatment shall include application of polymerized mastic over the roof to achieve smooth surface and primer coat. Wearing course on top of the membrane shall consist of 25 mmthick PCC (1:1 1/2:3), cast in panels of max. 1.5 mx 1.5 msize and reinforced with 0.56 mmdia. galvanised chicken wire meshandsealingofj ointsusingsealing compound/elastomeric water proofing membrane at all levels and for all types of work, in vertical and horizontal surfaces , handling, scaffolding, transporting, testing etc. all complete as per specifications, drawing and direction of the Engineer in charge.
Sq.M 11000 690 7,590,000 1.53 1058 11,641,078 902
PP252 Supplying and installing at all elevations Armstrong suspended ceiling in specified profile of following types as manufactured byArmstrong World Industries (I) Pvt. Ltd. strictly as per drawings, specifications, manufacturers specifications, standards and installed bymanufacturers authorized agencyin best workmanship manner complete in all respect with all materials, labour, tools, etc. including metal suspension systemconsisting of Armstrong stitched Trulok 15 exposed grid of 600 x 600 mmmodule with 15 mmwide T- section flanges, main runners at 1200 mmcenters, suspension channels, angles, braces as required, securelyfixed to the structural steel truss, purlins etc with approved adj ustable hangers at 1200 mm(max) centers, flush fitting cross tees, interlocked between main runners at 600 mmcenter forming 1200 x 600 mmmodules, flush fitting cut-cross Tees between the cross Tees to form600 x 600 mmmodule and 600 x 600 mmceiling tiles of approved type and colour finishing all edges, junctions, perimeters, corners, with appropriate trims etc complete including making openings for light fittings, HVAC grills, diffusers along with perimeter frames as per illumination and HVAC drawings etc to the entire satisfaction of the Engineer/Architect.
Sq.M 1500 1260 1,890,000 1.53 1933 2,898,766 1755
PP253 15 mmthick PRIMADUNE SUPREME RH 99 of Microlook type having minimum0.5 NRC value. Sq.M 100 1470 147,000 1.53 2255 225,460 1755
PP254 Providing and fixing pre-painted aluminum linear false ceiling systemto 'Luxalon' of Hunter Douglas or of approved equivalent at all levels for all kinds of workincluding matching pre-painted profile carrier for fixing of linear type panels bysnap fit arrangement suspended fromRCC slab/ structural steel or catwalk steel channel grid above with 4 mm(min.) rods with special height adj ustment clips ,providing angle section of minimum25 mmleg width along the perimeter of ceiling , including all labour, material, supporting grid systemequipment, handling transportation ,workmanship, anchor fasteners for making suspension arrangement , preparation of working drawings providing opening , for AC ducts return air grills, insulation light fixtures, etc. all complete as per specifications drawings & instruction of the Engineer (Cat walkwaygrid & insulation if provided to be paid separatelyunder relevant item)
Sq.M. 750 1890 1,417,500 1.53 2899 2,174,075 1873
PP255 Metal Cladding & Roofing and Metal Decking Sheets - 1.53 -
PP256 Supplying and laying & fixing of 0.8 mmthick metal deck formwork of cold formed steel profile - Trapezoidal decking profile with valleydepth 44mmand pitch/centre to centre distance of the valleyabout 130 mmincluding of approved make as permanent shuttering for casting R.C.C. roof on steel purlins, with all fixtures and welded studs (stud. dia 16 mmhex. head, 75 mmlong at a spacing @ 390 mmC/C welded to steel purlin) on top of steel purlins all complete as per drawings, specifications and direction of engineer. The decksheet shall conformto AS1397 / ASTM 653M or equivalent with Z275 coating. The exposed surface shall be 20 micron SMP over primer of 5 microns. The surface in contact with concrete will have 5 microns primer.
Sq.M 984 1585 1,559,689 1.53 2431 26,741,580 1268
PP257 Supplying and laying & fixing of 1.0 mmthick metal deck formwork of cold formed steel profile - Trapezoidal decking profile with valleydepth 44mmand pitch/centre to centre distance of the valleyabout 130 mmpermanent shuttering for casting R.C.C. floor on steel floor beams, with all fixtures and welded studs (stud. dia 16 mmhex. head, 75 mm long at a spacing @ 390mmC/C welded to steel purlin) on top of steel purlins all complete as per drawings, specifications and direction of engineer. The decksheet shall conformto AS1397 / ASTM 653M or equivalent with Z275 coating. The exposed surface shall be 20 micron SMP over primer of 5 microns. The surface in contact with concrete will have 5 microns primer.
Sq.M. 31000 2253 69,829,825 1.53 3455 107,100,714 NA
PP258 Supply, fitting, fixing in position true to line and level pre- coated GALVALUME cold rolled single skin sheet having profile depth of minimum30mmwith a pitch of maximum250 mm and minimumcover width of 1020mmwith two stiffening ribs made out of 0.5 mmBMT Galvalume steel. The profiled sheets shall be minimum0.5 mmBMT, Zinc Aluminum coated steel (AZ 150) of strength 550 MPa and finished with 20 microns color coating of SMP color paint coat as per AS/NZS - 2728 : 1997 on exposed surface over a primer coat of 5 microns of approved color. On other side (unexposed), 5 microns SMP over primer of 5 microns. Sheet shall conformto ASTM A792M / AS 1397 or equivalent
Sq.M. 17000 3070 52,190,000 1.53 4709 80,045,830 1350
PP259 Extra over item124.a above for cripping, curved profile as per the detailed drawing and as directed bythe Engineer. Sq.M 200 600 120,000 1.53 920 184,049 NA
PP260 Providing and fixing at all levels aluminum composite panels cladding comprising of 4 mmthick thermo plastic core of mind lowdensitypolyethylene sandwiched between two skins of minimum0.5 mmthickness aluminum sheet, protected with self adhesive peel of masking foil, coating thickness panel weight, thermal expansion, tensile strength, yield strength elongation, flexural elasticity, deflection, heat transmission etc. shall be as per the best international practice fixed on the supporting aluminumextruded section and MS structural sealants and
Sq.M. 100 3100 310,000 1.53 4755 475,459 1950
PP261 anchor/SS fasteners hardware complete with all labour, materials, equipment, handling, transportation, workmanship preparation of working drawings, staging, scaffolding, etc. all complete as per specifications, drawings, and instructions of the Engineer (aluminumwork, if anyshall be inclusive of the item)
- 1.53 -
PP262 Design, supply, installation of curved dome structure of 10 mdiameter (approx) with 4mhigh for the skylight in the roof of service building with embossed U.V. Resistant, multi wall polycarbonate sheet 6 mmthick with 82% light transmission, K value 3.5 and fixed to powder coated aluminumextruded framing including fabrication and erection of steel structural framing to obtain the required shape, with adequate provision for expansion including all fittings, anchoring accessories, fixtures, joint sealing with EPDM gaskets to make the complete structure water proof, fitting & fixing the structural member, etc. complete with all labour, material, equipments, handling, transportation, workmanship, preparation of working drawings, including structural design all as approved design and instructions of the Engineer. Itemto include foundation bolts, plates, square tubes, all supporting structures including painting etc. complete in all respects.
Each 1 1500000 1,500,000 1.53 2300608 2,300,608 NA
PP263 Supplying fitting & fixing in position 4mmthick, 2100mm wide and 2000 to 12000mmlong clear or colored transparent profiled (matching with profile of metal side cladding) polycarbonate sheets at all elevations having UV, Yellowing, Abrasion resistant properties including properties like- area weight shall be not less than 0.8kg/sqm, specific gravity- 1.2, Water absorption - 0.15 Light transmittance 86% Taber resistance (100 cycles)- 0.8 to 1.5, Shading coefficient - 1.02 for clear & 0.7 for colored sheets, Ignition temperature flashing- 465 degree C, Heat transfer coefficient - 4.1W/sqmK, etc., with EPDM gaskets, hermeticallysealed joints, clips, trims, flashings, including all necessaryaccessories as per manufactures specification, which shall be fixed on steel members or concrete members as sub structure, profile flushing on all exposed edges, complete in all respect up to the satisfaction of the Engineer.
Sq.M. 1000 2300 2,300,000 1.53 3528 3,527,599 NA
PP264 Plumbing, Sanitaryand Drainage Works LS 1 5001950 5,001,950 1.53 7671685 7,671,685 NA
PP328 MISCELLANEOUS ITEM - 1.53 -
PP329 Providing and fixing galvanized steel chain link fencing of 3.0 mhigh (consisting of 0.2 mtoe wall, 2.8 mchain linkportion with size, 3.15 mmdia mesh wire and mesh size as 75 mmx75 mmconforming to IS: 2721, MS stirrup wire 2.5 mm dia tying wire 1.6 mmdia mild steel including providing 25 mmx4.75 mmMS stretcher bars, eye bolt and strainer, ring nuts, hairpins, staples of 3.5 mmwire, cleats of MS angle 75 x60 x6 mm, MS droppers 25 mmx38 mmx 4.85 mmhalf round staples etc. including the cost of supplyand fixing of 2 nos end post of 65 x65 x62 L , intermediate post of 50 x 50 x6 at 2,5 minterval & strain post to be provided with of 65 x65 x62 L with struts of 50 x50 x6 on both sides at 25 M interval, all posts to be embedded in concrete blockof of size 450 x450 x400 (D)mmin M15 grade concrete including excavation. All structural steel shall conformto IS: 2062 and shall be painted with one coat of red oxide primmer and two coats synthetic enamel paint.
Sq.M. 100 2390 239,000 1.53 3666 366,564 3490
PP330 Providing and installation of Fencing, for transformer yard, boundary wall and other areas, including all labour, material, workmanship, including preparation of working drawings, equipment, fixing on structural steel members, all fixtures, clips, transportation, handling etc. all complete as per specification, drawings and instructions of the Engineer. (Structural Steel Posts and stays, toe wall, brick wall, concrete etc., if provided, shall be paid separatelyunder relevant term). Comprising of PVC coated chain link, mesh size 75 mm, diameter of the PVC coated wire as 4 mm(min.), diameter of bare wire not less than 2.5 mm, as per IS: 272
Sq.M. 200 600 120,000 1.53 920 184,049
PP331 Providing, fabrication, transportation and erection of structural steel work in gates, conforming to IS: 2062, including all labour material, equipment, workmanship, preparation of working drawings, transportation, handling, hardware, fixtures and fittings like fabricated hinges, mild steel aldrops, locking arrangement, tower bolts, pipes, stubs/post, tempered steel template, tempered steel pivots, guide trackof MS tee, bronze aluminumball and bearing arrangement, castor wheel, placing in position embedded parts in concrete/brickwork/road surface, cutting, grinding, frilling holes, welding, blast cleaning of steel surfaces to near white metal surface (Sa 2.5) applying inorganic zinc silicate primer of minimum 75 micron (DFT) touch up painting, application of intermediate (under) coat of minimum75 micron (DFT) epoxybased colour paint, all complete, as per specifications drawings and instructions of the Engineer
Kg. 50 95 4,750 1.53 146 7,285 6779.18/Sq m
PP332 Providing, fabricating and fixing of screen with M.S. angle frame of required size and fixing of IRC fabrics bywelding with M.S. angle frame fitting and fixing with M.S. clamps welded with main frame, one coat of primer paint all complete as per specifications and approval of Engineer
Sq.M. 20 4210 84,200 1.53 6457 129,141 NA
PP333 Providing and fixing 32 mmdia and minimum3 mmthick heavydutyStainless steel hand rail and balusters with 25 mm dia. Intermediate rail seamlessly joined with all necessaryaccessories, as per approved design, complete in all respect.
R.M. 1622.98 11490 18,648,040 1.53 17623 5,286,798 624/Kg
PP334 Supplying, fabricating and erecting railings for balconies / stairs at all elevations using M.S. round/square tubes/bars, MS flats, angles etc. with running welded joints including hinges, shoes, rollers, guide rails and other necessarylocking arrangements complete as per drawing, specifications with one coat of approved zinc chromate primer and two coats of synthetic enamel paint of approved make & shade. (cost of making & filling pockets for holding the railing shall be included in this itemrate)
Kg. 2500 100 250,000 1.53 153 383,435 17099.55/M T Str.Steel free issue
PP335 Supplying, fabricating and erecting MS gate built with galvanized tubes conforming to IS: 1161 of 50 mm dia frames including galvanized flats 25 x6 mmconnection bolts and nuts 8 mmdia welded wire fabric (50 x50 mmsquare mesh welded to galvanized flats 25 x6 mmbottomrollers, guide track, locking arrangement fromboth sides, handles, stoppers, hold fasts, pin clamps, MS aldrops etc. complete.
Kg. 500 157 78,500 1.53 241 120,398 17099.55/M T Str.Steel free issue
PP336 Providing and fixing in position at all levels, PTFE type sliding bearings individual bearing suitable for specified vertical loads as per construction drawings and having maximumdisplacement of +90 mm, including all labour, material, equipment, transportation, handling, installation, drilling, bolting, erecting, aligning, etc., all complete, as per specifications, drawings and instructions of the Engineer (Vertical load carrying capacityshall be as specified in the construction drawings).
- 1.53 - NA
PP337 Total vertical load carrying capacityfor all Bearings having vertical load carrying capacityfor each bearing from10.0M. T. to 40 MT.
MT 250 520 130,000 1.53 798 199,386 NA
PP338 Total vertical load carrying capacityfor all Bearings having vertical load carrying capacity for each bearing over 40 M.T.to 150 M.T.
MT 1000 250 250,000 1.53 383 383,435 NA
PP339 Supply, Fabrication, erection and connection of following conductors for grounding, lightning protection including all materials, accessories, labour and tools ect. as per drawings and specification (Base rate of structural steel will be applied for this item)
- 1.53 -
PP340 Ground Mat Grid - 1.53 -
PP341 36 mmdia M.S. rods RM 25000 - 1.53 - 142.35/ Rmt Str.Steel free issue
PP342 Ground Electrode - 1.53 -
PP343 36 mmdia 3M long M.S.rod Nos 1000 - 1.53 - 6600 Str.Steel free issue
PP344 Riser - 1.53 -
PP345 36 mmdia M.S.rod RM 1000 - 1.53 - 226.2/Rmt Str.Steel free issue
PP346 Risers above 0.0M - 1.53 -
PP346 50 x6 mmG.S. Flat RM 1000 - 1.53 - 940 Str.Steel free issue
819,354,969 3,329,502,821
CHECK RA - CHECK FTS -
Page 6 of 429
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
PP1 EARTHWORK
PP2 Earthwork in excavation in the all types of soil includingbailing / pumping out any water accumulating inside the excavation if required strutting, shoring / sheet piling, dressing and transporting the excavated soil up to 1.0 KM lead and filling / stacking selectively as directed by the Engineer, all complete as per drawing & specification.
PP3 Up to 2.0 m depth from Ground level 24,828.74 Cu.M 68 1,685,072
PP3
PP3 Plant
PP3 Plant- Excavation pl 24829 cum @ 56.43 per cum =Rs 1,400,977 /-
PP3 Plant labour- Excavation dl 24829 cum @ 1.44 per cum =Rs 35,807 /-
PP3
PP3 Labour
PP3 Misc excavation lc 24829 Cum @ 1.00 per cum 10.00 =Rs 248,287 /-
PP3
PP4 Between 2.0m to 4.0m depth from ground level 12,664.31 Cu.M 78 986,142
PP4
PP4 Plant
PP4 Plant- Excavation pl 12664 cum @ 56.43 per cum =Rs 714,592 /-
PP4 Plant labour- Excavation dl 12664 cum @ 1.44 per cum =Rs 18,264 /-
PP4
PP4 Labour
PP4 Misc excavation lc 12664 Cum @ 1.00 per cum 20.00 =Rs 253,286 /-
PP4
PP5 Between 4.0m to 6.0m depth from ground level 2,151.00 Cu.M 65 140,281
PP5
PP5 Plant
PP5 Plant- Excavation pl 2151 cum @ 24.59 per cum =Rs 52,889 /-
PP5 Plant labour- Excavation dl 2151 cum @ 0.63 per cum =Rs 1,352 /-
PP5
PP5 Labour
PP5 Misc excavation lc 2151 Cum @ 1.00 per cum 40.00 =Rs 86,040 /-
PP5
PP6 Between 6.0m to 8.0m depth from ground level 0.00 Cu.M 85 0
PP6
PP6 Plant
PP6 Plant- Excavation pl 0 cum @ 24.59 per cum =Rs 0 /-
PP6 Plant labour- Excavation dl 0 cum @ 0.63 per cum =Rs 0 /-
PP6
PP6 Labour
PP6 Misc excavation lc 0 Cum @ 1.00 per cum 60.00 =Rs 0 /-
PP6
PP7 Between 8.0m to 10.0m depth from ground level 0.00 Cu.M 225 0
PP7
PP7 Plant
PP7 Plant- Excavation pl 0 cum @ 24.59 per cum =Rs 0 /-
PP7 Plant labour- Excavation dl 0 cum @ 0.63 per cum =Rs 0 /-
PP7
Amount Description Cost code Analysis Item No Qty Unit Rate
Page 7 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP7 Labour
PP7 Misc excavation lc 0 Cum @ 2.50 per cum 80.00 =Rs 0 /-
PP7
PP8 Earthwork in excavation below ground level in hard rockby any mechanical means without blasting & wedging,without damaging the existing structures, including setting out, clearing & grubbing, removal of debris, dewatering if required, strutting & shoring if required, dressing the sides, leveling to grade and stacking / disposal of surplus excavated material within a lead of 1.0 KM etc as directed by the Engineer, all complete as per drawing & specification.
PP9 Up to 2.0 m depth from Ground level 0.00 Cu.M 15,793,170,883 15,793,171
PP9
PP9 Plant
PP9 Plant- Excavation pl 0 cum @ ########## per cum =Rs 15,399,580 /-
PP9 Plant labour- Excavation dl 0 cum @ ########## per cum =Rs 393,591 /-
PP9
PP9 Labour
PP9 Misc excavation lc 0 Cum @ 1.00 per cum 80.00 =Rs 0 /-
PP9
PP9 Subcontract
PP9 Excavation using chemical sc 0 Cum @ 1.00 per cum =Rs /-
PP9
PP10 Between 2.0m to 4.0m depth from ground level 0.00 Cu.M 15,793,170,913 15,793,171
PP10
PP10 Plant
PP10 Plant- Excavation pl 0 cum @ ########## per cum =Rs 15,399,580 /-
PP10 Plant labour- Excavation dl 0 cum @ ########## per cum =Rs 393,591 /-
PP10
PP10 Labour
PP10 Misc excavation lc 0 Cum @ 1.00 per cum 110.00 =Rs 0 /-
PP10
PP10 Subcontract
PP10 Excavation using chemical sc 0 Cum @ 1.00 per cum =Rs /-
PP10
PP11 Between 4.0m to 6.0m depth from ground level 0.00 Cu.M 301,339,012 301,339
PP11
PP11 Plant
PP11 Plant- Excavation pl 0 cum @ ########## per cum =Rs 293,829 /-
PP11 Plant labour- Excavation dl 0 cum @ ########## per cum =Rs 7,510 /-
PP11
PP11 Labour
PP11 Misc excavation lc 0 Cum @ 1.00 per cum 130.00 =Rs 0 /-
PP11
PP11 Subcontract
PP11 Excavation using chemical sc 0 Cum @ 1.00 per cum =Rs /-
PP11
PP12 Between 6.0m to 8.0m depth from ground level 0.00 Cu.M 301,339,042 301,339
PP12
PP12 Plant
PP12 Plant- Excavation pl 0 cum @ ########## per cum =Rs 293,829 /-
PP12 Plant labour- Excavation dl 0 cum @ ########## per cum =Rs 7,510 /-
PP12
Page 8 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP12 Labour
PP12 Misc excavation lc 0 Cum @ 1.00 per cum 160.00 =Rs 0 /-
PP12
PP12 Subcontract
PP12 Excavation using chemical sc 0 Cum @ 1.00 per cum =Rs /-
PP12
PP13 Between 8.0m to 10.0m depth from ground level 0.00 Cu.M 301,339,082 301,339
PP13
PP13 Plant
PP13 Plant- Excavation pl 0 cum @ ########## per cum =Rs 293,829 /-
PP13 Plant labour- Excavation dl 0 cum @ ########## per cum =Rs 7,510 /-
PP13
PP13 Labour
PP13 Misc excavation lc 0 Cum @ 1.00 per cum 200.00 =Rs 0 /-
PP13
PP13 Subcontract
PP13 Excavation using chemical sc 0 Cum @ 1.00 per cum =Rs /-
PP13
PP14 Earthwork in excavation below ground level in hard rockby means of controlled blasting including provision ofsensor to assess the impact of blast on the adjacent structures, without damaging the existing structures, including setting out, clearing & grubbing, removal of debris, dewatering if required, strutting & shoring if required, dressing the sides, leveling to grade and stacking / disposal of surplus excavated material within a lead of 1.0 KM etc as directed by the Engineer, all complete as per drawing & specification.
PP15 Up to 2.0 m depth from Ground level 0.00 Cu.M 361,607,308 361,607
PP15
PP15 Plant
PP15 Plant- Excavation pl 0 cum @ ########## per cum =Rs 352,595 /-
PP15 Plant labour- Excavation dl 0 cum @ ########## per cum =Rs 9,012 /-
PP15
PP15 Labour
PP15 Misc excavation lc 0 Cum @ 1.00 per cum 50.00 =Rs 0 /-
PP15
PP15 Subcontract
PP15 Controlled blasting sc 0 Cum @ 1.00 per cum 600.00 =Rs 1 /-
PP15
PP16 Between 2.0m to 4.0m depth from ground level 0.00 Cu.M 361,607,338 361,607
PP16
PP16 Plant
PP16 Plant- Excavation pl 0 cum @ ########## per cum =Rs 352,595 /-
PP16 Plant labour- Excavation dl 0 cum @ ########## per cum =Rs 9,012 /-
PP16
PP16 Labour
PP16 Misc excavation lc 0 Cum @ 1.00 per cum 80.00 =Rs 0 /-
PP16
PP16 Subcontract
PP16 Controlled blasting sc 0 Cum @ 1.00 per cum 600.00 =Rs 1 /-
PP16
PP17 Between 4.0m to 6.0m depth from ground level 0.00 Cu.M 241,071,826 241,072
PP17
PP17 Plant
Page 9 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP17 Plant- Excavation pl 0 cum @ ########## per cum =Rs 235,063 /-
PP17 Plant labour- Excavation dl 0 cum @ ########## per cum =Rs 6,008 /-
PP17
PP17 Labour
PP17 Misc excavation lc 0 Cum @ 1.00 per cum 120.00 =Rs 0 /-
PP17
PP17 Subcontract
PP17 Controlled blasting sc 0 Cum @ 1.00 per cum 600.00 =Rs 1 /-
PP17
PP18 Between 6.0m to 8.0m depth from ground level 0.00 Cu.M 241,071,856 241,072
PP18
PP18 Plant
PP18 Plant- Excavation pl 0 cum @ ########## per cum =Rs 235,063 /-
PP18 Plant labour- Excavation dl 0 cum @ ########## per cum =Rs 6,008 /-
PP18
PP18 Labour
PP18 Misc excavation lc 0 Cum @ 1.00 per cum 150.00 =Rs 0 /-
PP18
PP18 Subcontract
PP18 Controlled blasting sc 0 Cum @ 1.00 per cum 600.00 =Rs 1 /-
PP18
PP19 Between 8.0m to 10.0m depth from ground level 0.00 Cu.M 241,071,906 241,072
PP19
PP19 Plant
PP19 Plant- Excavation pl 0 cum @ ########## per cum =Rs 235,063 /-
PP19 Plant labour- Excavation dl 0 cum @ ########## per cum =Rs 6,008 /-
PP19
PP19 Labour
PP19 Misc excavation lc 0 Cum @ 1.00 per cum 200.00 =Rs 0 /-
PP19
PP19 Subcontract
PP19 Controlled blasting sc 0 Cum @ 1.00 per cum 600.00 =Rs 1 /-
PP19
PP20 Disposal of surplus excavated earth beyond a lead of 4.0KM but anywhere within plant boundary as directed by the Engineer dumping and leveling the area from where the dumped earth is to be transported complete with all lifts as specified and directed by Engineer. 13,705.68 Cu.M 415 5,682,896
PP20
PP20 Plant
PP20 Plant- Disposal pl 13706 cum @ 404.64 per cum =Rs 5,545,839 /-
PP20 Plant labour- Disposal dl 13706 cum @ per cum =Rs /-
PP20
PP20 Labour
PP20 Misc disposal lc 13706 Cum @ 1.00 per cum 10.00 =Rs 137,057 /-
PP20
PP21 Earthwork in Backfilling around foundations in plinths etcto proper grade and level with selected material within a lead of 1.0 KM from available excavated soil includingre- excavating loose thickness watering and ramming in layers with proper compaction as per specification and direction of Engineer. 30,746.17 Cu.M 305 9,382,448
PP21
PP21 Plant
PP21 Plant- backfill pl 30746 cum @ 285.16 per cum =Rs 8,767,524 /-
Page 10 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP21 Plant labour- backfill dl 30746 cum @ per cum =Rs /-
PP21
PP21 Labour
PP21 Labour misc lc 30746 cum @ 1.00 per cum 20 =Rs 614,923 /-
PP21
PP22 Supply and Laying sand under floor, foundations & Plinthsincluding cost of sand, transporting for all leads, loading, unloading & spreading in layers of 250 mm thickness at all depths, watering, compaction complete as per specification and direction of Engineer. 0.00 Cu.M 645 1
PP22
PP22 Material
PP22 Sand - filing sd 0 cum @ 1.20 per cum 300 =Rs 0 /-
PP22
PP22 Plant
PP22 Plant- backfill pl 0 cum @ 285.16 per cum =Rs 0 /-
PP22 Plant labour- backfill dl 0 cum @ per cum =Rs /-
PP22
PP22 Labour
PP22 Labour misc lc 0 cum @ 1.00 per cum =Rs /-
PP22
PP23 Providing and Laying rubble soiling with specified sizes ofapproved quality hard rock rubble or hard broken hard metal of sizes ranging from 100 mm to 230 mm below finished ground floor level, below foundation hand packing, filling in interstices with sand including watering thoroughly compacting the layer all complete as per drawings and direction of Engineer. 661.21 Cu.M 1,620 1,071,153
PP23
PP23 Material
PP23 Rubble agg 661 cum @ 1.00 per cum 1230 =Rs 813,283 /-
PP23 Sand - filing sd 661 cum @ 0.30 per cum 300 =Rs 59,509 /-
PP23
PP23 Labour
PP23 Laying rubble soiling lc 661 cum @ 1.00 per cum 300 =Rs 198,362 /-
PP23
PP23 Subcontract
PP23 sc 661 cum @ 1.00 per cum =Rs /-
PP23
PP24 Providing & laying of approved quality hard crushed stonemetal size 40 mm average thickness in transformer yard, stacker area and in other places where required as per drawing including loading, unloading & transportation spreading, compacting, all labour, materials complete. 0.00 Cu.M 1,510 2
PP24
PP24 Material
PP24 Aggregate 40mm agg 0 cum @ 1.05 per cum 1200 =Rs 1 /-
PP24 sd 0 cum @ 1.00 per cum =Rs /-
PP24
PP24 Labour
PP24 Labour misc lc 0 cum @ 1.00 per cum 250 =Rs 0 /-
PP24
PP24 Subcontract
PP24 sc 0 cum @ 1.00 per cum =Rs /-
PP24
PP25 Providing & laying of approved quality hard crushed stonemetal size 10 mm average thickness in transformer yard, stacker area and in other places where required as per drawing including loading, unloading & transportation complete. 0.00 Cu.M 1,668 2
PP25
PP25 Material =Rs /-
PP25 Aggregate 10mm agg 0 cum @ 1.05 per cum 1350 =Rs 1 /-
PP25
Page 11 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP25 Labour
PP25 Labour misc lc 0 cum @ 1.00 per cum 250 =Rs 0 /-
PP25
PP25 Subcontract
PP25 sc 0 cum @ 1.00 per cum =Rs /-
PP25
PP26 PLAIN AND REINFORCED CEMENT CONCRETE
PP27 The following items shall be read along with GeneralNotes.
PP28 Supplying and laying in position plain cement concrete offollowing nominal mix (by volume) using graded crushed stone (20 mm down) as coarse aggregate including mixing, conveying, laying, compacting and curing etc. complete as per drawings specification and directions of Engineer.
PP29 M-10 1,287.33 Cu.M 6,013 7,741,249
PP29 2% 1313 wastage conc
PP29 Material
PP29 Cement - OPC c 1313 cum @ 220 Kg / Cum 6.57 =Rs 1,896,923 /-
PP29 Coarse Aggregate - 20 mm down agg 1313 cum @ 0.87 cum / mtr 1,500 =Rs 1,707,659 /-
PP29 Sand - Coarse sd 1313 cum @ 0.47 cum / mtr 425 =Rs 263,683 /-
PP29 Plasticiser - SP430 SRV o 1313 cum @ 2.20 Kg / cum 45 =Rs 129,995 /-
PP29 Shuttering shu 1287 cum @ 1.00 cum / cum =Rs /-
PP29
PP29 Labour
PP29 Shutter mat +lab for PCC works lc 1287 Cu.M 0.10 Sqm / cum 450 =Rs 57,930 /-
PP29 Cement Feeding etc lc 1313 Cum @ 4.40 bag/Cum 2.00 =Rs 11,555 /-
PP29 Concrete pouring lc 1313 Cum @ 1.00 Cum / Cum 125 =Rs 164,135 /-
PP29
PP29 Plant
PP29 Plant- Conc Manf pl 1287 cum @ 1,465.75 per cum =Rs 1,886,910 /-
PP29 Plant labour- Manf dl 1287 cum @ 184.91 per cum =Rs 238,041 /-
PP29 Plant- Conc- insitu pouring pl cum @ ########## per cum =Rs /-
PP29 Plant labour- Insitu pouring dl cum @ ########## per cum =Rs /-
PP29 Plant- Conc- Misc pl 1287 cum @ 1,058.31 per cum =Rs 1,362,399 /-
PP29 Plant labour- Misc dl 1287 cum @ 17.10 per cum =Rs 22,019 /-
PP29
PP30 Supplying, laying, finishing and curing of following screedconcrete with 10 mm downgraded crushed stone over RCC roof and trenches etc. including cleaning and backing of surface before laying as per drawings and specification.
PP31 M-15 3,762.00 Cu.M 6,304 23,717,105
PP31 2% 3837 wastage conc
PP31 Material
PP31 Cement - OPC c 3837 cum @ 270 Kg / Cum 6.57 =Rs 6,803,289 /-
PP31 Coarse Aggregate - 10 mm down agg 3837 cum @ 0.87 cum / mtr 1,350 =Rs 4,491,298 /-
PP31 Sand - Coarse sd 3837 cum @ 0.47 cum / mtr 425 =Rs 770,566 /-
PP31 Plasticiser - SP430 SRV o 3837 cum @ 2.70 Kg / cum 45 =Rs 466,225 /-
PP31 Shuttering shu 3762 cum @ 1.00 cum / cum =Rs /-
PP31
PP31 Labour
PP31 Shutter mat +lab for PCC works lc 3762 Cu.M 0.10 Sqm / cum 450 =Rs 169,290 /-
PP31 Cement Feeding etc lc 3837 Cum @ 5.40 bag/Cum 2.00 =Rs 41,442 /-
PP31 Concrete pouring lc 3837 Cum @ 1.50 Cum / Cum 125 =Rs 719,483 /-
PP31
Page 12 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP31 Plant
PP31 Plant- Conc Manf pl 3762 cum @ 1,465.75 per cum =Rs 5,514,162 /-
PP31 Plant labour- Manf dl 3762 cum @ 184.91 per cum =Rs 695,633 /-
PP31 Plant- Conc- insitu pouring pl cum @ per cum =Rs /-
PP31 Plant labour- Insitu pouring dl cum @ per cum =Rs /-
PP31 Plant- Conc- Misc pl 3762 cum @ 1,058.31 per cum =Rs 3,981,371 /-
PP31 Plant labour- Misc dl 3762 cum @ 17.10 per cum =Rs 64,348 /-
PP31
PP32 Supplying and laying in position design mix cementconcrete of following grades for reinforced concrete work in foundation and substructure in all kinds of work using graded crushed stone (20 mm down) as coarse aggregate including mixing, conveying, laying, compacting and curing etc. complete as per drawings, specifications and directions of the Engineer.
PP33 M - 20 0.00 Cu.M 65,616 66
PP33 1% 0 wastage conc
PP33 Material
PP33 Cement - OPC c 0 cum @ 300 Kg / Cum 6.57 =Rs 2 /-
PP33 Coarse Aggregate - 20 mm down agg 0 cum @ 0.87 cum / mtr 1,500 =Rs 1 /-
PP33 Sand - Coarse sd 0 cum @ 0.47 cum / mtr 425 =Rs 0 /-
PP33 Plasticiser - SP430 SRV o 0 cum @ 3.00 Kg / cum 45 =Rs 0 /-
PP33 Shuttering shu 0 cum @ 1.00 cum / cum =Rs /-
PP33
PP33 Labour
PP33 Shutter mat +lab for PCC works lc 0 Cu.M 0.10 Sqm / cum =Rs /-
PP33 Cement Feeding etc lc 0 Cum @ 6.00 bag/Cum 2.00 =Rs 0 /-
PP33 Concrete pouring lc 0 Cum @ 1.00 Cum / Cum 150 =Rs 0 /-
PP33
PP33 Plant
PP33 Plant- Conc Manf pl 0 cum @ 1,465.75 per cum =Rs 1 /-
PP33 Plant labour- Manf dl 0 cum @ 184.91 per cum =Rs 0 /-
PP33 Plant- Conc- insitu pouring: substruct pl 0 cum @ 55,865.22 per cum =Rs 56 /-
PP33 Plant labour- Insitu pouring dl 0 cum @ 3,218.83 per cum =Rs 3 /-
PP33 Plant- Conc- Misc pl 0 cum @ 1,058.31 per cum =Rs 1 /-
PP33 Plant labour- Misc dl 0 cum @ 17.10 per cum =Rs 0 /-
PP33
PP34 M - 25 472.50 Cu.M 65,759 31,070,713
PP34 1% 477 wastage conc
PP34 Material
PP34 Cement - OPC c 477 cum @ 320 Kg / Cum 6.57 =Rs 1,002,781 /-
PP34 Coarse Aggregate - 20 mm down agg 477 cum @ 0.87 cum / mtr 1,500 =Rs 620,626 /-
PP34 Sand - Coarse sd 477 cum @ 0.47 cum / mtr 425 =Rs 95,832 /-
PP34 Plasticiser - SP430 SRV o 477 cum @ 3.20 Kg / cum 45 =Rs 68,720 /-
PP34 Shuttering shu 472 cum @ 1.00 cum / cum =Rs /-
PP34
PP34 Labour
PP34 Shutter lab lc 472 Cu.M 0.10 Sqm / cum =Rs /-
PP34 Cement Feeding etc lc 477 Cum @ 6.40 bag/Cum 2.00 =Rs 6,108 /-
PP34 Concrete pouring lc 477 Cum @ 1.00 Cum / Cum 150 =Rs 71,583 /-
PP34
PP34 Plant
Page 13 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP34 Plant- Conc Manf pl 472 cum @ 1,465.75 per cum =Rs 692,563 /-
PP34 Plant labour- Manf dl 472 cum @ 184.91 per cum =Rs 87,369 /-
PP34 Plant- Conc- insitu pouring: substruct pl 472 cum @ 55,865.22 per cum =Rs 26,396,112 /-
PP34 Plant labour- Insitu pouring dl 472 cum @ 3,218.83 per cum =Rs 1,520,887 /-
PP34 Plant- Conc- Misc pl 472 cum @ 1,058.31 per cum =Rs 500,049 /-
PP34 Plant labour- Misc dl 472 cum @ 17.10 per cum =Rs 8,082 /-
PP34
PP35 Extra over above item (12-a-ii) above for supplying and using special admixtures / plasticizers for producing Self Compacting Concrete (SCC) with a Slump value of 660 mm to 750 mm and Passing ability of 60 mm to 80 mm.Admixtures shall be of M/s. BASF / Sunandha Chemicalsor equivalent make, for small column and thin walled section concreting including additional precaution to ensure leak proof shuttering with smooth surface. 0.00 Cu.M 1,088 1
PP35 0 wastage conc
PP35 Material
PP35 Cement - OPC c 0 cum @ 320 Kg / Cum =Rs /-
PP35 Coarse Aggregate - 20 mm down agg 0 cum @ 0.87 cum / mtr =Rs /-
PP35 Sand - Coarse sd 0 cum @ 0.47 cum / mtr =Rs /-
PP35 Plasticiser Self compacting 2% o 0 cum @ 6.40 Kg / cum 170 =Rs 1 /-
PP35
PP36 Supplying and laying in position design mix cementconcrete of following grades for reinforced concrete work in superstructure in all kinds of work using graded crushed stone (20 mm down) as coarse aggregate including mixing, conveying, laying, compacting and curing etc. complete as per drawings, specifications and directions of the Engineer.
PP37 M - 25 0.00 Cu.M 6,514,000,870 6,514,001
PP37 1% 0 wastage conc
PP37 Material
PP37 Cement - OPC c 0 cum @ 320 Kg / Cum 6.57 =Rs 2 /-
PP37 Coarse Aggregate - 20 mm down agg 0 cum @ 0.87 cum / mtr 1,500 =Rs 1 /-
PP37 Sand - Coarse sd 0 cum @ 0.47 cum / mtr 425 =Rs 0 /-
PP37 Plasticiser - SP430 SRV o 0 cum @ 3.20 Kg / cum 45 =Rs 0 /-
PP37 Shuttering shu 0 cum @ 1.00 cum / cum =Rs /-
PP37
PP37 Labour
PP37 Shutter lab lc 0 Cu.M 0.10 Sqm / cum =Rs /-
PP37 Cement Feeding etc lc 0 Cum @ 6.40 bag/Cum 2.00 =Rs 0 /-
PP37 Concrete pouring lc 0 Cum @ 1.00 Cum / Cum 150 =Rs 0 /-
PP37
PP37 Plant
PP37 Plant- Conc Manf pl 0 cum @ 1,465.75 per cum =Rs 1 /-
PP37 Plant labour- Manf dl 0 cum @ 184.91 per cum =Rs 0 /-
PP37 Plant- Conc- insitu pouring: super struct pl 0 cum @ ########## per cum =Rs 6,159,119 /-
PP37 Plant labour- Insitu pouring dl 0 cum @ ########## per cum =Rs 354,875 /-
PP37 Plant- Conc- Misc pl 0 cum @ 1,058.31 per cum =Rs 1 /-
PP37 Plant labour- Misc dl 0 cum @ 17.10 per cum =Rs 0 /-
PP37
PP38 Extra over above item (12-b-i) above for supplying andusing special admixtures / plasticizers for producing SelfCompacting Concrete (SCC) with a Slump value of 660 mm to 750 mm and Passing ability of 60 mm to 80 mm. Admixtures shall be of M/s. BASF / Sunandha Chemicalsor equivalent make, for small column and thin walledsection concreting including additional precaution to ensure leak proof shuttering with smooth surface. 0.00 Cu.M 1,088 1
PP38 0 wastage conc
PP38 Material
PP38 Cement - OPC c 0 cum @ 320 Kg / Cum =Rs /-
PP38 Coarse Aggregate - 20 mm down agg 0 cum @ 0.87 cum / mtr =Rs /-
PP38 Sand - Coarse sd 0 cum @ 0.47 cum / mtr =Rs /-
PP38 Plasticiser Self compacting 2% o 0 cum @ 6.40 Kg / cum 170 =Rs 1 /-
PP38
Page 14 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP39 Supplying and laying in position design mix cementconcrete of following grades for reinforced concrete works in T.G. Foundation using graded crushed stone (20 mm down) as coarse aggregate including mixing, conveying, laying, compacting and curing of concrete by the application of a membrane curing compound to all concrete surfaces. The compound shall conform to ASTM C 309, Type I with white pigmentation and shall be applied by a sprayer. etc. complete as per drawings, specifications and directions of the Engineer.
PP40 M - 30 9,192.30 Cu.M 8,063 74,117,032
PP40 1% 9284 wastage conc
PP40 Material
PP40 Cement - OPC c 9284 cum @ 360 Kg / Cum 7.93 =Rs 26,505,792 /-
PP40 Coarse Aggregate - 20 mm down agg 9284 cum @ 0.87 cum / mtr 1,500 =Rs 12,074,127 /-
PP40 Sand - Coarse sd 9284 cum @ 0.47 cum / mtr 425 =Rs 1,864,387 /-
PP40 Plasticiser - SP430 SRV o 9284 cum @ 3.60 Kg / cum 45 =Rs 1,504,043 /-
PP40 Curing compound - NOT REQD o 9284 cum @ Sqm / cum 12 =Rs /-
PP40 Shuttering shu 9192 cum @ 1.00 Sqm / cum =Rs /-
PP40
PP40 Labour
PP40 Shutter lab lc 9192 Cu.M 1.00 Sqm / cum =Rs /-
PP40 Cement Feeding etc lc 9284 Cum @ 7.20 bag/Cum 2.00 =Rs 133,693 /-
PP40 Concrete pouring lc 9284 Cum @ 1.00 Cum / Cum 150 =Rs 1,392,633 /-
PP40
PP40 Plant
PP40 Plant- Conc Manf pl 9192 cum @ 1,465.75 per cum =Rs 13,473,633 /-
PP40 Plant labour- Manf dl 9192 cum @ 184.91 per cum =Rs 1,699,750 /-
PP40 Plant- Conc- insitu pouring: TG pl 9192 cum @ 574.31 per cum =Rs 5,279,244 /-
PP40 Plant labour- Insitu pouring dl 9192 cum @ 33.09 per cum =Rs 304,179 /-
PP40 Plant- Conc- Misc pl 9192 cum @ 1,058.31 per cum =Rs 9,728,320 /-
PP40 Plant labour- Misc dl 9192 cum @ 17.10 per cum =Rs 157,232 /-
PP40
PP41 M - 35 0.00 Cu.M 8,464 8
PP41 1% 0 wastage conc
PP41 Material
PP41 Cement - OPC c 0 cum @ 400 Kg / Cum 7.93 =Rs 3 /-
PP41 Coarse Aggregate - 20 mm down agg 0 cum @ 0.87 cum / mtr 1,500 =Rs 1 /-
PP41 Sand - Coarse sd 0 cum @ 0.47 cum / mtr 425 =Rs 0 /-
PP41 Plasticiser - SP430 SRV o 0 cum @ 4.00 Kg / cum 45 =Rs 0 /-
PP41 Curing compound o 0 cum @ 5.00 Sqm / cum 12 =Rs 0 /-
PP41 Shuttering shu 0 cum @ 1.00 Sqm / cum =Rs /-
PP41
PP41 Labour
PP41 Shutter lab lc 0 Cu.M 1.00 Sqm / cum =Rs /-
PP41 Cement Feeding etc lc 0 Cum @ 8.00 bag/Cum 2.00 =Rs 0 /-
PP41 Concrete pouring lc 0 Cum @ 1.00 Cum / Cum 150 =Rs 0 /-
PP41
PP41 Plant
PP41 Plant- Conc Manf pl 0 cum @ 1,465.75 per cum =Rs 1 /-
PP41 Plant labour- Manf dl 0 cum @ 184.91 per cum =Rs 0 /-
PP41 Plant- Conc- insitu pouring: TG pl 0 cum @ 574.31 per cum =Rs 1 /-
PP41 Plant labour- Insitu pouring dl 0 cum @ 33.09 per cum =Rs 0 /-
PP41 Plant- Conc- Misc pl 0 cum @ 1,058.31 per cum =Rs 1 /-
PP41 Plant labour- Misc dl 0 cum @ 17.10 per cum =Rs 0 /-
Page 15 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP41
PP42 Extra over above item (12-c-i & ii) above for supplying andusing special admixtures / plasticizers for producing Self Compacting Concrete (SCC) with a Slump value of 660 mm to 750 mm and Passing ability of 60 mm to 80 mm. Admixtures shall be of M/s. BASF / Sunandha Chemicals or equivalent make including additional precaution to ensure leak proof shuttering with smooth surface. 0.00 Cu.M 680 1
PP42 0 wastage conc M35
PP42 Material
PP42 Cement - OPC c 0 cum @ 400 Kg / Cum =Rs /-
PP42 Coarse Aggregate - 20 mm down agg 0 cum @ 0.87 cum / mtr =Rs /-
PP42 Sand - Coarse sd 0 cum @ 0.47 cum / mtr =Rs /-
PP42 Plasticiser Self compacting 1% o 0 cum @ 4.00 Kg / cum 170 =Rs 1 /-
PP42
PP43 Carrying our Ultrasonic Pulse Velocity (UPV) testing fortop deck of TG complete as per specification, drawing and direction of Engineer including labour, machinery and submission of test results complete 0.00 LSfor each TG 1,300,000 1,300

Material
o 0 cum @ 1.00 per cum =Rs /-

Labour
lc 0 cum @ 1.00 per cum =Rs /-

Subcontract
sc 0 cum @ 1.00 per cum 1300000 =Rs 1,300 /-

PP44 Supplying and laying in position design mix cement concrete of following grades forreinforced concrete work inEquipment foundations / Block foundations using graded crushed stone (20 mm down) as coarse aggregate including mixing, conveying, laying, compacting and curing ofconcrete by the application of a membrane curingcompound to all concrete surfaces. The compound shall conform to ASTM C 309, Type I with white pigmentation and shall be applied by a sprayer. etc. complete as per drawings, specifications and directions of the Engineer.
PP45 M - 35 0.00 Cu.M 66,529 67
PP45 1% 0 wastage conc
PP45 Material
PP45 Cement - OPC c 0 cum @ 400 Kg / Cum 6.57 =Rs 3 /-
PP45 Coarse Aggregate - 20 mm down agg 0 cum @ 0.87 cum / mtr 1,500 =Rs 1 /-
PP45 Sand - Coarse sd 0 cum @ 0.47 cum / mtr 425 =Rs 0 /-
PP45 Plasticiser - SP430 SRV o 0 cum @ 4.00 Kg / cum 45 =Rs 0 /-
PP45 Shuttering shu 0 cum @ 1.00 cum / cum =Rs /-
PP45
PP45 Labour
PP45 Shutter mat +lab for PCC works lc 0 Cu.M 0.10 Sqm / cum =Rs /-
PP45 Cement Feeding etc lc 0 Cum @ 8.00 bag/Cum 2.00 =Rs 0 /-
PP45 Concrete pouring lc 0 Cum @ 1.00 Cum / Cum 150 =Rs 0 /-
PP45
PP45 Plant
PP45 Plant- Conc Manf pl 0 cum @ 1,465.75 per cum =Rs 1 /-
PP45 Plant labour- Manf dl 0 cum @ 184.91 per cum =Rs 0 /-
PP45 Plant- Conc- insitu pouring: substruct pl 0 cum @ 55,865.22 per cum =Rs 56 /-
PP45 Plant labour- Insitu pouring dl 0 cum @ 3,218.83 per cum =Rs 3 /-
PP45 Plant- Conc- Misc pl 0 cum @ 1,058.31 per cum =Rs 1 /-
PP45 Plant labour- Misc dl 0 cum @ 17.10 per cum =Rs 0 /-
PP45
PP45 Misc
PP45 White pigment sc 0 Cum @ 1.00 Cum / Cum 200 =Rs 0 /-
PP45 =Rs /-
Page 16 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP45
PP46 Extra over above item (12-d-i) above for supplying andusing special admixtures / plasticizers for producing Self Compacting Concrete (SCC) with a Slump value of 660 mm to 750 mm and Passing ability of 60 mm to 80 mm. Admixtures shall be of M/s. BASF / Sunandha Chemicals or equivalent make including additional precaution to ensure leak proof shuttering with smooth surface. 0.00 Cu.M 544 1
PP46 0 wastage conc
PP46 Material
PP46 Cement - OPC c 0 cum @ 320 Kg / Cum =Rs /-
PP46 Coarse Aggregate - 20 mm down agg 0 cum @ 0.87 cum / mtr =Rs /-
PP46 Sand - Coarse sd 0 cum @ 0.47 cum / mtr =Rs /-
PP46 Plasticiser Self compacting 1% o 0 cum @ 3.20 Kg / cum 170 =Rs 1 /-
PP46
PP47 Supplying and laying pre cast reinforced cement concreteelements cast at Project site with following grade of concrete at various elevations in all kinds of work including supply of materials, formwork, mixing, laying, compacting and curing, storing, handling, transporting, erection without damage, setting in position with cement sand mortar (1:2 by volume) grouting/welding etc. complete as per drawings, specification and direction of Engineer.
PP48 M - 25 0.00 Cu.M 6,514,005,785 6,514,006
PP48 2% 0 wastage conc
PP48 Material
PP48 Cement - OPC c 0 cum @ 320 Kg / Cum 6.57 =Rs 2 /-
PP48 Coarse Aggregate - 20 mm down agg 0 cum @ 0.87 cum / mtr 1,500 =Rs 1 /-
PP48 Sand - Coarse sd 0 cum @ 0.47 cum / mtr 425 =Rs 0 /-
PP48 Plasticiser - SP430 SRV o 0 cum @ 3.20 Kg / cum 45 =Rs 0 /-
PP48 Shuttering shu 0 cum @ 6.00 Sqm / cum 300 =Rs 2 /-
PP48
PP48 Labour
PP48 Shutter lab lc 0 Cu.M 6.00 Sqm / cum 250 =Rs 2 /-
PP48 Cement Feeding etc lc 0 Cum @ 6.40 bag/Cum 2.00 =Rs 0 /-
PP48 Concrete pouring lc 0 Cum @ 1.50 Cum / Cum 150 =Rs 0 /-
PP48
PP48 Plant
PP48 Plant- Conc Manf pl 0 cum @ 1,465.75 per cum =Rs 1 /-
PP48 Plant labour- Manf dl 0 cum @ 184.91 per cum =Rs 0 /-
PP48 Plant- Conc- insitu pouring pl 0 cum @ ########## per cum =Rs 6,159,119 /-
PP48 Plant labour- Insitu pouring dl 0 cum @ ########## per cum =Rs 354,875 /-
PP48 Plant- Conc- Misc pl 0 cum @ 1,058.31 per cum =Rs 1 /-
PP48 Plant labour- Misc dl 0 cum @ 17.10 per cum =Rs 0 /-
PP48
PP48 Labour
PP48 transporting, erection, misc lc 0 Cum @ 1.00 Cum / Cum 1,500 =Rs 2 /-
PP48
PP49 Providing and mixing as cement concrete admixtures -super plasticizers (including super plasticizers cum retarder, super plasticizers cum water proofing and super plasticizers cum. pumping aid for concrete), at all levels, for all kinds of works, including all labour, material,equipment, handling, transportation, testing, etc., all complete, as per specifications, drawings and instructions ofthe Engineer / manufacturers. 0.00 MT 187,000 187
PP49 0 wastage conc
PP49 Material
PP49 Plasticiser Self compacting 1% o 0 0.00 1,100 lit/MT 170 =Rs 187 /-
PP48
PP50 Dismantling concrete work (both PCC and RCC of allgrades), for all types of structures, at all levels, including alllabour,equipment, scaffolding,staging, stacking of serviceable material upto a lead of 500 m and disposal of unserviceable material upto a lead of 2 km beyond the plant boundary or as directed by the Engineer, cutting of reinforcement, propping, shoring, enclosures, including all labour, material, equipment, handling, transportation, etc., all complete, as per specifications, drawings and instructions of the Engineer. 0.00 Cu.m 1,500 2
PP50
PP50 Material
PP50 o 0 cum @ 1.00 per cum =Rs /-
PP50
PP50 Labour
Page 17 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP50 Dismantling concrete work (both PCC and RCC of allgrades), for all types of structures, at all levels, including alllabour,equipment, scaffolding,staging,stacking of serviceable material upto a lead of 500 m and disposal of unserviceable material upto a lead of 2 km beyond the plant boundary or as directed by the Engineer, cutting of reinforcement, propping, shoring, enclosures, including all labour, material, equipment, handling, transportation, etc., all complete, as per specifications, drawings and instructions of the Engineer. lc 0 cum @ 1.00 per cum 1500 =Rs 2 /-
PP50
PP50 Subcontract
PP50 sc 0 cum @ 1.00 per cum =Rs /-
PP50
PP51 Chipping of Cement Concrete work (both PCC and RCC),for all type of structures, at all levels, for making grooves, removing surface concrete etc., according to shapes, sizes and profiles as shown on the construction drawings, stacking of serviceable material upto a lead of 500 m, disposal of unserviceable material upto a lead of 2.00 km. beyond the plant boundary or as directed by the Engineer, cutting of reinforcement, including all labour, equipment, scaffolding, staging, handling, transportation, propping and shoring, enclosures, etc., all complete, as per specifications, drawings and instructions of the Engineer. 0.00 Cu.m 2,200 2
PP51
PP51 Material
PP51 o 0 cum @ 1.00 per cum =Rs /-
PP51
PP51 Labour
PP51 Chipping of Cement Concrete work (both PCC and RCC),for all type of structures, at all levels, for making grooves, removing surface concrete etc., according to shapes, sizes and profiles as shown on the construction drawings, stacking of serviceable material upto a lead of 500 m, disposal of unserviceable material upto a lead of 2.00 km. beyond the plant boundary or as directed by the Engineer, cutting of reinforcement, including all labour, equipment, scaffolding, staging, handling, transportation, propping and shoring, enclosures, etc., all complete, as per specifications, drawings and instructions of the Engineer. lc 0 cum @ 1.00 per cum 2200 =Rs 2 /-
PP51
PP51 Subcontract
PP51 sc 0 cum @ 1.00 per cum =Rs /-
PP51
PP52 Making of Circular opening of diameter varying from 25mm to 150 mm and depth upto 450 mm in cement concrete work (both PCC and RCC) of all grades, for all type of structures, at all levels and for all positions, by coring using diamond bits for pockets / thorough opening according to size as shown on the construction drawings, stacking of serviceable material upto a lead of 500 m, disposal of unserviceable material upto a lead of 2.00 km. beyond the plant boundary or as directed by the Engineer, finishing neatly the surface area of cement concrete exposed after creation of circular opening including all labour, equipment, scaffolding, staging, handling, transportation, propping and shoring, enclosures, etc., all complete, as per specifications, drawings and instructions of the Engineer. 0.00 Sq.m 7,200 7
PP52
PP52 Material
PP52 o 0 Sq.m 1.00 per cum =Rs /-
PP52
PP52 Labour
PP52 lc 0 Sq.m 1.00 per cum =Rs /-
PP52
PP52 Subcontract
PP52 Making of Circular opening of diameter varying from 25mm to 150 mm and depth upto 450 mm in cement concrete work (both PCC and RCC) of all grades, for all type of structures, at all levels and for all positions, by coring using diamond bits for pockets / thorough opening according to size as shown on the construction drawings, stacking of serviceable material upto a lead of 500 m, disposal of unserviceable material upto a lead of 2.00 km. beyond the plant boundary or as directed by the Engineer, finishing neatly the surface area of cement concrete exposed after creation of circular opening including all labour, equipment, scaffolding, staging, handling, transportation, propping and shoring, enclosures, etc., all complete, as per specifications, drawings and instructions of the Engineer. sc 0 Sq.m 1.00 per cum 7200 =Rs 7 /-
PP52
PP53 Making of slit type opening of rectangular, square and orsimilar shape of varying size (in plan) and depth upto 450 mm in cement concrete work (both PCC and RCC) of all grades, for all type of structures, at all levels and for all positions, by sawing using wall saw machine with on the construction drawings, locating the reinforcement before making the opening by use of rebar detector and obtaining specific clearance from the Engineer, if the cutting of the reinforcement bar are involved in the making of the opening, cutting of reinforcement, stacking of serviceable material upto a lead of 500 m, disposal of unserviceable material upto a lead of 2.00 Kms. beyond the plant boundary or as directed by the Engineer, finishing neatly the surface area of cement concrete exposed after creation of opening including all labour,equipment,scaffolding,staging, handling, transportation, propping and shoring, enclosures, etc., all complete, as per specifications, drawings and instructions of t 0.00 Sq.m 6,000 6
PP53
PP53 Material
PP53 o 0 Sq.m 1.00 per cum =Rs /-
PP53
PP53 Labour
PP53 lc 0 Sq.m 1.00 per cum =Rs /-
PP53
PP53 Subcontract
PP53 Making of slit type opening of rectangular, square and orsimilar shape of varying size (in plan) and depth upto 450 mm in cement concrete work (both PCC and RCC) of all grades, for all type of structures, at all levels and for all positions, by sawing using wall saw machine with on the construction drawings, locating the reinforcement before making the opening by use of rebar detector and obtaining specific clearance from the Engineer, if the cutting of the reinforcement bar are involved in the making of the opening, cutting of reinforcement, stacking of serviceable material upto a lead of 500 m, disposal of unserviceable material upto a lead of 2.00 Kms. beyond the plant boundary or as directed by the Engineer, finishing neatly the surface area of cement concrete exposed after creation of opening including all labour,equipment,scaffolding,staging,handling, transportation, propping and shoring, enclosures, etc., all complete, as per specifications, drawings and instructions of t sc 0 Sq.m 1.00 per cum 6000 =Rs 6 /-
PP53
PP54 Supplying, fabricating and installing following embeddeditems in cement concrete, as per drawings and specification including necessary templates :(Base rate of structural steel will be applied for this item)
PP55 Anchor bolt assembly complete with sleeves, nuts,washers, anchor plates, etc. 0.00 MT 141,105 141
PP55
PP55 Material
PP55 Anchor bolt SS 0 cum @ 1.00 per cum 122400 =Rs 122 /-
PP55
PP55 Labour
PP55 Fab+erection bolt assembly+ assembly lc 0 cum @ 1.00 per cum 15,000 =Rs 15 /-
Page 18 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP55
PP55 Subcontract
PP55 sc 0 cum @ 1.00 per cum =Rs /-
PP55
PP55 Plant
PP55 Plant- SS pl 0 cum @ 3,705.10 per MT =Rs 4 /-
PP55 Plant labour- SS dl 0 cum @ per MT =Rs /-
PP55
PP56 Insert plates, edge protection angles, pipe sleeves,hangers, conducts and other miscellaneous embeddedfixtures of MS, GI, WI, CI, cast steel or other metal items. 1.00 MT 80,811 80,811
PP56
PP56 Material
PP56 Structural steel SS 1 cum @ 1.10 per cum 45551 =Rs 50,106 /-
PP56
PP56 Labour
PP56 lc 1 cum @ 1.00 per cum =Rs /-
PP56
PP56 Subcontract
PP56 Fab+erection bolt assembly sc 1 cum @ 1.00 per cum 27000 =Rs 27,000 /-
PP56
PP56 Plant
PP56 Plant- SS pl 1 cum @ 3,705.10 per MT =Rs 3,705 /-
PP56 Plant labour- SS dl 1 cum @ per MT =Rs /-
PP56
PP57 Taking, delivery and installing following embedded Items incement concrete, as per drawings and specifications including necessary templates :
PP58 Anchor bolt assembly complete with sleeves, nuts,washers, anchor plates, etc. 0.00 MT 21,705 22
PP58
PP58 Material
PP58 Structural steel SS 0 cum @ per cum 45551 =Rs /-
PP58
PP58 Labour
PP58 lc 0 cum @ 1.00 per cum =Rs /-
PP58
PP58 Subcontract
PP58 Fab+erection bolt assembly sc 0 cum @ 1.00 per cum 18000 =Rs 18 /-
PP58
PP58 Plant
PP58 Plant- SS pl 0 cum @ 3,705.10 per MT =Rs 4 /-
PP58 Plant labour- SS dl 0 cum @ per MT =Rs /-
PP58
PP59 Insert plates, edge protection angles, pipe sleeves,hangers, conducts and other miscellaneous embedded fixtures of MS, GI, WI, CI, cast steel or other metal items. 0.00 MT 36,105 36
PP59
PP59 Material
PP59 Structural steel SS 0 cum @ per cum 45551 =Rs /-
PP59
PP59 Labour
PP59 lc 0 cum @ 1.00 per cum =Rs /-
Page 19 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP59
PP59 Subcontract
PP59 Fab+erection bolt assembly sc 0 cum @ 1.20 per cum 27000 =Rs 32 /-
PP59
PP59 Plant
PP59 Plant- SS pl 0 cum @ 3,705.10 per MT =Rs 4 /-
PP59 Plant labour- SS dl 0 cum @ per MT =Rs /-
PP59
PP60 Supply, fabrication and fixing of necessary templatesagainst item no 20-a above, if templates are not supplied by JPL. 0.00 MT 75,411 75
PP60
PP60 Material
PP60 Structural steel SS 0 cum @ 1.10 per cum 45551 =Rs 50 /-
PP60
PP60 Labour
PP60 lc 0 cum @ 1.00 per cum =Rs /-
PP60
PP60 Subcontract
PP60 Fab+erection bolt assembly sc 0 cum @ 1.20 per cum 18000 =Rs 22 /-
PP60
PP60 Plant
PP60 Plant- SS pl 0 cum @ 3,705.10 per MT =Rs 4 /-
PP60 Plant labour- SS dl 0 cum @ per MT =Rs /-
PP60
PP61 Forming expansion / isolation joints in concrete as perdrawings and specifications using Bitumen boards / expanded polystyrene boards complete with bitumen sealing compound including supply of all materials
PP62 12 mm Thick 8,997.17 Sq.M. 681 6,127,071
PP62
PP62 Material
PP62 Forming expansion / isolation joints in concrete as perdrawings and specifications using Bitumen boards / expanded polystyrene boards complete with bitumen sealing compound including supply of all materials o 8997 Sq.M. 1.00 per sqm 631 =Rs 5,677,213 /-
PP62
PP62 Labour
PP62 laying lc 8997 Sq.M. 1.00 per sqm 50 =Rs 449,858 /-
PP62
PP62 Subcontract
PP62 sc 8997 Sq.M. 1.00 per sqm =Rs /-
PP62
PP63 25 mm Thick 0.00 Sq.M. 906 1
PP63
PP63 Material
PP63 25 mm Thick o 0 Sq.M. 1.00 per sqm 831 =Rs 1 /-
PP63
PP63 Labour
PP63 laying lc 0 Sq.M. 1.00 per sqm 75 =Rs 0 /-
PP63
PP63 Subcontract
PP63 sc 0 Sq.M. 1.00 per sqm =Rs /-
PP63
Page 20 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP64 50 mm Thick 0.00 Sq.M. 1,231 1
PP64
PP64 Material
PP64 50 mm Thick o 0 Sq.M. 1.00 per sqm 1131 =Rs 1 /-
PP64
PP64 Labour
PP64 laying lc 0 Sq.M. 1.00 per sqm 100 =Rs 0 /-
PP64
PP64 Subcontract
PP64 sc 0 Sq.M. 1.00 per sqm =Rs /-
PP64
PP65 Supplying and filling the expansion joints of followingdimension with bitumen / other joint sealing compound confirming to IS : 1834 including through cleaning of the joints, as per manufacturer's specification and as directed by the Engineer.
PP66 25 mm x 25 mm 0.00 RM 50 0
PP66
PP66 Material
PP66 HD 100 o 0 RM 1.00 per Rm 30 =Rs 0 /-
PP66
PP66 Labour
PP66 laying lc 0 RM 1.00 per Rm 20 =Rs 0 /-
PP66
PP66 Subcontract
PP66 sc 0 RM 1.00 per Rm =Rs /-
PP66
PP67 Same as above item (22-a) but with Silica Sealant 0.00 RM 775 1
PP67
PP67 Material
PP67 Silica sealant o 0 RM 1.00 per Rm 675 =Rs 1 /-
PP67
PP67 Labour
PP67 laying lc 0 RM 1.00 per Rm 100 =Rs 0 /-
PP67
PP67 Subcontract
PP67 sc 0 RM 1.00 per Rm =Rs /-
PP67
PP68 Providing vertical expansion joint with polyurethane foamroad of required diameter and sealed with silicon sealantover road including fixing of rod with all materials complete at various elevations as per drawings and specifications similar to C/S Group & McCoy or approved equivalent.
PP69 25 wide with 25 x 12 poly-sulphide including fixing of 25 mmdia rod. 0.00 R.M. 1,261 1
PP69
PP69 Material
PP69 25 wide with 25 x 12 poly-sulphide including fixing of 25 mmdia rod. o 0 R.M. 1.10 per Rm 942 =Rs 1 /-
PP69
PP69 Labour
PP69 laying lc 0 R.M. 1.50 per Rm 150 =Rs 0 /-
PP69
PP69 Subcontract
PP69 sc 0 R.M. 1.00 per Rm =Rs /-
PP69
PP70 50 wide with 50 x 12 poly-sulphide including fixing of 50 mmdia rod. 0.00 R.M. 2,607 3
Page 21 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP70
PP70 Material
PP70 50 wide with 50 x 12 poly-sulphide including fixing of 50 mmdia rod. o 0 R.M. 1.10 per Rm 2098 =Rs 2 /-
PP70
PP70 Labour
PP70 laying lc 0 R.M. 1.50 per Rm 200 =Rs 0 /-
PP70
PP70 Subcontract
PP70 sc 0 R.M. 1.00 per Rm =Rs /-
PP70
PP71 Providing horizontal expansion joint on roof withpolyurethane foam rod and sealed with silicon sealant including fixing of rod complete with all materials joint filler, sealing compound, etc. as per drawing and specifications similar to C/S Group & McCoy or approved equivalent.
PP72 25 wide with 25 x 12 poly-sulphide including fixing of 25 mm dia rod. 0.00 R.M. 1,042 1
PP72
PP72 Material
PP72 25 wide with 25 x 12 poly-sulphide including fixing of 25 mm dia rod. o 0 R.M. 1.00 per Rm 942 =Rs 1 /-
PP72
PP72 Labour
PP72 laying lc 0 R.M. 1.00 per Rm 100 =Rs 0 /-
PP72
PP72 Subcontract
PP72 sc 0 R.M. 1.00 per Rm =Rs /-
PP72
PP73 50 wide with 50 x 12 poly-sulphide including fixing of 50 mmdia rod. 0.00 R.M. 2,248 2
PP73
PP73 Material
PP73 50 wide with 50 x 12 poly-sulphide including fixing of 50 mmdia rod. o 0 R.M. 1.00 per Rm 2098 =Rs 2 /-
PP73
PP73 Labour
PP73 laying lc 0 R.M. 1.00 per Rm 150 =Rs 0 /-
PP73
PP73 Subcontract
PP73 sc 0 R.M. 1.00 per Rm =Rs /-
PP73
PP74 Providing & Fixing desired thickness of SIL FIL of DawnColor, manufactured by The Supreme Industries Limited or equivalent, thickness built up using minimum 10 mm specifically extruded high performance sheet, minimum density 30 kg/ cum & compression strength of 0.21 kg/sqm, when tested as per ASTM D-3575, including using double sided adhesive SIL SEAM TAPE(manufactured by The Supreme Industries Limited) or equivalent of 2 mm x 25 mm x25 mm at four places per sq.mtr to the casted surface to form the expansion joint. SIL FIL will become one side of the shuttering while the expansion joint is being created. 0.00 Sq.M. 636 1
PP74
PP74 Material
PP74 o 0 Sq.M. 1.00 per sqm =Rs /-
PP74
PP74 Labour
PP74 lc 0 Sq.M. 1.00 per sqm =Rs /-
PP74
PP74 Subcontract
PP74 Providing & Fixing desired thickness of SIL FIL of DawnColor, manufactured by The Supreme Industries Limited or equivalent, thickness built up using minimum 10 mm specifically extruded high performance sheet, minimum density 30 kg/ cum & compression strength of 0.21 kg/sqm, when tested as per ASTM D-3575, including using double sided adhesive SIL SEAM TAPE(manufactured by The Supreme Industries Limited) or equivalent of 2 mm x 25 mm x25 mm at four places per sq.mtr to the casted surface to form the expansion joint. SIL FIL will become one side of the shuttering while the expansion joint is being created. sc 0 Sq.M. 1.00 per sqm 636 =Rs 1 /-
PP74
PP75 Supplying and installing ribbed water stops with centralbulbs as per relevant Indian Standards, drawings and specification
PP76 230 mm x 6 mm 4,834.10 RM 300 1,450,230
Page 22 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP76
PP76 Material
PP76 230 mm x 6 mm o 4834 RM 1.00 per Rm 250 =Rs 1,208,525 /-
PP76
PP76 Labour
PP76 laying lc 4834 RM 1.00 per Rm 50 =Rs 241,705 /-
PP76
PP76 Subcontract
PP76 sc 4834 RM 1.00 per Rm =Rs /-
PP76
PP77 230 mm x 8 mm 0.00 RM 370 0
PP77
PP77 Material
PP77 230 mm x 8 mm o 0 RM 1.00 per Rm 320 =Rs 0 /-
PP77
PP77 Labour
PP77 laying lc 0 RM 1.00 per Rm 50 =Rs 0 /-
PP77
PP77 Subcontract
PP77 sc 0 RM 1.00 per Rm =Rs /-
PP77
PP78 150 mm x 6 mm 0.00 RM 280 0
PP78
PP78 Material
PP78 150 mm x 6 mm o 0 RM 1.00 per Rm 230 =Rs 0 /-
PP78
PP78 Labour
PP78 laying lc 0 RM 1.00 per Rm 50 =Rs 0 /-
PP78
PP78 Subcontract
PP78 sc 0 RM 1.00 per Rm =Rs /-
PP78
PP79 150 mm x 8 mm 0.00 RM 300 0
PP79
PP79 Material
PP79 150 mm x 8 mm o 0 RM 1.00 per Rm 250 =Rs 0 /-
PP79
PP79 Labour
PP79 laying lc 0 RM 1.00 per Rm 50 =Rs 0 /-
PP79
PP79 Subcontract
PP79 sc 0 RM 1.00 per Rm =Rs /-
PP79
PP80 Providing and placing in position at ground floor level,building paper (kraft paper) of 250 micron as per IS : 1397between the concrete surfaces including the cost of all labours, materials etc. complete as per drawings, specifications as directed by the Engineer in charge. 0.00 Sq.M. 50 0
PP80
PP80 Material
Page 23 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP80 Providing and placing in position at ground floor level,building paper (kraft paper) of 250 micron as per IS : 1397between the concrete surfaces including the cost of all labours, materials etc. complete as per drawings, specifications as directed by the Engineer in charge. o 0 Sq.M. 1.00 per sqm =Rs /-
PP80
PP80 Labour
PP80 laying lc 0 Sq.M. 1.00 per sqm =Rs /-
PP80
PP80 Subcontract
PP80 Providing and placing in position at ground floor level,building paper (kraft paper) of 250 micron as per IS : 1397between the concrete surfaces including the cost of all labours, materials etc. complete as per drawings, specifications as directed by the Engineer in charge. sc 0 Sq.M. 1.00 per sqm 50 =Rs 0 /-
PP80
PP81 Providing, applying and painting 85/25 industrial grade hotbitumen at the rate of 1.2 kg/sqm or 0.4 kg/sqm overconcrete surface after cleaning with brushes and finally with cloth soaked kerosene oil.
PP82 1.2 kg/sqm 0.00 Sq.M. 116 0
PP82
PP82 Material
PP82 o 0 Sq.M. 1.00 per sqm =Rs /-
PP82
PP82 Labour
PP82 lc 0 Sq.M. 1.00 per sqm =Rs /-
PP82
PP82 Subcontract
PP82 1.2 kg/sqm sc 0 Sq.M. 1.00 per sqm 116 =Rs 0 /-
PP82
PP83 0.4 kg/sq.m 0.00 Sq.M. 59 0
PP83
PP83 Material
PP83 o 0 Sq.M. 1.00 per sqm =Rs /-
PP83
PP83 Labour
PP83 lc 0 Sq.M. 1.00 per sqm =Rs /-
PP83
PP83 Subcontract
PP83 0.4 kg/sq.m sc 0 Sq.M. 1.00 per sqm 59 =Rs 0 /-
PP83
PP84 Providing, mixing and laying in position and curing ordinaryplum concrete of mix 1:4:8 mix using size less than 80 mm boulder as coarse aggregate as per drawing and specification and direction of Engineer at all locations for ground filling. 0.00 Cu.M 3,898 4
PP84
PP84 Material
PP84 o 0 cum @ 1.00 per cum =Rs /-
PP84
PP84 Labour
PP84 lc 0 cum @ 1.00 per cum =Rs /-
PP84
PP84 Subcontract
PP84 Providing, mixing and laying in position and curing ordinaryplum concrete of mix 1:4:8 mix using size less than 80 mm boulder as coarse aggregate as per drawing and specification and direction of Engineer at all locations for ground filling. sc 0 cum @ 1.00 per cum 3898 =Rs 4 /-
PP84
PP85 Supplying & laying of transformer rail 52 kg/m includingfixing with guard angle & U-bolts and whatever necessarycomplete as per approved drawing & direction of Engineer. 0.00 MT 77,330 77
PP85
PP85 Material
PP85 rail o 0 MT 1.05 per MT 54600 =Rs 57 /-
Page 24 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP85
PP85 Labour
PP85 Fab+erection with bolts lc 0 MT 1.00 per MT 20,000 =Rs 20 /-
PP85
PP85 Subcontract
PP85 sc 0 MT 1.00 per MT =Rs /-
PP85
PP86 Supplying necessary materials and grouting under columnbase using following flowable grout including preparation of concrete surfaces complete as per specification and instruction of Engineer (No formwork to be paid separately)
PP87 Ordinary grout with 1:2 cement : sand mix 0.00 Cu.M 6,683 7
PP87
PP87 Material
PP87 sand 80% extra sd 0 cum @ 1.2 per cum 425 =Rs 1 /-
PP87 cement 80% extra c 0 cum @ 864 kg per cum 7 =Rs 6 /-
PP87
PP87 Labour
PP87 pouring lc 0 cum @ 1.00 per cum 500 =Rs 1 /-
PP87
PP87 Subcontract
PP87 sc 0 cum @ 1.00 per cum =Rs /-
PP87
PP88 Non- shrink grout of approved make (Combextra GP1 orequivalent) 0.00 Cu.M 86,000 86
PP88
PP88 Material
PP88 GP1 o 0 cum @ 120.00 bags per cum 550 =Rs 66 /-
PP88
PP88 Labour
PP88 pouring lc 0 cum @ 1.00 per cum 20000 =Rs 20 /-
PP88
PP88 Subcontract
PP88 sc 0 cum @ 1.00 per cum =Rs /-
PP88
PP89 Concrete mix 1:1:2 (1 part Cement : 1 part Sand : 2 parts of6 mm downgraded stone chips) with non-shrink hand grout using approved admixture. 0.00 Cu.M 6,016 6
PP89
PP89 Material
PP89 sand 80% extra sd 0 cum @ 0.5 per cum 425 =Rs 0 /-
PP89 cement 80% extra c 0 cum @ 648 kg per cum 7 =Rs 4 /-
PP89 agg agg 0 cum @ 1 kg per cum 1300 =Rs 1 /-
PP89
PP89 Labour
PP89 pouring lc 0 cum @ 1.00 per cum 400 =Rs 0 /-
PP89
PP89 Subcontract
PP89 sc 0 cum @ 1.00 per cum =Rs /-
PP89
PP90 Taking, delivery of grouting material from store andgrouting for equipment foundations including preparation of concrete surfaces for TG level and other equipment foundations complete as per specifications and directions of Engineer (No formwork to be paid separately) 0.00 Cu.M 28,000 28
PP90
Page 25 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP90 Material
PP90 o 0 cum @ 1.00 per cum =Rs /-
PP90
PP90 Labour
PP90 pouring lc 0 cum @ 1.00 per cum 28000 =Rs 28 /-
PP90
PP90 Subcontract
PP90 sc 0 cum @ 1.00 per cum =Rs /-
PP90
PP91 Same as item no. (32) above except when non-shrinkgrout of approved make (Combextra GP2 or equivalent)are supplied by contractor. 0.00 Cu.M 30,000 30
PP91
PP91 Material
PP91 o 0 cum @ 1.00 per cum =Rs /-
PP91
PP91 Labour
PP91 pouring lc 0 cum @ 1.00 per cum 30000 =Rs 30 /-
PP91
PP91 Subcontract
PP91 sc 0 cum @ 1.00 per cum =Rs /-
PP91
PP92 Supplying and providing injection of cement mortar withapprovedwaterproofinggroutingcompoundat construction joints in concrete under pressure through nozzles along the joint including installation of 12 / 18 mm dia threaded nozzles in concrete, grouting, sealing the nozzles etc. all complete as per drawings, specification and direction of Engineer. 0.00 Each 900 1
PP92
PP92 Material
PP92 o 0 Each 1.00 per each =Rs /-
PP92
PP92 Labour
PP92 lc 0 Each 1.00 per each =Rs /-
PP92
PP92 Subcontract
PP92 Supplying and providing injection of cement mortar withapprovedwaterproofinggroutingcompoundat construction joints in concrete under pressure through nozzles along the joint including installation of 12 / 18 mm dia threaded nozzles in concrete, grouting, sealing the nozzles etc. all complete as per drawings, specification and direction of Engineer. sc 0 Each 1.00 per each 900 =Rs 1 /-
PP92
PP93 Providing, applying and fixing in position in line and level MSblack medium quality pipe sleeves with lugs including bends as per drawings of following sizes as embedment in masonry and concrete. 0.00
PP94 80 NB 0.00 RM 577 1
PP94
PP94 Material
PP94 80 NB o 0 RM 1.10 per Rm 343 =Rs 0 /-
PP94
PP94 Labour
PP94 fixing lc 0 RM 1.00 per Rm 200 =Rs 0 /-
PP94
PP94 Subcontract
PP94 sc 0 RM 1.00 per Rm =Rs /-
PP94
PP95 100 NB 0.00 RM 800 1
PP95
PP95 Material
Page 26 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP95 100 NB o 0 RM 1.10 per Rm 500 =Rs 1 /-
PP95
PP95 Labour
PP95 fixing lc 0 RM 1.00 per Rm 250 =Rs 0 /-
PP95
PP95 Subcontract
PP95 sc 0 RM 1.00 per Rm =Rs /-
PP95
PP96 150 NB 0.00 RM 1,145 1
PP96
PP96 Material
PP96 150 NB o 0 RM 1.10 per Rm 768 =Rs 1 /-
PP96
PP96 Labour
PP96 fixing lc 0 RM 1.00 per Rm 300 =Rs 0 /-
PP96
PP96 Subcontract
PP96 sc 0 RM 1.00 per Rm =Rs /-
PP96
PP97 200 NB 0.00 RM 1,766 2
PP97
PP97 Material
PP97 200 NB o 0 RM 1.10 per Rm 1333 =Rs 1 /-
PP97
PP97 Labour
PP97 fixing lc 0 RM 1.00 per Rm 300 =Rs 0 /-
PP97
PP97 Subcontract
PP97 sc 0 RM 1.00 per Rm =Rs /-
PP97
PP98 Supplying and laying in position Netlone 300 or equivalentGeo-textile of 3 mm thk. (min.) having tensile stress of6T/m2 in M/D as shown in design drawing below coal stock drainage pipe complete as per drawing. 0.00 Sq.M. 2,100 2
PP98
PP98 Material
PP98 Geo textile o 0 Sq.M. 1.20 per sqm 1500 =Rs 2 /-
PP98
PP98 Labour
PP98 laying lc 0 Sq.M. 1.00 per sqm 300 =Rs 0 /-
PP98
PP98 Subcontract
PP98 sc 0 Sq.M. 1.00 per sqm =Rs /-
PP98
PP99 Providing and laying as per Manufacturer's Instruction acrylicbased polymer modified cementitious composite coating system "Tapecrete of CICO" or Equivalent waterproofing to underground structure complete as per drawing and direction of Engineer. 0.00 Sq.M. 800 1
PP99
PP99 Material
PP99 o 0 Sq.M. 1.00 per sqm =Rs /-
PP99
Page 27 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP99 Labour
PP99 lc 0 Sq.M. 1.00 per sqm =Rs /-
PP99
PP99 Subcontract
PP99 Providing and laying as per Manufacturer's Instruction acrylicbased polymer modified cementitious composite coating system "Tapecrete of CICO" or Equivalent waterproofing to underground structure complete as per drawing and direction of Engineer. sc 0 Sq.M. 1.00 per sqm 800 =Rs 1 /-
PP99
PP100 FORMWORK
PP101 Supplying, installing, dismantling and removing following classes / class of formworks for foundation & sub-structure in all kinds of work including necessary renderingof concrete surface after exposure as per drawings, specification and direction of Engineer.
PP102 Ordinary 6,346.25 Sq.M. 935 5,935,138
PP102
PP102 Material
PP102 Shutter mat shu 6346 sqm @ 1.00 per sqm 204 =Rs 1,295,269 /-
PP102
PP102 Labour
PP102 Shutter labour lc 6346 sqm @ 1.00 per sqm 200 =Rs 1,269,250 /-
PP102 Staging lab lc 6346 sqm @ 1.00 per sqm =Rs /-
PP102
PP102 Subcontract
PP102 sc 6346 sqm @ 1.00 per sqm =Rs /-
PP102
PP102 Plant
PP102 Plant- Shutter pl 6346 sqm @ 531.12 per sqm =Rs 3,370,620 /-
PP102 Plant labour- Shutter dl 6346 sqm @ per sqm =Rs /-
PP102
PP103 Plywood 4,230.83 Sq.M. 1,021 4,320,628
PP103
PP103 Material
PP103 Shutter mat shu 4231 sqm @ 1.00 per sqm 240 =Rs 1,015,840 /-
PP103
PP103 Labour
PP103 Shutter labour lc 4231 sqm @ 1.00 per sqm 250 =Rs 1,057,708 /-
PP103 Staging lab lc 4231 sqm @ 1.00 per sqm =Rs /-
PP103
PP103 Subcontract
PP103 sc 4231 sqm @ 1.00 per sqm =Rs /-
PP103
PP103 Plant
PP103 Plant- Shutter pl 4231 sqm @ 531.12 per sqm =Rs 2,247,080 /-
PP103 Plant labour- Shutter dl 4231 sqm @ per sqm =Rs /-
PP103
PP104 Curved / Ornamental 4,160.40 Sq.M. 1,582 6,579,825
PP104
PP104 Material
PP104 Shutter mat shu 4160 sqm @ 1.00 per sqm 750 =Rs 3,122,034 /-
PP104
PP104 Labour
Page 28 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP104 Shutter labour lc 4160 sqm @ 1.00 per sqm 300 =Rs 1,248,120 /-
PP104 Staging lab lc 4160 sqm @ 1.00 per sqm =Rs /-
PP104
PP104 Subcontract
PP104 sc 4160 sqm @ 1.00 per sqm =Rs /-
PP104
PP104 Plant
PP104 Plant- Shutter pl 4160 sqm @ 531.12 per sqm =Rs 2,209,672 /-
PP104 Plant labour- Shutter dl 4160 sqm @ per sqm =Rs /-
PP104
PP105 Supplying, installing, dismantling and removing followingclasses / class of formwork for superstructures in all kindsof work including necessary rendering of concrete surface after exposure as per drawings, specification and direction of Engineer.
PP106 Ordinary 9,519.37 Sq.M. 833 7,925,466
PP106
PP106 Material
PP106 Shutter mat shu 9519 sqm @ 1.00 per sqm 204 =Rs 1,942,904 /-
PP106 Staging shu 9519 sqm @ 2.00 per sqm 75 =Rs 1,428,977 /-
PP106
PP106 Labour
PP106 Shutter labour lc 9519 sqm @ 1.00 per sqm 200 =Rs 1,903,874 /-
PP106 Staging lab lc 9519 sqm @ 2.00 per sqm 30 =Rs 571,162 /-
PP106
PP106 Subcontract
PP106 sc 9519 sqm @ 1.00 per sqm =Rs /-
PP106
PP106 Plant
PP106 Plant- Shutter pl 9519 sqm @ 218.35 per sqm =Rs 2,078,549 /-
PP106 Plant labour- Shutter dl 9519 sqm @ per sqm =Rs /-
PP106
PP107 Plywood 6,346.25 Sq.M. 1,304 8,276,457
PP107
PP107 Material
PP107 Shutter mat shu 6346 sqm @ 1.00 per sqm 240 =Rs 1,523,761 /-
PP107 Staging shu 6346 sqm @ 6.00 per sqm 69 =Rs 2,638,111 /-
PP107
PP107 Labour
PP107 Shutter labour lc 6346 sqm @ 1.00 per sqm 250 =Rs 1,586,562 /-
PP107 Staging lab lc 6346 sqm @ 6.00 per sqm 30 =Rs 1,142,325 /-
PP107
PP107 Subcontract
PP107 sc 6346 sqm @ 1.00 per sqm =Rs /-
PP107
PP107 Plant
PP107 Plant- Shutter pl 6346 sqm @ 218.35 per sqm =Rs 1,385,699 /-
PP107 Plant labour- Shutter dl 6346 sqm @ per sqm =Rs /-
PP107
PP108 Curved / Ornamental 6,240.60 Sq.M. 1,869 11,664,468
Page 29 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP108
PP108 Material
PP108 Shutter mat shu 6241 sqm @ 1.00 per sqm 750 =Rs 4,683,050 /-
PP108 Staging shu 6241 sqm @ 4.00 per sqm 120 =Rs 2,997,735 /-
PP108
PP108 Labour
PP108 Shutter labour lc 6241 sqm @ 1.00 per sqm 300 =Rs 1,872,180 /-
PP108 Staging lab lc 6241 sqm @ 4.00 per sqm 30 =Rs 748,872 /-
PP108
PP108 Subcontract
PP108 sc 6241 sqm @ 1.00 per sqm =Rs /-
PP108
PP108 Plant
PP108 Plant- Shutter pl 6241 sqm @ 218.35 per sqm =Rs 1,362,631 /-
PP108 Plant labour- Shutter dl 6241 sqm @ per sqm =Rs /-
PP108
PP109 Extra over formwork item 38.b for TG deck slab, columnsand beams using leak proof type laminated plywood shuttering, including designing the formwork for the lateral thrust due to SCC. 0.00 Sq.M. 12,870,000,593 12,870,001
PP109
PP109 Material
PP109 Shutter mat shu 0 sqm @ 1.00 per sqm 12870000000 =Rs 12,870,000 /-
PP109
PP109 Labour
PP109 Shutter labour lc 0 sqm @ 1.00 per sqm 250 =Rs 0 /-
PP109 Staging lab lc 0 sqm @ 12.50 per sqm 10 =Rs 0 /-
PP109 (extra over rate)
PP109 Subcontract
PP109 sc 0 sqm @ 1.00 per sqm =Rs /-
PP109
PP109 Plant
PP109 Plant- Shutter pl 0 sqm @ 218.35 per sqm =Rs 0 /-
PP109 Plant labour- Shutter dl 0 sqm @ per sqm =Rs /-
PP109
PP110 Modular shuttering consisting of prefabricated Steel / /Timber beams & formwork modules including necessaryfixtures, clips, pins, screws, fittings etc as directed byEngineer-in-Charge. 0.00 Sq.M. 391,372,457 391,372
PP110
PP110 Material
PP110 Shutter mat shu 0 sqm @ 1.00 per sqm 3500 =Rs 4 /-
PP110
PP110 Labour
PP110 Shutter labour lc 0 sqm @ 1.00 per sqm 250 =Rs 0 /-
PP110 Staging lab lc 0 sqm @ 5.00 per sqm 30 =Rs 0 /-
PP110
PP110 Subcontract
PP110 sc 0 sqm @ 1.00 per sqm =Rs /-
PP110
PP110 Plant
PP110 Plant- Shutter pl 0 sqm @ ########## per sqm =Rs 391,369 /-
Page 30 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP110 Plant labour- Shutter dl 0 sqm @ per sqm =Rs /-
PP110
PP111 Fixing in position and removing forms for pockets andopenings less than 0.1 sq.m including necessary rendering of concrete surface after exposure. 0.00 Each 400 0
PP111
PP111 Material
PP111 o 0 Each 1.00 Each =Rs /-
PP111
PP111 Labour
PP111 lc 0 Each 1.00 Each =Rs /-
PP111
PP111 Subcontract
PP111 Fixing in position and removing forms for pockets andopenings less than 0.1 sq.m including necessary rendering of concrete surface after exposure. sc 0 Each 1.00 Each 400 =Rs 0 /-
PP111
PP112 REINFORCEMENT STEEL
PP113 Supplying, cutting, bending and binding with 1.6 mm galvanized annealed soft iron wire and placing in position following types of Jindal Panther TMT / High Yield steeldeformed bars, of all diameters in RCC members as per drawings, including preparation of bar bending schedule as per specification and direction of Engineer.(Base rate of reinforcement steel will be applied for this item)
PP114 Using straight bar 0.00 MT 49,892 50
PP114
PP114 Material
PP114 Rebar in Civil Work, std hooks, bars, laps shall be measured for payment, ref tech spec part1 pg 45 pdf r 0 MT 1.05 MT / MT 42,542 =Rs 45 /-
PP114 Binding wire in Civil work o 0 MT 8.00 Kg / MT 75 =Rs 1 /-
PP114 Scrap in rebar re 0 MT MT / MT =Rs /-
PP114
PP114 Labour
PP114 Rebar binding & fixing - Civil lc 0 MT 1.00 MT / MT 4,200 =Rs 4 /-
PP114
PP114 Plant
PP114 Plant- Rebar pl 0 MT @ 422.85 per MT =Rs 0 /-
PP114 Plant labour-Rebar dl 0 MT @ per MT =Rs /-
PP114
PP115 Using cut and bent bar 1,044.02 MT 49,264 51,432,225
PP115
PP115 Material
PP115 Rebar in Civil Work, std hooks, bars, laps shall be measured for payment, ref tech spec part1 pg 45 pdf r 1044 MT 1.02 MT / MT 45,138 =Rs 48,067,504 /-
PP115 Binding wire in Civil work o 1044 MT 8.00 Kg / MT 75 =Rs 626,412 /-
PP115 Scrap in rebar re 1044 MT MT / MT =Rs /-
PP115
PP115 Labour
PP115 Rebar binding & fixing - Civil sc 1044 MT 1.00 MT / MT 2,200 =Rs 2,296,845 /-
PP115
PP115 Plant
PP115 Plant- Rebar pl 1044 MT @ 422.85 per MT =Rs 441,463 /-
PP115 Plant labour-Rebar dl 1044 MT @ per MT =Rs /-
PP115
PP116 Using welded reinforcement mesh 0.00 MT 50,618 51
PP116
PP116 Material
Page 31 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP116 Rebar in Civil Work r 0 MT 1.05 MT / MT 45,138 =Rs 47 /-
PP116 Binding wire in Civil work o 0 MT 8.00 Kg / MT 75 =Rs 1 /-
PP116 Scrap in rebar re 0 MT MT / MT =Rs /-
PP116
PP116 Labour
PP116 Rebar binding & fixing - Civil sc 0 MT 1.00 MT / MT 2,200 =Rs 2 /-
PP116
PP116 Plant
PP116 Plant- Rebar pl 0 MT @ 422.85 per MT =Rs 0 /-
PP116 Plant labour-Rebar dl 0 MT @ per MT =Rs /-
PP116
PP117 Extra over item no -40-i, for bending of bars at site as perBBS and as directed by the engineer. 0.00 MT 2,200 2
PP117
PP117 Material
PP117 Rebar in Civil Work r 0 MT 1.05 MT / MT =Rs /-
PP117 Binding wire in Civil work o 0 MT 6.00 Kg / MT =Rs /-
PP117 Scrap in rebar re 0 MT 0.03 MT / MT =Rs /-
PP117
PP117 Labour
PP117 Rebar binding & fixing - Civil sc 0 MT 1.00 MT / MT 2,200 =Rs 2 /-
PP117
PP117 Plant
PP117 Plant- Rebar pl 0 MT @ per MT =Rs /-
PP117 Plant labour-Rebar dl 0 MT @ per MT =Rs /-
PP117
PP118 STRUCTURAL STEEL WORKS
PP119 Preparation of fabrication drawing, receiving fabricatedmaterial at site, transporting, stacking at store, erecting structural steel works as per specification, drawings,including necessary loading, stacking, including addition of gussets, base-plate, cap-plates, stiffeners, shim plates, spacers, washers etc. as specified / required and erecting in position by all sorts of mechanical means including suitable type of crane and erection bolts, nuts [shot blasting of steel surfaces to near white metal surface (Sa 2) and applying Inorganic Zinc Silicate primer of minimum 75 micron (DFT)] etc. complete. 0.00 MT 19,905 20
PP119
PP119 Material
PP119 SS 0 MT @ 1.00 MT / MT =Rs /-
PP119
PP119 Labour
PP119 lc 0 MT @ 1.00 MT / MT =Rs /-
PP119
PP119 Subcontract
PP119 Preparation of fabrication drawing, receiving fabricatedmaterial at site, transporting, stacking at store, erecting structural steel works as per specification, drawings,including necessary loading, stacking, including addition of gussets, base-plate, cap-plates, stiffeners, shim plates, spacers, washers etc. as specified / required and erecting in position by all sorts of mechanical means including suitable type of crane and erection bolts, nuts [shot blasting of steel surfaces to near white metal surface (Sa 2) and applying Inorganic Zinc Silicate primer of minimum 75 micron (DFT)] etc. complete. sc 0 MT @ 1.00 MT / MT 15700 =Rs 16 /-
PP119 Shop drawings sc 0 MT @ 1.00 MT / MT 500 =Rs 1 /-
PP119
PP119 Plant
PP119 Plant- SS pl 0 MT @ 3,705.10 MT / MT =Rs 4 /-
PP119 Plant labour- SS dl 0 MT @ MT / MT =Rs /-
PP119
PP120 Supplying,fabricatinganderectionincludingtransportation, storing etc for Miscellaneous steel work in handrails, sag rods, ladders, platforms and other structures not included above. 75.55 MT 81,534 6,159,867
PP120
PP120 Material
PP120 ss SS 76 MT @ 1.05 MT / MT 45551 =Rs 3,613,447 /-
Page 32 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP120
PP120 Labour
PP120 lc 76 MT @ 1.00 MT / MT =Rs /-
PP120
PP120 Subcontract
PP120 FAB+EREC sc 76 MT @ 1.00 MT / MT 30000 =Rs 2,266,500 /-
PP120
PP120 Plant
PP120 Plant- SS pl 76 MT @ 3,705.10 MT / MT =Rs 279,921 /-
PP120 Plant labour- SS dl 76 MT @ MT / MT =Rs /-
PP120
PP121 Providing and application of synthetic enamel paint ofShalimar make or equivalent and colour in two coats of minimum 50 micron each including surface preparation using wire brush, necessary cleaning and applying twocoats of primer with Zinc chromate primer of DFT 25microns per coat over steel sections already having primer coats at all elevations 0.00 MT 7,000 7
PP121
PP121 Material
PP121 SS 0 MT 1.00 per MT =Rs /-
PP121
PP121 Labour
PP121 lc 0 MT 1.00 per MT =Rs /-
PP121
PP121 Subcontract
PP121 sc 0 MT 1.00 per MT 7000 =Rs 7 /-
PP121
PP121
PP122 Providing and applying high performance epoxy basedPolyamide cured painting system of approved colour and shade consisting of Zinc silicate primer, intermediate (under) coat, finish coat and final finish coat including shot blast cleaning of steel surfaces to near white metal surface (Sa 2), to steel surfaces of all types, shapes and sizes, at all levels, to achieve an even shade, including all labour,material,consumablesequipment,handling, transportation, protection and cleaning, scaffolding and staging, testing, etc., all complete, as per specifications, drawings and instructions of the Engineer.
PP123 Blast cleaning by shot blasting of steel surfaces to nearwhite metal surface (Sa 2) and applying Inorganic Zinc Silicate primer of minimum 75 micron (DFT), including touch up painting for the damaged surfaces of primer. 0.00 MT 10,300 10
PP123
PP123 Material
PP123 SS 0 MT 1.00 per MT =Rs /-
PP123
PP123 Labour
PP123 lc 0 MT 1.00 per MT =Rs /-
PP123
PP123 Subcontract
PP123 sc 0 MT 1.00 per MT 10300 =Rs 10 /-
PP123
PP123
PP124 Applying intermediate (under) coat over inorganic ZincSilicate primer, (excluding cost of primer), consisting of minimum 75 micron DFT epoxy based Titanium dioxide/ Miscellaneous iron oxide (pigmented) including touch up painting for the damaged surfaces of intermediate paint. 0.00 MT 2,500 3
PP124
PP124 Material
PP124 SS 0 MT 1.00 per MT =Rs /-
PP124
PP124 Labour
PP124 lc 0 MT 1.00 per MT =Rs /-
PP124
PP124 Subcontract
PP124 sc 0 MT 1.00 per MT 2500 =Rs 3 /-
Page 33 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP124
PP124
PP125 Applying finish coat over Intermediate (under) coat,(excluding cost of Intermediate coat), consisting of minimum 75 micron DFT Epoxy based colour pigmented finish Polyamide cured paint and Final Finish coat with minimum 25 micron DFT Polyurethane colour pigmented finish paint, including final touch up painting for the damaged surfaces of Finish and Final Finish Paint. 16,925.00 MT 4,050 68,546,250
PP125
PP125 Material
PP125 SS 16925 MT 1.00 per MT =Rs /-
PP125
PP125 Labour
PP125 lc 16925 MT 1.00 per MT =Rs /-
PP125
PP125 Subcontract
PP125 sc 16925 MT 1.00 per MT 4050 =Rs 68,546,250 /-
PP125
PP125
PP126 Dismantling of erected structural steel member at anyelevation, lowering of material and carriage of dismantled material up to field fabrication shop or return to owners store, includingtemporarydismantling,cutting,re-welding, supporting and restoring to correct position of all temporarily dismantled members, realignment of adjacent connected members to their correct position (Weight of such temporarily dismantled and adjacent members not to be paid), including all labour, material, equipment, handling, transportation, all complete as per specifications, drawings and Instructions of Engineer. 100.00 MT 18,000 1,800,000
PP126
PP126 Material
PP126 SS 100 MT 1.00 per MT =Rs /-
PP126
PP126 Labour
PP126 lc 100 MT 1.00 per MT =Rs /-
PP126
PP126 Subcontract
PP126 sc 100 MT 1.00 per MT 18000 =Rs 1,800,000 /-
PP126
PP126
PP127 Additions to, alterations in and / or modification of"Erection Marks" (of structural steel) either in erectedposition or in shop, including all labour, material, equipment, handling, transportation, cutting of parts, gouging of welds, cutting, grinding, fabrication, welding, drilling holes, straightening, removal of bends, raising to required levels, primer painting, with Zinc silicate primer, touch up painting,transportation, return of unutilized steel pieces to the Owner's store, temporarily dismantling, cutting, re-welding, supporting and restoring to correct position of all temporarily dismantled members, realignment of adjacent connected members to their correct position (Weight of such temporarily dismantled and adjacent members not to be paid),.etc, including all labour, material, equipment, handling, transportation, all complete as per specifications, drawings and Instructions of Engineer.
PP128 In erected Position 50.00 MT 30,000 1,500,000
PP128
PP128 Material
PP128 SS 50 MT 1.00 per MT =Rs /-
PP128
PP128 Labour
PP128 lc 50 MT 1.00 per MT =Rs /-
PP128
PP128 Subcontract
PP128 sc 50 MT 1.00 per MT 30000 =Rs 1,500,000 /-
PP128
PP128
PP129 In fabrication yard 50.00 MT 25,000 1,250,000
PP129
PP129 Material
PP129 SS 50 MT 1.00 per MT =Rs /-
PP129
PP129 Labour
PP129 lc 50 MT 1.00 per MT =Rs /-
Page 34 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP129
PP129 Subcontract
PP129 sc 50 MT 1.00 per MT 25000 =Rs 1,250,000 /-
PP129
PP129
PP130 Re-erection of dismantled fabricated structural steelmembers requiring addition to, alterations in and / or modification, (dismantling and additions to, alterations in and/ or modification to be paid separately under relevant items),includingalllabour,material,equipment,handling, transportation, carriage of modified "Erection Marks" from the field fabrication shop to erection site, raising to required levels, aligning in position, tack welding, final welding, touch up painting, including temporarily dismantling, cutting, re- welding, supporting and restoring to the correct position of all temporarily dismantled members, realignment of adjacent connected members to their correct position (Weight of such temporarily dismantled and adjacent members not to be paid), etc., all complete as per specifications, drawings and Instructions of Engineer. 80.00 MT 30,000 2,400,000
PP130
PP130 Material
PP130 SS 80 cum @ 1.00 per cum =Rs /-
PP130
PP130 Labour
PP130 lc 80 cum @ 1.00 per cum =Rs /-
PP130
PP130 Subcontract
PP130 sc 80 cum @ 1.00 per cum 30000 =Rs 2,400,000 /-
PP130
PP130
PP131 Providing, supplying,fabrication,transportation,erection and alignment including installation in position by bolting / welding / screwing of factory made electro- forged gratings fabricated using mild steel conforming to IS :2062, at all levels, in floorings, platforms, drain covers trench covers, walk-ways, passages, staircase treads with edge binding strips and anti-skid nosing etc. with all fittings and fixtures, (clips, bolts, self drilling and taping screws, nuts and lock washers) etc., self drilling and tapping screws, welding, edge preparation, painting by blast cleaning of steel surfaces to near white metal surface (Sa 2 ) and applying high performance painting system consisting of zinc silicate primer (minimum 75 micron DFT) followed by intermediate coat (minimum 75 micron DFT) consisting of epoxy based Titanium dioxide / Micaceous iron oxide and finished with finish coat (minimum 75 micron DFT) consisting of epoxy based coloured pigmented finish including all labour 130.00 MT 143,705 18,681,663
PP131
PP131 Material
PP131 SS 130 MT @ 1.00 MT / MT =Rs /-
PP131
PP131 Labour
PP131 lc 130 MT @ 1.00 MT / MT =Rs /-
PP131
PP131 Subcontract
PP131 sc 130 MT @ 1.00 MT / MT 140000 =Rs 18,200,000 /-
PP131
PP131 Plant
PP131 Plant- SS pl 130 MT @ 3,705.10 MT / MT =Rs 481,663 /-
PP131 Plant labour- SS dl 130 MT @ MT / MT =Rs /-
PP131
PP131
PP132 Extra over item 47.a above for finishing the fabricatedgrating unit with hot dipped galvanization @ 610 g. / Sq. M. over blast / chemically cleaned steel surfaces, instead of painting with high performance painting system 130.00 MT 27,000 3,510,000
PP132
PP132 Material
PP132 SS 130 MT 1.00 per MT =Rs /-
PP132
PP132 Labour
PP132 lc 130 MT 1.00 per MT =Rs /-
PP132
PP132 Subcontract
PP132 sc 130 MT 1.00 per MT 27000 =Rs 3,510,000 /-
PP132
PP132
PP133 Providing and fixing in position at all levels, highstrength structural steel bolts (Property class 8.8 ,class10.9 and product grade C as per IS:1367) conforming to IS: 3757 and high strength structural hardened and tempered nuts (Property class 8 as per IS:1367) conforming to IS :6623 with hardened and tempered washers as per IS:6649 etc., up to and inclusive of 39 mm diameter and 300 mmlong, installing the same as per IS:4000 for structural steelworks including all labour, material, equipment, handling, transportation, testing, all complete, as per specifications, drawings and instruction of Engineer. 250.00 MT 359,705 89,926,276
Page 35 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP133
PP133 Material
PP133 SS 250 MT 1.00 per MT =Rs /-
PP133
PP133 Labour
PP133 lc 250 MT 1.00 per MT =Rs /-
PP133
PP133 Subcontract
PP133 sc 250 MT 1.00 per MT 356000 =Rs 89,000,000 /-
PP133
PP133 Plant
PP133 Plant- SS pl 250 MT @ 3,705.10 MT / MT =Rs 926,276 /-
PP133 Plant labour- SS dl 250 MT @ MT / MT =Rs /-
PP133
PP133
PP134 Providing and fixing in position at all level, permanentmild steel bolts (Property class 4.6 as per IS:1367 and 50.00 MT 153,705 7,685,255
PP134
PP134 Material
PP134 SS 50 MT 1.00 per MT =Rs /-
PP134
PP134 Labour
PP134 lc 50 MT 1.00 per MT =Rs /-
PP134
PP134 Subcontract
PP134 sc 50 MT 1.00 per MT 150000 =Rs 7,500,000 /-
PP134
PP134 Plant
PP134 Plant- SS pl 50 MT @ 3,705.10 MT / MT =Rs 185,255 /-
PP134 Plant labour- SS dl 50 MT @ MT / MT =Rs /-
PP134
PP134
PP135 Product grade C as per IS:1363), nuts, washers, etc. up to and inclusive of 39 mm diameter and 300 mm long forstructural steel works, including all labour, material, equipment, handling, transportation, testing, all complete, asper specifications, Drawings and Instruction of Engineer.
PP136 Supplying, Fabricating, transporting, erecting in position at alllevels the chequered plates for platform walkways, stair treads, trenches, etc. Complete as per specification and approved fabrication drawings.
PP137 6 o/p chequered plate 6.00 MT 80,000 480,000
PP137
PP137 Material
PP137 SS 6 MT 1.00 per MT =Rs /-
PP137
PP137 Labour
PP137 lc 6 MT 1.00 per MT =Rs /-
PP137
PP137 Subcontract
PP137 sc 6 MT 1.00 per MT 80000 =Rs 480,000 /-
PP137
PP137
PP138 ARCHITECTURAL WORKS
Page 36 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP139 Damp Proofing / Protective Layer
PP140 Supplying and laying 40 mm thick damp proof course withcement concrete (1:1:3 nominal mix by volume) with a minimum of 2% admixture of waterproofing compound etc. with all materials complete. 700.00 Sq.M. 220 153,860
PP140
PP140 Material
PP140 o 700 Sq.M. 1.00 Sq.M. =Rs /-
PP140
PP140 Labour
PP140 lc 700 Sq.M. 1.00 Sq.M. =Rs /-
PP140
PP140 Subcontract
PP140 Supplying and laying 40 mm thick damp proof course withcement concrete (1:1:3 nominal mix by volume) with a minimum of 2% admixture of waterproofing compound etc. with all materials complete. sc 700 Sq.M. 1.00 Sq.M. 220 =Rs 153,860 /-
PP140
PP140
PP141 Makingplinth protection (minimum 75mm thick andminimum 750mm wide) of cement concrete M20 over75mm bed of dry brick ballast consolidated and grouted with fine sand including finishing the top smooth including shuttering. 954.00 Sq.M. 698 666,250
PP141
PP141 Material
PP141 o 954 Sq.M. 1.00 Sq.M. =Rs /-
PP141
PP141 Labour
PP141 lc 954 Sq.M. 1.00 Sq.M. =Rs /-
PP141
PP141 Subcontract
PP141 Makingplinth protection (minimum 75mm thick andminimum 750mm wide) of cement concrete M20 over75mm bed of dry brick ballast consolidated and grouted with fine sand including finishing the top smooth including shuttering. sc 954 Sq.M. 1.00 Sq.M. 698 =Rs 666,250 /-
PP141
PP141
PP142 Providing and injecting chemical emulsion for PRE-CONSTRUCTIONAL anti-termite treatment as per IS: 6313Part (II) - 1981 and creating a chemical barrier under and around the column pits, wall trenches, basement, excavation, top surface of plate filling, junction of wall and floor along the external perimeter of building floor together with plinth protection, expansion joints, surroundings of pipes and conduits etc. complete (plinth area of building at ground floor under action area only shall be measured).
PP143 Chlorpyriphos emulsifiable concentrate conforming toIS:8944 - 1978 with 1% concentration (The work shall be get executed by an approved specialist agency and the contractor shall furnish 10 years guarantee on non-judicial stamp paper) 100.00 Sq.m. 220 22,000
PP143
PP143 Material
PP143 o 100 Sq.m. 1.00 Sq.m. =Rs /-
PP143
PP143 Labour
PP143 lc 100 Sq.m. 1.00 Sq.m. =Rs /-
PP143
PP143 Subcontract
PP143 Chlorpyriphos emulsifiable concentrate conforming toIS:8944 - 1978 with 1% concentration (The work shall be get executed by an approved specialist agency and the contractor shall furnish 10 years guarantee on non-judicial stamp paper) sc 100 Sq.m. 1.00 Sq.m. 220 =Rs 22,000 /-
PP143
PP143
PP144 Masonry
PP145 Supplying and laying in position full brick work (Fly Ashbricks) of class designation minimum 75 in foundation and plinth in cement-sand mortar (1:6) including mixing mortar, laying bricks, raking joints, curing etc. with all materials complete as per drawings and specifications. 1,000.00 Cu.M 5,865 5,864,659
PP145
PP145 Material
PP145 Fly ash brick o 1000 Cu.M 525.00 no per cum 6.7 =Rs 3,522,750 /-
PP145 Sand sd 1000 Cu.M 0.94 cum 425.0 =Rs 398,438 /-
PP145 Cement c 1000 cum 93.75 kg per cum 7.9 =Rs 743,471 /-
PP145
PP145 Labour
Page 37 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP145 brick masonary lc 1000 Cu.M 1.00 no per cum 1200 =Rs 1,200,000 /-
PP145
PP145 Subcontract
PP145 sc 1000 Cu.M 1.00 no per cum =Rs /-
PP145
PP145
PP146 Supplying and laying in position full brick work (Fly Ashbricks)ofclassdesignationminimum75in superstructure at various elevations in cement-sand mortar (1:6) 661.17 Cu.M 6,164 4,075,125
PP146
PP146 Material
PP146 Fly ash brick o 661 Cu.M 525.00 no per cum 6.7 =Rs 2,329,119 /-
PP146 Sand sd 661 Cu.M 0.93 cum 425.0 =Rs 262,701 /-
PP146 Cement c 661 cum 93.75 kg per cum 7.9 =Rs 491,557 /-
PP146
PP146 Labour
PP146 brick masonary lc 661 Cu.M 1.00 1,500.00 1500 =Rs 991,748 /-
PP146
PP146 Subcontract
PP146 sc 661 Cu.M 1.00 1,500.00 =Rs /-
PP146
PP146
PP147 Supplying and laying in positionbrickwork of classdesignation minimum 75 in half brick (Fly Ash bricks) thick walls at various elevations in cement-sand mortar (1:4) with HB netting at every fourth layer including mixing mortar, laying bricks, raking joints curing scaffolding, equipment as required etc. with all materials complete as per drawings and specifications. 1,500.00 Sq.M. 6,586 9,878,654
PP147
PP147 Material
PP147 Fly ash brick o 1500 Sq.M. 525.00 no per cum 6.7 =Rs 5,284,125 /-
PP147 Sand sd 1500 Sq.M. 0.90 cum 425.0 =Rs 574,414 /-
PP147 Cement c 1500 cum 142.50 kg per cum 7.9 =Rs 1,695,114 /-
PP147
PP147 Labour
PP147 brick masonary with nets lc 1500 Sq.M. 1.00 1,500.00 1550 =Rs 2,325,000 /-
PP147
PP147 Subcontract
PP147 sc 1500 Sq.M. 1.00 1,500.00 =Rs /-
PP147
PP147
PP148 Optional for item (54 & 55) above for Laying in positionPre Engineered Non Load bearing light gauge steel (LGS) Structure (by Jindal Fab Infra Private Limited or equivalent) constructed using hot dip galvanized (275 gsm) cold rolledC profile sections having tensile strength of 350 Mpa withall necessary fasteners, fixtures and fittings etc complete.
PP149 External wall:The external / outer wall shall be Cladded with PPGI Sheet/ PPGL Sheets (0.5 thk ) including screwing, and all complete etc. 4,500.00 Sq.M. 1,500 6,750,000
PP149
PP149 Material
PP149 o 4500 Sq.M. 1.00 Sq.M. =Rs /-
PP149
PP149 Labour
PP149 lc 4500 Sq.M. 1.00 Sq.M. =Rs /-
PP149
PP149 Subcontract
PP149 External wall:The external / outer wall shall be Cladded with PPGI Sheet/ PPGL Sheets (0.5 thk ) including screwing, and all complete etc. sc 4500 Sq.M. 1.00 Sq.M. 1500 =Rs 6,750,000 /-
PP149
Page 38 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP149
PP150 Internal wall:Internal Surface of the wall shall be cladded with 6mm CPboard and 12.5 mm thick Gypsum Board and without paint. 4,500.00 Sq.M. 1,400 6,300,000
PP150
PP150 Material
PP150 o 4500 Sq.M. 1.00 Sq.M. =Rs /-
PP150
PP150 Labour
PP150 lc 4500 Sq.M. 1.00 Sq.M. =Rs /-
PP150
PP150 Subcontract
PP150 Internal wall:Internal Surface of the wall shall be cladded with 6mm CPboard and 12.5 mm thick Gypsum Board and without paint. sc 4500 Sq.M. 1.00 Sq.M. 1400 =Rs 6,300,000 /-
PP150
PP150
PP151 Supplying and fixing 17.5 cm. X 17.5 cm glass bricks inpattern with epoxy mortar match to the bricks as permanufacturer's manual, drawings and directions of theEngineer in charge. 200.00 Sq.M. 158 31,500
PP151
PP151 Material
PP151 o 200 Sq.M. 1.00 Sq.M. =Rs /-
PP151
PP151 Labour
PP151 lc 200 Sq.M. 1.00 Sq.M. =Rs /-
PP151
PP151 Subcontract
PP151 Supplying and fixing 17.5 cm. X 17.5 cm glass bricks inpattern with epoxy mortar match to the bricks as permanufacturer's manual, drawings and directions of theEngineer in charge. sc 200 Sq.M. 1.00 Sq.M. 158 =Rs 31,500 /-
PP151
PP151
PP152 Dismantling of brick work and removal of debris from thesite as directed by Engineer for all heads and lifts etc. 150.00 Cu.M 800 120,000
PP152
PP152 Material
PP152 o 150 Cu.M 1.00 Cu.M =Rs /-
PP152
PP152 Labour
PP152 lc 150 Cu.M 1.00 Cu.M =Rs /-
PP152
PP152 Subcontract
PP152 Dismantling of brick work and removal of debris from thesite as directed by Engineer for all heads and lifts etc. sc 150 Cu.M 1.00 Cu.M 800 =Rs 120,000 /-
PP152
PP152
PP153 Plastering
PP154 Providing 18 mm thick cement plaster on exteriorsurfaces in two layers vertical, horizontal or curved up to any elevation and heights under layer 12 mm thick Cement plaster 1:6 (1 cement: 6 coarse sand) finishing with a top layer 6 mm thick cement plaster 1:4 (1 cement: 4 fine sand) including the cost of all materials, equipment, labour, scaffolding, curing, as per specification and the direction of Engineer-in-charge. 3,220.50 Sq.M. 295 950,150
PP154
PP154 Material
PP154 Sand sd 3221 Sq.M. 0.18 cum 425.0 =Rs 244,880 /-
PP154 Cement c 3221 cum 8.70 kg per sqm 7.9 =Rs 222,196 /-
PP154 o 3221 Sq.M. 1.00 Sq.M. =Rs /-
PP154
PP154 Labour
Page 39 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP154 Laying +scaffolding lc 3221 Sq.M. 1.00 Sq.M. 150 =Rs 483,075 /-
PP154
PP154 Subcontract
PP154 sc 3221 Sq.M. 1.00 Sq.M. =Rs /-
PP154
PP154
PP155 12 mm thick (minimum) cement-sand (1:6) plaster tointerior faces of walls, beams columns etc. at various elevations including mixing etc., with all materials complete 54,300.00 Sq.M. 194 10,514,255
PP155
PP155 Material
PP155 Sand sd 54300 Sq.M. 0.12 cum 425.0 =Rs 2,758,915 /-
PP155 Cement c 54300 cum 5.40 kg per sqm 7.9 =Rs 2,325,340 /-
PP155
PP155 Labour
PP155 Laying +scaffolding lc 54300 cum 1.00 kg per sqm 100 =Rs 5,430,000 /-
PP155
PP155 Subcontract
PP155 sc 54300 cum 1.00 kg per sqm =Rs /-
PP155
PP155
PP156 Extra over plaster for supplying and fixing galvanizedchicken wire mesh (gauge-22) at junctions of brick workand concrete work with an minimum overlapping of 150 mm on either side of the junction and as per drawing & instruction of engineer, complete in all respect. 0.00 Sq.M. 250 0
PP156
PP156 Material
PP156 o 0 Sq.M. 1.00 Sq.M. =Rs /-
PP156
PP156 Labour
PP156 lc 0 Sq.M. 1.00 Sq.M. =Rs /-
PP156
PP156 Subcontract
PP156 Extra over plaster for supplying and fixing galvanizedchicken wire mesh (gauge-22) at junctions of brick workand concrete work with an minimum overlapping of 150 mm on either side of the junction and as per drawing & instruction of engineer, complete in all respect. sc 0 Sq.M. 1.00 Sq.M. 250 =Rs 0 /-
PP156
PP156
PP157 Providing 6 mm thick cement plaster on ceiling whereverdirected by the Engineer in 1:4 (1 cement: 4 sand) mortar including the cost of all materials, equipment, scaffolding, etc. complete. 1,815.00 Sq.M. 156 283,792
PP157
PP157 Material
PP157 Sand sd 1815 Sq.M. 0.06 cum 425.0 =Rs 46,157 /-
PP157 Cement c 1815 cum 3.90 kg per sqm 7.9 =Rs 56,135 /-
PP157 =Rs /-
PP157 Labour
PP157 Laying +scaffolding lc 1815 Sq.M. 1.00 cum 100 =Rs 181,500 /-
PP157
PP157 Subcontract
PP157 sc 1815 Sq.M. 1.00 cum =Rs /-
PP157
PP157
PP158 Supplying & laying Vineratex or equivalent granular decorative textured coat finish over plaster surfaces at various elevations including mixing, laying, finishing etc. with materials & labour complete as per manufacturers specification and drawing. 1,000.00 Sq.M. 500 500,000
PP158
Page 40 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP158 Material
PP158 o 1000 Sq.M. 1.00 Sq.M. =Rs /-
PP158
PP158 Labour
PP158 lc 1000 Sq.M. 1.00 Sq.M. =Rs /-
PP158
PP158 Subcontract
PP158 Supplying & laying Vineratex or equivalent granulardecorative textured coat finish over plaster surfaces at various elevations including mixing, laying, finishing etc. with materials & labour complete as per manufacturers specification and drawing. sc 1000 Sq.M. 1.00 Sq.M. 500 =Rs 500,000 /-
PP158
PP158
PP159 25 mm x 12 mm Drip course at various elevations toparapet, chajja, window heads, door heads etc. with all materials at all elevations complete as per drawings and specification. 2,000.00 R.M. 200 400,000
PP159
PP159 Material
PP159 o 2000 R.M. 1.00 R.M. =Rs /-
PP159
PP159 Labour
PP159 lc 2000 R.M. 1.00 R.M. =Rs /-
PP159
PP159 Subcontract
PP159 25 mm x 12 mm Drip course at various elevations toparapet, chajja, window heads, door heads etc. with all materials at all elevations complete as per drawings and specification. sc 2000 R.M. 1.00 R.M. 200 =Rs 400,000 /-
PP159
PP159
PP160 Flooring, Skirting and Dado
PP161 40 mm. thick cement concrete floor 1:1.5:3 with top ofconcrete floor painted with two coats of Epoxy paint as per manufacturer's specification. 200.00 Sq.M. 724 144,720
PP161
PP161 Material
PP161 o 200 Sq.M. 1.00 Sq.M. =Rs /-
PP161
PP161 Labour
PP161 lc 200 Sq.M. 1.00 Sq.M. =Rs /-
PP161
PP161 Subcontract
PP161 40 mm. thick cement concrete floor 1:1.5:3 with top ofconcrete floor painted with two coats of Epoxy paint as per manufacturer's specification. sc 200 Sq.M. 1.00 Sq.M. 724 =Rs 144,720 /-
PP161
PP161
PP162 Providing and laying overall 40 mm thick cement concreteflooring with metallic concrete hardener topping (ironite),at various elevations, consisting of under layer 28 mm average thick cement concrete of grade M 20 and top layer 12 mm thick metallic cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 stone aggregate 6 mm nominal size) by volume (Ironite shall be added in mix @1.5 kg / m2) including finishing of joints at maximum two (2)metres interval, or any surface, and including 40 mm wide and 4 mm thick, glass strip placed between the panels including labour, materials and equipment and curing including scouring of surface providing necessary shape etc. complete in all respects and in accordance with specifications and direction of the Engineer. 355.00 Sq.M. 404 143,349
PP162
PP162 Material
PP162 o 355 Sq.M. 1.00 Sq.M. =Rs /-
PP162
PP162 Labour
PP162 lc 355 Sq.M. 1.00 Sq.M. =Rs /-
PP162
PP162 Subcontract
PP162 Providing and laying overall 40 mm thick cement concreteflooring with metallic concrete hardener topping (ironite),at various elevations, consisting of under layer 28 mm average thick cement concrete of grade M 20 and top layer 12 mm thick metallic cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 stone aggregate 6 mm nominal size) by volume (Ironite shall be added in mix @1.5 kg / m2) including finishing of joints at maximum two (2)metres interval, or any surface, and including 40 mm wide and 4 mm thick, glass strip placed between the panels including labour, materials and equipment and curing including scouring of surface providing necessary shape etc. complete in all respects and in accordance with specifications and direction of the Engineer. sc 355 Sq.M. 1.00 Sq.M. 404 =Rs 143,349 /-
PP162
Page 41 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP162
PP163 Providing and laying overall 40 mm thick cement concrete(grade M25) flooring including cement slurry, finishing of joints at maximum two (2) metres interval, or any surface, and including 40 mm wide and 4 mm thick, glass strip placed between the panels including labour, materials and equipment and curing including scouring of surface providing necessary shape etc. complete in all respects and in accordance with specifications and direction of Engineer. 1,962.50 Sq.M. 368 722,985
PP163
PP163 Material
PP163 o 1963 Sq.M. 1.00 Sq.M. =Rs /-
PP163
PP163 Labour
PP163 lc 1963 Sq.M. 1.00 Sq.M. =Rs /-
PP163
PP163 Subcontract
PP163 Providing and laying overall 40 mm thick cement concrete(grade M25) flooring including cement slurry, finishing of joints at maximum two (2) metres interval, or any surface, and including 40 mm wide and 4 mm thick, glass strip placed between the panels including labour, materials and equipment and curing including scouring of surface providing necessary shape etc. complete in all respects and in accordance with specifications and direction of Engineer. sc 1963 Sq.M. 1.00 Sq.M. 368 =Rs 722,985 /-
PP163
PP163
PP164 Providing 25 mm thick and 150 mm high cement mortar(1:3) skirting finished with a floating coat of neat cement at all elevations including labour, materials and equipment and curing complete in all respects and in accordance with specifications and direction of the Engineer 2,000.00 Sq.M. 326 651,525
PP164
PP164 Material
PP164 o 2000 Sq.M. 1.00 Sq.M. =Rs /-
PP164
PP164 Labour
PP164 lc 2000 Sq.M. 1.00 Sq.M. =Rs /-
PP164
PP164 Subcontract
PP164 Providing 25 mm thick and 150 mm high cement mortar(1:3) skirting finished with a floating coat of neat cement at all elevations including labour, materials and equipment and curing complete in all respects and in accordance with specifications and direction of the Engineer sc 2000 Sq.M. 1.00 Sq.M. 326 =Rs 651,525 /-
PP164
PP164
PP165 Providing and laying non-skid fully vitrified 10 mm thicktiles similar to "MARBONITE","FERRASTONE",of "BOSS Profile Ltd." or similar approved laid on 20 mm thick cement mortar (1:4) including grouting the joints with white cement and matching pigments etc., in floors, skirting and dado complete as per manufacturer's specification .(Base rate of cement will be applied for this item)
PP166 600 mm x 600 mm (Base rate = Rs. 1500/-) 2,500.00 Sq.M. 1,963 4,908,125
PP166
PP166 Material
PP166 o 2500 Sq.M. 1.00 Sq.M. =Rs /-
PP166
PP166 Labour
PP166 lc 2500 Sq.M. 1.00 Sq.M. =Rs /-
PP166
PP166 Subcontract
PP166 600 mm x 600 mm (Base rate = Rs. 1500/-) sc 2500 Sq.M. 1.00 Sq.M. 1963 =Rs 4,908,125 /-
PP166
PP166
PP167 400 mm x 400 mm (Base rate = Rs. 1270/-) 1,500.00 Sq.M. 1,717 2,575,725
PP167
PP167 Material
PP167 o 1500 Sq.M. 1.00 Sq.M. =Rs /-
PP167
PP167 Labour
PP167 lc 1500 Sq.M. 1.00 Sq.M. =Rs /-
PP167
Page 42 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP167 Subcontract
PP167 400 mm x 400 mm (Base rate = Rs. 1270/-) sc 1500 Sq.M. 1.00 Sq.M. 1717 =Rs 2,575,725 /-
PP167
PP167
PP168 Supplying & laying 50 mm thick floor with matt finishunglazed ceramic tiles of approved colour and shade and of minimum thickness 7.2-7.5 mm over necessary under bed and 15 mm thick cement sand mortar 1:3 including cement slurry and joining with white cement slurry mixed with pigment to match the shade of tile complete with all materialsas per specification and drawing. (Base rate = Rs. 1000/-)(Base rate of cement will be applied for this item) 300.00 Sq.M. 1,433 429,825
PP168
PP168 Material
PP168 o 300 Sq.M. 1.00 Sq.M. =Rs /-
PP168
PP168 Labour
PP168 lc 300 Sq.M. 1.00 Sq.M. =Rs /-
PP168
PP168 Subcontract
PP168 Supplying & laying 50 mm thick floor with matt finishunglazed ceramic tiles of approved colour and shade and of minimum thickness 7.2-7.5 mm over necessary under bed and 15 mm thick cement sand mortar 1:3 including cement slurry and joining with white cement slurry mixed with pigment to match the shade of tile complete with all materialsas per specification and drawing. (Base rate = Rs. 1000/-)(Base rate of cement will be applied for this item) sc 300 Sq.M. 1.00 Sq.M. 1433 =Rs 429,825 /-
PP168
PP168
PP169 Same as above item no 70 but with tiles of designerseries of Kajaria, Nitco or of approved equivalent manufacturers (Base rate = Rs. 1200/-)(Base rate of cement will be applied for this item) 100.00 Sq.M. 1,717 171,715
PP169
PP169 Material
PP169 o 100 Sq.M. 1.00 Sq.M. =Rs /-
PP169
PP169 Labour
PP169 lc 100 Sq.M. 1.00 Sq.M. =Rs /-
PP169
PP169 Subcontract
PP169 Same as above item no 70 but with tiles of designerseries of Kajaria, Nitco or of approved equivalent manufacturers (Base rate = Rs. 1200/-)(Base rate of cement will be applied for this item) sc 100 Sq.M. 1.00 Sq.M. 1717 =Rs 171,715 /-
PP169
PP169
PP170 Supplying and placing 5 mm thick glazed ceramic tiles ofapproved make, size in skirting, dado etc on 12 mm thick1:3 cement mortar in base and jointed with white cement slurry and matching pigments etc, including labour, materials and equipment, cleaning of surfacelaid as per manufacturer's instruction and direction of Engineer in charge. (Base rate = Rs. 750/-)(Base rate of cement will be applied for this item) 2,600.00 Sq.M. 1,433 3,725,150
PP170
PP170 Material
PP170 o 2600 Sq.M. 1.00 Sq.M. =Rs /-
PP170
PP170 Labour
PP170 lc 2600 Sq.M. 1.00 Sq.M. =Rs /-
PP170
PP170 Subcontract
PP170 Supplying and placing 5 mm thick glazed ceramic tiles ofapproved make, size in skirting, dado etc on 12 mm thick1:3 cement mortar in base and jointed with white cement slurry and matching pigments etc, including labour, materials and equipment, cleaning of surfacelaid as per manufacturer's instruction and direction of Engineer in charge. (Base rate = Rs. 750/-)(Base rate of cement will be applied for this item) sc 2600 Sq.M. 1.00 Sq.M. 1433 =Rs 3,725,150 /-
PP170
PP170
PP171 Supplying & laying 40 mm thick acid/alkali resistant floorwith 20 mm thick unglazed ceramic vitreous acid / alkali resistant tiles laid on potassium silicate based under bed mortar as per IS: 4832 (part I) over a primer coat and alkaliresistant bituminoustic ready made paint conforming toIS: 158 with 6 mm wide joints in between tiles filled with resin type (epoxy/Furane) mortar conforming to IS- 4832(Part-II) including preparation of surface, acid curing sealing the edges by bituminastic filler etc complete as per specification, drawing and direction of Engineer. (Base rate = Rs. 4450/-)
PP172 The tile samples shall be approved by Engineer beforeexecution. 900.00 Sq.M. 1,156 1,040,625
PP172
PP172 Material
PP172 o 900 Sq.M. 1.00 Sq.M. =Rs /-
PP172
Page 43 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP172 Labour
PP172 lc 900 Sq.M. 1.00 Sq.M. =Rs /-
PP172
PP172 Subcontract
PP172 The tile samples shall be approved by Engineer beforeexecution. sc 900 Sq.M. 1.00 Sq.M. 1156 =Rs 1,040,625 /-
PP172
PP172
PP173 All as per item (73-a) above but with Acid/Alkali resistantpaint over 20 mm thick unglazed ceramic normal tile all as per specification complete. 400.00 Sq.M. 6,331 2,532,500
PP173
PP173 Material
PP173 o 400 Sq.M. 1.00 Sq.M. =Rs /-
PP173
PP173 Labour
PP173 lc 400 Sq.M. 1.00 Sq.M. =Rs /-
PP173
PP173 Subcontract
PP173 All as per item (73-a) above but with Acid/Alkali resistantpaint over 20 mm thick unglazed ceramic normal tile all as per specification complete. sc 400 Sq.M. 1.00 Sq.M. 6331 =Rs 2,532,500 /-
PP173
PP173
PP174 Supplying and laying polished kota stone slab of approvedsize and 20 mm thick (the tile sample shall be got approved from the Engineer) in flooring and skirting laid on 20 mm thick cement mortar 1:4 bedding, cement floated mixed with pigment, all joints well filled on completion, including polishing at site all as per specifications and directions of Engineer.(Base rate = Rs. 350/-)(Base rate of cement will be applied for this item) 500.00 Sq.M. 964 482,125
PP174
PP174 Material
PP174 o 500 Sq.M. 1.00 Sq.M. =Rs /-
PP174
PP174 Labour
PP174 lc 500 Sq.M. 1.00 Sq.M. =Rs /-
PP174
PP174 Subcontract
PP174 Supplying and laying polished kota stone slab of approvedsize and 20 mm thick (the tile sample shall be got approved from the Engineer) in flooring and skirting laid on 20 mm thick cement mortar 1:4 bedding, cement floated mixed with pigment, all joints well filled on completion, including polishing at site all as per specifications and directions of Engineer.(Base rate = Rs. 350/-)(Base rate of cement will be applied for this item) sc 500 Sq.M. 1.00 Sq.M. 964 =Rs 482,125 /-
PP174
PP174
PP175 Providing, supplying and laying 2 mm thick homogeneousflexible heavy duty antistatic PVC tiles of approvedmanufacture, size and colour on floor, dodo etc using rubber based adhesive of approved manufacture including rolling with light wooden roller weighing about 5 kg, material, labour, equipment etc. complete as per drawing and direction. (Base rate = Rs. 750/-) 200.00 Sq.M. 1,488 297,500
PP175
PP175 Material
PP175 o 200 Sq.M. 1.00 Sq.M. =Rs /-
PP175
PP175 Labour
PP175 lc 200 Sq.M. 1.00 Sq.M. =Rs /-
PP175
PP175 Subcontract
PP175 Providing, supplying and laying 2 mm thick homogeneousflexible heavy duty antistatic PVC tiles of approvedmanufacture, size and colour on floor, dodo etc using rubber based adhesive of approved manufacture including rolling with light wooden roller weighing about 5 kg, material, labour, equipment etc. complete as per drawing and direction. (Base rate = Rs. 750/-) sc 200 Sq.M. 1.00 Sq.M. 1488 =Rs 297,500 /-
PP175
PP175
PP176 Providing and laying 18 mm thick Polished granite stone(slab) over 20 mm thick base in cement mortar 1:4 (1 cement : 4 coarse sand) including labour materials andequipment and also including scouring of surface providing necessary shape etc. complete in all respect with standard accordance with specification & direction of engineer. The joints shall be grouted with white cement by mixing & matching colour pigment. (Base rate = Rs. 2750/-)(Base rate of cement will be applied for this item) 3,000.00 Sq.M. 3,484 10,452,750
PP176
PP176 Material
Page 44 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP176 o 3000 Sq.M. 1.00 Sq.M. =Rs /-
PP176
PP176 Labour
PP176 lc 3000 Sq.M. 1.00 Sq.M. =Rs /-
PP176
PP176 Subcontract
PP176 Providing and laying 18 mm thick Polished granite stone(slab) over 20 mm thick base in cement mortar 1:4 (1 cement : 4 coarse sand) including labour materials andequipment and also including scouring of surface providing necessary shape etc. complete in all respect with standard accordance with specification & direction of engineer. The joints shall be grouted with white cement by mixing & matching colour pigment. (Base rate = Rs. 2750/-)(Base rate of cement will be applied for this item) sc 3000 Sq.M. 1.00 Sq.M. 3484 =Rs 10,452,750 /-
PP176
PP176
PP177 Supplying, fitting and fixing Polished granite slabs 12 mmthick in columns, walls, facias, skirting, dado etc. with cement mortar (1:3) including making suitable arrangementto hold the stone properly by brass/copper hooks including filling the joints with necessary cement mortar (1 white cement : 2 stone dust) with admixture of pigment matching the shades, all complete including edge molding. (Base rate= Rs. 2000/-)(Base rate of cement will be applied for this item) 500.00 Sq.M. 2,697 1,348,375
PP177
PP177 Material
PP177 o 500 Sq.M. 1.00 Sq.M. =Rs /-
PP177
PP177 Labour
PP177 lc 500 Sq.M. 1.00 Sq.M. =Rs /-
PP177
PP177 Subcontract
PP177 Supplying, fitting and fixing Polished granite slabs 12 mmthick in columns, walls, facias, skirting, dado etc. with cement mortar (1:3) including making suitable arrangementto hold the stone properly by brass/copper hooks including filling the joints with necessary cement mortar (1 white cement : 2 stone dust) with admixture of pigment matching the shades, all complete including edge molding. (Base rate= Rs. 2000/-)(Base rate of cement will be applied for this item) sc 500 Sq.M. 1.00 Sq.M. 2697 =Rs 1,348,375 /-
PP177
PP177
PP178 Providing and laying 18 mm thick Adanga White Marbleslab (1.5 m x 0.6 m) flooring over 22 mm thick base in cement mortar 1:4 (1 cement : 4 coarse sand) having 5 mm thick white cement topping, including labour materials and equipment and also including scouring of surface providing necessary shape etc. Complete in all respect with standard accordance with specification & direction of engineer. The joints shall be grouted with grey cement by mixing & matching colour pigment. (Base rate = Rs. 1600/-) (Base rate of cement will be applied for this item) 500.00 Sq.M. 2,427 1,213,375
PP178
PP178 Material
PP178 o 500 Sq.M. 1.00 Sq.M. =Rs /-
PP178
PP178 Labour
PP178 lc 500 Sq.M. 1.00 Sq.M. =Rs /-
PP178
PP178 Subcontract
PP178 Providing and laying 18 mm thick Adanga White Marbleslab (1.5 m x 0.6 m) flooring over 22 mm thick base in cement mortar 1:4 (1 cement : 4 coarse sand) having 5 mm thick white cement topping, including labour materials and equipment and also including scouring of surface providing necessary shape etc. Complete in all respect with standard accordance with specification & direction of engineer. The joints shall be grouted with grey cement by mixing & matching colour pigment. (Base rate = Rs. 1600/-) (Base rate of cement will be applied for this item) sc 500 Sq.M. 1.00 Sq.M. 2427 =Rs 1,213,375 /-
PP178
PP178
PP179 Providing and laying over-all 40 mm thick granite workwith 18 mm thick grey granite in flooring above as per floorpattern indicated in drawing and/or instructed by the Engineer/ Architect. (Base rate = Rs. 2750/-)(Base rate of cement will be applied for this item) 100.00 Sq.M. 3,734 373,425
PP179
PP179 Material
PP179 o 100 Sq.M. 1.00 Sq.M. =Rs /-
PP179
PP179 Labour
PP179 lc 100 Sq.M. 1.00 Sq.M. =Rs /-
PP179
PP179 Subcontract
PP179 Providing and laying over-all 40 mm thick granite workwith 18 mm thick grey granite in flooring above as per floorpattern indicated in drawing and/or instructed by the Engineer/ Architect. (Base rate = Rs. 2750/-)(Base rate of cement will be applied for this item) sc 100 Sq.M. 1.00 Sq.M. 3734 =Rs 373,425 /-
PP179
PP179
PP180 18 mm thick marble slab skirting or dado matching withfloor marble slab as per instruction of engineer. (Base rate= Rs. 1600/-)(Base rate of cement will be applied for this item) 100.00 Sq.M. 2,527 252,675
Page 45 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP180
PP180 Material
PP180 o 100 Sq.M. 1.00 Sq.M. =Rs /-
PP180
PP180 Labour
PP180 lc 100 Sq.M. 1.00 Sq.M. =Rs /-
PP180
PP180 Subcontract
PP180 18 mm thick marble slab skirting or dado matching withfloor marble slab as per instruction of engineer. (Base rate= Rs. 1600/-)(Base rate of cement will be applied for this item) sc 100 Sq.M. 1.00 Sq.M. 2527 =Rs 252,675 /-
PP180
PP180
PP181 Supplying and fixing glass mosaic tiles 20 x 20 x 4.5 mmthick in pattern as per drawings and directions of theEngineer in charge. 25.00 Sq.M. 3,077 76,919
PP181
PP181 Material
PP181 o 25 Sq.M. 1.00 Sq.M. =Rs /-
PP181
PP181 Labour
PP181 lc 25 Sq.M. 1.00 Sq.M. =Rs /-
PP181
PP181 Subcontract
PP181 Supplying and fixing glass mosaic tiles 20 x 20 x 4.5 mmthick in pattern as per drawings and directions of theEngineer in charge. sc 25 Sq.M. 1.00 Sq.M. 3077 =Rs 76,919 /-
PP181
PP181
PP182 Supplying & Laying precast cement concrete tiles(minimum size 600 mm X 600 mm) 20 mm. thick on roof surface including preparation of bed with 15 mm thick sand cement mortar (4:1) to proper slope as per direction of the Engineer - in -charge complete including cost of all labour and materials etc. 800.00 Sq.M. 2,527 2,021,400
PP182
PP182 Material
PP182 o 800 Sq.M. 1.00 Sq.M. =Rs /-
PP182
PP182 Labour
PP182 lc 800 Sq.M. 1.00 Sq.M. =Rs /-
PP182
PP182 Subcontract
PP182 Supplying & Laying precast cement concrete tiles(minimum size 600 mm X 600 mm) 20 mm. thick on roof surface including preparation of bed with 15 mm thick sand cement mortar (4:1) to proper slope as per direction of the Engineer - in -charge complete including cost of all labour and materials etc. sc 800 Sq.M. 1.00 Sq.M. 2527 =Rs 2,021,400 /-
PP182
PP182
PP183 Doors, Windows, Ventilators and Rolling Shutters (Rateshall be inclusive of cost of all required hardware)
PP184 Supplying, fitting & fixing full glazed aluminum door withminimum 15 micron colour anodized aluminum frameand shutter of approved colour and make, complete with all fitting and fixtures (e.g. push plate, double actingfloor spring, locks etc.) sealing, grouting frames, raw bolt fixing, etc., as required with all materials complete including 8 mm thick toughened float glass (Vendor's drawing to be approved by Architect before fabrication).
PP185 Single leaf 20.00 Sq.M. 10,500 210,000
PP185
PP185 Material
PP185 o 20 Sq.M. 1.00 Sq.M. =Rs /-
PP185
PP185 Labour
PP185 lc 20 Sq.M. 1.00 Sq.M. =Rs /-
PP185
PP185 Subcontract
Page 46 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP185 Single leaf sc 20 Sq.M. 1.00 Sq.M. 10500 =Rs 210,000 /-
PP185
PP185
PP186 Double leaf 50.00 Sq.M. 8,500 425,000
PP186
PP186 Material
PP186 o 50 Sq.M. 1.00 Sq.M. =Rs /-
PP186
PP186 Labour
PP186 lc 50 Sq.M. 1.00 Sq.M. =Rs /-
PP186
PP186 Subcontract
PP186 Double leaf sc 50 Sq.M. 1.00 Sq.M. 8500 =Rs 425,000 /-
PP186
PP186
PP187 Supplying and fixing of best quality anodized aluminumwindows and ventilators conforming to IS: 1949 & IS: 1948 including supplying and fixing approved glazing including all fixtures and fittings, fixing material such as putty etc. and all labour complete as per specification, drawing and direction of Engineer. (thickness of aluminum sections is 3 mm)
PP188 With 4 mm thick clear float glass 500.00 Sq.M. 4,000 2,000,000
PP188
PP188 Material
PP188 o 500 Sq.M. 1.00 Sq.M. =Rs /-
PP188
PP188 Labour
PP188 lc 500 Sq.M. 1.00 Sq.M. =Rs /-
PP188
PP188 Subcontract
PP188 With 4 mm thick clear float glass sc 500 Sq.M. 1.00 Sq.M. 4000 =Rs 2,000,000 /-
PP188
PP188
PP189 With 4 mm thick ground glass 50.00 Sq.M. 4,300 215,000
PP189
PP189 Material
PP189 o 50 Sq.M. 1.00 Sq.M. =Rs /-
PP189
PP189 Labour
PP189 lc 50 Sq.M. 1.00 Sq.M. =Rs /-
PP189
PP189 Subcontract
PP189 With 4 mm thick ground glass sc 50 Sq.M. 1.00 Sq.M. 4300 =Rs 215,000 /-
PP189
PP189
PP190 With 6 mm thick clear toughened glass 29.00 Sq.M. 5,000 145,000
PP190
PP190 Material
PP190 o 29 Sq.M. 1.00 Sq.M. =Rs /-
PP190
PP190 Labour
Page 47 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP190 lc 29 Sq.M. 1.00 Sq.M. =Rs /-
PP190
PP190 Subcontract
PP190 With 6 mm thick clear toughened glass sc 29 Sq.M. 1.00 Sq.M. 5000 =Rs 145,000 /-
PP190
PP190
PP191 With 6 mm thick wired glass 400.00 Sq.M. 4,500 1,800,000
PP191
PP191 Material
PP191 o 400 Sq.M. 1.00 Sq.M. =Rs /-
PP191
PP191 Labour
PP191 lc 400 Sq.M. 1.00 Sq.M. =Rs /-
PP191
PP191 Subcontract
PP191 With 6 mm thick wired glass sc 400 Sq.M. 1.00 Sq.M. 4500 =Rs 1,800,000 /-
PP191
PP191
PP192 Fire proof glass (2hr fire rating) 100.00 Sq.M. 7,000 700,000
PP192
PP192 Material
PP192 o 100 Sq.M. 1.00 Sq.M. =Rs /-
PP192
PP192 Labour
PP192 lc 100 Sq.M. 1.00 Sq.M. =Rs /-
PP192
PP192 Subcontract
PP192 Fire proof glass (2hr fire rating) sc 100 Sq.M. 1.00 Sq.M. 7000 =Rs 700,000 /-
PP192
PP192
PP193 Extra for colour anodizing over and above item no 84natural colour anodizing 1,200.00 Sq.M. 450 540,000
PP193
PP193 Material
PP193 o 1200 Sq.M. 1.00 Sq.M. =Rs /-
PP193
PP193 Labour
PP193 lc 1200 Sq.M. 1.00 Sq.M. =Rs /-
PP193
PP193 Subcontract
PP193 Extra for colour anodizing over and above item no 84natural colour anodizing sc 1200 Sq.M. 1.00 Sq.M. 450 =Rs 540,000 /-
PP193
PP193
PP194 Supplying, erecting and fixing heavy duty steel louvers fromapproved manufacturer at various elevations including frame, louvers fitting including bird screen as per specification and fixture, mastic caulking, grouting the frame, rawl bolt including one coat of primer and two coat of approved synthetic paint with all material, labour, equipment etc. complete . 200.00 Sq.M. 3,800 760,000
PP194
PP194 Material
PP194 o 200 Sq.M. 1.00 Sq.M. =Rs /-
Page 48 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP194
PP194 Labour
PP194 lc 200 Sq.M. 1.00 Sq.M. =Rs /-
PP194
PP194 Subcontract
PP194 Supplying, erecting and fixing heavy duty steel louvers fromapproved manufacturer at various elevations including frame, louvers fitting including bird screen as per specification and fixture, mastic caulking, grouting the frame, rawl bolt including one coat of primer and two coat of approved synthetic paint with all material, labour, equipment etc. complete . sc 200 Sq.M. 1.00 Sq.M. 3800 =Rs 760,000 /-
PP194
PP194
PP195 Supplyingandinstallingpartitionfromapprovedmanufacturer at all elevations in 100 mm x 45 mm and bottom frame 200 mm x 45 mm of 3 mm thick Anodized aluminum section of best approved quality frame workincluding full glazing with 8 mm thick toughened floatglass superior quality first grade of Modi float or equivalent approved by Engineer including frame, glazing beds, fittings and fixture, mastic caulking, putty, grouting the frame, rawl bolt, sealing after finishing etc. (glazing to be fixed to the framework with anodized aluminum channels or angles and rubber beading all around. The item rate shall include for all works including fixing of partitions to floor and roof and fixing of glass etc. complete as per specification and directions) 400.00 Sq.M. 5,600 2,240,000
PP195
PP195 Material
PP195 o 400 Sq.M. 1.00 Sq.M. =Rs /-
PP195
PP195 Labour
PP195 lc 400 Sq.M. 1.00 Sq.M. =Rs /-
PP195
PP195 Subcontract
PP195 Supplyingandinstallingpartitionfromapprovedmanufacturer at all elevations in 100 mm x 45 mm and bottom frame 200 mm x 45 mm of 3 mm thick Anodized aluminum section of best approved quality frame workincluding full glazing with 8 mm thick toughened floatglass superior quality first grade of Modi float or equivalent approved by Engineer including frame, glazing beds, fittings and fixture, mastic caulking, putty, grouting the frame, rawl bolt, sealing after finishing etc. (glazing to be fixed to the framework with anodized aluminum channels or angles and rubber beading all around. The item rate shall include for all works including fixing of partitions to floor and roof and fixing of glass etc. complete as per specification and directions) sc 400 Sq.M. 1.00 Sq.M. 5600 =Rs 2,240,000 /-
PP195
PP195
PP196 Providing, erecting and fixing45 mm thick flush typehollow metal doors with two outer sheets of 18 G rigidly connected with continuous vertical 20 G stiffener at the rate of 150 mm centre to centre and reinforced by 18 G pressed steel channel fixed in pressed steel frame as per IS: 4351. Mineral wool insulation is to be provided inside the channel with fixtures, fittings, hold fast and locking arrangements etc. including finishing with two coats of zinc chromate primer and two coats of Synthetic enamel paint.
PP197 Single leaf shutters 200.00 Sq.M. 8,402 1,680,365
PP197
PP197 Material
PP197 o 200 Sq.M. 1.00 Sq.M. =Rs /-
PP197
PP197 Labour
PP197 lc 200 Sq.M. 1.00 Sq.M. =Rs /-
PP197
PP197 Subcontract
PP197 Single leaf shutters sc 200 Sq.M. 1.00 Sq.M. 8,402 =Rs 1,680,365 /-
PP197
PP197
PP198 Double leaf shutters 250.00 Sq.M. 11,024 2,756,124
PP198
PP198 Material
PP198 o 250 Sq.M. 1.00 Sq.M. =Rs /-
PP198
PP198 Labour
PP198 lc 250 Sq.M. 1.00 Sq.M. =Rs /-
PP198
PP198 Subcontract
PP198 Double leaf shutters sc 250 Sq.M. 1.00 Sq.M. 11,024 =Rs 2,756,124 /-
PP198
PP198
PP199 Supplying fitting and fixing fully glazed frame less door (10mm thick toughened) fitted with Stainless steel end capswith locating lug and screw. Single extrusion profile for universal frameless glass door rails. Track shall be extruded hardened aluminum with a maximum channel wall thickness of 4.20 mm in 6060-T5 alloy. The weight of the extrusion shall be no less than 5.76 kg per lineal meter length. The rate should include the twin wheel carriage with a stabilizer wheel to prevent free side swing of the slydstak door panel, all complete as per manufacturer's detail, drawing and direction of the Engineer in charge including the cost of glass. 25.00 Sq.M. 15,000 375,000
Page 49 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP199
PP199 Material
PP199 o 25 Sq.M. 1.00 Sq.M. =Rs /-
PP199
PP199 Labour
PP199 lc 25 Sq.M. 1.00 Sq.M. =Rs /-
PP199
PP199 Subcontract
PP199 Supplying fitting and fixing fully glazed frame less door (10mm thick toughened) fitted with Stainless steel end capswith locating lug and screw. Single extrusion profile for universal frameless glass door rails. Track shall be extruded hardened aluminum with a maximum channel wall thickness of 4.20 mm in 6060-T5 alloy. The weight of the extrusion shall be no less than 5.76 kg per lineal meter length. The rate should include the twin wheel carriage with a stabilizer wheel to prevent free side swing of the slydstak door panel, all complete as per manufacturer's detail, drawing and direction of the Engineer in charge including the cost of glass. sc 25 Sq.M. 1.00 Sq.M. 15000 =Rs 375,000 /-
PP199
PP199
PP200 Supplying and erecting including assembling, fitting and fixingbest qualityfully glazed openable, fixed or partly openable type steel windows,ventilators with framesfrom approved manufacturer including fabrication, one coat of shop paint, all fittings and fixtures as per Schedule of fixtures, at various elevations, includingglazing beads, frames, shutters, transom, coupling mullions, weather bars, inclusive of supply of caulking, mastic, putty etc. including supplying, fitting and fixing 4 mm thick clear float glass as per drawings, specification & window schedule. 0.00 Sq.M. 3,190 3
PP200
PP200 Material
PP200 o 0 Sq.M. 1.00 Sq.M. =Rs /-
PP200
PP200 Labour
PP200 lc 0 Sq.M. 1.00 Sq.M. =Rs /-
PP200
PP200 Subcontract
PP200 Supplying and erecting including assembling, fitting and fixingbest qualityfully glazed openable, fixed or partly openable type steel windows,ventilators with framesfrom approved manufacturer including fabrication, one coat of shop paint, all fittings and fixtures as per Schedule of fixtures, at various elevations, includingglazing beads, frames, shutters, transom, coupling mullions, weather bars, inclusive of supply of caulking, mastic, putty etc. including supplying, fitting and fixing 4 mm thick clear float glass as per drawings, specification & window schedule. sc 0 Sq.M. 1.00 Sq.M. 3190 =Rs 3 /-
PP200
PP200
PP201 Extra over item (90) above for providing 5 mm thick clearfloat glass. 30.00 Sq.M. 3,410 102,300
PP201
PP201 Material
PP201 o 30 Sq.M. 1.00 Sq.M. =Rs /-
PP201
PP201 Labour
PP201 lc 30 Sq.M. 1.00 Sq.M. =Rs /-
PP201
PP201 Subcontract
PP201 Extra over item (90) above for providing 5 mm thick clearfloat glass. sc 30 Sq.M. 1.00 Sq.M. 3410 =Rs 102,300 /-
PP201
PP201
PP202 Extra over item (90) above for providing 6 mm thick wiredglass. 10.00 Sq.M. 3,960 39,600
PP202
PP202 Material
PP202 o 10 Sq.M. 1.00 Sq.M. =Rs /-
PP202
PP202 Labour
PP202 lc 10 Sq.M. 1.00 Sq.M. =Rs /-
PP202
PP202 Subcontract
PP202 Extra over item (90) above for providing 6 mm thick wiredglass. sc 10 Sq.M. 1.00 Sq.M. 3960 =Rs 39,600 /-
PP202
Page 50 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP202
PP203 Providing fitting and fixing fire proof metal doors withmineral wool insulation, conforming to IS: 3614 (Parts I &II) meeting TAC requirements and having a fire rating of two hours (min) at all levels and for all type of work , including all labour, materials workmanship including preparation of working drawings, equipments, handlings, transportation, steel frames ,shutter insulation, fitting, hinges, panic lock, latch, horizontal full width lever, openable on pressing door stoppersholdfasts/expandinganchorboltsbolting arrangements , grouting frames , blast cleaning of steel surfaces to near white metal surfaces applying inorganic zinc silicate primer of minimum 75 micron (DFT) and finish with suitable fire retardant painting system testing etc. all complete as per drawings, specification
PP204 Single leaf 130.00 Sq.M. 23,000 2,990,000
PP204
PP204 Material
PP204 o 130 Sq.M. 1.00 Sq.M. =Rs /-
PP204
PP204 Labour
PP204 lc 130 Sq.M. 1.00 Sq.M. =Rs /-
PP204
PP204 Subcontract
PP204 Single leaf sc 130 Sq.M. 1.00 Sq.M. 23000 =Rs 2,990,000 /-
PP204
PP204
PP205 Double leaf 100.00 Sq.M. 24,000 2,400,000
PP205
PP205 Material
PP205 o 100 Sq.M. 1.00 Sq.M. =Rs /-
PP205
PP205 Labour
PP205 lc 100 Sq.M. 1.00 Sq.M. =Rs /-
PP205
PP205 Subcontract
PP205 Double leaf sc 100 Sq.M. 1.00 Sq.M. 24000 =Rs 2,400,000 /-
PP205
PP205
PP206 Providing and fixing doors fabricated from roll formedsection made of Galvanized steel colour coated with total thickness of 0.6 mm. Coated sections should be painted with 12-16 microns thick polyester paint over a primer coat of Epoxy primer of 5-7 microns thick. The frame and shutter should be cut and mitre jointed with corner bracket made of CRCA electroplated made of CRCA electroplated EPDM gasket should be used all around glass in shutter, 10.00 Sq.M. 9,000 90,000
PP206
PP206 Material
PP206 o 10 Sq.M. 1.00 Sq.M. =Rs /-
PP206
PP206 Labour
PP206 lc 10 Sq.M. 1.00 Sq.M. =Rs /-
PP206
PP206 Subcontract
PP206 Providing and fixing doors fabricated from roll formedsection made of Galvanized steel colour coated with total thickness of 0.6 mm. Coated sections should be painted with 12-16 microns thick polyester paint over a primer coat of Epoxy primer of 5-7 microns thick. The frame and shutter should be cut and mitre jointed with corner bracket made of CRCA electroplated made of CRCA electroplated EPDM gasket should be used all around glass in shutter, sc 10 Sq.M. 1.00 Sq.M. 9000 =Rs 90,000 /-
PP206
PP206
PP207 between frame and glazed shutter and both sides of fixed glass. The frame along with the shutter should be fixed tobrick /concrete masonry by using Nylon self expanding caps and driving MS electroplated 80 mm long screws into thecaps through frames similar to NCL ALTECK and Seccolorltd.
PP208 Providing and fixing factory made 38 mm thick solid coreflush door from approved manufacturer with frame of teak wood and well matched commercial ply veneering wood with vertical grains or cross bands and face veneer on both faces of shutters including providing and fixing lipping with first class wood batten 10 mm thick on all edges of shutters including anodized aluminumtower bolt and mortised lock, with one coat of approved primer and two coats of synthetic enamel paint of approved make and shade, complete in all respect. 700.00 Sq.M. 13,500 9,450,000
PP208
PP208 Material
PP208 o 700 Sq.M. 1.00 Sq.M. =Rs /-
PP208
PP208 Labour
PP208 lc 700 Sq.M. 1.00 Sq.M. =Rs /-
Page 51 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP208
PP208 Subcontract
PP208 Providing and fixing factory made 38 mm thick solid coreflush door from approved manufacturer with frame of teak wood and well matched commercial ply veneering wood with vertical grains or cross bands and face veneer on both faces of shutters including providing and fixing lipping with first class wood batten 10 mm thick on all edges of shutters including anodized aluminumtower bolt and mortised lock, with one coat of approved primer and two coats of synthetic enamel paint of approved make and shade, complete in all respect. sc 700 Sq.M. 1.00 Sq.M. 13500 =Rs 9,450,000 /-
PP208
PP208
PP209 Same as above item no 93 but low in height as perdrawing and direction of the engineer in charge. 50.00 Sq.M. 12,500 625,000
PP209
PP209 Material
PP209 o 50 Sq.M. 1.00 Sq.M. =Rs /-
PP209
PP209 Labour
PP209 lc 50 Sq.M. 1.00 Sq.M. =Rs /-
PP209
PP209 Subcontract
PP209 Same as above item no 93 but low in height as perdrawing and direction of the engineer in charge. sc 50 Sq.M. 1.00 Sq.M. 12500 =Rs 625,000 /-
PP209
PP209
PP210 Supplying and fixing glazed vision panel (of minimum size200 mm X 200 mm) to doors with 6 mm thick glazing of tempered safety glass or wired glass including fitting andfixture with all material, labour, equipment etc. complete as per the instructions of Engineer. (Actual size of vision panel will be measured and paid) 5.00 Sq.M. 10,000 50,000
PP210
PP210 Material
PP210 o 5 Sq.M. 1.00 Sq.M. =Rs /-
PP210
PP210 Labour
PP210 lc 5 Sq.M. 1.00 Sq.M. =Rs /-
PP210
PP210 Subcontract
PP210 Supplying and fixing glazed vision panel (of minimum size200 mm X 200 mm) to doors with 6 mm thick glazing of tempered safety glass or wired glass including fitting andfixture with all material, labour, equipment etc. complete as per the instructions of Engineer. (Actual size of vision panel will be measured and paid) sc 5 Sq.M. 1.00 Sq.M. 10000 =Rs 50,000 /-
PP210
PP210
PP211 Supplying, fitting and fixing in position PVC door upto 1.0 M.wide including PVC frame and shutter of approved colour and make of approved System DS-06 or approved equal, complete in all respect including all accessories, complete hardware, grouting, fitting and fixing hardware with necessary fittings etc. as per manufacturer's specification, drawing and instruction of Engineer/Architect 50.00 Sq.M. 6,000 300,000
PP211
PP211 Material
PP211 o 50 Sq.M. 1.00 Sq.M. =Rs /-
PP211
PP211 Labour
PP211 lc 50 Sq.M. 1.00 Sq.M. =Rs /-
PP211
PP211 Subcontract
PP211 Supplying, fitting and fixing in position PVC door upto 1.0 M.wide including PVC frame and shutter of approved colour and make of approved System DS-06 or approved equal, complete in all respect including all accessories, complete hardware, grouting, fitting and fixing hardware with necessary fittings etc. as per manufacturer's specification, drawing and instruction of Engineer/Architect sc 50 Sq.M. 1.00 Sq.M. 6000 =Rs 300,000 /-
PP211
PP211
PP212 Supplying, erecting and fixing of steel rolling shutter with 18SWG steel laths with the provision of manual operation arrangement / mechanical gear operation arrangement, of any size with slide guides, bottom rail brackets, door supervision shaft, housing box at top with all necessary fittings, fixtures, locking arrangements gear, mechanical device etc. including finishing with 2 coats of Synthetic enamel paint of approved quality over one shop coat of zinc chromate primer etc. complete as per drawings specification and direction of Engineer including, labour, material equipment etc. complete (Measurement on the basis of opening covered by rolling shutters).
PP213 Hand operated 100.00 Sq.M. 4,500 450,000
PP213
PP213 Material
PP213 o 100 Sq.M. 1.00 Sq.M. =Rs /-
Page 52 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP213
PP213 Labour
PP213 lc 100 Sq.M. 1.00 Sq.M. =Rs /-
PP213
PP213 Subcontract
PP213 Hand operated sc 100 Sq.M. 1.00 Sq.M. 4500 =Rs 450,000 /-
PP213
PP213
PP214 With mechanically operated 18.00 Sq.M. 6,000 108,000
PP214
PP214 Material
PP214 o 18 Sq.M. 1.00 Sq.M. =Rs /-
PP214
PP214 Labour
PP214 lc 18 Sq.M. 1.00 Sq.M. =Rs /-
PP214
PP214 Subcontract
PP214 With mechanically operated sc 18 Sq.M. 1.00 Sq.M. 6000 =Rs 108,000 /-
PP214
PP214
PP215 With electrically operated 200.00 Sq.M. 25,000 5,000,000
PP215
PP215 Material
PP215 o 200 Sq.M. 1.00 Sq.M. =Rs /-
PP215
PP215 Labour
PP215 lc 200 Sq.M. 1.00 Sq.M. =Rs /-
PP215
PP215 Subcontract
PP215 With electrically operated lc 200 Sq.M. 1.00 Sq.M. 25000 =Rs 5,000,000 /-
PP215
PP215
PP216 Providing and fixing automatic operation system for doors(4 nos. sliding opening of openable size 2.4 m x 2.4 m) suitable for door openings consisting of sliding door shutters, opening on opposite sides, complete with solid state controller unit heavy duty reversible associate cabling and circuit etc. so as to provide flawless automatic operation, with all labour, material, equipment, handling, transportation,workmanship, preparation of working drawings, testing etc allcomplete as per specification, drawings, testing etc all complete as per specification, drawings and instructions of the Engineer. The Electric operating mechanism shall be mounted and concealed within Aluminum header and the controller unit shall be Micro processor based. The bottom rail of the door shall have security lock. Weather 25.00 Sq.M. 30,000 750,000
PP216
PP216 Material
PP216 o 25 Sq.M. 1.00 Sq.M. =Rs /-
PP216
PP216 Labour
PP216 lc 25 Sq.M. 1.00 Sq.M. =Rs /-
PP216
PP216 Subcontract
PP216 Providing and fixing automatic operation system for doors(4 nos. sliding opening of openable size 2.4 m x 2.4 m) suitable for door openings consisting of sliding door shutters, opening on opposite sides, complete with solid state controller unit heavy duty reversible associate cabling and circuit etc. so as to provide flawless automatic operation, with all labour, material, equipment, handling, transportation,workmanship, preparation of working drawings, testing etc allcomplete as per specification, drawings, testing etc all complete as per specification, drawings and instructions of the Engineer. The Electric operating mechanism shall be mounted and concealed within Aluminum header and the controller unit shall be Micro processor based. The bottom rail of the door shall have security lock. Weather sc 25 Sq.M. 1.00 Sq.M. 30000 =Rs 750,000 /-
PP216
PP216
PP217 stripping shall be provided along the edges of sliding door panels. Basic sensor system shall be of active infraredsensor type, header mounted on each side of the door and shall remain active throughout the door opening and closingcycle. Two pulsed infrared photo
PP218 Glazing
Page 53 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP219 Providing and fixing Unitised vertical Structural glazingsystem with IG unit(insulated double Glass unit) for vision panel and single glass for spandrel panel of approved make having main frame of verticals and horizontals made out of specially designed extruded aluminum sections to withstand wind pressure of 200 kg/sq.m. at a height to the Masonry /RC wall with necessary clamps, brackets and anchor fasteners . All clamps and brackets shall be Mild steel Hot Dip galvanized minimum80 microns thick and shall conform to IS: 4756-1996 .The extruded aluminum sections shall be anodized as per the approved colour withanodic coating of minimum 20microns .Extruded section shall be 6063 T5 or T6 alloyconforming to ASTM B 221 or BSH79 conforming to IS:63400. Any other fastening straps, clamps, nuts, bolts, rivets, washers etc. shall be stainless steel SS 304 grade or aluminum. All tapes shall be Norton make. Rate shall include providing Column closers, 200.00 Sq.M. 1,800 360,000
PP219
PP219 Material
PP219 o 200 Sq.M. 1.00 Sq.M. =Rs /-
PP219
PP219 Labour
PP219 lc 200 Sq.M. 1.00 Sq.M. =Rs /-
PP219
PP219 Subcontract
PP219 Providing and fixing Unitised vertical Structural glazingsystem with IG unit(insulated double Glass unit) for vision panel and single glass for spandrel panel of approved make having main frame of verticals and horizontals made out of specially designed extruded aluminum sections to withstand wind pressure of 200 kg/sq.m. at a height to the Masonry /RC wall with necessary clamps, brackets and anchor fasteners . All clamps and brackets shall be Mild steel Hot Dip galvanized minimum80 microns thick and shall conform to IS: 4756-1996 .The extruded aluminum sections shall be anodized as per the approved colour withanodic coating of minimum 20microns .Extruded section shall be 6063 T5 or T6 alloyconforming to ASTM B 221 or BSH79 conforming to IS:63400. Any other fastening straps, clamps, nuts, bolts, rivets, washers etc. shall be stainless steel SS 304 grade or aluminum. All tapes shall be Norton make. Rate shall include providing Column closers, sc 200 Sq.M. 1.00 Sq.M. 1800 =Rs 360,000 /-
PP219
PP219
PP220 Supplying bubble free float glass set in putty and fitted andfixed with nails and putty complete in all floors.
PP221 6 mm thick clear glass 15.00 Sq.M. 800 12,000
PP221
PP221 Material
PP221 o 15 Sq.M. 1.00 Sq.M. =Rs /-
PP221
PP221 Labour
PP221 lc 15 Sq.M. 1.00 Sq.M. =Rs /-
PP221
PP221 Subcontract
PP221 6 mm thick clear glass sc 15 Sq.M. 1.00 Sq.M. 800.00 =Rs 12,000 /-
PP221
PP221
PP222 4 mm thick clear glass 15.00 Sq.M. 700 10,500
PP222
PP222 Material
PP222 o 15 Sq.M. 1.00 Sq.M. =Rs /-
PP222
PP222 Labour
PP222 lc 15 Sq.M. 1.00 Sq.M. =Rs /-
PP222
PP222 Subcontract
PP222 4 mm thick clear glass sc 15 Sq.M. 1.00 Sq.M. 700 =Rs 10,500 /-
PP222
PP222
PP223 10 mm thick clear glass 15.00 Sq.M. 1,200 18,000
PP223
PP223 Material
PP223 o 15 Sq.M. 1.00 Sq.M. =Rs /-
PP223
PP223 Labour
PP223 lc 15 Sq.M. 1.00 Sq.M. =Rs /-
PP223
PP223 Subcontract
Page 54 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP223 10 mm thick clear glass sc 15 Sq.M. 1.00 Sq.M. 1200 =Rs 18,000 /-
PP223
PP223
PP224 4 mm thick figured glass 15.00 Sq.M. 1,500 22,500
PP224
PP224 Material
PP224 o 15 Sq.M. 1.00 Sq.M. =Rs /-
PP224
PP224 Labour
PP224 lc 15 Sq.M. 1.00 Sq.M. =Rs /-
PP224
PP224 Subcontract
PP224 4 mm thick figured glass sc 15 Sq.M. 1.00 Sq.M. 1500 =Rs 22,500 /-
PP224
PP224
PP225 Supplying and fixing composite double glazing consistingof clear float glass of 6 mm thick on one side and tinted glass of 6 mm thick on other side and are separated by12 mm air gap hermetically sealed by beading of anodized aluminum. 200.00 Sq.M. 3,500 700,000
PP225
PP225 Material
PP225 o 200 Sq.M. 1.00 Sq.M. =Rs /-
PP225
PP225 Labour
PP225 lc 200 Sq.M. 1.00 Sq.M. =Rs /-
PP225
PP225 Subcontract
PP225 Supplying and fixing composite double glazing consistingof clear float glass of 6 mm thick on one side and tinted glass of 6 mm thick on other side and are separated by12 mm air gap hermetically sealed by beading of anodized aluminum. sc 200 Sq.M. 1.00 Sq.M. 3500 =Rs 700,000 /-
PP225
PP225
PP226 Extra for 12 mm clear toughened float glass on bothsides instead of 6 mm thick glass 200.00 Sq.M. 3,200 640,000
PP226
PP226 Material
PP226 o 200 Sq.M. 1.00 Sq.M. =Rs /-
PP226
PP226 Labour
PP226 lc 200 Sq.M. 1.00 Sq.M. =Rs /-
PP226
PP226 Subcontract
PP226 Extra for 12 mm clear toughened float glass on bothsides instead of 6 mm thick glass sc 200 Sq.M. 1.00 Sq.M. 3200 =Rs 640,000 /-
PP226
PP226
PP227 Extra for 8 mm clear toughened float glass on both sidesinstead of 6 mm glass 100.00 Sq.M. 3,000 300,000
PP227
PP227 Material
PP227 o 100 Sq.M. 1.00 Sq.M. =Rs /-
PP227
PP227 Labour
PP227 lc 100 Sq.M. 1.00 Sq.M. =Rs /-
Page 55 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP227
PP227 Subcontract
PP227 Extra for 8 mm clear toughened float glass on both sidesinstead of 6 mm glass sc 100 Sq.M. 1.00 Sq.M. 3000 =Rs 300,000 /-
PP227
PP227
PP228 Supplying and fixing Glaverbal heat reflecting glass ofthickness 8 mm of AIS float glass or of approved equivalent 10.00 Sq.M. 5,000 50,000
PP228
PP228 Material
PP228 o 10 Sq.M. 1.00 Sq.M. =Rs /-
PP228
PP228 Labour
PP228 lc 10 Sq.M. 1.00 Sq.M. =Rs /-
PP228
PP228 Subcontract
PP228 Supplying and fixing Glaverbal heat reflecting glass ofthickness 8 mm of AIS float glass or of approved equivalent sc 10 Sq.M. 1.00 Sq.M. 5000 =Rs 50,000 /-
PP228
PP228
PP229 Painting
PP230 Providing and applying white cement putty of minimum 2mm thick (over plaster) at various elevations in interior surfaces with all materials etc. complete as per specifications 1,000.00 Sq.M. 120 120,000
PP230
PP230 Material
PP230 o 1000 Sq.M. 1.00 Sq.M. =Rs /-
PP230
PP230 Labour
PP230 lc 1000 Sq.M. 1.00 Sq.M. =Rs /-
PP230
PP230 Subcontract
PP230 Providing and applying white cement putty of minimum 2mm thick (over plaster) at various elevations in interior surfaces with all materials etc. complete as per specifications sc 1000 Sq.M. 1.00 Sq.M. 120 =Rs 120,000 /-
PP230
PP230
PP231 Providing and applying Oil bound crylic distemper of approved makeconsisting of a priming coat with approved primer over white cement putty and two (2) finishing coats of paint ofapproved manufacture and quality approved shades, including labour, materials, equipment and scaffolding etc. complete as per manufacturer's instructions at all elevations. 2,683.00 Sq.M. 160 429,280
PP231
PP231 Material
PP231 o 2683 Sq.M. 1.00 Sq.M. =Rs /-
PP231
PP231 Labour
PP231 lc 2683 Sq.M. 1.00 Sq.M. =Rs /-
PP231
PP231 Subcontract
PP231 sc 2683 Sq.M. 1.00 Sq.M. 160 =Rs 429,280 /-
PP231
PP231
PP232 Providing and applying acrylic emulsion paint of approvedmake consisting of a priming coat with approved primer over white cement putty and two (2) finishing coats of paint of approved manufacture and quality approved shades, including labour, materials, equipment and scaffolding etc. complete as per manufacturer's instructions at all elevations. 5,500.00 Sq.M. 160 880,000
PP232
PP232 Material
PP232 o 5500 Sq.M. 1.00 Sq.M. =Rs /-
Page 56 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP232
PP232 Labour
PP232 lc 5500 Sq.M. 1.00 Sq.M. =Rs /-
PP232
PP232 Subcontract
PP232 sc 5500 Sq.M. 1.00 Sq.M. 160 =Rs 880,000 /-
PP232
PP232
PP233 Providing and applying chemical resistant paint ofapproved make applied on a clean surface free of oils etc. after applying approved primer coat to seal the surface porosity followed by two (2) full coats of the paint, including labour, material, equipment, and scaffolding etc. at all elevations and heights as per manufacturer's specification and direction of the Engineer. 1,000.00 Sq.M. 320 320,000
PP233
PP233 Material
PP233 o 1000 Sq.M. 1.00 Sq.M. =Rs /-
PP233
PP233 Labour
PP233 lc 1000 Sq.M. 1.00 Sq.M. =Rs /-
PP233
PP233 Subcontract
PP233 sc 1000 Sq.M. 1.00 Sq.M. 320 =Rs 320,000 /-
PP233
PP233
PP234 Providing and applying three (3) coats of water proofcement paint of approved manufacturer (Snowcem or equivalent approved by the Engineer-in-charge) and in approved shades to plastered surfaces including cleaning and preparing the wall surface, curing etc. complete as per specifications and directions of Engineer at all elevations including labour, material, scaffolding etc. complete. 3,755.50 Sq.M. 180 675,990
PP234
PP234 Material
PP234 o 3756 Sq.M. 1.00 Sq.M. =Rs /-
PP234
PP234 Labour
PP234 lc 3756 Sq.M. 1.00 Sq.M. =Rs /-
PP234
PP234 Subcontract
PP234 sc 3756 Sq.M. 1.00 Sq.M. 180 =Rs 675,990 /-
PP234
PP234
PP235 Providing and applying three (3) coats of synthetic plastercomposed of synthetic fiber and petroleum based chemical similar to 'RENOVO' of approved shade to plastered surfaces including cleaning and preparing the wall surface, curing etc. complete as per specifications and directions of Engineer at all elevations including labour, material, scaffolding etc. complete. 1,500.00 Sq.M. 350 525,000
PP235
PP235 Material
PP235 o 1500 Sq.M. 1.00 Sq.M. =Rs /-
PP235
PP235 Labour
PP235 lc 1500 Sq.M. 1.00 Sq.M. =Rs /-
PP235
PP235 Subcontract
PP235 sc 1500 Sq.M. 1.00 Sq.M. 350 =Rs 525,000 /-
PP235
PP235
PP236 Providing and application of ready mix two componentresin and polymer bonded granular textured coating finish of approved colour and shade for all types plaster and/ exposed concrete surfaces in all kinds of work at all levels including preparation of surfaces , preparation of working drawing,labour,materials,equipments,handling, transportation, mixing , laying, applying , finishing, testing, curing, making grooves, scaffolding, staging, etc. all complete as per specifications, drawing and the instruction of the Engineer for the following nominal thickness:
PP237 1.2 mm pigmented granular for interior application 2,500.00 Sq.M. 420 1,050,000
Page 57 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP237
PP237 Material
PP237 o 2500 Sq.M. 1.00 Sq.M. =Rs /-
PP237
PP237 Labour
PP237 lc 2500 Sq.M. 1.00 Sq.M. =Rs /-
PP237
PP237 Subcontract
PP237 sc 2500 Sq.M. 1.00 Sq.M. 420 =Rs 1,050,000 /-
PP237
PP237
PP238 2.5 mm natural stone chips for external finish in ready mix. 2,500.00 Sq.M. 480 1,200,000
PP238
PP238 Material
PP238 o 2500 Sq.M. 1.00 Sq.M. =Rs /-
PP238
PP238 Labour
PP238 lc 2500 Sq.M. 1.00 Sq.M. =Rs /-
PP238
PP238 Subcontract
PP238 sc 2500 Sq.M. 1.00 Sq.M. 480 =Rs 1,200,000 /-
PP238
PP238
PP239 Painting with best qualitysynthetic enamel paint ofapproved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface , if necessary:
PP240 On timber or plastered surface: 1,000.00 Sq.m. 150 150,000
PP240
PP240 Material
PP240 o 1000 Sq.m. 1.00 Sq.m. =Rs /-
PP240
PP240 Labour
PP240 lc 1000 Sq.m. 1.00 Sq.m. =Rs /-
PP240
PP240 Subcontract
PP240 sc 1000 Sq.m. 1.00 Sq.m. 150 =Rs 150,000 /-
PP240
PP240
PP241 False Ceiling
PP242 Providing and fixing Glass Reinforced (GRG) false ceilingsystem having fine texture finish, at all levels for all kind ofwork which includes providing and fixing GI perimeter Channels of size 0.55 mm thickness having one flange of 20 mm and another flange of 30 mm and a web of 27 mm along with perimeter of ceiling, screw fixed to brick wall / partition with the help of nylon sleeves and screws at 610 mm centers. Then suspending GI intermediate channels of size 45 mm,0.9 mm thick with two flanges of size 45 mm, 0.9 mm thick with two flanges of size 15 mm each from the soffit at 1200 mm centers with ceiling angle of width 25 mm x 25 mm x 0.55 mm thick fixed to soffit with GI cleat and steel expansion fastener. Ceiling section of 0.55 mm thickness having knurled web of 51.5 mm and two flanges of 26 mm each with lips of10.5 mm are then fixed to the intermediate channel with the help of connecting clips and in direction perpendicular to the intermediate channel at 457 mm centers. 12 mm thick GRG Board is then
PP243 12 mm thick GRG plaster board, finished seamless. 1,000.00 Sq M. 1,241 1,240,625
PP243
PP243 Material
PP243 o 1000 Sq M. 1.00 Sq M. =Rs /-
PP243
PP243 Labour
PP243 lc 1000 Sq M. 1.00 Sq M. =Rs /-
PP243
Page 58 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP243 Subcontract
PP243 12 mm thick GRG plaster board, finished seamless. sc 1000 Sq M. 1.00 Sq M. 1241 =Rs 1,240,625 /-
PP243 quote received
PP243
PP244 Providing and fixing insulation of resin bonded mineralwool 25 mm nominal thickness conforming to IS: 8183, having a density of 32 kg/cum for glass wool or 48 kg/cum for rock wool insulation over false ceiling , at all levels for all kinds of work, handling transportation etc. including all labour, material, scaffolding, equipment, wrapped in polyethylene sheet bags with or without framed strips 25 x 3 mm (minimum) at maximum 300 mm. centre to centre spacing to hold the insulation between horizontal sheeting runners, keeping in position with galvanized hexagonal wire netting of 0.3 mm wire diameter and 19 mm mesh size for glass/rock wool as per specifications drawings and instruction of the Engineer . 200.00 Sq M 525 105,000
PP244
PP244 Material
PP244 o 200 Sq M 1.00 Sq M =Rs /-
PP244
PP244 Labour
PP244 lc 200 Sq M 1.00 Sq M =Rs /-
PP244
PP244 Subcontract
PP244 Providing and fixing insulation of resin bonded mineralwool 25 mm nominal thickness conforming to IS: 8183, having a density of 32 kg/cum for glass wool or 48 kg/cum for rock wool insulation over false ceiling , at all levels for all kinds of work, handling transportation etc. including all labour, material, scaffolding, equipment, wrapped in polyethylene sheet bags with or without framed strips 25 x 3 mm (minimum) at maximum 300 mm. centre to centre spacing to hold the insulation between horizontal sheeting runners, keeping in position with galvanized hexagonal wire netting of 0.3 mm wire diameter and 19 mm mesh size for glass/rock wool as per specifications drawings and instruction of the Engineer . sc 200 Sq M 1.00 Sq M 525 =Rs 105,000 /-
PP244 quote received
PP244
PP245 Providing and fixing insulation of resin bonded mineralwool 50 mm nominal thickness conforming to IS: 8183, having a density of 32 kg/cum for glass wool or 48 kg/cum for rock wool under deck insulation, at all levels for all kinds of work, handling transportation etc. including all labour ,material, scaffolding, equipment, wrapped in polyethylene sheet bags with or without framed strips 25 x 3 mm (minimum ) at maximum 300 mm. centre to centre spacing to hold the insulation between horizontal sheeting runners, keeping in position with galvanized hexagonal wire netting of 0.3 mm wire diameter and 19 mm mesh size for glass/rock wool as per specifications drawings and instruction of the Engineer . 100.00 SQM 709 70,875
PP245
PP245 Material
PP245 o 100 SQM 1.00 SQM =Rs /-
PP245
PP245 Labour
PP245 lc 100 SQM 1.00 SQM =Rs /-
PP245
PP245 Subcontract
PP245 Providing and fixing insulation of resin bonded mineralwool 50 mm nominal thickness conforming to IS: 8183, having a density of 32 kg/cum for glass wool or 48 kg/cum for rock wool under deck insulation, at all levels for all kinds of work, handling transportation etc. including all labour ,material, scaffolding, equipment, wrapped in polyethylene sheet bags with or without framed strips 25 x 3 mm (minimum ) at maximum 300 mm. centre to centre spacing to hold the insulation between horizontal sheeting runners, keeping in position with galvanized hexagonal wire netting of 0.3 mm wire diameter and 19 mm mesh size for glass/rock wool as per specifications drawings and instruction of the Engineer . sc 100 SQM 1.00 SQM 709 =Rs 70,875 /-
PP245 quote received
PP245
PP246 Providing and fixing Polyisocyanurate or rigid fenolic foam(fire and non toxic) preformed insulation slab conforming to IS: 12436/ IS: 13204 having 30 mm nominal thickness, having a density of 32 kg/cum bottom face of the slablaminated with 0.05 mm thick aluminum foil, as underdeck insulation at all levels fixed with adhesive followed by metal expansion fasteners at the spacing not more than 450 center to center including all labour ,material, scaffolding etc. all complete as per specifications drawings and instruction of the Engineer 3,000.00 Sq.m. 1,313 3,937,500
PP246
PP246 Material
PP246 o 3000 Sq.m. 1.00 Sq.m. =Rs /-
PP246
PP246 Labour
PP246 lc 3000 Sq.m. 1.00 Sq.m. =Rs /-
PP246
PP246 Subcontract
PP246 Providing and fixing Polyisocyanurate or rigid fenolic foam(fire and non toxic) preformed insulation slab conforming to IS: 12436/ IS: 13204 having 30 mm nominal thickness, having a density of 32 kg/cum bottom face of the slablaminated with 0.05 mm thick aluminum foil, as underdeck insulation at all levels fixed with adhesive followed by metal expansion fasteners at the spacing not more than 450 center to center including all labour ,material, scaffolding etc. all complete as per specifications drawings and instruction of the Engineer sc 3000 Sq.m. 1.00 Sq.m. 1313 =Rs 3,937,500 /-
PP246 quote received
PP246
PP247 Preparation of grading underbed with 1:1 1/2:3 concrete ofcement: coarse sand: 12 mm down stone chips (by volume) at various elevations for roof waterproofing works etc. complete including mixing laying, curing etc. with all materials complete as per drawing and specification. 500.00 Cu.m. 5,200 2,600,000
PP247
PP247 Material
PP247 o 500 Cu.m. 1.00 Cu.m. =Rs /-
PP247
PP247 Labour
Page 59 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP247 lc 500 Cu.m. 1.00 Cu.m. =Rs /-
PP247
PP247 Subcontract
PP247 Preparation of grading underbed with 1:1 1/2:3 concrete ofcement: coarse sand: 12 mm down stone chips (by volume) at various elevations for roof waterproofing works etc. complete including mixing laying, curing etc. with all materials complete as per drawing and specification. sc 500 Cu.m. 1.00 Cu.m. 5200 =Rs 2,600,000 /-
PP247
PP247
PP248 Preparation of minimum 25 mm to maximum 50 mm thickgrading underbed with 1:4 cement: coarse sand mortar (by volume) at various elevations for roof waterproofing works including mixing, laying, curing etc. with all materials complete as per drawings and specifications. 11,000.00 Sq.M 210 2,310,000
PP248
PP248 Material
PP248 o 11000 Sq.M 1.00 Sq.M =Rs /-
PP248
PP248 Labour
PP248 lc 11000 Sq.M 1.00 Sq.M =Rs /-
PP248
PP248 Subcontract
PP248 sc 11000 Sq.M 1.00 Sq.M 210 =Rs 2,310,000 /-
PP248
PP248
PP249 Supplying and laying roof insulation with 50 mm thickexpanded polystyrene Blocks similar to Supreme or similar approved make at various elevations including preparation of surface, laying blocks, pointing etc. as per manufacturers specification with al materials etc. complete as per drawings and specifications. 200.00 Sq.M 680 136,000
PP249
PP249 Material
PP249 o 200 Sq.M 1.00 Sq.M =Rs /-
PP249
PP249 Labour
PP249 lc 200 Sq.M 1.00 Sq.M =Rs /-
PP249
PP249 Subcontract
PP249 Supplying and laying roof insulation with 50 mm thickexpanded polystyrene Blocks similar to Supreme or similar approved make at various elevations including preparation of surface, laying blocks, pointing etc. as per manufacturers specification with al materials etc. complete as per drawings and specifications. sc 200 Sq.M 1.00 Sq.M 680 =Rs 136,000 /-
PP249
PP249
PP250 Supplying and laying 150 mm x 150 mm fillets at junctionof roof and parapet wall with Expanded Polystyrene Blocks at various elevations etc. complete similar to Item above. 5.00 Rm 120 600
PP250
PP250 Material
PP250 o 5 Rm 1.00 Rm =Rs /-
PP250
PP250 Labour
PP250 lc 5 Rm 1.00 Rm =Rs /-
PP250
PP250 Subcontract
PP250 Supplying and laying 150 mm x 150 mm fillets at junctionof roof and parapet wall with Expanded Polystyrene Blocks at various elevations etc. complete similar to Item above. sc 5 Rm 1.00 Rm 120 =Rs 600 /-
PP250
PP250
PP251 Roof water proofing treatment for buildings and structureshall be provided using high solid content liquid elastomeric water proofing membrane with separate wearing course as per ASTM C-898. Thickness of the membrane shall be 1.5 mm. This treatment shall include application of polymerized mastic over the roof to achieve smooth surface and primer coat. Wearing course on top of the membrane shall consist of 25 mm thick PCC (1:11/2:3), cast in panels of max. 1.5 m x 1.5 m size and reinforced with 0.56 mm dia. galvanised chicken wire meshandsealingofjointsusingsealing compound/elastomeric water proofing membrane at all levels and for all types of work, in vertical and horizontal surfaces , handling, scaffolding, transporting, testing etc. all complete as per specifications, drawing and direction of the Engineer in charge. 11,000.00 Sq.M 690 7,590,000
PP251
PP251 Material
PP251 o 11000 Sq.M 1.00 Sq.M =Rs /-
Page 60 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP251
PP251 Labour
PP251 lc 11000 Sq.M 1.00 Sq.M =Rs /-
PP251
PP251 Subcontract
PP251 Roof water proofing treatment for buildings and structureshall be provided using high solid content liquid elastomeric water proofing membrane with separate wearing course as per ASTM C-898. Thickness of the membrane shall be 1.5 mm. This treatment shall include application of polymerized mastic over the roof to achieve smooth surface and primer coat. Wearing course on top of the membrane shall consist of 25 mm thick PCC (1:11/2:3), cast in panels of max. 1.5 m x 1.5 m size and reinforced with 0.56 mm dia. galvanised chicken wire meshandsealingofjointsusingsealing compound/elastomeric water proofing membrane at all levels and for all types of work, in vertical and horizontal surfaces , handling, scaffolding, transporting, testing etc. all complete as per specifications, drawing and direction of the Engineer in charge. sc 11000 Sq.M 1.00 Sq.M 690 =Rs 7,590,000 /-
PP251 site rate
PP251
PP252 Supplying and installing at all elevations Armstrongsuspended ceiling in specified profile of following types as manufactured by Armstrong World Industries (I) Pvt. Ltd. strictly as per drawings, specifications, manufacturers specifications, standards and installed by manufacturers authorized agency in best workmanship manner complete in all respect with all materials, labour, tools, etc. including metal suspension system consisting of Armstrong stitched Trulok 15 exposed grid of 600 x 600 mm module with 15 mm wide T-section flanges, main runners at 1200 mm centers, suspension channels, angles, braces as required, securely fixed to the structural steel truss, purlins etc with approved adjustable hangers at 1200 mm (max) centers, flush fitting cross tees, interlocked between main runners at 600 mm center forming 1200 x 600 mm modules, flush fitting cut-cross Tees between the cross Tees to form 600 x 600 mm module and 600 x 600 mm ceiling tiles of approved type and colour finishin 1,500.00 Sq.M 1,260 1,890,000
PP252
PP252 Material
PP252 o 1500 Sq.M 1.00 Sq.M =Rs /-
PP252
PP252 Labour
PP252 lc 1500 Sq.M 1.00 Sq.M =Rs /-
PP252
PP252 Subcontract
PP252 Supplying and installing at all elevations Armstrong suspended ceiling in specified profile of following types as manufactured by Armstrong World Industries (I) Pvt. Ltd. strictly as per drawings, specifications, manufacturers specifications, standards and installed by manufacturers authorized agency in best workmanship manner complete in all respect with all materials, labour, tools, etc. including metal suspension system consisting of Armstrong stitched Trulok 15 exposed grid of 600 x 600 mm module with 15 mm wide T-section flanges, main runners at 1200 mm centers, suspension channels, angles, braces as required, securely fixed to the structural steel truss, purlins etc with approved adjustable hangers at 1200 mm (max) centers, flush fitting cross tees, interlocked between main runners at 600 mm center forming 1200 x 600 mm modules, flush fitting cut-cross Tees between the cross Tees to form 600 x 600 mm module and 600 x 600 mm ceiling tiles of approved type and colour finishin sc 1500 Sq.M 1.00 Sq.M 1260 =Rs 1,890,000 /-
PP252
PP252
PP253 15 mm thick PRIMA DUNE SUPREME RH 99 of Microlooktype having minimum 0.5 NRC value. 100.00 Sq.M 1,470 147,000
PP253
PP253 Material
PP253 o 100 Sq.M 1.00 Sq.M =Rs /-
PP253
PP253 Labour
PP253 lc 100 Sq.M 1.00 Sq.M =Rs /-
PP253
PP253 Subcontract
PP253 sc 100 Sq.M 1.00 Sq.M 1470 =Rs 147,000 /-
PP253
PP253
PP254 Providing and fixing pre-painted aluminum linear falseceiling system to 'Luxalon' of Hunter Douglas or of approved equivalent at all levels for all kinds of work including matching pre-painted profile carrier for fixing oflinear type panels by snap fit arrangement suspendedfrom RCC slab/ structural steel or catwalk steel channel grid above with 4 mm (min.) rods with special height adjustment clips ,providing angle section of minimum 25 mm leg width along the perimeter of ceiling , including all labour, material, supporting grid system equipment, handling transportation ,workmanship, anchor fasteners for making suspension arrangement , preparation of working drawings providing opening , for AC ducts return air grills, insulation light fixtures, etc. all complete as per specifications drawings& instruction of the Engineer (Cat walkway grid & insulation if provided to be paid separately under relevant item) 750.00 Sq.M. 1,890 1,417,500
PP254
PP254 Material
PP254 o 750 Sq.M. 1.00 Sq.M. =Rs /-
PP254
PP254 Labour
PP254 lc 750 Sq.M. 1.00 Sq.M. =Rs /-
PP254
PP254 Subcontract
PP254 Providing and fixing pre-painted aluminum linear falseceiling system to 'Luxalon' of Hunter Douglas or of approved equivalent at all levels for all kinds of work including matching pre-painted profile carrier for fixing oflinear type panels by snap fit arrangement suspendedfrom RCC slab/ structural steel or catwalk steel channel grid above with 4 mm (min.) rods with special height adjustment clips ,providing angle section of minimum 25 mm leg width along the perimeter of ceiling , including all labour, material, supporting grid system equipment, handling transportation ,workmanship, anchor fasteners for making suspension arrangement , preparation of working drawings providing opening , for AC ducts return air grills, insulation light fixtures, etc. all complete as per specifications drawings& instruction of the Engineer (Cat walkway grid & insulation if provided to be paid separately under relevant item) sc 750 Sq.M. 1.00 Sq.M. 1890 =Rs 1,417,500 /-
PP254
PP254
PP255 Metal Cladding & Roofing and Metal Decking Sheets
PP256 Supplying and laying & fixing of 0.8 mm thick metal deckformwork of cold formed steel profile - Trapezoidal decking profile with valley depth 44mm and pitch/centre to centre distance of the valley about 130 mm including of approved make as permanent shuttering for casting R.C.C. roof on steel purlins, with all fixtures and welded studs (stud. dia 16 mm hex. head, 75 mm long at a spacing @390 mm C/C welded to steel purlin) on top of steel purlins all complete as per drawings, specifications and direction of engineer. The deck sheet shall conform to AS1397 / ASTM653M or equivalent with Z275 coating. The exposedsurface shall be 20 micron SMP over primer of 5 microns. The surface in contact with concrete will have 5 microns primer. 984.00 Sq.M 1,585 1,559,689
Page 61 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP256
PP256 Material rate seems to be v ery less
PP256 Metal deck: site rate including studs o 984 Sq.M 1.05 Sq.M 1081 =Rs 1,116,889 /-
PP256
PP256 Labour
PP256 Supplying and laying & fixing of 0.8 mm thick metal deckformwork of cold formed steel profile - Trapezoidal decking profile with valley depth 44mm and pitch/centre to centre distance of the valley about 130 mm including of approved make as permanent shuttering for casting R.C.C. roof on steel purlins, with all fixtures and welded studs (stud. dia 16 mm hex. head, 75 mm long at a spacing @390 mm C/C welded to steel purlin) on top of steel purlins all complete as per drawings, specifications and direction of engineer. The deck sheet shall conform to AS1397 / ASTM653M or equivalent with Z275 coating. The exposedsurface shall be 20 micron SMP over primer of 5 microns. The surface in contact with concrete will have 5 microns primer. lc 984 Sq.M 1.00 Sq.M 450 =Rs 442,800 /-
PP256 site rate including studs
PP256 Subcontract
PP256 sc 984 Sq.M 1.00 Sq.M =Rs /-
PP256
PP256
PP257 Supplying and laying & fixing of 1.0 mm thick metal deckformwork of cold formed steel profile - Trapezoidal decking profile with valley depth 44mm and pitch/centre to centre distance of the valley about 130 mm permanent shuttering for casting R.C.C. floor on steel floor beams, with all fixtures and welded studs (stud. dia 16 mm hex. head, 75 mm long at a spacing @ 390mm C/C welded to steel purlin) on top of steel purlins all complete as per drawings, specifications and direction of engineer. The deck sheet shall conform to AS1397 / ASTM 653M or equivalent with Z275 coating. The exposed surface shall be 20 micron SMP over primer of 5 microns. The surface in contact with concrete will have 5 microns primer. 31,000.00 Sq.M. 2,253 69,829,825
PP257
PP257 Material
PP257 Metal deck: assumed o 31000 Sq.M. 1.05 Sq.M. 1622 =Rs 52,779,825 /-
PP257
PP257 Labour
PP257 Supplying and laying & fixing of 1.0 mm thick metal deckformwork of cold formed steel profile - Trapezoidal decking profile with valley depth 44mm and pitch/centre to centre distance of the valley about 130 mm permanent shuttering for casting R.C.C. floor on steel floor beams, with all fixtures and welded studs (stud. dia 16 mm hex. head, 75 mm long at a spacing @ 390mm C/C welded to steel purlin) on top of steel purlins all complete as per drawings, specifications and direction of engineer. The deck sheet shall conform to AS1397 / ASTM 653M or equivalent with Z275 coating. The exposed surface shall be 20 micron SMP over primer of 5 microns. The surface in contact with concrete will have 5 microns primer. lc 31000 Sq.M. 1.00 Sq.M. 550 =Rs 17,050,000 /-
PP257
PP257 Subcontract
PP257 sc 31000 Sq.M. 1.00 Sq.M. =Rs /-
PP257
PP257
PP258 Supply, fitting, fixing in position true to line and level pre-coated GALVALUME cold rolled single skin sheet havingprofile depth of minimum 30mm with a pitch of maximum 250 mm and minimum cover width of 1020mm with two stiffening ribs made out of 0.5 mm BMT Galvalume steel. Theprofiled sheets shall be minimum 0.5 mm BMT, Zinc Aluminum coated steel (AZ 150) of strength 550 MPa and finished with 20 microns color coating of SMP color paint coat as per AS/NZS - 2728 : 1997 on exposed surface over a primer coat of 5 microns of approved color. On other side (unexposed), 5 microns SMP over primer of 5 microns. Sheet shall conform to ASTM A792M / AS 1397 or equivalent 17,000.00 Sq.M. 3,070 52,190,000
PP258
PP258 Material
PP258 skin sheet o 17000 Sq.M. 1.05 Sq.M. 2400 =Rs 42,840,000 /-
PP258
PP258 Labour
PP258 Supply, fitting, fixing in position true to line and level pre-coated GALVALUME cold rolled single skin sheet havingprofile depth of minimum 30mm with a pitch of maximum 250 mm and minimum cover width of 1020mm with two stiffening ribs made out of 0.5 mm BMT Galvalume steel. Theprofiled sheets shall be minimum 0.5 mm BMT, Zinc Aluminum coated steel (AZ 150) of strength 550 MPa and finished with 20 microns color coating of SMP color paint coat as per AS/NZS - 2728 : 1997 on exposed surface over a primer coat of 5 microns of approved color. On other side (unexposed), 5 microns SMP over primer of 5 microns. Sheet shall conform to ASTM A792M / AS 1397 or equivalent lc 17000 Sq.M. 1.00 Sq.M. 550 =Rs 9,350,000 /-
PP258
PP258 Subcontract
PP258 sc 17000 Sq.M. 1.00 Sq.M. =Rs /-
PP258
PP258
PP259 Extra over item 124.a above for cripping, curved profile asper the detailed drawing and as directed by the Engineer. 200.00 Sq.M 600 120,000
PP259
PP259 Material
PP259 o 200 Sq.M 1.05 Sq.M =Rs /-
PP259
PP259 Labour
PP259 Extra over item 124.a above for cripping, curved profile asper the detailed drawing and as directed by the Engineer. lc 200 Sq.M 1.00 Sq.M 600 =Rs 120,000 /-
PP259
PP259 Subcontract
PP259 sc 200 Sq.M 1.00 Sq.M =Rs /-
PP259
Page 62 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP259
PP260 Providing and fixing at all levels aluminum compositepanels cladding comprising of 4 mm thick thermo plastic core of mind low density polyethylene sandwiched between two skins of minimum 0.5 mm thickness aluminum sheet, protected with self adhesive peel of masking foil, coating thickness panel weight, thermal expansion, tensile strength, yield strength elongation, flexural elasticity, deflection, heat transmission etc. shall be as per the best international practice fixed on the supporting aluminum extruded section and MS structural sealants and 100.00 Sq.M. 3,100 310,000
PP260
PP260 Material
PP260 o 100 Sq.M. 1.00 Sq.M. =Rs /-
PP260
PP260 Labour
PP260 lc 100 Sq.M. 1.00 Sq.M. =Rs /-
PP260
PP260 Subcontract
PP260 Providing and fixing at all levels aluminum compositepanels cladding comprising of 4 mm thick thermo plastic core of mind low density polyethylene sandwiched between two skins of minimum 0.5 mm thickness aluminum sheet, protected with self adhesive peel of masking foil, coating thickness panel weight, thermal expansion, tensile strength, yield strength elongation, flexural elasticity, deflection, heat transmission etc. shall be as per the best international practice fixed on the supporting aluminum extruded section and MS structural sealants and sc 100 Sq.M. 1.00 Sq.M. 3100 =Rs 310,000 /-
PP260 quote received
PP260
PP261 anchor/SS fasteners hardware complete with all labour, materials, equipment, handling, transportation, workmanshippreparation of working drawings, staging, scaffolding, etc. all complete as per specifications, drawings, and instructions ofthe Engineer (aluminum work, if any shall be inclusive of theitem)
PP262 Design, supply, installation of curved dome structure of 10m diameter (approx) with 4m high for the sky light in the roof of service building with embossed U.V. Resistant, multi wall poly carbonate sheet 6 mm thick with 82% light transmission, K value 3.5 and fixed to powder coated aluminumextruded framing including fabrication and erection of steel structural framing to obtain the required shape, with adequate provision for expansion including all fittings, anchoring accessories, fixtures, joint sealing with EPDM gaskets to make the complete structure water proof, fitting & fixing the structural member, etc. complete with all labour, material, equipments, handling, transportation, workmanship, preparation of working drawings, including structural design all as approved design and instructions of the Engineer. Item to include foundation bolts, plates, square tubes, all supporting structures including painting etc. complete in all respects. 1.00 Each 1,500,000 1,500,000
PP262
PP262 Material
PP262 o 1 Each 1.00 Each =Rs /-
PP262
PP262 Labour
PP262 lc 1 Each 1.00 Each =Rs /-
PP262
PP262 Subcontract
PP262 Design, supply, installation of curved dome structure of 10m diameter (approx) with 4m high for the sky light in the roof of service building with embossed U.V. Resistant, multi wall poly carbonate sheet 6 mm thick with 82% light transmission, K value 3.5 and fixed to powder coated aluminumextruded framing including fabrication and erection of steel structural framing to obtain the required shape, with adequate provision for expansion including all fittings, anchoring accessories, fixtures, joint sealing with EPDM gaskets to make the complete structure water proof, fitting & fixing the structural member, etc. complete with all labour, material, equipments, handling, transportation, workmanship, preparation of working drawings, including structural design all as approved design and instructions of the Engineer. Item to include foundation bolts, plates, square tubes, all supporting structures including painting etc. complete in all respects. sc 1 Each 1.00 Each 1500000 =Rs 1,500,000 /-
PP262
PP262
PP263 Supplying fitting & fixing in position 4mm thick, 2100mmwide and 2000 to 12000mm long clear or colored transparent profiled (matching with profile of metal side cladding) polycarbonate sheets at all elevations having UV, Yellowing, Abrasion resistant properties includingproperties like- area weight shall be not less than0.8kg/sqm, specific gravity- 1.2, Water absorption - 0.15Light transmittance 86% Taber resistance (100 cycles)-0.8 to 1.5, Shading coefficient - 1.02 for clear & 0.7 for colored sheets, Ignition temperature flashing- 465 degree C, Heat transfer coefficient - 4.1W/sqmK, etc., with EPDM gaskets, hermetically sealed joints, clips, trims, flashings, including all necessary accessories as per manufactures specification, which shall be fixed on steel members or concrete members as sub structure, profile flushing on all exposed edges, complete in all respect up to the satisfaction of the Engineer. 1,000.00 Sq.M. 2,300 2,300,000
PP263
PP263 Material
PP263 o 1000 Sq.M. 1.00 Sq.M. =Rs /-
PP263
PP263 Labour
PP263 lc 1000 Sq.M. 1.00 Sq.M. =Rs /-
PP263
PP263 Subcontract
PP263 Supplying fitting & fixing in position 4mm thick, 2100mmwide and 2000 to 12000mm long clear or colored transparent profiled (matching with profile of metal side cladding) polycarbonate sheets at all elevations having UV, Yellowing, Abrasion resistant properties includingproperties like- area weight shall be not less than0.8kg/sqm, specific gravity- 1.2, Water absorption - 0.15Light transmittance 86% Taber resistance (100 cycles)-0.8 to 1.5, Shading coefficient - 1.02 for clear & 0.7 for colored sheets, Ignition temperature flashing- 465 degree C, Heat transfer coefficient - 4.1W/sqmK, etc., with EPDM gaskets, hermetically sealed joints, clips, trims, flashings, including all necessary accessories as per manufactures specification, which shall be fixed on steel members or concrete members as sub structure, profile flushing on all exposed edges, complete in all respect up to the satisfaction of the Engineer. sc 1000 Sq.M. 1.00 Sq.M. 2300 =Rs 2,300,000 /-
PP263
PP263
PP264 Plumbing, Sanitary and Drainage Works 1.00 LS 5,001,950 5,001,950
PP264
PP264 Material
PP264 o 1 LS 1.00 LS =Rs /-
PP264
PP264 Labour
PP264 lc 1 LS 1.00 LS =Rs /-
PP264
Page 63 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP264 Subcontract
PP264 Plumbing, Sanitary and Drainage Works sc 1 LS 1.00 LS 5,001,950 =Rs 5,001,950 /-
PP264
PP264
PP328 MISCELLANEOUS ITEM
PP329 Providing and fixing galvanized steel chain link fencing of3.0 m high (consisting of 0.2 m toe wall, 2.8 m chain link portion with size, 3.15 mm dia mesh wire and mesh size as75 mm x 75 mm conforming to IS: 2721, MS stirrup wire 2.5 mm dia tying wire 1.6 mm dia mild steel including providing25 mm x 4.75 mm MS stretcher bars, eye bolt and strainer, ring nuts, hairpins, staples of 3.5 mm wire, cleats of MS angle75 x 60 x 6 mm, MS droppers 25 mm x 38 mm x 4.85 mm half round staples etc. including the cost of supply and fixingof 2 nos end post of 65 x 65 x 62 L , intermediate post of 50 x50 x 6 at 2,5 m interval & strain post to be provided with of 65 x 65 x 62 L with struts of 50 x 50 x 6 on both sides at 25 M interval, all posts to be embedded in concrete block of of size450 x 450 x 400 (D)mm in M15 grade concrete including excavation. All structural steel shall conform to IS: 2062 and shall be painted with one coat of red oxide primmer and two coats synthetic enamel paint. 100.00 Sq.M. 2,390 239,000
PP329
PP329 Material
PP329 o 100 Sq.M. 1.00 Sq.M. =Rs /-
PP329
PP329 Labour
PP329 lc 100 Sq.M. 1.00 Sq.M. =Rs /-
PP329
PP329 Subcontract
PP329 Providing and fixing galvanized steel chain link fencing of3.0 m high (consisting of 0.2 m toe wall, 2.8 m chain link portion with size, 3.15 mm dia mesh wire and mesh size as75 mm x 75 mm conforming to IS: 2721, MS stirrup wire 2.5 mm dia tying wire 1.6 mm dia mild steel including providing25 mm x 4.75 mm MS stretcher bars, eye bolt and strainer, ring nuts, hairpins, staples of 3.5 mm wire, cleats of MS angle75 x 60 x 6 mm, MS droppers 25 mm x 38 mm x 4.85 mm half round staples etc. including the cost of supply and fixingof 2 nos end post of 65 x 65 x 62 L , intermediate post of 50 x50 x 6 at 2,5 m interval & strain post to be provided with of 65 x 65 x 62 L with struts of 50 x 50 x 6 on both sides at 25 M interval, all posts to be embedded in concrete block of of size450 x 450 x 400 (D)mm in M15 grade concrete including excavation. All structural steel shall conform to IS: 2062 and shall be painted with one coat of red oxide primmer and two coats synthetic enamel paint. sc 100 Sq.M. 1.00 Sq.M. 2390 =Rs 239,000 /-
PP329 Site rate
PP329
PP330 Providing and installation of Fencing, for transformer yard,boundary wall and other areas, including all labour, material, workmanship, including preparation of working drawings, equipment, fixing on structural steel members, all fixtures, clips, transportation, handling etc. all complete as per specification, drawings and instructions of the Engineer. (Structural Steel Posts and stays, toe wall, brick wall, concrete etc., if provided, shall be paid separately under relevant term). Comprising of PVC coated chain link, mesh size 75 mm, diameter of the PVC coated wire as 4 mm (min.), diameter of bare wire not less than 2.5 mm, as per IS: 272 200.00 Sq.M. 600 120,000
PP330
PP330 Material
PP330 o 200 Sq.M. 1.00 Sq.M. =Rs /-
PP330
PP330 Labour
PP330 lc 200 Sq.M. 1.00 Sq.M. =Rs /-
PP330
PP330 Subcontract
PP330 Providing and installation of Fencing, for transformer yard,boundary wall and other areas, including all labour, material, workmanship, including preparation of working drawings, equipment, fixing on structural steel members, all fixtures, clips, transportation, handling etc. all complete as per specification, drawings and instructions of the Engineer. (Structural Steel Posts and stays, toe wall, brick wall, concrete etc., if provided, shall be paid separately under relevant term). Comprising of PVC coated chain link, mesh size 75 mm, diameter of the PVC coated wire as 4 mm (min.), diameter of bare wire not less than 2.5 mm, as per IS: 272 sc 200 Sq.M. 1.00 Sq.M. 600 =Rs 120,000 /-
PP330
PP330
PP331 Providing, fabrication, transportation and erection ofstructural steel work in gates, conforming to IS: 2062, including all labour material, equipment, workmanship, preparation of working drawings, transportation, handling, hardware, fixtures and fittings like fabricated hinges, mildsteel aldrops, locking arrangement, tower bolts, pipes,stubs/post, tempered steel template, tempered steel pivots, guide track of MS tee, bronze aluminum ball and bearing arrangement, castor wheel, placing in position embedded parts in concrete/brickwork/road surface, cutting, grinding, frilling holes, welding, blast cleaning of steel surfaces to near white metal surface (Sa 2.5) applying inorganic zinc silicate primer of minimum 75 micron (DFT) touch up painting, application of intermediate (under) coat of minimum 75 micron (DFT) epoxy based colour paint, all complete, as per specifications drawings and instructions of the Engineer 50.00 Kg. 95 4,750
PP331
PP331 Material
PP331 o 50 Kg. 1.00 Kg. =Rs /-
PP331
PP331 Labour
PP331 lc 50 Kg. 1.00 Kg. =Rs /-
PP331
PP331 Subcontract
PP331 Providing, fabrication, transportation and erection ofstructural steel work in gates, conforming to IS: 2062, including all labour material, equipment, workmanship, preparation of working drawings, transportation, handling, hardware, fixtures and fittings like fabricated hinges, mildsteel aldrops, locking arrangement, tower bolts, pipes,stubs/post, tempered steel template, tempered steel pivots, guide track of MS tee, bronze aluminum ball and bearing arrangement, castor wheel, placing in position embedded parts in concrete/brickwork/road surface, cutting, grinding, frilling holes, welding, blast cleaning of steel surfaces to near white metal surface (Sa 2.5) applying inorganic zinc silicate primer of minimum 75 micron (DFT) touch up painting, application of intermediate (under) coat of minimum 75 micron (DFT) epoxy based colour paint, all complete, as per specifications drawings and instructions of the Engineer sc 50 Kg. 1.00 Kg. 95 =Rs 4,750 /-
PP331
PP331
PP332 Providing, fabricating and fixing of screen with M.S. angleframe of required size and fixing of IRC fabrics by welding with M.S. angle frame fitting and fixing with M.S. clamps welded with main frame, one coat of primer paint all complete as per specifications and approval of Engineer 20.00 Sq.M. 4,210 84,200
PP332
PP332 Material
PP332 o 20 Sq.M. 1.00 Sq.M. =Rs /-
PP332
Page 64 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP332 Labour
PP332 lc 20 Sq.M. 1.00 Sq.M. =Rs /-
PP332
PP332 Subcontract
PP332 Providing, fabricating and fixing of screen with M.S. angleframe of required size and fixing of IRC fabrics by welding with M.S. angle frame fitting and fixing with M.S. clamps welded with main frame, one coat of primer paint all complete as per specifications and approval of Engineer sc 20 Sq.M. 1.00 Sq.M. 4210 =Rs 84,200 /-
PP332 site rate
PP332
PP333 Providing and fixing 32 mm dia and minimum 3 mm thickheavy duty Stainless steel hand rail and balusters with25 mm dia. Intermediate rail seamlessly joined with allnecessary accessories, as per approved design, complete in all respect. 1,622.98 R.M. 11,490 18,648,040
PP333
PP333 Material
PP333 o 1623 R.M. 1.00 R.M. =Rs /-
PP333
PP333 Labour
PP333 lc 1623 R.M. 1.00 R.M. =Rs /-
PP333
PP333 Subcontract
PP333 Providing and fixing 32 mm dia and minimum 3 mm thickheavy duty Stainless steel hand rail and balusters with25 mm dia. Intermediate rail seamlessly joined with allnecessary accessories, as per approved design, complete in all respect. sc 1623 R.M. 1.00 R.M. 11490 =Rs 18,648,040 /-
PP333 site rate
PP333
PP334 Supplying, fabricating and erecting railings for balconies /stairs at all elevations using M.S. round/square tubes/bars, MS flats, angles etc. with running welded joints including hinges, shoes, rollers, guide rails and other necessary locking arrangements complete as per drawing, specifications withone coat of approved zinc chromate primer and twocoats of synthetic enamel paint of approved make &shade. (cost of making & filling pockets for holding the railing shall be included in this item rate) 2,500.00 Kg. 100 250,000
PP334
PP334 Material
PP334 o 2500 Kg. 1.00 Kg. =Rs /-
PP334
PP334 Labour
PP334 lc 2500 Kg. 1.00 Kg. =Rs /-
PP334
PP334 Subcontract
PP334 Supplying, fabricating and erecting railings for balconies /stairs at all elevations using M.S. round/square tubes/bars, MS flats, angles etc. with running welded joints including hinges, shoes, rollers, guide rails and other necessary locking arrangements complete as per drawing, specifications withone coat of approved zinc chromate primer and twocoats of synthetic enamel paint of approved make &shade. (cost of making & filling pockets for holding the railing shall be included in this item rate) sc 2500 Kg. 1.00 Kg. 100 =Rs 250,000 /-
PP334 site rate
PP334
PP335 Supplying, fabricating and erecting MS gate built withgalvanized tubes conforming to IS: 1161 of 50 mm dia frames including galvanized flats 25 x 6 mm connection bolts and nuts 8 mm dia welded wire fabric (50 x 50 mm square mesh welded to galvanized flats 25 x 6 mm bottom rollers, guide track, locking arrangement from both sides, handles, stoppers, hold fasts, pin clamps, MS aldrops etc. complete. 500.00 Kg. 157 78,500
PP335
PP335 Material
PP335 o 500 Kg. 1.00 Kg. =Rs /-
PP335
PP335 Labour
PP335 lc 500 Kg. 1.00 Kg. =Rs /-
PP335
PP335 Subcontract
PP335 Supplying, fabricating and erecting MS gate built withgalvanized tubes conforming to IS: 1161 of 50 mm dia frames including galvanized flats 25 x 6 mm connection bolts and nuts 8 mm dia welded wire fabric (50 x 50 mm square mesh welded to galvanized flats 25 x 6 mm bottom rollers, guide track, locking arrangement from both sides, handles, stoppers, hold fasts, pin clamps, MS aldrops etc. complete. sc 500 Kg. 1.00 Kg. 157 =Rs 78,500 /-
PP335 site rate
PP335
PP336 Providing and fixing in position at all levels, PTFE typesliding bearings individual bearing suitable for specified vertical loads as per construction drawings and having maximum displacement of +90 mm, including all labour, material, equipment, transportation, handling, installation, drilling, bolting, erecting, aligning, etc., all complete, as per specifications, drawings and instructions of the Engineer(Vertical load carrying capacity shall be as specified in theconstruction drawings).
PP337 Total vertical load carrying capacity for all Bearings havingvertical load carrying capacity for each bearing from 10.0M. T. to 40 MT. 250.00 MT 520 130,000
PP337
Page 65 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP337 Material
PP337 o 250 MT 1.00 MT =Rs /-
PP337
PP337 Labour
PP337 lc 250 MT 1.00 MT =Rs /-
PP337
PP337 Subcontract
PP337 Total vertical load carrying capacity for all Bearings havingvertical load carrying capacity for each bearing from 10.0M. T. to 40 MT. sc 250 MT 1.00 MT 520 =Rs 130,000 /-
PP337
PP337
PP338 Total vertical load carrying capacity for all Bearings havingvertical load carrying capacity for each bearing over 40M.T.to 150 M.T. 1,000.00 MT 250 250,000
PP338
PP338 Material
PP338 o 1000 MT 1.00 MT =Rs /-
PP338
PP338 Labour
PP338 lc 1000 MT 1.00 MT =Rs /-
PP338
PP338 Subcontract
PP338 Total vertical load carrying capacity for all Bearings havingvertical load carrying capacity for each bearing over 40M.T.to 150 M.T. sc 1000 MT 1.00 MT 250 =Rs 250,000 /-
PP338
PP338
PP339 Supply, Fabrication, erection and connection of followingconductors for grounding, lightning protection includingall materials, accessories, labour and tools ect. as per drawings and specification(Base rate of structural steel will be applied for this item)
PP340 Ground Mat Grid
PP341 36 mm dia M.S. rods 25,000.00 RM
PP341
PP341 Material
PP341 o 25000 RM 1.00 RM =Rs /-
PP341
PP341 Labour
PP341 lc 25000 RM 1.00 RM =Rs /-
PP341
PP341 Subcontract
PP341 sc 25000 RM 1.00 RM =Rs /-
PP341
PP341
PP342 Ground Electrode
PP343 36 mm dia 3M long M.S.rod 1,000.00 Nos
PP343
PP343 Material
PP343 o 1000 Nos 1.00 Nos =Rs /-
PP343
PP343 Labour
PP343 lc 1000 Nos 1.00 Nos =Rs /-
PP343
PP343 Subcontract
Page 66 of 421
Amount Description Cost code Analysis Item No Qty Unit Rate
PP343 sc 1000 Nos 1.00 Nos =Rs /-
PP343
PP343
PP344 Riser
PP345 36 mm dia M.S.rod 1,000.00 RM
PP345
PP345 Material
PP345 o 1000 RM 1.00 RM =Rs /-
PP345
PP345 Labour
PP345 lc 1000 RM 1.00 RM =Rs /-
PP345
PP345 Subcontract
PP345 sc 1000 RM 1.00 RM =Rs /-
PP345
PP345
PP346 Risers above 0.0M
PP346 50 x 6 mm G.S. Flat 1,000.00 RM
PP346
PP346 Material
PP346 o 1000 RM 1.00 RM =Rs /-
PP346
PP346 Labour
PP346 lc 1000 RM 1.00 RM =Rs /-
PP346
PP346 Subcontract
PP346 sc 1000 RM 1.00 RM =Rs /-
PP346
PP346
check 819,354,969
819,354,969 819,354,969 TOTAL
Page 67 of 421
PRICE VARIATION CALCULATION Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
1 2
Oct-13 Nov-13
Total Turnover 33,295 (Rs. L) -29436 0 29
ESCALATION % CONSIDERED FOR DIFFERENT COMPONENT
ESCALATION PAYABLE Per Annum 0.00 0.00
Labour
Supervisory staff (ITD's increment avg) 8.0% (Rs. L) 4.31 5.85
6.05 0.00 0.00
Labour- Operator & Helper as per trend 5.0% (Rs. L) 1.19 1.84
1.10 0.00 0.00
Labour Contract & direct labour (all
commodity index)
5.0% (Rs. L) 0.00 1.50
2.90 0.00 0.00
Sub-Contracts: assumed as per trends 5.0% (Rs. L) 0.00 12.58
13.96 0.00 0.00
Materials : 2yrs EI
Cement (grey cement index) 5.9% (Rs. L) 0.00 0.00
6.11 0.00 0.00
Rebar ,Strl Steel, pre-stressing steel (rebar
index) @ 80%
9.4% (Rs. L) 0.00 0.00
35.81 0.00 0.00
Sand + Agreegates (stone chips index) 6.9% (Rs. L) 0.00 0.00
6.10 0.00 0.00
Other material (all commodity index) 8.5% (Rs. L) 0.00 0.00
3.52 0.00 0.00
POL & Power & GTE :
Fuel (HSD index) 10.5% (Rs. L) 1.06 3.90
6.82 0.00 0.00
GTE (assumed as per trend) 2.0% (Rs. L) 0.00 0.29
0.30 0.00 0.00
External Hire of Equipment (assumed as per
trend)
5.0% (Rs. L) 0.22 5.73
2.08 0.00 0.00
Total Escalation 84.75 L 0.00 0.00
ESCALATION USING FORMULA GIVEN IN TENDER DOC.
Actual labour #REF! #REF!
Labour Component (Rs.L) 15.00% 0.00
RBI Index 204.00 206.00 208.00
Total Escalation in Labour (Rs.L) 0.00 0.00 0.00
Actual cement 4.03% 1341.12
Cement Component (Rs.L) 15% 0.00
RBI Index 204.00 206.00 208.00
Total Escalation in Cement (Rs.L) 0.00 0.00 0.00
ID Description Quantity Check
Actual Fuel
Fuel Component (Rs.L)
RBI Index
Total Escalation in Fuel (Rs.L)
Actual Machinery
Machinery Component (Rs.L)
RBI Index
Total Escalation in Machinery (Rs.L)
Actual Steel
Steel Component (Rs.L)
RBI Index
Total Escalation in Machinery (Rs.L)
Total Escalation Recievable (Rs.L) 0.00
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
3 4 5 6 7 8 9 10 11 12 13
Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14
191 225 654 791 509 486 375 221 95 53 75
0.00 0.00 0.00 0.00 7.00 8.00 9.00 10.00 11.00 12.00 13.00
7.54 7.54 7.90 7.90 7.90 7.90 6.54 6.54 6.26 6.26 6.26
0.00 0.00 0.00 0.00 0.37 0.42 0.39 0.44 0.46 0.50 0.54
2.67 2.67 2.67 2.67 2.67 2.67 2.55 2.43 1.84 1.84 1.84
0.00 0.00 0.00 0.00 0.08 0.09 0.10 0.10 0.08 0.09 0.10
6.84 7.66 21.38 29.38 20.82 20.37 15.32 11.30 5.54 1.95 1.95
0.00 0.00 0.00 0.00 0.61 0.68 0.57 0.47 0.25 0.10 0.11
18.96 23.61 52.22 36.32 7.43 17.54 47.93 33.99 19.47 19.80 35.03
0.00 0.00 0.00 0.00 0.22 0.58 1.80 1.42 0.89 0.99 1.90
21.46 25.75 90.92 88.66 20.17 41.91 45.59 19.90 6.67 2.00 2.00
0.00 0.00 0.00 0.00 0.70 1.66 2.03 0.98 0.36 0.12 0.13
0.77 0.93 89.68 199.49 238.41 173.84 75.10 49.76 20.35 3.37 3.37
0.00 0.00 0.00 0.00 13.03 10.85 5.28 3.88 1.75 0.32 0.34
17.08 20.49 83.22 81.73 16.36 34.15 37.70 17.16 6.01 2.31 2.31
0.00 0.00 0.00 0.00 0.66 1.58 1.96 0.99 0.38 0.16 0.17
5.57 6.69 23.89 25.49 9.46 7.84 8.82 6.71 0.94 5.46 5.46
0.00 0.00 0.00 0.00 0.47 0.44 0.56 0.47 0.07 0.46 0.50
15.77 15.77 16.23 16.66 15.70 13.87 8.45 7.91 7.39 6.04 5.98
0.00 0.00 0.00 0.00 0.96 0.97 0.66 0.69 0.71 0.63 0.68
1.91 2.25 6.54 7.91 5.09 4.86 3.75 2.21 0.95 0.53 0.75
0.00 0.00 0.00 0.00 0.06 0.06 0.06 0.04 0.02 0.01 0.02
12.98 12.98 12.98 14.33 12.58 9.61 6.01 4.66 4.66 3.31 2.53
0.00 0.00 0.00 0.00 0.37 0.32 0.23 0.19 0.21 0.17 0.14
0.00 0.00 0.00 0.00 17.51 17.66 13.63 9.68 5.20 3.55 4.62
210.00 212.00 214.00 216.00 218.00 220.00 222.00 224.00 226.00 228.00 230.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
210.00 212.00 214.00 216.00 218.00 220.00 222.00 224.00 226.00 228.00 230.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14 15 16 17 18 19 20 DLP CHECK
Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15
47 24 29 29 27 0 0 29,436.09
14.00 15.00 16.00 17.00 18.00 19.00 20.00
6.26 5.77 5.77 5.53 4.39 0.00 0.00 0
0.58 0.58 0.62 0.63 0.53 0.00 0.00 0.00
1.84 1.37 1.25 1.25 1.25 0.00 0.00 0
0.11 0.09 0.08 0.09 0.09 0.00 0.00
1.92 0.00 0.00 0.00 0.00 0.00 0.00 0
0.11 0.00 0.00 0.00 0.00 0.00 0.00
15.56 16.60 20.32 20.32 18.94 0.00 0.00 0
0.91 1.04 1.35 1.44 1.42 0.00 0.00
2.00 0.00 0.00 0.00 0.00 0.00 0.00 0
0.14 0.00 0.00 0.00 0.00 0.00 0.00
3.37 0.00 0.00 0.00 0.00 0.00 0.00 0
0.37 0.00 0.00 0.00 0.00 0.00 0.00
2.31 0.00 0.00 0.00 0.00 0.00 0.00 0
0.19 0.00 0.00 0.00 0.00 0.00 0.00
5.46 0.00 0.00 0.00 0.00 0.00 0.00 0
0.54 0.00 0.00 0.00 0.00 0.00 0.00
4.11 1.81 1.81 1.81 1.56 0.00 0.00
0.50 0.24 0.25 0.27 0.25 0.00 0.00
0.47 0.24 0.29 0.29 0.27 0.00 0.00
0.01 0.01 0.01 0.01 0.01 0.00 0.00
3.48 1.18 1.18 1.18 0.22 0.00 0.00
0.20 0.07 0.08 0.08 0.02 0.00 0.00
3.66 2.02 2.39 2.51 2.31 0.00 0.00 0
0.00
232.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00
232.00
0.00
Plywood Shutter (Film Faced)
Plywood shutter 10577.08 sqm
Plywood shutter sqm
Total 10577.08 sqm
Considering 4 repetations 2644.27 sqm
Cost/sqm 19mm th plywood 960.42 (12mm ply + battens + making etc)
Total cost 25.40 Lacs ..b
Charged to contract 100% 25.40 Lacs 240.10
Add cost of cribs MT 600 390 Lacs old cribs
Charge 33% 128.7 Lacs
TG qty 0.001 sqm
Cost per sqm for cribs ######### sqm
Plywood Shutter (Ordinary)
Plywood shutter 15865.62 sqm
Plywood shutter sqm
Plywood shutter sqm
Block outs 0.00 sqm
RCC Precast elements
Total 15865.62 sqm
Considering 5 repetations x 1.2 3807.75 sqm
Cost/sqm 12mm th plywood 850.42 (12mm ply + battens + making etc)
Total cost 32.38 Lacs ..b
Charged to contract 100% 32.38 Lacs 204.10
Plywood Shutter (CURVED)
Plywood shutter 10401.00 sqm
Plywood shutter sqm
Plywood shutter sqm
Block outs 0.00 sqm
RCC Precast elements
Total 10401.00 sqm
Considering 1 repetations 10401.00 sqm
Cost/sqm 12mm th plywood 750.42 (12mm ply + battens + making etc)
Total cost 78.05 Lacs ..b
Charged to contract 100% 78.05 Lacs 750.42
Staging material
Accrow pipes Nos 2700.00 32.40 Lacs 1200.00
Cuplock Arrangement - Vertical Nos 2500.00 18.75 Lacs 750.00
Cuplock Arrangement - Ledgers Nos 6500.00 22.75 Lacs 350.00
Accrow jacks Nos 5000.00 45.00 Lacs 900.00
Swivel Clamps Nos 5000.00 3.75 Lacs 75.00
Stirrup Head Nos 5000.00 20.00 Lacs 400.00
Adjustable Base Plate Nos 5000.00 20.00 Lacs 400.00
ISMC 100 for Wallers MT 50.00 27.50 Lacs 55000.00
Fasteners 10.00 Lacs
Total 200.15 Lacs c
Resale Value 40% residual -80.06 Lacs
Charged to Contract 120.09 Lacs
Shutter for superstructure sqm height cum % contribution
Ordinary 6400 2 12800 8.0%
Plywood 26000 6 156000 90.0%
Curved / Ornamental 500 4 2000 2.0%
TOTAL 32,900 170,800 100.0%
Foundation Shutter
Rs/sqm
Staging
Rs/cum
Staging
Rs/sqm
Ordinary 61000 204.10
Plywood 61000 240.10
Curved / Ornamental 100 750.42
Superstructure
Ordinary 6400 204.10 75.06 150.11
Plywood 26000 240.10 69.28 415.70
Curved / Ornamental 500 750.42 120.09 480.36
(12mm ply + battens + making etc) Plywood -600/m2+making 100/m2
CAPEX-2
Rs/sqm 19mm ply with 2x3" batten
0.33
1.67
750.00
2016.00
2766.00
960.42
12mm ply with 2x3" batten
0.33
(12mm ply + battens + making etc) 1.67
CAPEX-2 750.00
Rs/sqm 1699.20
2449.20
850.42
6mm ply with 2x3" batten
0.33
(12mm ply + battens + making etc) 1.67
CAPEX-2 750.00
Rs/sqm 1411.20
2161.20
750.42
CAPEX-3
% contribution Rs/cum
960,720 75.06 150.11
10,808,100 69.28 415.70
240,180 120.09 480.36
12,009,000
TOTAL Rs/sqm
204.10
240.10
750.42
354.21
655.80
1230.78
Subcontract / LC
Description Unit Rate
Controlled blasting cum 600
Rubble soling LC cum 300
Hard stone laying LC cum 250
PCC LC+mat shutter sqm 450
Ordinary shutter LC sqm 200
Plywood shutter LC sqm 250
Curved shutter LC sqm 300
Staging LC cum 30
Cement feeding per bag 2
Concrete pouring PCC cum 125
Concrete pouring RCC cum 150
UPV test per no 1,300,000
Dismantling conc cum 1,500
Chipping of Cement Concrete work (both PCC and RCC),
for all type of structures, at all levels, for making grooves, removing
surface concrete etc., according to shapes, sizes and profiles as
shown on the construction drawings, stacking of serviceable material
upto a lead of 500 m, disposal of unserviceable material upto a lead
of 2.00 km. beyond the plant boundary or as directed by the
Engineer, cutting of reinforcement, including all labour, equipment,
scaffolding, staging, handling, transportation, propping and shoring,
enclosures, etc., all complete, as per specifications, drawings and
instructions of the Engineer.
cum 2,200
Making of Circular opening of diameter varying from 25
mm to 150 mm and depth upto 450 mm in cement concrete work
(both PCC and RCC) of all grades, for all type of structures, at all
levels and for all positions, by coring using diamond bits for pockets /
thorough opening according to size as shown on the construction
drawings, stacking of serviceable material upto a lead of 500 m,
disposal of unserviceable material upto a lead of 2.00 km. beyond
the plant boundary or as directed by the Engineer, finishing
neatly the surface area of cement concrete exposed after creation of
circular opening including all labour, equipment, scaffolding, staging,
handling, transportation, propping and shoring, enclosures, etc., all
complete, as per specifications, drawings and instructions of the
Engineer.
sqm 7,200
Making of slit type opening of rectangular, square and or
similar shape of varying size (in plan) and depth upto 450 mm in
cement concrete work (both PCC and RCC) of all grades, for all
type of structures, at all levels and for all positions, by sawing
using wall saw machine with on the construction drawings, locating
the reinforcement before making the opening by use of rebar
detector and obtaining specific clearance from the Engineer, if the
cutting of the reinforcement bar are involved in the making of the
opening, cutting of reinforcement, stacking of serviceable
material upto a lead of 500 m, disposal of unserviceable material
upto a lead of 2.00 Kms. beyond the plant boundary or as directed by
the Engineer, finishing neatly the surface area of cement concrete
exposed after creation of opening including all
labour, equipment, scaffolding, staging, handling, transportation,
propping and shoring, enclosures, etc., all complete, as per
specifications, drawings and instructions of the Engineer.
sqm 6,000
Fab & erection embedded items, anchor bolt assembly MT 27,000
Providing & Fixing desired thickness of SIL FIL of Dawn
Color, manufactured by The Supreme Industries Limited or
equivalent, thickness built up using minimum 10 mm specifically
extruded high performance sheet, minimum density 30 kg/ cum
& compression strength of 0.21 kg/sqm, when tested as per ASTM D-
3575, including using double sided adhesive SIL SEAM
TAPE(manufactured by The Supreme Industries Limited) or
equivalent of 2 mm x 25 mm x
25 mm at four places per sq.mtr to the casted surface to form the
expansion joint. SIL FIL will become one side of the shuttering
while the expansion joint is being created.
sqm 636
Providing and placing in position at ground floor level,
building paper (kraft paper) of 250 micron as per IS : 1397
between the concrete surfaces including the cost of all labours,
materials etc. complete as per drawings, specifications as directed
by the Engineer in charge.
sqm 50
Providing, applying and painting 85/25 industrial grade hot
bitumen at the rate of 1.2 kg/sqm or 0.4 kg/sqm over
concrete surface after cleaning with brushes and finally with cloth
soaked kerosene oil.
1.2 kg/sqm sqm 116
0.4 kg/sq.m sqm 59
Providing, mixing and laying in position and curing ordinary
plum concrete of mix 1:4:8 mix using size less than 80 mm boulder
as coarse aggregate as per drawing and specification and direction
of Engineer at all locations for ground filling.
cum 3,898
Providing and laying as per Manufacturer's Instruction acrylic
based polymer modified cementitious composite coating system
"Tapecrete of CICO" or Equivalent waterproofing to underground
structure complete as per drawing and direction of Engineer.
sqm 800
Rebar subcontract straight MT 4,200
Rebar subcontract straight MT 2,200
Preparation of fabrication drawing, receiving fabricated
material at site, transporting, stacking at store, erecting structural
steel works as per specification, drawings,
including necessary loading, stacking, including addition of gussets,
base-plate, cap-plates, stiffeners, shim plates, spacers, washers etc.
as specified / required and erecting in position by all sorts of
mechanical means including suitable type of crane and erection
bolts, nuts [shot blasting of steel surfaces to near white metal
surface (Sa 2) and applying Inorganic Zinc Silicate primer of
minimum 75 micron (DFT)] etc. complete.
MT 15,700
shop drawinsg MT 500
Supplying, fabricatinganderectionincluding
transportation, storing etc for Miscellaneous steel work in handrails,
sag rods, ladders, platforms and other structures not included above.
MT 30,000
Providing and application of synthetic enamel paint of
Shalimar make or equivalent and colour in two coats of minimum
50 micron each including surface preparation using wire brush,
necessary cleaning and applying two
coats of primer with Zinc chromate primer of DFT 25
microns per coat over steel sections already having primer coats at
all elevations
MT 7,000
Providing and applying high performance epoxy based
Polyamide cured painting system of approved colour and shade
consisting of Zinc silicate primer, intermediate (under) coat, finish
coat and final finish coat including shot blast cleaning of steel
surfaces to near white metal surface (Sa 2), to steel surfaces of all
types, shapes and sizes, at all levels, to achieve an even shade,
including all labour, material, consumablesequipment, handling,
transportation, protection and cleaning, scaffolding and staging,
testing, etc., all complete, as per specifications, drawings and
instructions of the Engineer.
Blast cleaning by shot blasting of steel surfaces to near
white metal surface (Sa 2) and applying Inorganic Zinc Silicate
primer of minimum 75 micron (DFT), including touch up painting for
the damaged surfaces of primer.
MT 10,300
Applying intermediate (under) coat over inorganic Zinc
Silicate primer, (excluding cost of primer), consisting of minimum 75
micron DFT epoxy based Titanium dioxide/ Miscellaneous iron oxide
(pigmented) including touch up painting for the damaged surfaces of
intermediate paint.
MT 2,500
Applying finish coat over Intermediate (under) coat,
(excluding cost of Intermediate coat), consisting of minimum 75
micron DFT Epoxy based colour pigmented finish Polyamide cured
paint and Final Finish coat with minimum 25 micron DFT
Polyurethane colour pigmented finish paint, including final touch
up painting for the damaged surfaces of Finish and Final Finish
Paint.
MT 4,050
Dismantling of erected structural steel member at any
elevation, lowering of material and carriage of dismantled material up
to field fabrication shop or return to owners store,
includingtemporarydismantling, cutting, re-welding, supporting
and restoring to correct position of all temporarily dismantled
members, realignment of adjacent connected members to their
correct position (Weight of such temporarily dismantled and adjacent
members not to be paid), including all labour, material, equipment,
handling, transportation, all complete as per specifications, drawings
and Instructions of Engineer.
MT 18,000
Additions to, alterations in and / or modification of
"Erection Marks" (of structural steel) either in erected
position or in shop, including all labour, material, equipment,
handling, transportation, cutting of parts, gouging of welds, cutting,
grinding, fabrication, welding, drilling holes, straightening, removal of
bends, raising to required levels, primer painting, with Zinc silicate
primer, touch up painting,
transportation, return of unutilized steel pieces to the Owner's store,
temporarily dismantling, cutting, re-welding, supporting and restoring
to correct position of all temporarily dismantled members,
realignment of adjacent connected members to their correct
position (Weight of such temporarily dismantled and adjacent
members not to be paid),.etc, including all labour, material,
equipment, handling, transportation, all complete as per
specifications, drawings and Instructions of Engineer.
In erected Position MT 30,000
In fabrication yard MT 25,000
Re-erection of dismantled fabricated structural steel
members requiring addition to, alterations in and / or modification,
(dismantling and additions to, alterations in and
/ or modification to be paid separately under relevant items),
includingalllabour, material, equipment, handling,
transportation, carriage of modified "Erection Marks" from the field
fabrication shop to erection site, raising to required levels,
aligning in position, tack welding, final welding, touch up painting,
including temporarily dismantling, cutting, re- welding, supporting and
restoring to the correct position of all temporarily dismantled
members, realignment of adjacent connected members to their
correct position (Weight of such temporarily dismantled and
adjacent members not to be paid), etc., all complete as per
specifications, drawings and Instructions of Engineer.
MT 30,000
Providing, supplying, fabrication, transportation,
erection and alignment including installation in position by bolting /
welding / screwing of factory made electro- forged gratings fabricated
using mild steel conforming to IS :
2062, at all levels, in floorings, platforms, drain covers trench covers,
walk-ways, passages, staircase treads with edge binding strips and
anti-skid nosing etc. with all fittings and fixtures, (clips, bolts, self
drilling and taping screws, nuts and lock washers) etc., self drilling
and tapping screws, welding, edge preparation, painting by blast
cleaning of steel surfaces to near white metal surface (Sa 2 ) and
applying high performance painting system consisting of zinc silicate
primer (minimum 75 micron DFT) followed by intermediate coat
(minimum 75 micron DFT) consisting of epoxy based
Titanium dioxide / Micaceous iron oxide and finished with finish coat
(minimum 75 micron DFT) consisting of epoxy based coloured
pigmented finish including all labour, material, equipment,
handling, transportation, preparation of fabrication drawings, etc., all
complete, as per specifications, drawings and instructions of
Engineer.
MT 140,000
Extra over item 47.a above for finishing the fabricated
grating unit with hot dipped galvanization @ 610 g. / Sq. M. over
blast / chemically cleaned steel surfaces, instead of painting with
high performance painting system
MT 27,000
Providing and fixing in position at all levels, high
strength structural steel bolts (Property class 8.8 ,class
10.9 and product grade C as per IS:1367) conforming to IS
: 3757 and high strength structural hardened and tempered nuts
(Property class 8 as per IS:1367) conforming to IS :
6623 with hardened and tempered washers as per IS:6649 etc., up
to and inclusive of 39 mm diameter and 300 mm
long, installing the same as per IS:4000 for structural steel
works including all labour, material, equipment, handling,
transportation, testing, all complete, as per specifications, drawings
and instruction of Engineer.
MT 356,000
Providing and fixing in position at all level, permanent
mild steel bolts (Property class 4.6 as per IS:1367 and
MT 150,000
Product grade C as per IS:1363), nuts, washers, etc. up to and
inclusive of 39 mm diameter and 300 mm long for
structural steel works, including all labour, material,
equipment, handling, transportation, testing, all complete, as
per specifications, Drawings and Instruction of Engineer.
Supplying, Fabricating, transporting, erecting in position at all
levels the chequered plates for platform walkways, stair treads,
trenches, etc. Complete as per specification and approved
fabrication drawings.
6 o/p chequered plate MT 80,000
Supplying and laying 40 mm thick damp proof course with
cement concrete (1:1:3 nominal mix by volume) with a minimum of
2% admixture of waterproofing compound etc. with all materials
complete.
sqm 220
Makingplinth protection (minimum 75mm thick and
minimum 750mm wide) of cement concrete M20 over
75mm bed of dry brick ballast consolidated and grouted with fine
sand including finishing the top smooth including shuttering.
sqm 698
Chlorpyriphos emulsifiable concentrate conforming to
IS:8944 - 1978 with 1% concentration (The work shall be get
executed by an approved specialist agency and the
contractor shall furnish 10 years guarantee on non-judicial stamp
paper)
sqm 220
External wall:
The external / outer wall shall be Cladded with PPGI Sheet
/ PPGL Sheets (0.5 thk ) including screwing, and all complete
etc.
Sq.M. 1,500
Internal wall:
Internal Surface of the wall shall be cladded with 6mm CP
board and 12.5 mm thick Gypsum Board and without paint.
Sq.M. 1,400
Supplying and fixing 17.5 cm. X 17.5 cm glass bricks in
pattern with epoxy mortar match to the bricks as per
manufacturer's manual, drawings and directions of the
Engineer in charge.
Sq.M. 158
Supplying & laying Vineratex or equivalent granular
decorative textured coat finish over plaster surfaces at various
elevations including mixing, laying, finishing etc. with materials &
labour complete as per manufacturers specification and drawing.
sqm 500
25 mm x 12 mm Drip course at various elevations to
parapet, chajja, window heads, door heads etc. with all materials at
all elevations complete as per drawings and specification.
R.M. 200
40 mm. thick cement concrete floor 1:1.5:3 with top of
concrete floor painted with two coats of Epoxy paint as per
manufacturer's specification.
Sq.M. 724
Providing and laying overall 40 mm thick cement concrete
flooring with metallic concrete hardener topping (ironite),
at various elevations, consisting of under layer 28 mm average
thick cement concrete of grade M 20 and top layer 12 mm thick
metallic cement hardener consisting of mix 1:2 (1 cement hardener
mix : 2 stone aggregate 6 mm nominal size) by volume (Ironite shall
be added in mix @
1.5 kg / m2) including finishing of joints at maximum two (2)
metres interval, or any surface, and including 40 mm wide and 4 mm
thick, glass strip placed between the panels including labour,
materials and equipment and curing including scouring of
surface providing necessary shape etc. complete in all respects and
in accordance with specifications and direction of the Engineer.
Sq.M. 404
Providing and laying overall 40 mm thick cement concrete
(grade M25) flooring including cement slurry, finishing of joints at
maximum two (2) metres interval, or any surface, and including 40
mm wide and 4 mm thick, glass strip placed between the panels
including labour, materials and equipment and curing including
scouring of surface providing necessary shape etc. complete in all
respects and in accordance with specifications and direction of
Engineer.
Sq.M. 368
Providing 25 mm thick and 150 mm high cement mortar
(1:3) skirting finished with a floating coat of neat cement at all
elevations including labour, materials and equipment and curing
complete in all respects and in accordance with specifications and
direction of the Engineer
Sq.M. 325.76
Providing and laying non-skid fully vitrified 10 mm thick
tiles similar to "MARBONITE","FERRASTONE",of "BOSS Profile
Ltd." or similar approved laid on 20 mm thick cement mortar
(1:4) including grouting the joints with white cement and matching
pigments etc., in floors, skirting and dado complete as per
manufacturer's specification .
(Base rate of cement will be applied for this item)
600 mm x 600 mm (Base rate = Rs. 1500/-) Sq.M. 1,963
400 mm x 400 mm (Base rate = Rs. 1270/-) Sq.M. 1,717
Supplying & laying 50 mm thick floor with matt finish
unglazed ceramic tiles of approved colour and shade and of
minimum thickness 7.2-7.5 mm over necessary under bed and 15
mm thick cement sand mortar 1:3 including cement slurry and
joining with white cement slurry mixed with pigment to match the
shade of tile complete with all materials
as per specification and drawing. (Base rate = Rs. 1000/-)
(Base rate of cement will be applied for this item)
Sq.M. 1,433
Same as above item no 70 but with tiles of designer
series of Kajaria, Nitco or of approved equivalent
manufacturers (Base rate = Rs. 1200/-)
(Base rate of cement will be applied for this item)
Sq.M. 1,663
Supplying and placing 5 mm thick glazed ceramic tiles of
approved make, size in skirting, dado etc on 12 mm thick
1:3 cement mortar in base and jointed with white cement slurry and
matching pigments etc, including labour, materials and equipment,
cleaning of surfacelaid as per manufacturer's instruction
and direction of Engineer in charge. (Base rate = Rs. 750/-)
(Base rate of cement will be applied for this item)
Sq.M. 1,156
Supplying & laying 40 mm thick acid/alkali resistant floor
with 20 mm thick unglazed ceramic vitreous acid / alkali resistant
tiles laid on potassium silicate based under bed mortar as per IS:
4832 (part I) over a primer coat and alkali
resistant bituminoustic ready made paint conforming to
IS: 158 with 6 mm wide joints in between tiles filled with resin type
(epoxy/Furane) mortar conforming to IS- 4832(Part-II) including
preparation of surface, acid curing sealing the edges by
bituminastic filler etc complete as per specification, drawing and
direction of Engineer. (Base rate = Rs. 4450/-)
The tile samples shall be approved by Engineer before
execution.
Sq.M. 5,981
All as per item (73-a) above but with Acid/Alkali resistant
paint over 20 mm thick unglazed ceramic normal tile all as per
specification complete.
Sq.M. 6,331
Supplying and laying polished kota stone slab of approved
size and 20 mm thick (the tile sample shall be got approved from the
Engineer) in flooring and skirting laid on 20 mm thick cement mortar
1:4 bedding, cement floated mixed with pigment, all joints well filled
on completion, including polishing at site all as per specifications and
directions of Engineer.
(Base rate = Rs. 350/-)
(Base rate of cement will be applied for this item)
Sq.M. 964
Providing, supplying and laying 2 mm thick homogeneous
flexible heavy duty antistatic PVC tiles of approved
manufacture, size and colour on floor, dodo etc using rubber based
adhesive of approved manufacture including rolling with light
wooden roller weighing about 5 kg, material, labour, equipment etc.
complete as per drawing and direction. (Base rate = Rs. 750/-)
Sq.M. 1,488
Providing and laying 18 mm thick Polished granite stone
(slab) over 20 mm thick base in cement mortar 1:4 (1 cement : 4
coarse sand) including labour materials and
equipment and also including scouring of surface providing
necessary shape etc. complete in all respect with standard
accordance with specification & direction of engineer. The joints
shall be grouted with white cement by mixing & matching colour
pigment. (Base rate = Rs. 2750/-)
(Base rate of cement will be applied for this item)
Sq.M. 3,484
Supplying, fitting and fixing Polished granite slabs 12 mm
thick in columns, walls, facias, skirting, dado etc. with cement mortar
(1:3) including making suitable arrangement
to hold the stone properly by brass/copper hooks including filling the
joints with necessary cement mortar (1 white cement : 2 stone dust)
with admixture of pigment matching the shades, all complete
including edge molding. (Base rate
= Rs. 2000/-)
(Base rate of cement will be applied for this item)
Sq.M. 2,697
Providing and laying 18 mm thick Adanga White Marble
slab (1.5 m x 0.6 m) flooring over 22 mm thick base in cement
mortar 1:4 (1 cement : 4 coarse sand) having 5 mm thick white
cement topping, including labour materials and equipment and
also including scouring of surface providing necessary shape etc.
Complete in all respect with standard accordance with
specification & direction of engineer. The joints shall be grouted
with grey cement by mixing & matching colour pigment. (Base rate =
Rs. 1600/-) (Base rate of cement will be applied for this item)
Sq.M. 2,427
Providing and laying over-all 40 mm thick granite work
with 18 mm thick grey granite in flooring above as per floor
pattern indicated in drawing and/or instructed by the Engineer
/ Architect. (Base rate = Rs. 2750/-)
(Base rate of cement will be applied for this item)
Sq.M. 3,734
18 mm thick marble slab skirting or dado matching with
floor marble slab as per instruction of engineer. (Base rate
= Rs. 1600/-)
(Base rate of cement will be applied for this item)
Sq.M. 2,527
Supplying and fixing glass mosaic tiles 20 x 20 x 4.5 mm
thick in pattern as per drawings and directions of the
Engineer in charge.
Sq.M. 3,077
Supplying & Laying precast cement concrete tiles
(minimum size 600 mm X 600 mm) 20 mm. thick on roof surface
including preparation of bed with 15 mm thick sand cement mortar
(4:1) to proper slope as per direction of the Engineer - in -charge
complete including cost of all labour and materials etc.
Sq.M. 2,527
as per Mr. BSP 8lacs for testing + travel +lodging+ misc
1sqm will cover 56 holes of 150mm dia CHECK
Only
installation
MT 18000
as per verbal
quote by Patil
very high
rates
QUOTES
RECEIVED
veeyem interiors 292
very high
rates
QUOTES
RECEIVED
veeyem interiors 194
CHECK
incl shifting
incl shifting
Quoted by Morya
Quoted by Morya
Quoted by Morya
CHECK
CHECK
CHECK
CHECK
CHECK
dsr rate of
epoxy paint
25rs/kg
ironite + 20%
wastage
glass strip:
18 rs/rm
assume
panel 10m x
10m
100rs lab 50rs misc
glass strip:
25 rs/rm
assume
panel 2m x
4m
5,030.51
40 rs for
prime coat
Rs. 650 for
mastic
Material rates
Description unit Rate inclusive of tax
Sand coarse cum 425
Boulder cum 1230 ??????
Sand filling cum 300
Aggregate 40mm cum 1200
Aggregate 20mm cum 1650
Aggregate 10mm cum 1350
Cement slag kg 6.57 as per Jindal Basic rate
Cement OPC kg 7.93 as per Jindal Basic rate
Structural steel (angle, beam, channel) MT 45,551.0 as per Jindal Basic rate
Structural steel plates MT 39,820.0 as per Jindal Basic rate
Reinf steel straight MT 42,542.0 as per Jindal Basic rate
Reinf steel cut & bend MT 45,138.0 as per Jindal Basic rate
Binding wire, 1.6mm thick GI kg 75 check
Plasticizer kg 45 ??
Self compacting plasticizer kg 170 CHECK
12mm thick bituminous board joints Sq.M 631.00 as per site
25mm thick bituminous board joints Sq.M 831.00 as per site
50mm thick bituminous board joints Sq.M 1131.00 as per site
25mm x 25mm HD-100 poly ethy exp joint Rm 29.8 540 rs/sqm
Silica sealant Rm 675
Providing vertical expansion joint with polyurethane foam
road of required diameter and sealed with silicon sealant
over road including fixing of rod with all materials complete at
various elevations as per drawings and specifications similar to
C/S Group & McCoy or approved equivalent.
25 wide with 25 x 12 poly-sulphide including fixing of 25 mm
dia rod.
Rm 941.5
50 wide with 50 x 12 poly-sulphide including fixing of 50 mm
dia rod.
Rm 2097.5
Supplying and installing ribbed water stops with central
bulbs as per relevant Indian Standards, drawings and
specification
230 mm x 6 mm RM 250
230 mm x 8 mm RM 320
150 mm x 6 mm RM 230
150 mm x 8 mm RM 250
rail MT 54600
MS black medium quality pipe sleeves basic
i) 80 mm NB RM 342.69 295.00
ii) 100 mm NB RM 500.43 427.00
iii) 150 mm NB RM 767.78 661.00
iv) 200mm NB RM 1332.66 1150.00
Geo textile Netlon 300 3mm thick sqm 1500
inclusive of tax
as per Jindal Basic rate add CST, ED, & freight Check with Purchase
as per Jindal Basic rate add CST, ED, & freight Check with Purchase
as per Jindal Basic rate add CST, ED, & freight freight & taxes given by Purchase no cst on beam. Colm, channel, only on ANGLES
as per Jindal Basic rate add CST, ED, & freight freight & taxes given by Purchase
as per Jindal Basic rate add VAT, ED, & freight freight & taxes given by Purchase
as per Jindal Basic rate add VAT, ED, & freight freight & taxes given by Purchase
??????????
ED cst transp
8.24% 2% 17.00
8.24% 2% 29.00
8.24% 2% 38.00
8.24% 2% 63.00
no cst on beam. Colm, channel, only on ANGLES
ITD Cementation India Limited Div2 : 2x660 MW Jindal Power Project_Jharkhand ---Estimate_r0
Shuttering and Staging Requirement
Alluminum Shutter fot TG
Shuttering for TG deck,col,beam
0.00
Total 0.00
Considering 2 repetations 0.00
Weight of shuttering/ sqm 45.00
Material cost 100.00
Fabrication cost 75.00
Total 175.00
Cost/sqm 7875.00
Total cost 0.00
Residual Value @ 20% of Total Cost 0.00
Charged to Contract 0.00
Plywood Shutter (Film Faced)
Plywood shutter 10577.08
Plywood shutter
Total 10577.08
Considering 4 repetations 2644.27
Cost/sqm 19mm th plywood 960.42
Total cost 25.40
Charged to contract 100% 25.40
Plywood Shutter (Ordinary)
Plywood shutter 15865.62
Plywood shutter
Plywood shutter
Block outs 0.00
RCC Precast elements
Total 15865.62
Considering 5 repetations x 1.2 3807.75
Cost/sqm 12mm th plywood 850.42
Total cost 32.38
Charged to contract 100% 32.38
Staging material
Accrow pipes Nos 2700.00 32.40
Cuplock Arrangement - Vertical Nos 2500.00 18.75
Cuplock Arrangement - Ledgers Nos 6500.00 22.75
Accrow jacks Nos 5000.00 45.00
Swivel Clamps Nos 5000.00 3.75
Stirrup Head Nos 5000.00 20.00
Adjustable Base Plate Nos 5000.00 20.00
ISMC 100 for Wallers MT 50.00 27.50
Fasteners 10.00
Total 200.15
Resale Value -80.06
Charged to Contract 120.09
Total Charged to contract 437.22
Ordinary shutt substructure 171.34
Plywood shutt substructure 193.30
Ordinary shutt superstructure 17.87
Plywood shutt superstructure 82.84
Curved shutter 2.64
177.87
-290.12
26442.70 Sqm
56.50 Sqm/Day
Plywood Shutter (TG)
Item no.2.16 v Plywood shutter
Item no. 2.16 vi Plywood shutter
Item no. 2.16 vi Plywood shutter
Item no 2.17 Block outs
Item no C.7i RCC Precast elements
Item no C.9i
Total 0.00
Considering 2 repetations 0.00
Cost/sqm 12mm th plywood 2111.00
Total cost 0.00
Charged to contract 100% 0.00
Staging material
Accrow pipes Nos 0.00
Cuplock Arrangement - Vertical Nos 2500.00 18.75
Cuplock Arrangement - Ledgers Nos 6500.00 22.75
Accrow jacks Nos 2000.00 18.00
Swivel Clamps Nos 1000.00 0.75
Stirrup Head Nos 0.00
Adjustable Base Plate Nos 2500.00 10.00
ISMC 100 for Wallers MT 0.00
ISMB 500 MT 40.00 20.00
ISMB 200 MT 40.00 20.00
50x50 MS Tube MT 20.00 10.00
ISA 50x50x6 MT 20.00 10.00
ISMB 500 MT 60.00 30.00
ISMB 250 MT 102.00 51.00
ISLC 75 MT 46.00 23.00
0.00 0.00
Angle 50x50x6 MT 256.00 128.00
Angle 75x75x6 MT 140.00 70.00
Total 432.25
Resale Value -172.90
Charged to Contract 259.35
Total Charged to contract 259.35
Cost of Allum. shuttering fot TG deck,col,wall charged to contract #DIV/0!
Cost of steel shuttering charged to contract - above Plinth #DIV/0!
Nos Rate
40 NB pipe 4000.00 234.00 9.36
Coup lock-Vertical - 2m Ht 1000.00 550.00 5.50
Coup lock-Vertical - 1.5m Ht 750.00 415.00 3.11
Coup lock-Hor - 2m Ht 750.00 385.00 2.89
Coup lock-Hor - 1.5m Ht 750.00 295.00 2.21
Accrow spans 300.00 2925.00 8.78
Base plates 2000.00 156.00 3.12
Clamps 1000.00 143.00 1.43
STRRIUP Head 200.00 325.00 0.65
Swivel Coupler 500.00 1690.00 8.45
Supporting props for foundations 400.00 2080.00 8.32
53.82
Cost of enabling works
2.40 Providing & Laying in position design mix cement concrete of following grades as specified in drawings for reinforced concrete work in foundations, in all kinds of work using graded crushed stone (20mm down) as coarse aggregate including conveying,laying,vibrating, compacting and curing etc complete as per drawings & specifications and direction of the Engineer. (Note: Cement will be free issue. 30 % Fly ash to be used for making Concrete. Shuttering & Fixing steel reinforcement will be paid separately under relevant items.)
2.4i (i) M-20
2.4ii (ii) M-25
2.4iii (iii) M-30
Total
1.00 Cost of chute 4.00
2.00 Structural steel for enabling works (Material) 30.00
Charged to contract 1.00
Labour charges - fabrication 30.00
Material enabling
Labour - enabling
0.00
sqm
sqm #DIV/0! #DIV/0!
sqm
sqm Considering 30% New Purchase
sqm
kg
/kg
/kg
/kg
Lacs .a CAPEX-1
Lacs
Lacs
sqm
sqm
sqm
sqm
(12mm ply + battens + making etc) Plywood -600/m2+making 100/m2
Lacs ..b CAPEX-2
Lacs 240.10 Rs/sqm 12mm ply with 2x3" batten
0.33
sqm 1.67
sqm 750.00
sqm 2016.00
sqm 2766.00
960.42
sqm 12mm ply with 2x3" batten
sqm 0.33
(12mm ply + battens + making etc) 1.67
Lacs ..b CAPEX-2 750.00
Lacs 204.10 Rs/sqm 1699.20 ordinaryPlywood -490/m2+making 100/m2
2449.20
850.42
Lacs 1200.00
Lacs 750.00
Lacs 350.00
Lacs 900.00
Lacs 75.00
Lacs 400.00
Lacs 400.00
Lacs 55000.00
Lacs
Lacs c CAPEX-3
Lacs
Lacs
L
280.88 Rs./m2 Ordinary shutt sub Sq.M. 0.00 61000.00 39%
316.88 Rs./m2 Plywood shutt sub Sq.M. 0.00 61000.00 39%
279.16 Rs./m2 Curved / Ornamental shutt sub Sq.M. 0.00 100.00 0%
318.62 Rs./m2 0%
440.25 Rs./m2 Ordinary shutt Sup Sq.M. 0.00 6400.00 4%
Plywood shutt Sup Sq.M. 0.00 26000.00 17%
Curved / Ornamental shutt Sup Sq.M. 0.00 500.00 0%
0.00 Formwork for TG deck slab, columns and beams using Aluminum shuttering All shutt Sq.M. 0.00 10000.00
155000.00
sqm
sqm
sqm 1.00
sqm 8.00
3200.00
2880.00
sqm 6080.00
sqm 2111.11
(12mm ply + battens + making etc)
Lacs ..b CAPEX-2
Lacs
Lacs 1200.00
Lacs 750.00
Lacs 350.00
Lacs 900.00
Lacs 75.00
Lacs 400.00
Lacs 400.00
Lacs 50000.00
Lacs 50000.00
Lacs 50000.00
Lacs 50000.00
Lacs 50000.00
Lacs 50000.00
Lacs 50000.00
Lacs 50000.00
Lacs 50000.00
Lacs 50000.00
Lacs 50000.00
Lacs c CAPEX-3
Lacs
Lacs
L
#DIV/0! Rs./m2
#DIV/0! Rs./m2
Providing & Laying in position design mix cement concrete of following grades as specified in drawings for reinforced concrete work in foundations, in all kinds of work using graded crushed stone (20mm down) as coarse aggregate including conveying,laying,vibrating, compacting and curing etc complete as per drawings & specifications and direction of the Engineer. (Note: Cement will be free issue. 30 % Fly ash to be used for making Concrete. Shuttering & Fixing steel reinforcement will be paid separately under relevant items.)
1000.00 Cu.M.
158000.00 Cu.M.
1000.00 Cu.M.
160000.00 m3
2.00 8.00
15000.00 4.50
4.50
15000.00 4.50
7.81 /m3
2.81 /m3
Plywood -600/m2+making 100/m2
12mm ply with 2x3" batten
12mm ply with 2x3" batten
ordinaryPlywood -490/m2+making 100/m2
31%
31%
0%
79%
21%
Providing & Laying in position design mix cement concrete of following grades as specified in drawings for reinforced concrete work in foundations, in all kinds of work using graded crushed stone (20mm down) as coarse aggregate including conveying,laying,vibrating, compacting and curing etc complete as per drawings & specifications and direction of the Engineer. (Note: Cement will be free issue. 30 % Fly ash to be used for making Concrete. Shuttering & Fixing steel reinforcement will be paid separately under relevant items.)
Providing & Laying in position design mix cement concrete of following grades as specified in drawings for reinforced concrete work in foundations, in all kinds of work using graded crushed stone (20mm down) as coarse aggregate including conveying,laying,vibrating, compacting and curing etc complete as per drawings & specifications and direction of the Engineer. (Note: Cement will be free issue. 30 % Fly ash to be used for making Concrete. Shuttering & Fixing steel reinforcement will be paid separately under relevant items.)
Providing & Laying in position design mix cement concrete of following grades as specified in drawings for reinforced concrete work in foundations, in all kinds of work using graded crushed stone (20mm down) as coarse aggregate including conveying,laying,vibrating, compacting and curing etc complete as per drawings & specifications and direction of the Engineer. (Note: Cement will be free issue. 30 % Fly ash to be used for making Concrete. Shuttering & Fixing steel reinforcement will be paid separately under relevant items.)
Providing & Laying in position design mix cement concrete of following grades as specified in drawings for reinforced concrete work in foundations, in all kinds of work using graded crushed stone (20mm down) as coarse aggregate including conveying,laying,vibrating, compacting and curing etc complete as per drawings & specifications and direction of the Engineer. (Note: Cement will be free issue. 30 % Fly ash to be used for making Concrete. Shuttering & Fixing steel reinforcement will be paid separately under relevant items.)
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
PLANNING : Quantity Spread
Quantity Spread
BOQ Tender Quoted rate 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
S.No Description Qty Unit 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
PP102 Ordinary shu 6,346 =BOQ!C112 #REF! 167 334 334 334 334 367 367 367 367 367 367 367 367 367 367 334 334 334 167
PP103 Plywood shu 4,231 =BOQ!C113 #REF! 167 334 334 334 334 367 367 367 367 367 367 367 367 367 367 334 334 334 167
PP104 Curved / Ornamental shu 4,160 =BOQ!C114 #REF! 347 347 347 347 347 347 347 347 347 347 347 347
PP106 Ordinary shu 9,519 =BOQ!C116 238 476 476 476 476 476 476 476 476 476 476 476 476 476 476 476 476 476 476
PP107 Plywood shu 6,346 =BOQ!C117 #REF! 159 317 317 317 317 317 317 317 317 317 317 317 317 317 317 317 317 317 317
PP108 Curved / Ornamental shu 6,241 =BOQ!C118 #REF! 520 520 520 520 520 520 520 520 520 520 520 520
PP109 Extra over formwork item 38.b for TG deck slab,
columns
and beams using leak proof type laminated plywood
shuttering, including designing the formwork for the
lateral thrust due to SCC.
shu
0
=BOQ!C119 #REF!
3064 3064 3064 0
PP110 Modular shuttering consisting of prefabricated
Steel / /
Timber beams & formwork modules including
necessary
fixtures, clips, pins, screws, fittings etc as
directed by
Engineer-in-Charge.
shu
0
=BOQ!C120 #REF!
0 0 0 0 0 0 0 0
24 25 26 27 28 29 30 31 32 33 34 35 36 1 Yr END
24 25 26 27 28 29 30 31 32 33 34 35 36 DLP CLOSE
-
2,115
-
476 238 -
317 159 -
-
9,192
-
C
C
Project Name :-
[All amounts in Lacs]
VAT
Contract value 32,325.27
Margin @ 10.0% 3233
Balance (i.e. Total Contract cost) 29093
Material value [FTS item B.01] 2,380.75
- do - As % of Total Contract cost 36.76%
Others (Total cost less material) 18398.18
- do - As % of Total Contract cost 63.24%
Allowable Deductions from Others:
i) Labour ch. [FTS item A.03 + B.05 + B11] 862.66
ii) Sub-contract [FTS item B.06] 3,363.13
iii) Plant Hire [FTS item B.07] 1,009.29
iv) Consumable [FTS item B.08 + C.01] 764.55
v) Establishment [FTS item A.04] 697.78
vi) Labour cess [FTS item C.02] 323.25
vii) Design & engg. [FTS item A.10] 0.00
Total 11813.57
Balance of Others 6585.00
Prorated bifurcation of Balnce of Others into material and others:
Material @ 36.76% 2421.00
Others @ 63.24% 4164.00
Revised material value after above bifurcation 13116.00
Less Tax 166.00
12543.00
Material composition as per Tax working sheet:
Cement 18.85% 2323.00
Sand& agg 11.63% 1769.00
Steel 20.67% 4875.00
Other 47.19% 3026.00
Struct steel 1.65% 549.80
Tax liability: 100.00% 12542.80
Material
Value
Add margin Total Tax rate Tax amt.
Cement 2323.00 232.00 2555.00 12.5% 319.00
Sand& agg 1769.00 177.00 1946.00 5.0% 97.00
Steel 4875.00 488.00 5363.00 5.0% 268.00
Other 3026.00 303.00 3329.00 12.5% 416.00
Struct steel 549.80 55.00 604.80 12.5% 76.00
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
Total liability 12542.80 1255.00 13797.80 1176.00 1176.00
Less : Input Tax credit (as per 'Tax working' sheet) 166.00
Net liability 603.00
Service tax (if applicable)
Contract Value add free issue material 7142 lacs 39,467.27
VAT 1,176.00
Taxable amount 38,291.27
Tax @ 4.94% 1,893.00
CENVAT credit
Net liability (Service Tax) 1,893.00
-----(1)
-----(2)
-----(3) = (1) - (2)
-----(4)
-----(5) = (4) / (3)
-----(6) = (3) - (4)
-----(7) = (6) / (3)
-----(8)
-----(9)
-----(10)
-----(11)
-----(12)
-----(13)
-----(14)
-----(15) = Sum(8:14)
-----(16) = (6) - (15)
-----(17) = (16) * (5)
-----(18) = (16) * (7)
-----(19) = (4) + (17)
-----(20) = (19) * % composition
-----(21) = (19) * % composition
-----(22) = (19) * % composition
-----(23) = (19) * % composition
-----(24) = (19) * % composition
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
-----(25) 3.64%
-----(26) 1.77%
-----(27) = (25) - (26) 1.87% 253.8497
-----(26) = (1)
-----(27) = (23)
-----(28) = (26) - (27)
-----(29) = (28) * tax rate
-----(30) Figures Not Available
-----(31) = (29) - (30)
Name of the Project:
JOB No.
Contract Value 32,325.27
Margin Value 3,233.00
Net Value 29,092.27
ITEMS Qnty Unit Rate/Unit Amount
(Lacs)
LOCAL PURCHASES
Cement-OPC MT 0
Sand Cum 7,339,483
Aggregate Cum 19,707,003
Structural Steel MT
Reinforcement Steel & HTS MT 48,067,596
Binding Wire Kg -
-
Other Material 0.00 117,554,172
TOTAL-Local Purchases 192,668,254
OUTSTATION / IMPORT PURCHASES
Cement-OPC & SLAG 41,742,620.20
Structural Steel 3,663,725.56
-
-
-
-
TOTAL-Outstation/Import Purchases 45,406,345.76
OTHER
-
-
-
OTHER -
238,074,599.62
Composite Tax By Calculation
Composition Tax Calculation Cement/Admixture -
Tax Amount Sand 7,339,482.97
Reinf 48,067,595.90
ITC Other 117,554,172.05
Tax on Purchase 16,638,436 Aggregate 19,707,002.94
Tax on Margin 33,944,026
Total Gr. Tax 91,274,621 Cement 41,742,620.20
Structural steel 3,663,725.56
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
LOCAL PURCHASES
OUTSTATION / IMPORT PURCHASES
913 -
238,074,600
-
lacs
STATE NAME Jharkhand
Rate of Margin 10.0%
RD Tax Tax On Basic Purch Margin Margin Total
URD Rate Purchases Value Amount Amount
RD 12.50 - - 10.00% - -
5.00 349,499 6,989,984 10.00% 2,352,556 25,878,119
RD 5.00 938,429 18,768,574 10.00% 11,922,970 131,152,666
5.00 - - 10.00% - -
RD 5.00 2,288,933 45,778,663 10.00% 39,339,764 432,737,404
5.00 - - 10.00% - -
RD 5.00 - - 10.00% - -
RD 0.00 - - 10.00% - -
RD 12.50 13,061,575 104,492,597 10.00% 24,418,360 268,601,961
16,638,436 176,029,818 78,033,650 858,370,150
OS 0.00 41742620.20 10.00% 18742473.00 206167203.29
OS 0.00 3663725.56 10.00% 4436484.00 48801326.75
OS 0.00 0.00 10.00% 0.00 0.00
OS 0.00 0.00 10.00% 0.00 0.00
OS 0.00 0.00 10.00% 0.00 0.00
OS 0.00 0.00 10.00% 0.00 0.00
- 45,406,345.76 23,178,957.00 254,968,530.04
RD 0.00 0.00 0.00 10.00% 0.00 0.00
0.00 0.00 10.00% 0.00 0.00
0.00 0.00 10.00% 0.00 0.00
- - - -
16,638,436.00 221,436,163.62 101,212,607.00 1,113,338,679.62
RD 12.50 - - 10.00% - -
RD 5.00 349,499.00 6,989,984 10.00% 2,352,556 25,878,118.71
RD 5.00 2,288,933.00 45,778,663 10.00% 39,339,764 432,737,404.00
RD 12.50 13,061,575.00 104,492,597 10.00% 24,418,360 268,601,961.22
RD 5.00 938,429.00 18,768,574 10.00% 11,922,970 131,152,665.65
OS 0.00 - 41,742,620.20 10.00% 18,742,473.00 206,167,203.29
OS 0.00 - 3,663,725.56 10.00% 4,436,484.00 48,801,326.75
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
OUTSTATION / IMPORT PURCHASES
OS 0.00 - - 10.00% - -
OS - - 10.00% - -
OS - - 10.00% - -
16,638,436 221,436,164 101,212,607 1,113,338,680
- - - -
Percentage
Consider
Tax Tax on purchase
Rate Margin Source
12.50% - Jharkhand
5.00% 117,628 Jharkhand
5.00% 596,149 Jharkhand
5.00% - Jharkhand
5.00% 1,966,988 Jharkhand
5.00% - Jharkhand
5.00% - Jharkhand
0.00% - Jharkhand
12.50% 3,052,295 Jharkhand
5,733,060
12.50% 25770900.00 Chattisgarh
5.00% 2440066.00 Chattisgarh
0.00% 0.00
0.00% 0.00
0.00% 0.00
0.00% 0.00
28,210,966
0.00% 0.00
0.00% 0.00
0.00% 0.00
-
33,944,026.00
12.50% 0.00 Local 0.00%
5.00% 117628.00 Local 3.16%
5.00% 1966988.00 Local 20.67%
12.50% 3052295.00 Local 47.19%
5.00% 596149.00 Local 8.48%
0.00%
12.50% 25770900.00 18.85%
5.00% 2440066.00 1.65%
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
0.00% 0.00 0.00%
0.00% 0.00 0.00%
0.00% 0.00 0.00%
33,944,026 100.00%
-
1.05%
1.05%
PLANT COST BUILD-UP
ITD Cementation India Limited
Rs. Lakhs
New
Pur.
Depreci
ation
Hire
charges External Total Cost
Sl.
No.
List of Plant Existg New hire
Capital
Cost
New Existg hire Charged to
contract
A Concrete - Manufacture
1 Batching Plant - 30cum/hr 20 1 24.00 24.00
2 Batching Plant - 30cum/hr 33 1 39.60 39.60
3 Chiller plant 17 1 36.15 10.37 10.37
4 Generator - 125KVA standby 33 1 6.19 6.19
5 Pump - 5Hp 53 2 0.45 0.45
6 JCB 3D - Aggregate handling - 30cum/hr B/P 33 1 25.00 13.92 13.92
7 JCB 3D - Aggregate handling - 30cum/hr B/P 20 1 16.00 16.00
B Concrete - Placing
1 Concrete Pump BP1800 13 1 8.29 8.29
2 Transit mixers - Exis 65 2 34.13 34.13
3 Transit mixers - Hire 80 4 96.00 96.00
4 Vibrator - High Frequency 117 5 12.50 4.94 4.94
5 Vibrator 254 10 2.86 2.86
6 Concrete placer boom - 32m 30 1 142.50 142.50
7 Compressor - 335CFM (1 site & 1 B/P for filling cement in silos) 62 2 6.98 6.98
C Excavation
1 Ex-100 48 2 67.20 67.20
2 Ex-200 with breaker 26 2 72.80 72.80
3 Tipper 10T 59 3 35.40 35.40
4 Pump - 10Hp (dewatering) 111 10 1.25 1.25
5 JCB 35 1 31.50 31.50
D Backfill
1 JCB 18 1 14.40 14.40
2 Dozer 36 2 25.20 25.20
3 Tractor mounted water tank 10KL 72 4 18.00 18.00
E Reinforcement steel
1 Bar Cutting & Bending m/c 79 3 19.50 8.67 8.67
2 Welding Rectifier 79 3 3.15 1.40 1.40
3 Welding Transformer 140 5 3.50 1.65 1.65
4 F15 new generation Hydra 17 1 18.70 18.70
5 Generator 62.5KVA backup 34 1 3.32 3.32
6 Trailor - 20 T 26 1 20.80 20.80
F Disposal
1 JCB 13 1 10.40 10.40
2 Tipper 25T 12 1 14.40 14.40
3 Tipper 10T 24 2 14.40 14.40
G Shutter
1 Truck Mounted crane 30T 27 2 59.40 59.40
2 F15 new generation Hydra 29 1 31.90 31.90
3 Builder hoist 48 2 14.00 5.67 5.67
4 Generator 62.5KVA backup 34 1 6.00 3.44 3.44
5 Welding Rectifier 106 4 4.20 1.88 1.88
H Structural Steel
1 Welding Rectifier 64 4 4.20 1.13 1.13
2 Generator - 125KVA standby 17 1 3.19 3.19
3 Welding Transformer 64 4 2.80 0.76 0.76
I General Plant
1 Total Station 62 2 15.00 7.85 7.85
2 Levelling Instrument 148 5 3.05 1.52 1.52
3 Tractor trailor 59 2 11.80 11.80
4 Cube testing machine 34 1 0.57 0.57
5 62.5 KVA DG - labour camp 33 1 3.22 3.22
6 Hydra F12 28 1 25.20 25.20
7 Tipper 22 1 11.00 11.00
8 Electric Grout Pump 31 1 0.70 0.70
Total Plant 149.05
Depriciation (Old/New) / Ext. Hire : 63.20 159.92 711.80 934.92
Maintenance (New/Internal Hire) : 74.37
Plant Cost to Contract (to item B.07 of FTS) : 1009.29
Fuel/ Oil / Lub (to item B.08 of FTS) : 421.77
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
Total
machine
months at
site
Plant nos.
130-430-9/12/2014--2:42 AM--244006447.xlsx.ms_office--FTS-PNM
PLANT COST BUILD-UP
ITD Cementation India Limited
Rs. Lakhs
New
Pur.
Depreci
ation
Hire
charges External Total Cost
Sl.
No.
List of Plant Existg New hire
Capital
Cost
New Existg hire Charged to
contract
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
Total
machine
months at
site
Plant nos.
Wear Parts Cost (to item B.09 of FTS) : 65.37
Total for plant and equipment :
1496.43
131-430-9/12/2014--2:42 AM--244006447.xlsx.ms_office--FTS-PNM
1 10 eff. hrs Existg New Plant Hire Charges @ 2.25% per month of purchase price
PLANT & EQUIPMENT BUILD UP 1 6 working days New
1 4 weeks Hire
260 hrs / mth with 1 shift Service Tax on hired P&M (here not considered) = NA as
ST
composit
e
Diesel 56.29 Rs/lit Ranchi price as on 16th sept'13
52 hrs / mth
Factor New Plant Quantity based Running based POL Cost
D
e
p
r
e
c
i a
t i o
n
M
a
i n
t a
n
c
e Resuidal
Value (Rs)
%
C
o
n
s
i d
e
r
e
d

O
u
t p
u
t / h
r
U
t i l i z
a
t i o
n

F
a
c
t o
r
T
o
t a
l
R
u
n
n
i n
g

H
o
u
r
M
o
n
t h
l y

R
u
n
n
i n
g

H
o
u
r
s
T
o
t a
l
R
u
n
n
i n
g

H
o
u
r
(Power/
Fuel)/N
o/Hr
(ltr)
Qty (ltr/KW)
L
u
b
F
a
c
t o
r
Cost incld
lub.
Unit
Cost
Total
Amount
A Concrete - Manufacture Concrete Various Grades = 14714 m3
1 Batching Plant - 30cum/hr 1 Existg 20 1 160,000 - 0.75 0.25 2,400,000 800000 14714 m3 100% 130 2600 0.10 231 600000 1150000 350000 632743
2 Batching Plant - 30cum/hr 1 Existg 33 1 160,000 - - 0.75 0.25 3,960,000 1320000 14714 m3 100% 130 4290 0.10 231 990000 1150000 350000 1044026
3 Chiller plant 1 new 17 1 81,338 3,615,000 3,615,000 0.75 0.25 1,037,053 345684 2577947 71% 14714 m3 100% 130 2210 0.10 77 170000 100000
4 Generator - 125KVA standby 1 Existg 33 1 25,000 - 0.75 0.25 618750 206250 14714 m3 100% 26 858 12 10296 0.10 637518 77 66000 20000
5 Pump - 5Hp 2 Existg 53 1 1,125 - 0.75 0.25 44719 14906 14714 m3 100% 78 4134 0.3 1240 0.10 76792 6 26500 4000
6 JCB 3D - Aggregate handling - 30cum/hr B/P 1 new 33 1 56,250 2,500,000 2,500,000 0.75 0.25 1392188 464063 1107813 44% 14714 m3 100% 78 2574 5.5 14157 0.10 876587 64 165000 50000 1044026
7 JCB 3D - Aggregate handling - 30cum/hr B/P 1 hire 20 1 80,000 - 1.00 1600000 14714 m3 100% 78 1560 5.5 8580 0.10 531265 50000
B Concrete - Placing Concrete Various Grades = 14714 m3
1 Concrete Pump BP1800 1 Existg 13 1 85,000 - 0.75 0.25 828750 276250 14714 m3 100% 104 1352 9 12168 0.10 753430 24 32500 130000 478409
2 Transit mixers - Exis 2 Existg 65 1 70,000 - 0.75 0.25 3412500 1137500 14714 m3 100% 130 8450 6 50700 0.10 3139293 77 650000 70000 2056414
3 Transit mixers - Hire 4 Hire 80 1 120,000 - 1.00 9600000 14714 m3 100% 130 10400 6 62400 0.12 3933996 140000
4 Vibrator - High Frequency 5 New 117 1 5,625 250,000 1,250,000 0.75 0.25 493594 164531 756406 61% 14714 m3 100% 130 15210 0.10 8 117000 5000
5 Vibrator 10 Existg 254 1 1,500 - 0.75 0.25 285750 95250 14714 m3 100% 130 33020 0.10 10000
0.8 6 Concrete placer boom - 32m 1 hire 30 1 475,000 - 1.00 14250000 14714 m3 30 80% 613 104 3120 10 6131 0.20 414129 50000
7 Compressor - 335CFM (1 site & 1 B/P for filling cement
in silos)
2 Existg 62 1 15,000 - 0.75 0.25 697500 232500 14714 m3 100% 75 4650 10 46500 0.10 2879234 33 155000 40000
C Excavation Excavation = 39644 Cum
1 Ex-100 2 hire 48 1 140,000 - 1.00 6720000 39644 Cum 100% 234 11232 8 89856 0.10 5563794 200000
2 Ex-200 with breaker 2 hire 26 1 280,000 - 1.00 7280000 39644 Cum 100% 312 8112 13 105456 0.10 6529730 200000
3 Tipper 10T 3 hire 59 1 60,000 - 1.00 3540000 39644 m3 100% 52 3068 0.10 30000
4 Pump - 10Hp (dewatering) 10 Existg 111 1 1,500 - 0.75 0.25 124875 41625 39644 m3 100% 78 8658 0.4 3463 0.10 214438 6 55500 10000 901181
5 JCB 1 Hire 35 1 90,000 - 1.00 3150000 39644 Cum 100% 130 4550 6 25025 0.10 1549523 50000
D Backfill Backfill = 30746 Cum
1 JCB 1 Hire 18 1 80,000 - 1.00 1440000 30746 Cum 100% 78 1404 6 7722 0.10 478139 50000
2 Dozer 2 Hire 36 1 70,000 - 1.00 2520000 30746 Cum 100% 78 2808 12 33696 0.10 2086423 40000
3 Tractor mounted water tank 10KL 4 Hire 72 1 25,000 - 1.00 1800000 30746 Cum 100% 78 5616 1 5054 0.10 312963 40000
E Reinforcement steel - Reinforcement steel = 21355 MT
1 Bar Cutting & Bending m/c 3 New 79 1 14,625 650,000 1,950,000 0.75 0.25 866531 288844 1083469 56% 21355 MT 100% 260 20540 0.10 50 1027000 30000
2 Welding Rectifier 3 New 79 1 2,363 105,000 315,000 0.75 0.25 139978 46659 175022 56% 21355 MT 100% 260 20540 0.10 50 1027000 3750
3 Welding Transformer 5 New 140 1 1,575 70,000 350,000 0.75 0.25 165375 55125 184625 53% 21355 MT 100% 200 28000 0.10 12500
4 F15 new generation Hydra 1 Hire 17 1 110,000 - 1.00 1870000 21355 MT 100% 78 1326 5 6630 0.10 410523 50000
5 Generator 62.5KVA backup 1 Existg 34 1 13,000 - 0.75 0.25 331500 110500 21355 MT 100% 26 884 6 5304 0.10 328418 15 13260 10000
6 Trailor - 20 T 1 Hire 26 1 80,000 - 1.00 2080000 21355 MT 100% 78 2028 0.9 1825 0.10 113015 50000
F Disposal Disposal = 13706 m3
1 JCB 1 Hire 13 1 80,000 - 1.00 1040000 13706 m3 100% 78 1014 6 6084 0.10 376715 50000
2 Tipper 25T 1 Hire 12 1 120,000 - 1.00 1440000 13706 m3 100% 156 1872 4.0 7488 0.10 463649 20000
3 Tipper 10T 2 hire 24 1 60,000 - 1.00 1440000 13706 m3 100% 156 3744 3.0 11232 0.10 695474 20000
G Shutter Shutter = 34264 MT
1 Truck Mounted crane 30T 2 Hire 27 1 220,000 - 1.00 5940000 34264 MT 100% 78 2106 8 16848 0.10 1043211 200000
2 F15 new generation Hydra 1 Hire 29 1 110,000 - 1.00 3190000 34264 MT 100% 78 2262 5 11310 0.10 700304 50000
3 Builder hoist 2 new 48 1 15,750 700,000 1,400,000 0.75 0.25 567000 189000 833000 60% 34264 MT 100% 156 7488 0.10 100000
4 Generator 62.5KVA backup 1 new 34 1 13,500 600,000 600,000 0.75 0.25 344250 114750 255750 43% 34264 MT 100% 26 884 6 5304 0.10 328418 15 13260 10000
5 Welding Rectifier 4 New 106 1 2,363 105,000 420,000 0.75 0.25 187819 62606 232181 55% 34264 MT 100% 130 13780 0.10 5000
H Structural Steel Structural Steel = m3
1 Welding Rectifier 4 New 64 1 2,363 105,000 420,000 0.75 0.25 113400 37800 306600 73% MT 100% 260 16640 0.10 50 832000 5000
2 Generator - 125KVA standby 1 Existg 17 1 25,000 - 0.75 0.25 318750 106250 m3 100% 26 442 12 5304 0.10 328418 10 4420 20000
3 Welding Transformer 4 New 64 1 1,575 70,000 280,000 0.75 0.25 75600 25200 204400 73% MT 100% 200 12800 0.10 10000
-
I General Plant General Plant = 14714 m3
1 Total Station 2 new 62 1 16,875 750,000 1,500,000 0.75 0.25 784688 261563 715313 48% 14714 m3 100% 150 9300 25 232500 10000
2 Levelling Instrument 5 New 148 1 1,373 61,000 305,000 0.75 0.25 152348 50783 152653 50% 14714 m3 100% 200 29600 10 296000 25000
3 Tractor trailor 2 Hire 59 1 20,000 - 1.00 1180000 14714 m3 100% 104 6136 4 24544 0.10 1519740 20000
4 Cube testing machine 1 Existg 34 1 2,250 - 0.75 0.25 57375 19125 14714 m3 100% 104 3536 0.10 5000
5 62.5 KVA DG - labour camp 1 Existg 33 1 13,000 - 0.75 0.25 321750 107250 14714 m3 100% 300 9900 5 49500 0.10 3064991 5 49500 5000
6 Hydra F12 1 Existg 28 1 120,000 - 0.75 0.25 2520000 840000 14714 m3 100% 104 2912 10 29120 0.10 1803081 5 14560 5000
7 Tipper 1 hire 22 1 50,000 - 1.00 1100000 14714 m3 100% 104 2288 3 6864 0.10 425012 5000
8 Electric Grout Pump 1 Existg 31 1 3,000 - 0.75 0.25 69750 23250 14714 m3 100% 104 3224 3 9672 0.10 598881 5000 251681
Wear Parts Cost
T
o
t a
l
M
o
b
i l i s
a
t i o
n
T
o
t a
l
D
e
m
o
b
i l i s
a
t i o
n
T
o
t a
l D
i r
e
c
t
L
a
b
o
r
Unit
A
v
g
W
o
r
k
i n
g

H
r
s
/ U
n
i t / d
a
y
@

2
6
d
a
y
/ mS.N. Plant / Equipment
P
e
a
k
N
o
a
t s
i t e
N
e
w
/ E
x
i s
t i n
g
/
H
i r
e
T
o
t a
l m
a
c
h
i n
e

m
o
n
t h
s
a
t s
i t e
S
h
i f t / d
a
y
H
i r
e
/ N
o
/ M
t h

/ S
h
i f t
U
n
i t P
r
i c
e
-
N
e
w

(
R
s
)
T
o
t a
l N
e
w

P
u
r
c
h
a
s
e
(
R
s
)
T
o
t a
l
D
e
p
r
e
c
i a
t i o
n
/
E
x
t H
i r
e
T
o
t a
l M
a
i n
t a
n
c
eQty
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
Factor New Plant Quantity based Running based POL Cost
D
e
p
r
e
c
i a
t i o
n
M
a
i n
t a
n
c
e Resuidal
Value (Rs)
%
C
o
n
s
i d
e
r
e
d

O
u
t p
u
t / h
r
U
t i l i z
a
t i o
n

F
a
c
t o
r
T
o
t a
l
R
u
n
n
i n
g

H
o
u
r
M
o
n
t h
l y

R
u
n
n
i n
g

H
o
u
r
s
T
o
t a
l
R
u
n
n
i n
g

H
o
u
r
(Power/
Fuel)/N
o/Hr
(ltr)
Qty (ltr/KW)
L
u
b
F
a
c
t o
r
Cost incld
lub.
Unit
Cost
Total
Amount
Wear Parts Cost
T
o
t a
l
M
o
b
i l i s
a
t i o
n
T
o
t a
l
D
e
m
o
b
i l i s
a
t i o
n
T
o
t a
l D
i r
e
c
t
L
a
b
o
r
Unit
A
v
g
W
o
r
k
i n
g

H
r
s
/ U
n
i t / d
a
y
@

2
6
d
a
y
/ mS.N. Plant / Equipment
P
e
a
k
N
o
a
t s
i t e
N
e
w
/ E
x
i s
t i n
g
/
H
i r
e
T
o
t a
l m
a
c
h
i n
e

m
o
n
t h
s
a
t s
i t e
S
h
i f t / d
a
y
H
i r
e
/ N
o
/ M
t h

/ S
h
i f t
U
n
i t P
r
i c
e
-
N
e
w

(
R
s
)
T
o
t a
l N
e
w

P
u
r
c
h
a
s
e
(
R
s
)
T
o
t a
l
D
e
p
r
e
c
i a
t i o
n
/
E
x
t H
i r
e
T
o
t a
l M
a
i n
t a
n
c
eQty
TOTAL PLANT & EQUIPMENT 14,905,000 93491791 7437264 8585178 58% 42177104 6537000 4315250 700000 6408480
Total External Hire= 71180000
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
A B C D E F G H I J K L M N O P Q R X
Plant Unit Rates
ITEM Code Plant Code Labour
Amount Amount
A Concrete - Manufacture P1 INR 21,567,275 L1 INR 2,720,794
Items: Qnty. Amount(INR) Rate (INR) Amount(INR) Rate (INR)
Concrete=> Cum 14714 100.0% 21,567,275 1465.8 100.0% 2,720,794 184.91
B Concrete - Placing P2 INR 43,993,707 L2 INR 2,534,823
Items: Qnty. Amount(INR) Rate (INR) Amount(INR) Rate (INR)
TG conc => cum 9192 12% 5279245 574 12.0% 304179 33
Sub struct => cum 472 60% 26396224 55865 60.0% 1520894 3219
Superstruct => cum 0 28% 12318238 6159118957 28.0% 709750 354875239
9,665 100.00% 43,993,707 4552 100.00% 2534823 262.27
C Excavation P3 INR 35,259,485 L3 INR 901,181
Items: Qnty. Amount(INR) Rate (INR) Amount(INR) Rate (INR)
soil 2 to 4 Excavation=> Cum 37,493 6.0% 2,115,569 56 6.0% 54,070.88 1.44
soil 4 to 10 Excavation=> Cum 2,151 0.2% 52,889 25 0.2% 1,351.77 0.63
hard rock wo blasting 2 to 4 Excavation=> Cum 0 87.4% 30,799,160 15399579892 87.4% 787,182 #########
hard rock wo blasting 4 to 10 Excavation=> Cum 0 2.5% 881,487 293829038 2.5% 22,529.53 #########
hard rock with blasting 2 to 4 Excavation=> Cum 0 2.0% 705,190 352594846 2.0% 18,023.63 #########
hard rock with blasting 4 to 10 Excavation=> Cum 0 2.0% 705,190 235063231 2.0% 18,023.63 #########
39,644 100.00% 35,259,485 889 100.0% 901181 22.73
D Backfill P7 INR 8,767,525 L3 INR -
Items: Qnty. Amount(INR) Rate (INR) Amount(INR) Rate (INR)
Excavation=> Cum 30,746 100.0% 8,767,525 285 100.0% 0 0.00
E Reinforcement steel P4 INR 9,029,978 L4 INR -
Items: Qnty. Amount(INR) Rate (INR) Amount(INR) Rate (INR)
Rebar => MT 21355 100% 9029978 423 100.0% 0 0
F Disposal P5 INR 5,545,839 L5 INR -
Items: Qnty. Amount(INR) Rate (INR) Amount(INR) Rate (INR)
Precast=> cum 13706 100.0% 5545839 405 100.0% 0 0.00
G Shutter P6 INR 13,045,619 L6 INR -
Items: Qnty. Amount(INR) Rate (INR) Amount(INR) Rate (INR)
Sub structure Shutter => sqm 14737 60.0% 7827371 531 60.0% 0 0.00
Superstructure Shutter => Cum 22106 37.0% 4826879 218 37.0% 0 0.00
Modular Shutter => Cum 0 3.0% 391369 391368557 3.0% 0 0.00
36844 100.00% 13045619 354
0 Structural Steel P7 INR 1,876,838 L6 INR -
Items: Qnty. Amount(INR) Rate (INR) Amount(INR) Rate (INR)
SS => MT 507 100.0% 1,876,838 3705 100.0% - 0.00
Cum 0 0.0% 0
I General Plant P8 INR 15,572,144 L8 INR 251,681
Items: Qnty. Amount(INR) Rate (INR) Amount(INR) Rate (INR)
Concrete=> Cum 14714 100.0% 15572144.3 1058 100.0% 251681.25 17.10
TOTAL FROM PLANT 1 154,658,409 6,408,480
CHECK FROM PLANT 154,658,409 6,408,480
Difference - -
TOTAL === 154,658,409 6,408,480
chk PR1 == 146,069,895 6,408,480
(8,588,514) (0.001)
Total project duration 36 months
Mob period 2 month
Execution period - proposed 34 months
Demob period 1 months
DLP 12 months
A. ONCOST
A.01 STAFF - INDIAN
i) Salaries
General Supervision B/F from Sheet <<Org>> 80 = 100,514,600
Division of A.01 cost to match FTS format
Construction manpower 38 no. with total sal= 47,462,700 + other cost 10152745
Other manpower 42 no. with total sal= 53,051,900 + other cost 11221455
ii) Travel
a) Initial Staff Travel (Mobilization)
SM & Above 3 Nos @ 1 Trip @ 40,000 Rs / Trip /- 120,000
Managers 16 Nos @ 1 Trip @ 20,000 Rs / Trip /- 320,000
Other Staff 61 Nos @ 1 Trip @ 10,000 Rs / Trip /- 610,000
General Oncost Lab 66 Nos @ 1 Trip @ 5,000 Rs / Trip /- 330,000
b) Annual Staff Travel (To and fro) (LTA included in Salary)
AGM - Mgr Nos @ 6 Trips @ 15,000 Rs / Trip /- -
DM /AM Nos @ 2 Trips @ 5,000 Rs / Trip /- -
Engrs Nos @ 2 Trips @ 2,500 Rs / Trip /- -
Sup Nos @ 2 Trips @ 2,000 Rs / Trip /- -
others Nos @ 2 Trips @ 1,500 Rs / Trip /- -
c) Final Staff Travel (Demobilization)
SM & Above 3 Nos @ 1 Trip @ 40,000 Rs / Trip /- 120,000
Managers 16 Nos @ 1 Trip @ 20,000 Rs / Trip /- 320,000
Other Staff 61 Nos @ 1 Trip @ 10,000 Rs / Trip /- 610,000
General Oncost Lab 66 Nos @ 1 Trip @ 5,000 Rs / Trip /- 330,000
iii) Accommodation
Guest house 1 No 34 months @ 25,000 Rs / month /- 850,000
PM Accommodation 2 No 36 months @ 15,000 Rs / month /- 1,080,000
Managerial Accommodation 17 Nos 34 months @ 10,000 Rs / month /- 5,780,000
Bachelor Accommodation 10 Nos 34 months @ 18,000 Rs / month /- 6,120,000
Operator mess incl plant lab & office, survey, QAQC boy 4 Nos 34 months @ 12,000 Rs / month /- 1,550,400
Sr. Mess 1 Nos 34 months @ 15,000 Rs / month /- 510,000
Electricity charges 34 Nos 34 months @ 1,500 Rs / month /- 1,723,800
Furniture & Utencils 1 LS @ 1,000,000 Rs / LS /- 1,000,000
= -
Total In Rupees A.01 Subtotal = 121,888,800
A.02 STAFF - EXPAT
i) Salaries - all inclusive travel , accommodation & fooding B/F from Sheet <<Org>> =
ii) Travel Expat - Main office trips Rs / trip = -
iii) Accommodation & Fooding Rs / month months = -
Total In Rupees A.02 Subtotal = -
A.03 INDIRECT LABOUR
Wages
i) Construction
Others 66 nos. 20,886,267
ii) Accommodation (payroll lab only) included above 38 Nos months @ 1,500 Rs / month /- -
iii) Furniture & Utencils -
Total In Rupees A.03 Subtotal 20,886,267
A.04 SITE ESTABLISHMENT
i) Temporary facilities
Approach road (detail in enabling sheet) 1 LS Rs / LS /-
Misc. structural steel MT @ 40,000 Rs / MT /- -
Access Roads Rm x m @ 1,500 Rs / sqm /- -
Construction of :
Site Office - using aerocon panel 350 Sqm @ 60% charged 10,000 Rs / sqm /- 2,100,000
Laboratory : 125 Sqm @ 6,000 Rs / sqm /- 750,000
Store : 200 Sqm @ 7,000 Rs / sqm /- 1,400,000
Cement Godown 350 Sqm @ 4,000 Rs / sqm /- 1,400,000
Maitenance Workshop/ fab - shed 250 Sqm @ 2,500 Rs / sqm /- 625,000
Containers / Porta cabins (STAFF) 3 Nos @ 50% charged 300,000 Rs / no /- 450,000
Labour accommodation & conveyence, NA here Labour @ 32 months @ 600 Rs / month /- -
Land rent - labour camp, 1 Acre @ 32 months @ 40,000 Rs / acre/ m /- 1,280,000
Furniture for Offices 1 LS @ 500,000 Rs / LS /- 500,000
Water Tanks Nos @ months @ 25,000 Rs / no /- -
Gen : Tube Well Install Nos @ 125,000 Rs / no /- -
Lbr cmp: Tube Well Install Nos @ 125,000 Rs / no /- -
Install Pipe lines G.I. - 1" Dia. RM @ 300 Rs / LS /- -
Install Pipe lines G.I. - 4" Dia. - for bentonite RM @ 700 Rs / RM /- -
Bentonite tanks Nos @ Charged 50% 150,000 Rs / no /- -
Weigh Bridge platform - 60T 1 No @ Charged 50% 2,000,000 Rs / no /- 1,000,000
Barricade / fencing: Main Yard - in CY Rm @ 80% 1,200 Rs / Rm /- -
Water charges Cum 2 Rs /KL /- -
Tyre Washing arrangement 1 Locations @ 350,000 Rs / location /- 350,000
High pressure pump no @ 300,000 Rs / no /- -
Labour accommodation (rooms cosntructed) 30 sqft per lab 1000 lab 1,000 Rs / no /- 30,000,000
Final Site Clearance 1 LS @ 2,000,000 Rs / LS /- 2,000,000
ii) Vehicles, General equipments etc.
Site Transport
Verna 1 Nos @ 36 months @ 45,000 Rs / month /- 1,620,000
TATA Sumo 4 Nos @ 32 months @ 36,364 Rs / month /- 4,654,592
Xilo for Expat Nos @ 32 months @ 35,000 Rs / month /- -
STAFF BUS 3 Nos @ 32 months @ 73,240 Rs / month /- 7,031,040
Ambulance 1 Nos @ 32 months @ 35,000 Rs / month /- 1,120,000
Utility / Pickup- Hire 2 Nos @ 32 months @ 35,000 Rs / month /- 2,240,000
Machineshop equipments
Laboratory Equipment 1 LS @ 1,000,000 Rs / LS /- 1,000,000
Surveying accessories 1 LS @ 200,000 Rs / LS /- 200,000
Surveying Agency cost nos @ 36 months @ 75,000 Rs / month /- -
AirConditioners 10 nos @ Charged 50% 25,000 Rs / no /- 125,000
Water Coolers & Aquaguards 5 nos @ 15,000 Rs / no /- 75,000
Fax Machine 1 nos @ 25,000 Rs / no /- 25,000
Xerox machine 1 nos @ Charged 50% 125,000 Rs / no /- 125,000
Telephone / EPABX 1 LS @ 150,000 Rs / LS /- 150,000
Walkie Talkies nos @ - Rs / no /- -
Cell phones 40 nos @ 4,000 Rs / no /- 160,000
IT Equipment & Installation Costs 1 LS @ 1,710,548 Rs / LS /- 1,710,548
Client Facilities 1 LS @ Rs / LS /- -
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
1. Plant labour not to be included in On Cost. [To be
taken to FTS via FTS-PLN]
2. Plant transport not to be included in On Cost. [To be
taken to FTS via FTS-PLN]
3. GTE & DLP Provision not to be included in On Cost.
[To be entered in FTS directly on % basis]
A. ONCOST
iii) Electrical installations
Office 1 LS @ 300,000 Rs / LS /- 300,000
Labour Camp - SEB connection 1 LS @ 200,000 Rs / LS /- 200,000
Field locations distribution 5 locations @ 300,000 Rs/location /- 1,500,000
iv) Electrical consumptions
Electricity charges:
Office 5 Rs. / Month /- -
Office, store etc.
Staff accommodation
Labour accommodation 34 months @ 5,000 Rs / month /- 170,000
Consumables 34 months @ 10,000 Rs / month /- 340,000
v) Tools, protective clothing, Safety etc.
Special tools & consumables
Safety Expenses - including manpower of C.V. 42.79 Lakhs /- 4,279,125
Safety Shoe labours 3 times 300.00 Rs / shoe
Helmet labours 3 times 100.00 Rs / shoe
Jacket labours 3 time 150.00 Rs / shoe
Safety hyness labours 3 time 300.00 Rs / shoe
Other accessories 1 LS 200000
Fire Extinguisher 1 LS 200000
Safety Tape/barricade 1 LS 300000
SaFETY SIGNBOARDS ETC 1 LS
Other safety measures 1 LS
vi) Administration costs
House rent - Site Office, Store
IT Running Cost 34 months @ 36,234 Rs / month /- 1,231,946
Post & Stationery 32 months @ 15,000 Rs / month /- 480,000
Telephone, Fax & courier 32 months @ 15,000 Rs / month /- 480,000
Xerox & Typing 32 months @ 10,000 Rs / month /- 320,000
Photograph & Advertisement 32 months @ 10,000 Rs / month /- 320,000
Tea/Coffe, Client Entertainment 32 months @ 15,000 Rs / month /- 480,000
Medical 32 months @ 10,000 Rs / month /- 320,000
Cell phone bills 32 months 40 nos 500 Rs/no/month /- 640,000
Passes, Permits etc.
Internal Testing Expenses 32 months 25,000 Rs / month /- 800,000
Visits/ Local Travels
- by ITDCem HO personnel 36 months 1 visits / month 25,000 Rs / visit /- 900,000
- Messenger Visits 36 months 1 trips / month 2,500 Rs / visit /- 90,000
Local Cartage 36 months 3 trips / month 1,000 Rs / visit /- 108,000
Misc Client/Local Expenses 36 months 15,000 Rs / month /- 540,000
Casting Yard 1.00 Nos
Enabling works 1.00 Nos
Total In Rupees A.04 Subtotal 75,590,250
A.05 INSURANCE : Revenue = Lakhs -
Project Insurance
Plant & Machinery of plant value P.A
Com. PI Insurance Of T.o.
Transit Insurance of plant value P.A
Motor Insurance of plant value P.A
Hull Insurance of plant value P.A
TPL/PI/WC on direct lab of
Other Co. Insurance 0.25% of Revenue
As calculted from attached "Insurance" sheet of Mr. A. George 355.71 Lakhs 35,571,239
-
TOTAL IN RUPEES A.05 Subtotal 35,571,239
A.06 BANK GUARANTEE / BONDS Bank Comm. P.A. 1.0%
Performance BG - 1 10% 32325.27 Lakhs 50 months /- 13,468,863
BG on Mob Advance 5.0% 32325.27 Lakhs 36 months /- 4,848,791
BG On Plant Advance 32325.27 Lakhs 36 months /- -
Retention money BG - 1 32325.27 Lakhs 36 months /- -
BG Bearings, Exp joints, Waterproofing etc Rs. included in Reten money BG-1
Total In Rupees A.06 Subtotal 18,317,653
A.07 INTEREST ON ADVANCES
Advance Interest @10% L =
Total In Rupees A.07 Subtotal -
A.08 BANK CHARGES
Interest on external borrowings Lakhs 1 LS /- -
Bank Charges 20 months 0.281% for lakhs /- -
Total In Rupees A.08 Subtotal -
FTS Plant (to Direct Cost) GTE
PLANT / TOOLS etc.
GTE Levy Other Than Div - III Lakhs 1.00% x 32325.27 Lakhs = 32,325,270
Total In Rupees Subtotal 32,325,270
A.09 TAXES
Registration tax
Vehicle tax
Road tax tax sheet
VAT at output Lakhs
Service Tax 189,300,000
WCT { Please refer Tax Calculation Sheet} Lakhs 60,300,000
Total In Rupees A.09 Subtotal 249,600,000
A.10 DESIGN & PROFESSIONAL SERVICES
post tender design charge Temp works
External Testing Expenses per month for 36 months -
Total In Rupees A.10 Subtotal -
TOTAL ONCOST 554,179,480
oncost from FTS
Indirect cost 5,160
SITE ORGANISATION Peak Monthly Salary/Wage Total
Man-months
A. SUPERVISION
Project Director - GM 1 241300 32
Project Manager - SM 2 159100 65
Sub structure M 1 120800 21
AM 1 59600 21
SE 1 49300 21
E 36300
AE 2 28500 40
SA 5 26300 99
Super structure - M 1 120800 26
AM 1 59600 26
SE 1 49300 26
E 2 36300 47
SA 6 26300 138
Finishing works - AM 1 59600 23
SE 1 49300 22
E 36300
AE 3 28500 66
SA 8 26300 160
- M 120800
SE 49300
AE 28500
SA 26300
- AM 59600
SA 26300
- AM 59600
Reinforcement E 1 36300 27
SA 1 26300 31
QA / QC
Incharge AM 1 59600 28
E 2 36300 53
Safety
AM 1 59600 35
SA 3 26300 80
Commercial
Commerical & Planning head M 1 120800 35
Client & Subcon SE 1 49300 34
Planning
Cost Eng AM 1 59600 36
QS E 2 36300 61
Autocad CL 1 23900 35
Survey
Incharge DM 1 72700 36
E 1 36300 36
CL 2 23900 64
Mechanical
137 of 430 244006447.xlsx.ms_office org9/12/2014 2:42 AM
SITE ORGANISATION Peak Monthly Salary/Wage Total
DM 1 72700 36
AM 1 59600 25
E 1 36300 35
Mechanic CL 4 23900 104
Electrician CL 4 23900 104
Accounts
DM 1 72700 36
O 1 33400 36
CL 2 23900 61
Admin
DM 1 72700 36
CL 2 23900 69
Purchase / Procurement
DM 1 72700 33
O 1 33400 35
Stores
DM 1 72700 29
SA 1 26300 35
CL 2 23900 59
Indian
Expat
TOTAL SUPERVISION 80
Execution staff 38 55,189 860
Support Staff 42 40,904 1297
CHK
138 of 430 244006447.xlsx.ms_office org9/12/2014 2:42 AM
SALARY STRUCTURE CONSIDERED
Mean CTC Email dt 07/12/2011& 20/04/12-GBR
Category Cost to company O/S All Prod Bonus Gross income (Rs)
Per anum Per Month Per Month Per Month
SGM (Technical) 3,360,000 280000 280000 Not given assumed
GM (Technical) 2,895,000 G1 241300 241300 G2
DGM (Technical) 2,659,000 D3 221600 221600 D3
AGM (Technical) 2,280,000 190000 190000 D2
SM (Technical) 1,909,000 159100 159100 D1
M (Technical) 1,450,000 avg of M4,5, 6 120800 120800 M6
ME (Technical) 981,662 81800 81800
DM (Technical) 872,058 72700 72700
AM (Technical) 714,877 59600 59600
SE (Technical) 591,845 49300 49300
E (Technical) 435,410 36300 36300
SUP (Technical) 337,467 28100 28100
AE (Technical) 342,148 28500 28500
AS (Technical) 343,467 28600 28600
TA (Technical) 277,523 23100 23100
SO (Non Tech) 483,190 40300 40300
O (Non Tech) 400,895 33400 33400
CL (Non Tech) 286,751 23900 23900
SA (Non Tech) 315,174 26300 26300
EXPAT1 300000
EXPAT2 200000
EXPAT3 150000
AGENCY 75000
LABOUR PAY SCALE
COMPANY LABOUR
OT = 4 Hrs
Sr.No. Basic/day OT Benifts/day OS-Conv/day Total Company /week /month /Month
1 200 200.00 130 44 574 Unskilled 3444 6572.94 14913
2 225 225.00 146.25 44 640.25 Semiskilled 3841.5 6871.71 16634
3 325 325.00 211.25 44 905.25 Skilled 5431.5 7768.02 23518
4 400 400.00 260 44 1104 Highly skilled 6624 9005.67 28682
LOCAL LABOUR
OT = 8 Hrs JHARKHAND RATES
Sr.No. Basic/day OT Benifts/day OS-Conv/day Total Local /week /month /Month RATE Considered
1 125.00 125.00 62.50 312.50 Unskilled 1875.00 8119 175
2 130.00 130.00 65.00 325.00 Semiskilled 1950.00 8444 182
3 150.00 150.00 75.00 375.00 Skilled 2250.00 9743 210
4 180.00 180.00 90.00 450.00 Highly skilled 2700.00 11691 252
CONSIDERED IN ESTIMATE
Local =Rs 8119 Helper /head per month
Local =Rs 8444 Pump Optrs /head per month
Company =Rs 23518 Optr /head per month
Company =Rs 28682 Heavy Optr /head per month
Exchange Rate 1.27
Expat Salary Exchange Rate -Nov 2008 1.39 to be incorporated
Gross Sal Travell+Visa/m Food/m Acc/ele/m
PM 307758 8300 6000 15000 337058 ITD -BKK
AFM 217176 8300 6000 15000 246476 Figures recvd fromITD
A= Basic
(Baht)
0.45 A
(In
1.5 * A
(In india)
Allowance
(In India)
3 AIR
TKT /YR
ACCM
(INR)
VISA
(INR)
FOOD
(INR)
Total INR
ET 177247 8300 6000 15000 206547 1 EXPATS-1-CAT-Manager 439047 EX-1 439047 150000 95985 319950 7082 5330 5000 700 5000 439047
S1 95000 5800 6000 15000 121800 2 EXPATS-2-CAT- Sr Engineer 194304 EX-2 194304 80000 51192 120000 7082 5330 5000 700 5000 194304
S2 46000 5800 6000 15000 72800 3 EXPATS-3-CAT-Engineer 151506 EX-3 151506 60000 38394 90000 7082 5330 5000 700 5000 151506
EA 220000 8300 6000 15000 249300 4 EXPATS-4-CAT- Superintendent 87309 EX-4 87309 30000 19197 45000 7082 5330 5000 700 5000 87309
TM 148000 8300 6000 15000 177300 5 EXPATS-5-CAT- Technical Asst 76610 EX-5 76610 25000 15998 37500 7082 5330 5000 700 5000 76610
EE 189500 8300 6000 15000 218800 6 EXPATS-6-CAT- Sr officer 76610 EX-6 76610 25000 15998 37500 7082 5330 5000 700 5000 76610
C 64859 5800 6000 15000 91659 7 EXPATS-7-CAT- Officer 61630 EX-7 61630 18000 11518 27000 7082 5330 5000 700 5000 61630
SFM 255000 8300 6000 15000 284300 A= Basic 0.45 A 1.5 * A Allowance 2 AIR ACCM VISA FOOD Total INR
8 EXPAT - OPERATOR 52332 LX-8 52332 13520 8651 28838 7082 3560 500 700 3000 52332
9 EXPAT - SKILLED 41878 LX-9 41878 9750 6239 20797 7082 3560 500 700 3000 41878
139 of 430 244006447.xlsx.ms_office-Salary9/12/2014 2:42 AM
Plumbing, Sanitary and Drainage Works
Sr.no Description Unit Qty
Providing, supplying and fixing cast iron soil & waste pipes
(conforming to IS 1729) heavy type including necessary fixtures
and fitting such as bends, tees, single junction, double
junction, slotted vent, offsets, traps, jointing supports,
equipment, scaffolding, all labour, material etc. complete with
lead caulked fully water tight joints as per Engineers directions.
a 150 mm dia. Pipe R.M. 250
b 100 mm dia. Pipe R.M. 100
c 75 mm dia. Pipe R.M. 50
Same as above item no 129 but extra heavy type pipe
(conforming to IS 1536) used for below ground including
necessary fixtures and fitting such as bends, tees, single
junction, double junction, slotted vent, offsets, traps, jointing
supports, equipment, scaffolding, all labour, material etc.
complete with lead caulked fully water tight joints as per
Engineers directions.
a 150 mm dia. Pipe R.M. 50
b 100 mm dia. Pipe R.M. 50
Providing, supplying and fixing of UPVC rain water down
take pipe as per IS 4985 Class II including necessary
fixtures and fittings such as bends, tees, single junction,
offset, jointing, scaffolding all labour materials etc. complete
a 100 mm dia. RM 100
b 150 mm dia. RM 1,000
c 200 mm dia. RM 100
Supplying, fitting and fixing UPVC roof drain heads with
UPVC High domes gratings as per drawings at various
elevations, including fabrication and connecting to roof drain
pipes, lead caulking, sealing with poly-sulphide sealant at
the junction of pipe and slab openings for perfect water
tightness complete with all materials including two coats of
synthetic enamel paint over a coat of approved primer as per
drawing, specification and instruction of Engineer for the
following sizes of rainwater pipe
a 150 mm. Dia. UPVC. Pipe Each 75
b 100 mm dia. UPVC . Pipe Each 20
Providing and fixing Salem Stainless steel AISI (18/8)
kitchen sink as per IS: 13983 with C.I. Brackets and stainless
steel plug 40 mm including painting of fittings and brackets ,
cutting and making good the walls wherever required. (with
integrated drain-board)
Each 4
Providing, supplying and fixing approved make white glazed
vitreous china oval shaped wash basin as per IS: 2556 with
supporting brackets, CP brass 30 mm dia. Waste fittings
& 32 mm dia waste pipe of suitable length. 15 mm dia. CP
brass pillar cock and supply connections with 300 mm Long
15 mm, dia. flexible connector with brass nuts at both ends and
one CP brass angular stop tap and CP bottle trap complete .
a Size 630 mm x 450 mm flat back Each 25
b Size 550 mm x 400 mm flat back Each 5
630 mm x 500 mm counter top wash basin with one no.
15 mm. Dia. Pillar cock (Jaguar Continental or
equivalent) including all accessories etc. with C P angular
stop cock and bottle trap complete as per instruction of
Engineer in charge.
Each 2
a Same as above item (136) but with photo voltaic control
system for water controls,
Each 5
Providing , supplying and fixing approved make white
vitreous china large flat back type urinal of 580 mm x 380
mm x 350 mm size conforming to IS: 2556, without photo
voltaic flushing system, CP flush pipe, CP stop cock, CP
waste strainer, CP spreaders with unions and clamps, GI waste
pipe to CI waste shaft on the outside wall complete including
providing and fitting half round porcelain channel, and making
chases, holes etc. in floors or walls and making good the same
including materials, labour etc. complete as per specifications ,
drawings & directions of Engineer:
Each 20
a Same as above item (138) but with photo voltaic control
system for flushing system.
Each 10
Providing, supplying and fixing approved superior quality
squatting type (Indian type) Orissa pattern white vitreous
china water closet of 580 mm size with white vitreous china
foot rests and ten (10) liters low level vitreous China
low level flushing cistern with fittings of brackets, P- trap,
stopcocks, 32 mm dia. GI-flush pipe with fittings, 20 mm dia
overflow pipe with specials, coupling anti - siphonage
connection PVC pipe connections with unions at both ends
including painting of fittings and making chases, holes etc. and
making good the same where required including
materials, labour and equipment complete as per
specification, drawings & directions of Engineer
Each 5
Providing, supplying and fixing approved superior quality wall
mounted coloured (excluding premium colours) glazed
vitreous China European water closet &tenliters
flushing cistern with photo voltaic control system, with all
necessary fittings including materials, labour and
equipment complete as per manufacturer's manual &
specification including directions of Engineer
Each 5
Providing, supplying and fixing approved superior quality
white vitreous china European type water closet of
standard size with low level white vitreous china flushing
cistern of ten (10) liters capacity with CI brackets, hard
rubber seat, lid with CP hinges and rubber buffer P-trap,
stopcocks,32 mm dia. GI flush pipe with fittings, anti-
siphonage connection, PVC pipe connections with unions at
both ends including painting of fittings and making chases,
holes etc. and making good the same where required
including materials, labour and equipment complete as per
specification, drawings & directions of Engineer.
Each 5
Providing, supplying and fixing 125 mm dia. Heavy
chromium plated (CP) shower roses with rim of approved
quality including materials, labour and equipment complete as
per specification, drawings & directions of Engineer.
Each 10
Providing, supplying and fixing 12 mm dia. Stainless steel
towel rail 500 mm long with clamps screwed to wall with rawl
plugs and CP brass screws including all accessories etc.
complete as per specification, drawings & directions of
Engineer.
Each 10
Providing and fixing stainless steel liquid soap dispensers
of best and approved quality with brackets screws etc. all
complete as per Engineers directions including all labour,
materials etc. complete.
Each 10
Providing, supplying and fixing 600 mm x 900 mm high
square edge approved quality Belgium mirror with 6 mm
thick float glass and asbestos cement sheet backing
fixed to wooden cleats with CP brass screws etc.
complete as per Engineers directions including all labour,
materials etc.
Each 15
Providing, supplying and fixing stainless steel toilet paper
holder of approved quality and make including all fixtures etc.
complete as per Engineers directions including all labour,
materials complete.
Each 10
a Providing, supplying and fixing vitreous china urinal
partitions of Hindware or any other approved make and shade
of size 690 mm x 320 mm for urinals including fixing
it to wall etc. complete as per drawing and direction of
Engineer.
Each 10
b Same as item 147.a above but with polished granite slab
partitions
Each 10
Supplying, fitting and fixing porcelain soap tray of approved
make:
a Recessed soap tray of size 150 mm x 150 mm Each 10
Supplying, fitting and fixing bathroom self of approved make
of size 580 mm x 150 mm ( porcelain)
Each 5
Providing and fixing 80 mm CI Nahani trap conforming to
IS:-5219 fixed in cement concrete including CI grating, bend
and CI pipe upto the outside face of the wall including cutting
holes in walls and making good the same in cement mortar 1:4
etc. complete as directed.
Each 70
Providing and fixing chile's trap fixed in cement concrete
including CI grating, bend and CI pipe upto the outside face
of the wall including cutting holes in walls and making good the
same in cement mortar 1:4 etc. in kitchen and pantry complete
as directed.
Each 20
Providing and fixing 225 mm x 225 mm stoneware gully
trap with 150 mm outlet with 230 mm thick brick masonry
chamber in cement mortar 1:6, 600 mm x 600 mm inside
plan with 20 mm thick cement plaster 1:4 inside on 150 mm
thick 1:3:6 cement concrete bedding with CI frame and CI
cover 300 mm x 460 mm including cast iron grating in
the sink and for the gully trap fixed complete as per
specification and direction.
Each 40
Providing, supplying and fixing medium class GI water pipe
conforming to IS:1239 having embossed ISI mark with all
fittings such as tees, bends, elbows, couplings, flanges,
plugs, bends including testing, clamps, making threads, making
chases, hole in walls, slabs etc. and making good the same
to the original condition neatly where required all complete
including supports, straps, all labour, material and equipment
etc.
Each
a 15 mm NB R.M. 300
b 20 mm NB R.M. 250
c 25 mm NB R.M. 80
Same as above item no 153 but fitted with holder bat
clamps.
a 25 mm NB R.M. 75
b 32 mm NB R.M. 100
c 40 mm NB R.M. 80
d 50 mm NB R.M. 60
Supplying, fitting and fixing medium class GI water pipe
including cost of jointing materials,fitting and fixing all
necessary specials, cutting pipes, making threads, cutting
trenches upto 1.5 metre below surface in all sorts of soil and
refilling the same as directed with two coats of painting on
pipes and specials with bituminous paint complete in all
respect. (Payment will be made on the centre line
measurements of total pipe line including all specials. No
separate payment will be made for accessories, specials).
a 50 mm NB R.M. 200
b 100 mm NB R.M. 25
Providing, supplying and fixing CP brass stop cocks (
heavy type) of approved make and design conforming to IS:
781 and as per Engineer's approval
a 15 mm NB Each 50
b 20 mm NB Each 50
Supplying fitting and fixing CP angular stop cock of size 20
mm complete with bonnet, glands etc. conforming to I.S. 781
having body spindle and handle of approved design.
Each 20
Providing, supplying and fixing CP brass bib cocks( heavy
type) of approved make and design conforming to IS: 781 and
as per Engineer's approval
a 15 mm dia. Each 25
Supplying fitting and fixing gun metal wheel valve of
approved brand & make tested to 21 kg. Per sq.cm.(for water
lines only)
a 50 mm Each 10
b 40 mm Each 10
c 32 mm Each 10
d 25 mm Each 10
Providing and constructing 600 mm x 600 mm x 750 mm
deep brick masonry inspection chambers with 75 class
designation brick work with 1:4 cement mortar having
200 mm thick concrete mat in 1:4:8 with 150 mm offsets
beyond face of walls with 12 mm thick internal plaster in
1:4 cement mortar, 100 mm RCC M-25 cover slab
plastered and cementrendered, channels and sloping
bottom, suitable medium duty (16.6 kg) 500 mm internal dia.
C.I. approved manhole cover with framing, MS rungs etc.
complete including fixing of inlet and outlet pipes, excavation
and backfilling with sand etc. all complete including all
labour, materials and equipment etc.
Each 10
Supplying and hoisting and fixing syntax or equivalent
water storage tank of approved quality with closed top with
lid (Black) multilayer 1000 liter
Each 2
PLUMBING TOTAL
Rate Amount
2,800 700,000
1,855 185,500
1,475 73,750
-
3,519 175,950
2,500 125,000
-
450 45,000
900 900,000
2,100 210,000
-
100 7,500
75 1,500
12,500 50,000
-
12,800 320,000
10,500 52,500
14,000 28,000
17,500 87,500
13,200 264,000
19,000 190,000
9,200 46,000
23,100 115,500
13,700 68,500
2,300 23,000
1,600 16,000
1,575 15,750
3,300 49,500
1,300 13,000
5,400 54,000
5,100 51,000
-
800 8,000
2,100 10,500
1,600 112,000
3,700 74,000
3,400 136,000
-
210 63,000
300 75,000
300 24,000
-
380 28,500
430 43,000
460 36,800
570 34,200
-
940 188,000
1,550 38,750
-
450 22,500
500 25,000
950 19,000
-
500 12,500
-
1,000 10,000
950 9,500
925 9,250
900 9,000
10,500 105,000
20,000 40,000
5,001,950
Mix Design
M10 220 kg/cum 0.180
M15 270 kg/cum 0.280
M20 300 kg/cum 0.350
M25 320 kg/cum 0.400
M30 360 kg/cum 0.400
M35 400 kg/cum 0.410
M40 kg/cum
M45 kg/cum
M50 kg/cum
Aggregate 0.87 2% wastage included
Sand 0.47 5% wastage included
BASIC RATES
Item Description Unit Rate Remarks
Cement -OPC -53 Grade Tonne 5,000 by Venkat dt 09.01.13 from Mundhra
International
Cement -OPC -43 Grade Tonne
PSC Cement - for Pile Tonne 6,500 ACC rates by venkat
40 mm down aggregate cum 1,294 By Metromine from AC mail dt 08.01.13
20 mm down agreegate cum 1,530 By Metromine from AC mail dt 08.01.13
10 mm down agreegate cum 1,530 By Metromine from AC mail dt 08.01.13
Coarse Aggregate - 20 mm & 10mm down cum 1,530 By Metromine from AC mail dt 08.01.13
Boulder for apron cum 1,639 Assumed
Sand - Coarse cum 1,428 By Metromine from AC mail dt 08.01.13
Filling sand cum 441 Quoted recent
Plasticiser - SP430 SRV Kg 46 From CC-15
Granular Material cum 1,000 Assumed
Bitumen - VG30 (60/70) MT 44,371 Comparative statement by ABK dt.29.05.12
Silica fumes Kg 25 TO BE CHECKED
Diesel Ltr 47.15 Rate at Delhi vide dt 5.12.12
Rebars ( TMT-Fe 415 grade)
6/8mm-dia MT 44975 SAIL rate mail by Venkat dt 07.01.13
10mm- dia MT 44450 SAIL rate mail by Venkat dt 07.01.13
12mm -dia MT 43925 SAIL rate mail by Venkat dt 07.01.13
16mm- dia MT 43925 SAIL rate mail by Venkat dt 07.01.13
20mm-dia MT 43925 SAIL rate mail by Venkat dt 07.01.13
25mm-dia MT 43925 SAIL rate mail by Venkat dt 07.01.13
28mm-dia MT 43925 SAIL rate mail by Venkat dt 07.01.13
32mm-dia MT 43925 SAIL rate mail by Venkat dt 07.01.13
Weighted average rate as per above incl inhibitor soln MT 44,762
Inhibitor soln 1T requires 25kg @ Rs26/kg
application Rs200/T
Inhibitor soln & application 640.38 per MT
HT Strand- 15.2 mm MT 57,485 Usha Martin offer dt 28-11-12
GI Binding wire Kg 65 CC-15 rate
Structural steel(plate sections) MT 51,275 by Venkat dt 12.09.12
Structural steel(rolled sections) MT 51,275 by Venkat dt 12.09.12
Resale value of structural steel - new MT 22,000
Resale value of reinforcement steel MT 18,000
Shear connector - SC nos. 65 KMM Engineer
Material Consumptions
Cement for M15 Concrete kg/cum 170
151 OF 430 244006447.xlsx.ms_office9/12/2014 2:42 AM
Cement for M15 Concrete kg/cum 260
Cement for M20 Concrete kg/cum 320
Cement for M25 Concrete kg/cum 340
Cement for M30 Concrete kg/cum 380
Cement for M35 Concrete(piling) kg/cum 410
Cement for M35 Concrete kg/cum 380
Cement for M40 Concrete kg/cum 380
Cement for M45 Concrete kg/cum 450
Cement for M50 Concrete kg/cum 460
Cement for M55 Concrete kg/cum 510
Cement for M60 Concrete kg/cum 440 20
Cement for Brick work 1:6 kg/cum 63
Cement for Brick work 1:4 kg/cum 110
Cement for Concrete block 1:4 kg/cum 110
Aggregate cum/cum 0.85
Sand - Coarse cum/cum 0.44
Dust cum/cum 0.00
sand for brick work cum/cum 0.30
Plasticiser - SP430 ( for all concrete except piling)
Cement for M15 Concrete kg/cum 2.6
Cement for M25 Concrete kg/cum 3.4
Cement for M30 Concrete kg/cum 3.8
Cement for M30 Concrete(piling) kg/cum 3.0
Cement for M35 Concrete kg/cum 3.8
Cement for M45 Concrete kg/cum 4.5
Cement for M50 Concrete kg/cum 4.6
Cement for M60 Concrete kg/cum 4.4
Binding wire- Civil Work kg/MT 6.00
Binding wire- pile kg/MT 4.00
Wastage of Materials
Concrete materials (Cement, sand aggregate etc) 0.00%
Reinforcement
Wastage in pile - rebar 4%
Civil work - cutting wastage 1%
Laps chairs etc. 4%
Structural Steel 3%
152 OF 430 244006447.xlsx.ms_office9/12/2014 2:42 AM
Direct labour Mobilzation Schedule
Max
Sr Position Qualification Class Q'ty Feb-13 Mar-13 Apr-13 May-13 Jun-13
No 1 2 3 4 5
Semi skilled rigger ITDCem 6 2 4 6
Mason ITDCem 3 2 3 3
Welder ITDCem 3 2 3 3
Helper ITDCem 5 5 5 5 5 5
Grand Total Total 17 5 5 11 15 17
0 0 1 2 2
Progress : Monthly %
1
.
3
3
%
1
.
3
3
%
2
.
9
3
%
3
.
9
9
%
4
.
5
2
%
Progress : Acc %
1
%
3
%
6
%
1
0
%
1
4
%
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
Direct labour Mobilzation Schedule
Jul-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14
6 7 8 9 10 11 12 13 14 15 16 17
6 6 6 6 6 6 6 6 6 6 6 6
3 3 3 3 3 3 3 3 3 3 3 3
3 3 3 3 3 3 3 3 3 3 3 3
5 5 5 5 5 5 5 5 5 5 5 5
17 17 17 17 17 17 17 17 17 17 17 17
2 2 2 2 2 2 2 2 2 2 2 2
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
1
9
%
2
3
%
2
8
%
3
2
%
3
7
%
4
1
%
4
6
%
5
0
%
5
5
%
5
9
%
6
4
%
6
8
%
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
Direct labour Mobilzation Schedule
Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15
18 19 20 21 22 23 24 25 26 27 28 29
6 6 6 6 6 6 6 6 6 6 6 6
3 3 3 3 3 3 3 3 3 3 3 3
3 3 3 3 3 3 3 3 3 3 3 3
5 5 5 5 5 5 5 5 5 5 5 5
17 17 17 17 17 17 17 17 17 17 17 17
2 2 2 2 2 2 2 2 2 2 2 2
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
4
.
5
2
%
7
3
%
7
7
%
8
2
%
8
6
%
9
1
%
9
5
%
1
0
0
%
1
0
5
%
1
0
9
%
1
1
4
%
1
1
8
%
1
2
3
%
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
Dated
Direct labour Mobilzation Schedule
Total Rate Total Amount
Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 M-Month (Rs/Mon) (Rs)
30 31 32 33 34 35 36
4 4 4 4 2 2 2 126 16634 2,095,846
3 3 3 3 2 2 2 65 16634 1,081,190
3 3 3 3 2 2 2 65 16634 1,081,190
5 5 5 5 5 5 5 120 9000 1,080,000
-
15 15 15 15 11 11 11 376 58,901 5,338,226
376
2 2 2 2 1 1 1
3
.
9
9
%
3
.
9
9
%
3
.
9
9
%
3
.
9
9
%
2
.
9
3
%
2
.
9
3
%
2
.
9
3
%
1
2
7
%
1
3
1
%
1
3
5
%
1
3
9
%
1
4
1
%
1
4
4
%
1
4
7
%
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
Project : Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
Shutter Calculations
Total Structural requirement
Material Cost
Resale
Labour for fabrication
Liner Cost
Total
Total Concrete
So, shuttering cost per Cum
For spine & wings
Total Structural requirement
Material Cost
Resale
Labour for fabrication
Total
Total Concrete
So, shuttering cost per Cum
For Precast CB
Total Structural requirement
Material Cost
Resale
Labour for fabrication
Liner Cost
Total
Total Concrete
So, shuttering cost per Cum
For CB
Total Structural requirement
Material Cost
Resale
Labour for fabrication
Total
Total Concrete
So, shuttering cost per Cum
For drain
Total Structural requirement
Material Cost
Resale
Labour for fabrication
Total
Total Concrete
So, shuttering cost per Cum
For deck slab on viaduct
Total Structural requirement
Material Cost
Resale
Labour for fabrication
Total
Total Concrete
So, shuttering cost per Cum
For Pile Cap
Total Structural requirement = 17.60 MT
Material Cost = 902440
Resale = -387200
Labour for fabrication = 264000
Total = 779240
Total Concrete = 15481 Cum
So, shuttering cost per Cum = 50
For Pier
Total Structural requirement = 67.73 MT
Material Cost = 3472811
Resale = -1490041
Labour for fabrication = 1693228
Liner Cost 37.73 = 188,646
Total = 3864644
Total Concrete = 6503 Cum
So, shuttering cost per Cum = 594
For spine & wings (included in PNM)
Total Structural requirement =
Material Cost =
Resale =
Labour for fabrication =
Total =
Total Concrete =
So, shuttering cost per Cum = (already considered in PNM, only for per cum cost analysis)
For Precast CB
Total Structural requirement = 9.00 MT
Material Cost = 461475
Resale = -198000
Labour for fabrication = 135000
Liner Cost 9.00 = 45,000
Total = 443475
Total Concrete = 2495 Cum
So, shuttering cost per Cum = 178
For CB
Total Structural requirement = 18.75 MT
Material Cost = 961406
Resale = -412500
Labour for fabrication = 281250
Total = 830156
Total Concrete = 2551 Cum
So, shuttering cost per Cum = 325
For drain
Total Structural requirement = 80.00 MT
Material Cost = 4102000
Resale = -1760000
Labour for fabrication = 800000
Total = 3142000
Total Concrete = 8918 Cum
So, shuttering cost per Cum = 352
For deck slab on viaduct
Total Structural requirement = 2.00 MT ASSUMED
Material Cost = 102550
Resale = -44000
Labour for fabrication = 20000
Total = 78550
Total Concrete = 300 Cum
So, shuttering cost per Cum = 262
(already considered in PNM, only for per cum cost analysis)
RISK / BENEFIT COSTS
A Sub con
A-1 For all sub conn 14% 3363 Lakhs = (47,083,768)
B Better Negotiation in Direct Material
Rebate in Cement, Steel, HT
Strand,aggregate
5% on 935 Lakhs = (4,673,697)
Rebate in other material 4% on 1176 Lakhs = (4,702,167)
C Insurance
Rebate 20% of 356 Lakhs = (7,114,248)
D Using OPC instead of PSC in pile & pile cap
Concrete in foundation #REF! Cum
25% replacement #REF! Cum 600 #REF!
E Hire Plant Negotiation
Better Negotiation 8% of 712 Lakhs = (5,694,400)
F Pile
Div - iii offer is Rs. 4225/ Rm
Hence considering rate from other subcontract
#REF! Rm @ 400 Rs. Per Rm #REF!
G HT strand
Using Usha Martin HT strand instead of TATA
Saving #REF! MT 3641 Rs. Per MT #REF!
H Saving in quantities
Total Cost of Risks = #REF!
/-
/-
/-
/-
/-
/-
/-
/-
Tender no: __________ Div 2: 40/12
Project : ____________________________ Comprehensive Development of Corridor (Outer Ring Road) between Madhuban Chowk to Mukarba Chowk. SH:- C/o Elevated road, RCC drain, Footpath, cycle track, widening/strengthening of road, rain water harvesting scheme, electrical works and other allied works.
CASHFLOW STATEMENT TOTAL Check M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14
Sl. No. FTS It.
No.
Description
33295 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
1 2 3 4 5 6 7 8 9 10 11 12 13 14
RECEIPTS : 26636
1 MOBILISATION ADVANCE 3330 1664.75 1664.75
2 PLANT ADVANCE - 1665 554.92 554.92 554.92
3 MONTHLY R.A. BILLS #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4 Secured Advance
5 RECOVERY OF MOBILISATION ADVANCE -3330 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
6 RECOVERY OF PLANT ADVANCE -1665 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
7 RECOVERY OF SECURED ADVANCE
8 RETENTION FROM BILL -1665 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
9 RELEASE OF RETENTION 1665 1039.75
10 DEDUCTION OF INCOME TAX AT SOURCE #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
11 CREDIT OF INCOME TAX AT SOURCE #REF! #REF!
12 DEDUCTION OF WC TAX AT SOURCE #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
13 CREDIT OF WC TAX AT SOURCE #REF! #REF!
MONTHLY RECEIPTS : #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
PAYMENTS :
1 A.01 STAFF - INDIAN 1218.89 33555832 8.79 20.91 26.61 32.00 36.82 37.77 37.77 38.09 38.09 38.09 38.09 38.09 38.09 41.06
2 A.02 STAFF - EXPAT
3 A.03 INDIRECT LABOUR 208.86 6114826 2.60 3.03 4.92 5.49 5.78 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63
4 A.04 SITE ESTABLISHMENT 755.90 11576698 64.71 81.99 84.88 50.13 42.98 38.71 38.71 38.71 38.71 38.71 8.71 8.71 8.71 8.71
5 A.05 INSURANCE 355.71 11857080 59.29 59.29 59.29
6 A.06 BONDS 183.18 158.93 24.24
7 A.07 INTEREST ON ADVANCE #REF! 13.87 13.87 32.37 36.99 41.62 41.62 #REF! #REF! #REF! #REF! #REF! #REF!
8 A.08 BANK CHARGES
9 A.09 TAXES 2496.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
10 A.10 DESIGN & PROFESSIONAL SERVICES
11 B.01 LOCAL MATERIALS ( DM )
12 i) CEMENT 417.43 41742620
13 ii) REBAR 480.68 48067596
14 iii) STRUCTURAL STEEL 36.64 3663726
15 iv) SALVAGE
16 v) OTHERS 1 (Aggrigate) 197.07 19707003
17 vi) OTHERS 2 (SAND) 73.39 7339483
18 vii) REMAINING OTHERS 1175.54 117554172
19 B.02 IMPORTED MATERIALS
20 B.03 ENABLING WORKS
21 B.04 SHUTTERING & STAGING MATERIAL 335.18 33517685
22 B.05 LABOUR CONTRACT (PRW) 589.72 58971677
23 B.06 SUB-CONTRACT 3363.13 336312632
B.06 SUB-CONTRACT (DIV 3 PILING) #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
24 B.07 PLANT
25 i) CAPITAL COST - PLANT ONLY 149.05 29.81 29.81 29.81 29.81 29.81
i.a) DEPRICIATION FOR NEW PLANT
26 ii) DEPRICIATION/ INT.HIRE - OLD PLANT 159.92
27 iii) EXTERNAL HIRE CHARGES 711.80 12960000 0.20 11.50 21.20 26.00 28.40 33.35 34.45 35.65 35.65 35.65 35.65 35.65 33.45
28 iv) PLANT MAINTENANCE 74.37 2084426 0.05 0.11 0.24 1.61 2.07 2.11 2.44 2.47 2.47 2.68 2.68 2.75 2.83
29 v) WEAR PARTS 65.37 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72
30 vi) RESIDUAL VALUE - NEW PLANT -85.85
31 B.08 POL 421.77 8836477 0.26 8.66 11.51 15.31 16.77 17.83 18.71 19.36 19.36 19.94 19.94 20.00 19.61
32 B.09 PLANT MOB & DE-MOB 50.15 5.00 10.03 10.03 10.03
33 B.10 PLANT LABOUR/OPERATOR 64.08 3621716 0.16 0.16 1.43 1.74 1.83 1.83 2.47 2.47 2.84 2.84 2.27 2.27 2.27
34 C.01 GTE 323.25 #REF!
35 C.02 LABOUR CESS 323.25 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
36 C.03 PRICE INFLATION
37 C.04 RISK & BENEFIT COSTS #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
FORMAT
38 C.05 DLP PROVISION 64.65
39 C.06 PROVISIONAL SUMS
40 C.07 OTHERS (Bank/LC Charges)
41 D.01 PROJECT CONTINGENCY 161.63 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73
42 D.02 ADDITIONAL CONTINGENCY 646.51 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94
43 E TENDER ADJUSTMENT
44 F.01 OVERHEAD -ITD CEM 1293.01 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
45 G OTHER DIVISION'S WORK (SPECIFY)
MONTHLY PAYMENTS : 29739 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
MONTHLY SURPLUS ( + ) / DEFICIT ( - ) #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
CUMULATIVE SURPLUS(+)/ DEFICIT(-) #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Tender no: __________ Div 2: 40/12
Project : ____________________________ Comprehensive Development of Corridor (Outer Ring Road) between Madhuban Chowk to Mukarba Chowk. SH:- C/o Elevated road, RCC drain, Footpath, cycle track, widening/strengthening of road, rain water harvesting scheme, electrical works and other allied works.
CASHFLOW STATEMENT TOTAL
Sl. No. FTS It.
No.
Description
33295
RECEIPTS :
1 MOBILISATION ADVANCE 3330
2 PLANT ADVANCE - 1665
3 MONTHLY R.A. BILLS #REF!
4 Secured Advance
5 RECOVERY OF MOBILISATION ADVANCE -3330
6 RECOVERY OF PLANT ADVANCE -1665
7 RECOVERY OF SECURED ADVANCE
8 RETENTION FROM BILL -1665
9 RELEASE OF RETENTION 1665
10 DEDUCTION OF INCOME TAX AT SOURCE #REF!
11 CREDIT OF INCOME TAX AT SOURCE #REF!
12 DEDUCTION OF WC TAX AT SOURCE #REF!
13 CREDIT OF WC TAX AT SOURCE #REF!
MONTHLY RECEIPTS : #REF!
PAYMENTS :
1 A.01 STAFF - INDIAN 1218.89
2 A.02 STAFF - EXPAT
3 A.03 INDIRECT LABOUR 208.86
4 A.04 SITE ESTABLISHMENT 755.90
5 A.05 INSURANCE 355.71
6 A.06 BONDS 183.18
7 A.07 INTEREST ON ADVANCE
8 A.08 BANK CHARGES
9 A.09 TAXES 2496.00
10 A.10 DESIGN & PROFESSIONAL SERVICES
11 B.01 LOCAL MATERIALS ( DM )
12 i) CEMENT 417.43
13 ii) REBAR 480.68
14 iii) STRUCTURAL STEEL 36.64
15 iv) SALVAGE
16 v) OTHERS 1 (Aggrigate) 197.07
17 vi) OTHERS 2 (SAND) 73.39
18 vii) REMAINING OTHERS 1175.54
19 B.02 IMPORTED MATERIALS
20 B.03 ENABLING WORKS
21 B.04 SHUTTERING & STAGING MATERIAL 335.18
22 B.05 LABOUR CONTRACT (PRW) 589.72
23 B.06 SUB-CONTRACT 3363.13
B.06 SUB-CONTRACT (DIV 3 PILING)
24 B.07 PLANT
25 i) CAPITAL COST - PLANT ONLY 149.05
i.a) DEPRICIATION FOR NEW PLANT
26 ii) DEPRICIATION/ INT.HIRE - OLD PLANT 159.92
27 iii) EXTERNAL HIRE CHARGES 711.80
28 iv) PLANT MAINTENANCE 74.37
29 v) WEAR PARTS 65.37
30 vi) RESIDUAL VALUE - NEW PLANT -85.85
31 B.08 POL 421.77
32 B.09 PLANT MOB & DE-MOB 50.15
33 B.10 PLANT LABOUR/OPERATOR 64.08
34 C.01 GTE 323.25
35 C.02 LABOUR CESS 323.25
36 C.03 PRICE INFLATION
37 C.04 RISK & BENEFIT COSTS
M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
15 16 17 18 19 20 21 22 23 24
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
625.00
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
42.37 42.37 42.37 43.01 43.01 43.01 43.01 41.26 36.33 36.33
6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63
8.71 8.71 8.71 8.71 8.71 8.71 8.71 8.71 8.71 8.71
59.29
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
33.45 22.55 22.55 22.55 22.55 22.55 20.15 14.75 14.75 14.75
2.83 2.83 2.83 2.83 2.83 2.83 2.83 2.83 2.63 2.40
2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72
19.61 12.36 12.36 12.36 12.36 12.36 11.38 9.40 9.40 8.78
2.27 2.27 2.27 2.27 2.27 2.27 2.27 2.27 1.74 1.43
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Tender Cashflow Tender Cashflow
38 C.05 DLP PROVISION 64.65
39 C.06 PROVISIONAL SUMS
40 C.07 OTHERS (Bank/LC Charges)
41 D.01 PROJECT CONTINGENCY 161.63
42 D.02 ADDITIONAL CONTINGENCY 646.51
43 E TENDER ADJUSTMENT
44 F.01 OVERHEAD -ITD CEM 1293.01
45 G OTHER DIVISION'S WORK (SPECIFY)
MONTHLY PAYMENTS : 29739
MONTHLY SURPLUS ( + ) / DEFICIT ( - )
CUMULATIVE SURPLUS(+)/ DEFICIT(-) #REF!
6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73
26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
COST FLOW STATEMENT
Estimate_r0
COST FLOWSTATEMENT 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 1 yr END
M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 DLP CLOSE
INVOICE Rs.
1 Progress Billing L 33295 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2 Escalation L
3 Others L
Total Invoice 33295.03 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Costs
A GENERAL COSTS
1 Staff - Indian including Accomodation etcL 1218.89 8.79 20.91 26.61 32.00 36.82 37.77 37.77 38.09 38.09 38.09 38.09 38.09 38.09 41.06 42.37 42.37 42.37 43.01 43.01 43.01 43.01 41.26 36.33 36.33 (335.56)
2 Staff - Expat L
3 Site Establishment incld running costs L 755.90 64.71 81.99 84.88 50.13 42.98 38.71 38.71 38.71 38.71 38.71 8.71 8.71 8.71 8.71 8.71 8.71 8.71 8.71 8.71 8.71 8.71 8.71 8.71 8.71 (115.77)
4 General Costs L
5 Camp/Accommodation / Indirect Labour L 208.86 2.60 3.03 4.92 5.49 5.78 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 6.63 (61.15)
6 Direct Labour (Optr+Hlpr) L 64.08 0.16 0.16 1.43 1.74 1.83 1.83 2.47 2.47 2.84 2.84 2.27 2.27 2.27 2.27 2.27 2.27 2.27 2.27 2.27 2.27 2.27 1.74 1.43 (18.11)
7 Site Transport L
B PLANT
1 Depreciation - New Plant L 63.20 0.14 0.29 0.58 1.33 2.11 2.12 2.16 2.16 2.16 2.16 2.16 2.28 2.52 2.52 2.52 2.52 2.52 2.52 2.52 2.52 2.52 1.91 1.87 1.14 (16.00)
2 Depreciation - Old L 159.92 0.02 0.14 3.51 4.09 4.23 5.15 5.24 5.24 5.88 5.88 5.99 5.99 5.99 5.99 5.99 5.99 5.99 5.99 5.99 5.99 5.99 5.33 2.86 (46.53)
3 External Plant Hire L 711.80 0.20 11.50 21.20 26.00 28.40 33.35 34.45 35.65 35.65 35.65 35.65 35.65 33.45 33.45 22.55 22.55 22.55 22.55 22.55 20.15 14.75 14.75 14.75 4.80 (129.60)
4 Plant Maintenance L 74.37 0.05 0.11 0.24 1.61 2.07 2.11 2.44 2.47 2.47 2.68 2.68 2.75 2.83 2.83 2.83 2.83 2.83 2.83 2.83 2.83 2.83 2.63 2.40 1.33 (20.84)
5 POL - Plant L 421.77 0.26 8.66 11.51 15.31 16.77 17.83 18.71 19.36 19.36 19.94 19.94 20.00 19.61 19.61 12.36 12.36 12.36 12.36 12.36 11.38 9.40 9.40 8.78 5.78 (88.36)
6 GTE L 323.25 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
7 Plant Mob/Demob L 50.15 5.00 10.03 10.03 10.03 10.03 5.03
8 Plant Wear Part 65.37 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72 2.72
C Direct Material
1 Cement L 417.43 (417.43)
2 Reinforcement & HT Strands L 480.68 (480.68)
3 Structral Steel L 36.64 (36.64)
4 Resale - Reinf / SS L
5 Aggregate L 197.07 (197.07)
6 Sand L 73.39 (73.39)
7 Other- Materials L 1175.54 (1175.54)
D Temp Mt'l / Shuttering Mt'l L 335.18 (335.18)
E
1 Labour contract L 589.72 (589.72)
2 Sub contract L 3363.13 (3363.13)
3 Div-III -PILING L #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
F Other Costs
1 Maintenance Provision L 65 64.65
2 Insurance L 355.71 59.29 59.29 59.29 59.29 (118.57)
3 Bonds L 183.18 158.93 24.24
6a 4 Intrest On Advance L 13.87 13.87 32.37 36.99 41.62 41.62 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
6b 5 Escalation L
6d 6 Bank Charges/LC Charges L
6e 7 TAXES L 2496.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
6f 8 Design Cost L
6g 9 Labour Cess L 323.25 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4 10 Project Contingency L 161.63 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73 6.73
5 11 Additional Contingency L 646.51 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94 26.94
12 Risk & Benefit cost L #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
MONTHLY COST : 28446 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 70 #REF!
#REF!
CUMULATIVE MONTHLY COST L 4848.79 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
U
N
I
T
Estimate_r0
No Description Subjob Unit Qty Rate Basic Amount Remark
Site Offices
Main Office
Sub Structure Sq. Ft. 3,550.800 80.00
Super Structure(Including Toilet Block Area) Sq. Ft. 3,686.000 528.33
Total -
DMRC ,Engineer Office,Laboratory
Sub Structure Sq. Ft. 3,066.600 80.00
Super Structure "DMRC ,Engineer Office" Sq. Ft. 1,899.00 554.00
Super Structure "Laboratory" Sq. Ft. 1,248.00 405.00
Extra Work (DMRC Building Toilet Block, Partition Walls, Enterance Porch) LS 1.00 282,680.00
Total -
Grand Total -
Store Buildings
Main Construction Sq.Ft. 2,152.00 170.00
Total -
Labour Camp
Main Building Nos. 4.000 843,932.96
Toilet Building LS 1.000 258,721.00
Electric Fixing LS 1.000 127,840.00
Erection Of Over Head Tank for Labour Colony MT 1.16 2,500.00 All item considered in oncost and rate
Total -
Workshop
Workshop Foundation LS 1.000 18,968.35
Workshop Tin Shed Sq.M. 50.000 56.00
Total -
Others Buildings
Batching Plant Foundation
Dressing Of Earth Sq.M. 200.000 3.00
Concreting Work
For Rafts Cu.M. 130.000 100.00
For Columns Cu.M. 25.000 130.00
Shuttering Work
For Rafts Cu.M. 150.000 100.00
For Columns Cu.M. 90.000 130.00
Reinforcement Steel Work MT 9.250 3,200.00
Plat Fixing,"J" Bolt Fixing etc. Job 20,000.000 1.00
-
Borewell Construction LS 1.000 204,000.00
Borewell Construction LS 1.000 164,000.00
Cement Godown LS 1.000 335,900.00
-
-
Raw Material Supply for Casting Yard Establishment
GSB Supply
GSB (Crushed) Supply
A Foundation Structure :-
(10,30,90) Gantry Foundation
Raft Cu.M. 960.00 900.00 864,000 Fine sand +agg.
Tower Crane Foundation
Raft Cu.M. 0.00 390.00 -
25 MT Gantry Foundation
Raft Cu.M. 0.00 390.00 -
Base Of Bed Concrete including Reinforcement Yard, Workshop Platform,
Service Roads,Petrol Pump etc.
- Cu.M. 3,187.50 900.00 2,868,750 Casting Yard Size = 80 x 400 Meters, Fine sand+agg
Grand Total GSB
Coarse Sand Cu.M. 540.00 -
Stone Dust Cu.M. 540.00 -
Dust Cu.M. 390.00 -
Aggregate 10 mm Cu.M. 540.00 -
WBM Supply Cu.M. 540.00 -
B Reinforcement Steel
Gantry Foundation MT 80.00 40,000.00 3,200,000 Lenth Of One Gantry Foundation is 430.00 Meter,Total Nos. Of Gantry foundation are = 4
Tower Crane Foundation MT 0.00 52,000.00 - Lenth Of Tower Crane Foundation is 205.00 Meter,Total Nos. Of Gantry foundation are = 2
25 MT Gantry Foundation MT 0.00 52,000.00 - Lenth Of Tower Crane Foundation is 250.00 Meter,Total Nos. Of Gantry foundation are = 2
Weigh Bridge MT 2.50 40,000.00 100,000
Wsatage @ 5%
Total Reinforcement Steel Rate is refered to DSR 2012 Item No.5.22 A
C Structural Steel MT 30.00 42,500.00 1,275,000 Rate is refered to DSR 2012 Basic Rates 0.3-Material Item No.1007
MT 30.00 30,000.00 900,000 From C3
D Rail Line (90 lb) MT 68.80 22,500.00 1,548,000 Total Rail Length is 2710 Meter where Unit Weight Of 90 lb Rail is taken is 40 Kg/Meter.
E CGI Sheets Quintal 191.53 4,075.00 780,490 Rate is refered to DSR 2012 Basic Rates 0.3-Material Item No. 3050
Add 10% for Transporatation,Loading,Unloading,Contractor Profits etc. LS 1.00 labour rate inclusive of profit
Grand Total
F RMC Providing and Laying
F.1 Mix 30
F.1.1 Foundation Structure :-
(10,30,90) Gantry Foundation
Raft Cu.M. 727.20 4,150.00 3,017,880 CC26 enabling concrete rates, flyash based;
Wall Cu.M. 323.20 4,150.00 1,341,280
F.1.2 Tower Crane Foundation
Raft Cu.M. 0.00 4,150.00 -
F.1.3 Stacking Pedestal 4497.8
pedestal: for 100no spine stacking/ level * 2 level Cu.M. 177.76 4,150.00 737,704
Cu.M. -
F.1.4
Bed Concrete including Weigh Bridge,Reinforcement Yard,Workshop
Platform,Service Roads,Petrol Pump and Other Structure etc.
- Cu.M. 1,262.50 3,800.00 4,797,500 Average Thickness Of Bed = 125 mm, lean conc to be used
Total Mix 30
Wastage @ 5%
Total Mix 30 (Including Wastage) -
G Mix 10
G.1 Gantry Foundation
Raft Cu.M. 252.00 3,600.00 907,200 CC26 enabling concrete rates, flyash based; basic 3200+vat 12.5%
G.2 Tower Crane Foundation
Raft Cu.M. -
G.3 25 MT Crane Foundation
Raft Cu.M. -
Total Mix 10 252.00
Wastage @ 5%
Total Mix 10 (Including Wastage) -
H Shuttering Work 5046.91
H.1.1 Foundation Structure :-
(10,30,90) Gantry Foundation
Base PCC (Side Area) Sq.M. 125.00 - Rate is refered to DSR 2012 Item No.5.9.1
Base PCC (End Face Area) Sq.M. 125.00 - Rate is refered to DSR 2012 Item No.5.9.1
Raft (Side Area) Sq.M. 1,032.00 150.00 154,800 Rate is refered to DSR 2012 Item No.5.9.1
Raft (End Face Area) Sq.M. 3.60 150.00 540 Rate is refered to DSR 2012 Item No.5.9.1
Wall (Side Area) Sq.M. 2,752.00 150.00 412,800 Rate is refered to DSR 2012 Item No.5.9.2
Wall (End Face Area) Sq.M. 1.60 150.00 240 Rate is refered to DSR 2012 Item No.5.9.2
H.1.2 Tower Crane Foundation
Base PCC (Side Area) Sq.M. 125.00 - Rate is refered to DSR 2012 Item No.5.9.1
Base PCC (End Face Area) Sq.M. 125.00 - Rate is refered to DSR 2012 Item No.5.9.1
Raft (Side Area) Sq.M. 0.00 125.00 - Rate is refered to DSR 2012 Item No.5.9.1
Raft (End Face Area) Sq.M. 0.00 125.00 - Rate is refered to DSR 2012 Item No.5.9.2
H.1.3 25 MT Gantry Foundation
Base PCC (Side Area) Sq.M. 125.00 - Rate is refered to DSR 2012 Item No.5.9.1
Base PCC (End Face Area) Sq.M. 125.00 - Rate is refered to DSR 2012 Item No.5.9.1
Raft (Side Area) Sq.M. 0.00 125.00 - Rate is refered to DSR 2012 Item No.5.9.1
Raft (End Face Area) Sq.M. 0.00 125.00 - Rate is refered to DSR 2012 Item No.5.9.1
Wall (Side Area) Sq.M. 0.00 125.00 - Rate is refered to DSR 2012 Item No.5.9.2
Wall (End Face Area) Sq.M. 0.00 125.00 - Rate is refered to DSR 2012 Item No.5.9.2
Total Amount for Shuttering Work
I PVC Pipes
75 mm Dia Pipe(Supply and Fixing) Rmt 175.00 75.00 13,125
200 mm Dia Pipe(Supply and Fixing) Rmt 45.00 210.00 9,450
Other Labour Conrtract
Site Cleaning
Site Cleaning/Grading Sq.M. 40,500.00 10.00 405,000
Casting Yard Fencing Work
Fencing Work (ISA Fixing with Concrete Pedestal) Rmt. 1,135.00 135.00 153,225
Fencing Work (CGI Sheet Fixing) Rmt. 1,135.00 70.00 79,450
Foundation for Gantry/Tower Crane
Earthwork in Excavation
Earthwork in Excavation (Manual) in Foundation for Structures Cu.M. 3,990.000 75.00 299,250
Total
Dressing Of Earth
Dressing Of Earth Sq.M. -
GSB Laying with Compaction
GSB Laying with Compaction
Sq.M. 0.00 5.00 -
Total Total 0.000 -
Drain Work
Side PCC Drains
Casting bay - inside pcc drain - Rmt 2,400.000 50.00 120,000 To be constucted along with casting bay PCC flooring
Side PCC Drains -
Side PCC Drains -
One Side Brick Work Drain along Gantry Wall
One Side Brick Work Drain along Gantry Wall Rmt 860.000 568.75 489,125
Casting yard preferal drains - 2 side brick Rmt 500.000 857.50 428,750
Total
Bamboo Reinforcement
Fixing of Bamboo Reinforcement Sq.M. 2,000.00 100.00 200,000
Total
U G Tank (Complete Construction)
U G Tank (Complete Construction) LS 4.000 100,000.00 400,000
Earth Pits
Earthing Pits Nos. 35.00 528.00 18,480
Earthing Pits Nos. 6.00 528.00 3,168
Tin Shed Establishment
Reinforcement Yard Sq.M. 300.000 56.00 16,800
Rebar Area, Lab Testing Area Sq.M. 424.240 52.00 22,060
Erection of ISMB/ISMC for Sheds MT 2.500 1,500.00 3,750
Soak Pit and Septic Tank
Soak Pit and Septic Tank LS 1.000 178,079.25 178,079
DG Room and Labour Rest Room
DG Room and Labour Rest Room LS 1.000 50,000.00 50,000
Labour Charges for General Fabrication Work
ISA 40 x 40 x 5 for Fencing Work MT 3.000 8,500.00 25,500
Insert Plate Fabrication MT 8.080 8,500.00 68,680
Water Tank Shed,Mechanical Work Shop Shed MT 2.159 8,500.00 18,352
Template Of Batching Plant Foundation MT 0.602 8,500.00 5,115
Tower Stand for Water Tank Of Labour Colony MT 0.432 8,500.00 3,673
DG Platform for 90 MT Gantry MT 0.476 8,500.00 4,046
Roller Bench for Steel Yard MT 1.061 8,500.00 9,016
Rail Joint Plate MT 1.561 8,500.00 13,265
Main Gate Of CY MT 1.687 8,500.00 14,342
Safety Indication Board MT 0.137 8,500.00 1,161
Cutting Set Trolly MT 0.332 8,500.00 2,819
Stairs for Water Tank MT 0.026 8,500.00 220
Survey Tower MT 0.571 8,500.00 4,854
Insert Plate Fabrication MT 0.363 8,500.00 3,089
Fire Extinguisher Stand MT 0.249 8,500.00 2,115
Cutting Machine Table etc. MT 0.220 8,500.00 1,870
Survey Tower MT 2.280 8,500.00 19,379
Table Form for Bar Cutting Machines MT 0.828 8,500.00 7,035
DG Platform for 70 MT Gantry MT 0.405 8,500.00 3,445
Operator Cabin Platform on 70 MT Gantry with Ladder MT 0.159 8,500.00 1,350
Insert Plate Fabrication MT 4.481 8,500.00 38,089
Logo Board MT 0.158 8,500.00 1,345
Fishing Plate for Batching Plant MT 0.382 8,500.00 3,245
Table Form for Bar Cutting Machines MT 0.098 8,500.00 830
Roller Bench for Steel Yard MT 0.628 8,500.00 5,340
Insert Plate Fabrication,Lifter Beam,Precast Concrete Shutter,Rebar
Zig,Ladder,Water Tank Roof,Labour Rest Room Shed,Bar Cutting Machine
Shed,Survey Tower,Bearing Plate
MT 9.142 8,500.00 77,707
Bar Cutting Machine Table MT 4.000 8,500.00 34,000
Safety Bed or Strecher MT 0.072 8,500.00 612
Table for Bar Cutting Machines MT 1.420 8,500.00 12,070
Roller Bench for Steel Yard MT 1.144 8,500.00 9,724
Foundation Table for Steel Cutting Machines MT 0.220 8,500.00 1,870
LPG and Oxygen Trolly MT 0.072 8,500.00 612
Shed for RO Plant MT 0.650 8,500.00 5,525
MS Plate Cutting for Foundation Work MT 0.091 8,500.00 777
MS Plate Cutting for Foundation Work MT 0.392 8,500.00 3,336
Electric Tower MT 0.707 8,500.00 6,012
Template for Batching Plant Foundation MT 0.343 8,500.00 2,917
MS Plate Cutting for Survey Tower MT 0.007 8,500.00 60
Cement Stacking Platform MT 5.000 8,500.00 42,500
Total
Gantry/Hoist/Weigh Bridge etc.
Transportation
Transportation Of Gantry/ Tower Crane LS 1.000 260,000.00
Fabrication/Modification for Gantry Crane
70 MT Gantry MT 11.711 3,000.00
90 MT Gantry MT 33.633 7,000.00
25 MT Gantry MT 13.757 7,000.00
25 MT Gantry (For Cantilever Arm Area) MT 10.115 7,000.00
Gantry 25 MT Legs MT 11.510 20,000.00
Gantry 25 MT Legs MT 0.300 20,000.00
10 MT Gantry (For Cantilever Arm Area) MT 14.916 7,000.00
Modification Of Weigh Bridge MT 12.460 9,000.00
Fabrication Of Gantry Parts MT 1.900 17,000.00
Total 110.302
Erection
70 MT Gantry
MT 30.10 2,500.00 Taken in plant sheet
90 MT Gantry
MT 15.39 2,500.00
10 MT Gantry
MT 18.00 2,500.00
10 MT Gantry
MT 18.00 2,500.00
70 MT Gantry Wheel Balances
MT 4.36 2,500.00
90 MT Gantry
MT 37.25 2,500.00
Erection Of Gantry/Weigh Bridge
MT 40.75 2,500.00
Erection Of Weigh Bridge
MT 13.39 2,500.00
Erection Of Over Head Tank for Casting Yard
MT 2.99 2,500.00
25 MT Gantry (For Cantilever Arm Area) MT 21.500 2,500.00
Total 201.719 -
Erection Of Hoist
Nos. 2.00 10,000.00
Total 2.000 -
Railway Track
Fixing Rmt. 2,710.000 100.00 271,000
Total
Plumbing Work LS 500,000
Fixing Over Head PVC Water Supply Tank Liter 5,000.000 -
Making Excavation for Pipe Line upto 300 mm Depth Meter 160.000 -
Fixing 20 mm G.I. Pipe Meter 15.500 -
Fixing 25 mm G.I. Pipe Meter 13.500 -
Fixing 20 mm/15 mm Gate/Ball Valves No. 55.000 -
Fixing Bib Cocks No. 3.000 -
Fixing 50 mm G.I. Pipe Meter 1,200.000 -
Fixing 25 mm Gate/Ball Valves No. 2.000 -
Fixing 50 mm Gate/Ball Valves No. 15.000 -
Fixing Monoblock Pump 5 H.P. No. 2.000 -
Another Accessories LS 1.000 -
Total -
Labour Rest Room
Labour Rest Room LS 1.000 18,391.00 18,391
Labour Toilet Block
Labour Toilet Block LS 1.000 200,000.00 200,000
Panel Room
Panel Room LS 1.000 100,000.00 100,000
Petrol Pump
Petrol Pump (Compound Wall and Office) LS 1.000 -
Raw Material Bin
Raw Material Bin LS 1.00 300,000.00 300,000
Raw Material Bin LS 1.00 300,000.00 300,000
Total
Security Guard Room
Security Guard Room LS 1.00 150,000.00 150,000
Miscellaneous Work
Miscellaneous Work (RO Plant Foundation,Transformer Foundation,DG
Foundation, Laying Of Hume Pipe, Backfilling etc.)
LS 1.00 250,000.00 250,000
Cantilever arm stacking
Strructual steel - Material MT 375.00 32,000.00 12,000,000 Secondray producers - C2 Cantilever stacking material
Fabrication - Labour MT 375.00 8,500.00 3,187,500 Modification
Less slavage for structural steel MT 375.00 (25,000.00) (9,375,000)
Total

Total Expenditure for Casting Yard Establishment/Enabling Work 34,153,684
Bidder Name :
1 Part A- Schedule of Quantity (Civil Works)
2 1. Soil investigation by boring hole of 47 m depth each by
using shell and auger equipment including standard
panitration test, collection of undistrubed soil samples at
every identifiable change of strata, Conducting laboratory
tests on soil samples to decide necessary shear strength
parameters of soil as well as compression index and
coefficient of consolidation. These tests include natural
moisture content, bulk and dry density, liquid and plastic
limits, particle size distribution, and specific gravity,
unconfined compression tests, tri-axial shear tests and
consolidation tests on specimen from collected undisturbed
soil samples and particle size distribution, liquid limit,
plastic limit etc. on specimen from collected disturbed soil
samples. Conducting chemical analysis of subsoil water
samples for evaluation of pH value, sulphate content,
calcium content, chloride content and total dissolved solids
in water for each borehole including preparation &
submission soil investigation report, giving complete
comprehensive record of field and laboratory investigations
and interpretation in soft and hard copy all complete as per
SP002, as per MORTH Technical Specification - 1102,
2403, 2404, 2405 and as per direction of Engineer-in-
Charge.
a) all kind of soil.
66 Each
3 2. Add or deduct for boring each one meter depth beyond
47 m depth or lesser than 47 m depth for soil investigation
including the testing and reporting complete as per
direction of Engineer-in-Charge.
a) All kind of soil.
462 m
Sl.
No
Description of work No.or
Qty.
Unit Estimate
d Rate
Tender Inviting Authority: Executive Engineer, Flyover Project Division F-131, PWD
Name of Work: Comprehensive Development of Corridor (Outer Ring Road) between Madhuban Chowk to Mukarba
Contract No: 55/CE/PWD Zone F-1/2012-13
SCHEDULE OF WORKS
4 3. Boring, providing and installing Bored cast-in-situ
Reinforced Cement Concrete Piles of M-35 grade of 1200
mm dia using Portland slag Cement (confirming to
strength requirement of IS:8112) excluding the cost of
steel reinforcement but including the cost of boring and
temporary liner etc. complete as per approved drawings
and Technical Specifications Sections 1100, 1700 of
MORTH and IRC: 78 -2000 or as directed by Engineer-in-
charge.
23280 m
5 A) The scope of work in the item includes:
6 1. All initial layout of piles after site clearance by
dismantling existing structures as per instructions of
Engineer-in-Charge and setting out of piles using total
station survey including initial excavation (if any).
7 2. Boring through all type of soils, existing road/pavement
using hydraulic piling rig, removal of all obstructions like
boulders etc. by chiselling or any other method as
approved by the Engineer-in-Charge. If a bore is
abandoned for any reasons no payment shall be made for
such incomplete boring and shifting of the equipments.If
rocky strata is present, boring through rocky strata shall
have to be done at no extra cost.
3. 100mm dia empty boring through all type of soils,
existing road/pavement for 5m depth to identify the utility
services at all pile locations, removal of all obstructions like
boulders etc. by chiselling or any other method as
approved by the Engineer-in-Charge.
4. Providing, preparation, circulation and handling of
bentonite slurry/polymer including cleaning of bore bottom
after completion of boring.
5. Stacking of usable earth coming out of boring or any
other activity (which can be used as random fill) at
locations as directed by Engineer-in-charge.
8 6. Disposal of all spoils, bentonite waste, dismantled
material, surplus unusable earth for all leads and lifts and
keep the work area neat and tidy during the work and
thereafter, as per directions of Engineer-in-Charge.
7. Providing, driving/placing and withdrawal of 6mm thick (
or thickness as per design, whichever is more) temporary
Mild Steel liner for each pile upto a depth of 5m below
adjoining Ground Level or as per site requirement beyond
which the bore hole can be stabilised using Bentonite slurry
and as directed by Engineer-in-charge. Nothing extra shall
be paid for non-withdrawal of temporary mild steel liner.
Wherever permanent liner is required as per designs &
drawings, measurement and payment for the same shall
be made separately under relevant item.
8. Providing and mixing all ingredients of cement concrete
including admixture if required, with fully computerised
weigh batching plant, transportation, placement of concrete
by tremie pipe for the required lengths of pile including pile
heads at all locations.
9. Placement of reinforcement cage including cost of any
stiffeners, lapping and welding of bars, etc. with cover
blocks of approved quality and thickness to maintain the
cage in its designed shape and spacing of bars as per
directions of Engineer-in-charge.
9 10. Breaking of pile head (manual chipping) after a
minimum of 3 days and to remove and dispose spoiled
concrete to bring the pile head to the cut off level including
cleaning and arranging the extended reinforcement bars as
per drawings.
10 11. Working for all leads, lifts, pumping / bailing out of
water, labour, materials and equipments etc.
12. Mobilising to site, installation at different locations
transferring / dismantling, shifting, reinstalling and removal
from site of the piling rigs and/or other equipments and all
accessories including working platforms from site.
13. Identification, protection and maintenance of existing
services, if any, which in the opinion of Engineer-in-charge
are likely to be affected by piling operation or any related
activities including temporary shifting of such services to
facilitate piling job at no extra cost.
14. Safety measures including Barricading around the bore
holes during and after boring as specified elsewhere in the
tender document.
15. All incidentals, labour, materias, equipments and works
required to execute and complete the job.
16. Filling up of the abandoned empty bore with M15 grade
cement concrete and restoration of road if required.
11 17. The quoted rate will be applicable for all lengths of
piles.
18. The quoted rate will include cost of all load tests
conforming to section 1113.1 of MORTH specifications and
integrity tests of piles as described in relevant portion of
this document. Minimum number of tests shall be as
follows :
Initial vertical load test: 2 nos.
Initial horizontal load test: 2 nos.
Routine vertical load test: 2% of total number of
working piles.
Routine horizontal load test: 2% of total number of
working piles.
Integrity test: Each pile
Working piles may be used for reaction for routine load test
but not for initial load test of piles.
19. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
12 B) Mode of Measurement :
13 Measurement for payment shall be made on the length of
pile measured from cut off level to the tip of the pile correct
to a centimetre. The tentative length of piles to be
measured as detailed in the specifications is 30 meters.
This shall be considered as a guidance only and there will
be no change in the rate of pile in case of increase or
decrease in pile length. Reinforcement shall be measured
and paid separately under relevant item.
14 4. Extra for providing Permanent Liner of 6mm thick mild
steel plate in place of temporary liner wherever required for
piling works including fabrication and setting out in position.
63 MT
15 Mode of Measurement :
16 Measurement shall be based on length of liner becoming
part of permanent structure and nothing extra shall be paid
for cutting & withdrawl of liner upto cut-off level.
17 5. Providing and laying Design Mix Reinforced Cement
Concrete in Pile Caps, Open Foundations and any other
foundation etc. in M35 grade of concrete using Portland
Slag Cement (confirming to strength requirement of
IS:8112) including the cost of centering and shuttering, but
excluding the cost of reinforcement & PCC levelling
course, with all leads, lifts and depths all complete as per
approved drawings and as directed by Engineer-in-charge.
15481 Cum
18 The scope of work in the item includes:
19 1. All initial layout and setting out work using total station
survey and including identification and temporary
supporting and protecting of existing services.
2. Excavation up to the bottom level of PCC levelling
course through all types of soils with stable slopes
including removal of all obstructions like boulders, rocks,
cement concrete structures etc.
3. Disposal of all spoils, dismantled materials, surplus earth
for all leads and lifts, and to keep the work area neat and
tidy during the work and thereafter.
4. Cost of pumping/bailing out of water, including its labour,
material and equipments etc.
5. Cost of providing centering and shuttering including its
erection, dismantling and removal for all leads and lifts with
all required tools and plants.
20 6. Providing and mixing all ingredients including
admixtures, if required , with weigh batching plant,
transportation, placement, finishing and curing of concrete
for all leads, lifts and depths.
7. All arrangements needed to keep the reinforcement bars
of pile cap and pier in position with due cover blocks of
approved quality and thickness.
8. Cost of compacted backfilling around the pile
cap/isolated footing with approved material i.e. Yamuna
Sand and temporary restoration of road if required.
9. Cost of Maintenance and protection of existing services
if any which in the opinion of Engineer-in-charge are likely
to be affected by any related activities including temporary
shifting of such services to facilitate construction of pile
cap/footing work shall also have to be done, if so required
by the Engineer-in-charge, and the cost for the same shall
be included in the quoted rates.
10. Installation of any fixture into the pile cap/footing (cost
of fixture to be paid separately as per requirement).
21 11. Barricading and all safety requirements as specified
elsewhere in the tender documents.
12. All incidental labour, materials, equipment and works
required to execute and complete the job as per approved
drawings and specifications.
13. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
22 Mode of Measurement :
23 Measurements for payment shall be made on the volume
basis in cubic meters of concrete and the volume shall be
calculated by simple geometrical concepts and formulae
for the finished volume (excluding PCC levelling course to
be laid down below pile caps and open foundations,which
is to be measured and paid separately under relevent item)
only. Quantity of concrete of piles, which has gone into the
pile caps shall be deducted. Reinforcement shall be
measured and paid separately unde under relevent item.
24 6. Providing and laying machine batched, machine mixed
and machine vibrated design mix reinforced concrete for
construction of piers, pier caps, abutments, abutment caps,
shear key, bearing pedestals, Portal frame etc., with M45
grades of concrete using Ordinary Portland Cement
(conforming to strength requirement of IS:8112) as per
approved drawings supplied by the Engineer-in-charge
including all types of shuttering, staging, scaffolding,
necessary tools, plants, machinery and all related
operations as required to complete the work with all leads,
lifts, and depths true to level and position all complete but
excluding the cost of reinforcement .
6503 Cum
25 The scope of work in the item includes:
26 1. All incidental work required including providing,
placement and removal of shuttering, staging, scaffolding
and form liner etc, for piers, abutments, pier/abutment
caps, bearing pedestals, Portal frame and other works, as
stated in other parts of the tender documents.
2. Casting of piers, pier caps, abutments, abutment caps,
bearing pedestals, Portal frame etc. after approved
mockup including providing and mixing all ingredients and
admixtures (if required) etc. with batching plant,
transportation, placement, finishing and curing as per
specifications and the directions of the Engineer-in-charge.
3. Disposal of all spoils and rubbish and to keep the work
area neat and tidy during the work and thereafter.
4. Installation of any fixture into piers/pier caps or any
similar structure etc. (cost of fixtures if any, to be paid
separately).
5. Safety measures including Barricading around the
piers/abutments or any similar structure during construction
as specified in approved drawings and as directed by the
Engineer-in-Charge.
27 6. All incidental labour, materials and testing, equipment
and works required to execute and complete the job as per
specifications and as directed by the Engineer-in-Charge.
7. Payment of Mock up shall be made (once only)
separately under relevent items after its final approval.
28 Mode of Measurement :
29 Measurements for payment shall be made on the volume
basis in cubic meters of concrete and the volume shall be
calculated by simple geometrical concepts and formulae
for the finished volume. No deduction shall be made for the
volume occupied by any fixture provided in the pier,
abutment, etc. For form finish on the pier surface, actual
volume of concrete after deduction for all grooves and
indentation shall be considered for measurement.
Reinforcement shall be measured separately under
relevent item.
30 7. Providing and laying machine batched, machine mixed
and machine vibrated design mix reinforced concrete in
Retaining Walls, Dirt wall,columns, beams of lift well and
coping of RE wall etc., with M35 grade of concrete using
Ordinary Portland Cement (conforming to strength
requirement of IS:8112) as per approved drawings
supplied by the Engineer-in-charge including all types of
shuttering, staging, scaffolding, necessary tools, plants,
machinery and all related operations as required to
complete the work with all leads, lifts, and depths true to
level and position all complete but excluding the cost of
reinforcement .
411 Cum
31 The scope of work in the item includes:
32 1. All incidental work required including providing,
placement and removal of shuttering, staging, scaffolding
stated in other parts of the tender documents.
2. Casting of structural elements including providing and
mixing all ingredients and admixtures (if required) etc. with
batching plant, transportation, placement, finishing and
curing as per specifications and the directions of the
Engineer-in-charge.
3. Disposal of all spoils and rubbish and to keep the work
area neat and tidy during the work and thereafter.
4. Installation of any fixture into wall or any similar
structure etc. (cost of fixtures if any, to be paid separately).
5. Safety measures including Barricading around the walls
or any similar structure during construction as specified in
approved drawings and as directed by the Engineer-in-
Charge.
6. All incidental labour, materials and testing, equipment
and works required to execute and complete the job as per
specifications and as directed by the Engineer-in-Charge.
33 Mode of Measurement :
34 Measurements for payment shall be made on the volume
basis in cubic meters of concrete and the volume shall be
calculated by simple geometrical concepts and formulae
for the finished volume. No deduction shall be made for the
volume occupied by any fixture provided. Reinforcement
shall be measured separately under relevent item.
35 8. Providing and installing to true lines levels PIN/POT-cum-
PTFE bearings of specified load capacity as detailed here
under and as per section 2000 of MORTH Specifications.
Item includes preparation of designs and drawings and its
approval from the Engineer-in-charge, manufacturing,
testing, transportation to site, storage with all handling,
leads & lifts etc. and placing the permanent bearings in
position, grouting holes and filling the underside of base
plates using prepacked, free flowing high strength, non-
shrinkage grout such as CONBEXTRA HF of M/s
FOSROC or approved equivalent, as per manufacturer's
specifications. (Bearings shall be provided with a warranty
of trouble free maintenance of 15 years).
36 Note : The range of total movement of guide either free or
Guided bearing i.e. longitudinal or transverse movement
shall be 30 to 130mm. Coefficient of friction between
PTFE and SS Plate shall be taken as 5% for designing the
bearings.
37 (i) Pot cum PTFE - Free Bearings
(a) 600 T vertical capacity
122 Each
38 (ii) Pot cum PTFE - Guided Bearings
(a) 600 T vertical capacity and 150 T - Lateral
capacity
122 Each
39 (iii) Pinned Bearings
(a) 500 T capacity
20 Each
40 The scope of work in the item includes:
41 1. Cost of designs and submission of bearing designs &
drawings to get the approval from Engineer-in-charge
before execution of such works.
2. Cost of placement of various types of bearings or its
components in position during casting of piers, pier caps,
abutments and any similar structure etc., as per detailed
specifications/instructions attached, including grouting of
the holes underside of base plate with approved quality of
ready mix non-shrink cementatious grout is included in the
scope of the item itself.
3. Cost of all materials, labour, equipments, tools and
plants, machinery required for execution of works.
4. Cost of providing temporary bearings/supports as
required and other incidental expenses (if any).
5. Cost of cleaning blocks, placing and grouting anchor
bolts in position after proper levelling etc.
6. Cost of maintenance of bearings during construction
period.
7. Cost of supervision by bearing manufacturer(s) during
installation.
8. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
42 Note: There may be a variation of 15 % the above
mentioned load. The quoted rate should include such
variation and nothing extra shall be paid on this account
43 B) Mode of Measurement :
44 Measurements for payment shall be made in number.
45 9. Providing and fixing in position true to line and level
elastomeric pads of required thickness conforming to
MoRT&H technical Specifications complete including all
accessories as per drawings and technical specifications.
2037940 Cu-cm
46 10. Providing, pre-casting, transporting, erecting and
placing in position precast segments (spine & wings etc. )
of uniform widths as well as varying width in transition zone
with epoxy jointing including temporary prestressing in
M60 grade reinforced cement concrete and using 43/53
grade OPC Cement and micro silica , using overhead
launching girders or ground supported staging / trestles as
specifically mentioned in the drawings or as per site
requirements, cast-in-situ concrete stitching with M60
grade concrete to join wings with spines and wings with
wings, cast -in-situ concreting in deck continuity and
recess filling around Expansion joint with M60 grade
concrete including the cost of providing necessary
shuttering, staging, tools, plants and machinery complete,
provision of connector for crash barriers all complete as
per approved drawings, specifications and as directed by
Engineer-in-charge but excluding the cost of reinforcement
and permanent prestressing strands, sheathing,
anchorages and other prestressing hardware, which shall
be paid separately under relevant items.
25775 Cum
47 The scope of work in the item includes :
48 1. Arranging all infrastructure including casting
yard,stacking yard, casting beds, machines, tools and
plants at the casting yard for precasting, curing, lifting and
stacking of segments in stcking yard. The proposal /
layout/ scheme of casting yard with all salient details shall
be got approved from Engineer-in-charge. Central spines
will be match cast.
2. All expenses incurred for casting yard, casting bed,
stacking yard, moulds, gantry, launchers, cantilever
launching frames, cranes, tools & plants, machineries etc.
to be used by the contractor for casting, curing of finished
concrete, all handling, stacking, transportation,
erection/launching and placing in final position at site etc.
complete.
3. Preparation of shop drawing i/c BBS for each segment
showing all details as specified in drawings and the
specifications.
4. Providing & mixing all ingredients of cement concrete as
per approved mix design including admixture, if any in
approved concrete batching & mixing plant, transportation
to speficied location in transit mixer of adequate capacity,
placement of concrete with appropriate means including
concrete pump, compacting/ vibrating concrete, finishing to
line and level and curing etc.
49 5. Making arrangement and/or fixing/embedding all
necessary electrical, drainage, prestressing ducts, other
prestressing hardware and other fixtures etc. (cost of
fixtures, if any, shall be paid for separately).
6. Making arrangement for precasting of spines and wings
separately.
7. Casting of one successful mock segments at casting
yard true to line, level and shape as per the direction of the
Engineer-in-charge at no extra cost
8. Providing and placing form work in position required for
casting of segments and its removal including cleaning,
oiling and maintenance during pendency of work. Longline
method shall may be used for precast segments for
portions curved in plan with radius less than 250 m.
However, for straight portion of elevated road and plan
curve greater than or equal to 250m, short line method can
be adopted. Internal moulds of precast segments shall be
able to cater for variable web thickness (transition and
constant), variable soffit slab thickness (transition and
constant) and various types of intermediate blisters either
at web deck junction or soffit web junction.
50 9. Water/steam curing, stacking at casting yard including
all handling, rehandling, interim storage operations
required for the precast segments. The stacking of precast
segments at site in two or more tiers shall be done with an
intermediate frame which will receive upper box at web
location and transfer the load on lower box at web location
only (with three point support). and the scheme of stacking
shall be got approved from the Engineer-in-charge.
10. Shifting of segments to the site using low bedded
trailers in accordance with the prevailing traffic rules
including loading and unloading at site with the help of
cranes/ launching girders/ plants and equipments required.
11. Fabrication, assembling, testing, shifting of launching
trusses whenever and wherever required.
51 12. Providing, preparing and applying approved epoxy
agent for joining the segments including application of
temporary prestressing for joining two precast segments or
precast segment with cast-in-situ diaphragm segment till
permanent prestressing.
13. All the operations involved in launching of segments by
use of launching girder or ground supported
staging/trestles, providing temporary bearings / jacks for
supporting/ maintaining line and level, hanging of
segments, movement, application of epoxy at joints,
temporary prestressing etc. Load testing of the launching
girder shall be done by the contractor at no additional cost
to PWD.
14. Working for all leads, lifts, labour, material and
equipment etc.
15. Testing all the materials involved in the execution of the
item as per QAP and specifications including providing the
samples and transporting the same to the testing
laboratory.
52 16. All recess in the segments to be filled with grout as
approved by Engineer-in-charge after erection of structure
and removal of temporary prestressing.
17. No payment shall be made for hooks provided for
handling and lifting of precast segments etc.
18. All expenses incurred for provision for curvature in
plan, elevation & superelevation
19. casting of concrete projection along with deck slab for
supporting electric poles/signages including providing steel
insert plates for fixing the same. Steel items shall be paid
separately.
20. Contractor shall also install Bearings and Expansion
Joints wherever required in the bridge deck as per
approved drawings and as per manufacturer specifications/
directions of Engineer-in-Charge. Nothing extra shall be
paid on account of any incidental expenditure/ charges
required for the fixing of Bearing and Expansion Joints.
The cost of M60 grade concrete for filling the recess
around EJs shall be measured and paid in this item.
However the cost of providing and fixing Bearings and
expansion joints shall be paid separately.
53 21. Cost of all provisions for fixing of rain water spouts as
per drawings and as approved by the Engineer-in-Charge
to be kept in concrete during casting of concrete. The cost
of material for recess filling around the rain water spouts is
included in this item. However the cost of providing and
fixing of the rain water spout shall be paid seperately.
22. Cost of steel blasting to expose the aggregate for
proper bonding, cement washing and other incidental
expenditures.
23. Providing barricading and all traffic safety requirements
including management of traffic as desired by Engineer-in-
charge and traffic police and as specified elsewhere in
tender document.
24. Installation of any fixture into the precast segments
(Cost of fixture to be paid separately.
25. All incidental labour, materials, equipment and works
required to execute the job as per the directions of
Engineer-in-charge.
54 Mode of Measurement :
55 Measurement shall be made for the volume of finished
concrete which will include the concrete of segments in
erected in position, concrete in cast-in-situ stitching,
concrete in recess filling around EJ, concrete casted in
deck continuity portion, concrete used in projection for
supporting electirc poles / signages. All linear dimensions
shall be measured correct to one centimeter restricted to
design dimension and volume calculations shall be correct
to two decimal place in cubic meter. There will be no
measurement/payment for the mock segment. The
reinforcement shall be measured and paid separately. The
permanent prestressing work shall be measured and paid
separately under relevent item. The volume occupied by
reinforcement, high tensile steel, sheathing, anchorages
and opening for for drainage spouts shall not be deducted.
There will be no separate measurement/ payment for
temporary prestressing and it is deemed to be included in
the quoted rates.
56 11. Providing & placing in position at all depths and heights
Thermo-Mechanically Treated (TMT) Fe 500 D grade
Reinforcement Bars including cutting, straightening,
bending, binding with mild steel annealed binding wire of
18 SWG i/c, testing of materials complete as per approved
drawings, specifications and as per directions of the
Engineer-in-charge.
11522 MT
57 The scope of work in the item includes:
58 1. The item includes the cost of all the operations involved
from procurement of the steel in the stacking yard up to the
placement including cutting and bending as per the Bar
Bending schedules (BBS to be prepared by the contractor
and approved by the Engineer-in-charge) including the cost
of stacking.
2. The item includes the cost of applying of one coat of
cement wash slurry (1kg cement and 600cc inhibitor
solution - Patent no.:109784/67 or equivalent) by dipping or
brushing and drying for atleast 24 hrs on the steel
immediately after procurement for its protection from
corrosion.
3. Binding the steel with binding wires of 18 SWG gauge
and/or by welding by electric arc recess at two of the four
points at each crossing of reinforcement bars as per
direction of Engineer-in-charge and as per the
specifications. The size of the weld shall be adequate to
ensure that it can withstand the handling till concreting.
59 4. The item includes the cost of spacers, chair bars, cover
blocks, couplers (if used) reinforcement bars for lifting,
hooks, handling and overlapping of bars for placing the
steel.
5.Providing Laps in bars as shown on drawings or
otherwise specified by the Engineer-in-Charge. However,
bars of maximum length shall be used in the work.
6. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
7. Providing barricading and all traffic safety requirements
as directed by Engineer-in-charge and Traffic Police.
8. The item includes all other incidental expenditures for
completing the job.
60 B) Mode of Measurement :
61 The measurement for the payment shall be made on the
weight in Tonnes and the weight shall be calculated by
multiplying the total length of all the reinforcement of
different diameter as per BBS by the standard coefficient
for each diameter of bar. Method of deriving the weight of
reinforcement used is as follows :
(i) Reinforcement shall be measured in length of different
diameters as per drawings nearest to a centimeter.
(ii) The standard sectional weights referred to as in Table
IV in para 5.3.4. in revised CPWD specifications for C.M,
C.C & RCC works, 2009 of volume -II will be considered for
conversion of length of various sizes of TMT Fe 500D bars
into standard weight. The weight shall be computed correct
upto two decimal places but payment shall be made as per
given in sub para (iii) and (iv) below.
(iii) Records of actual sectional weights shall be kept
diameterwise and lotwise. The average sectional weight for
each diameter shall be arrived at from samples from each
lot of steel received at site. The decision of the Engineer-in-
Charge shall be final w.r.t. the procedure to be followed for
determining the average sectional weight of each lot.
Quantity of each diameter of steel received at site of work
each day will constitute one single lot for the purpose. The
weight of steel by conversion of length of various sizes of
bars based on the actual weighted average sectional
weight shall be termed as Derived Actual Weight.
62 (iv) (a) If the Derived Weight as in sub-para (iii) above is
lesser than the standard weight as in sub-para (ii) above
then the derived actual weight shall be taken for payment.
(b) If the derived actual weight is found more than the
standard weight, then the standard weight as worked out in
sub-para (ii) above shall be taken for payment. In such
case nothing extra shall be paid for the difference between
the derived actual weight and the standard weight.
v) For deviation purpose, the quantity of reinforcement in
sub structure will be treated under super structure,
therefore the quantity of reinforcement in super structure is
6596 MT and foundation is 4926 MT.
63 12. Providing/fabricating and stressing of post-tension H.T
low relaxation strands, threading them (i.e. cutting, pulling,
pushing and placing) in HDPE sheathing ducts, placing
them in proper profiles for permanent prestressing of
concrete segments/RCC members including anchorages,
bearing plates, wedges,recess filling etc.complete as per
detailed drawings and approved specifications, grouting the
cables after prestressing as per specifications, recording
the prestressing data, presenting/reporting the same in the
manner required by the Engineer-in-Charge, treating the
projected end of the strands after anchorages and covering
the same with prepacked, freeflow, highstrength, nonshrink
grout/mortar such as conbextra HF of M/s FOSROC or
approved equivalent as per the specifications, all
complete including the cost of all labour, machinery and
materials and prestressing hardware etc, as per the
specifications and directions of the Engineer-in-charge.
2061968 Kg
64 The scope of work in this item includes :
65 1. Engaging a specialised agency for execution of
Prestressing work with the approval of Engineer-in-charge.
2. Provision of all materials and accessories for permanent
as well as temporary use like necessary prestressing
hardware such as trumpet cone, bearing plates,
anchorages, wedges, bursting reinforcement, Jacks and
Pumps of suitable capacity, all other tools & Plants,
machinery and manpower of all categories to complete the
job of prestressing as per the specifications and as per the
directions of the Engineer-in-charge.
3. Providing and laying HDPE sheathing of different shape
and size, as per technical specifications in the required line
and level as per approved construction drawing.
4. Procurement of H.T. low relaxation strands from
approved supplier. The extra pieces of strands after
stressing of the cables will be the liability / property of the
contractor.
5. Therading of strands in HDPE ducts as per
specifications and direction of Engineer-in-charge.
6. All other items of materials, plants and equipments and
works (not specifically excluded above), for proper
prestressing operation of the cables, providing and mixing
cement grout as per specification and grouting the ducts
including provision of vents and grouting etc. will be
included in the cost of this item.
66 7. Carrying out the tests on the Prestressing systems
including making all other necessary arrangements in an
approved manner.
67 8. Stressing of strands conforming to relevant
specifications to the required force and to required
extensions as per the specifications mentioned elsewhere
in tender documents, approved drawing and in accordance
with the approved and established system of prestressing
with necessary jacks (multi strand jacks only), power
pumps, and locking each strand in accordance with
prescribed system at both ends including cutting the
superfluous strands and sealing the ends etc. complete.
9. Provision of all steel chairs/spacer bars wherever
required.
10. Presentation of the test reports and prestressing data
in the approved format to the Engineer-in-charge including
the corrective measures that may be necessary and
required.
11. Testing all the materials involved in the execution of the
item as per QAP and specifications including providing the
samples and transporting the same to the testing
laboratory.
12. All incidental labour, materials, equipment and works
required to execute the job as per the directions of
Engineer-in-charge.
13. Providing barricading and all traffic safety requirements
and management of traffic as per direction of Engineer-in-
charge and Traffic Police.
68 Mode of Measurement :
69 The measurement for this item will be based on the
theoretical quantity of the weight of strands prestressed.
Length of strands will be calculated from anchorage Plate
face to anchorage plate face(s) at the two ends and weight
should be worked out by multiplying with standard weight
of individual strands as per relevant IS code. Any length
beyond anchorage plate face as above including those due
to attaching jacks, elongation etc. shall not be measured
for payments. There will be no separate
measurement/payment for any prestressing hardware like
anchorages, bearing plates, wedges, bursting
reinforcements, trumpet etc. and are deemed to be
included in the quoted rate.
70 13. Providing and installing expansion joints as per
specifications detailed in IRC-SP:69-2005 duly
supplemented with manufacturer's recommendations.
Entire installation is to be carried out strictly in the
presence of manufacturer's representative only at all times.
Item to include preparation of designs and drawings to
obtain the necessary approval from the Engineer-in-
charge. The seal of the expansion joints shall be such as
not to permit any dust collection at all times.
71 Single strip seal joint with a total allowable movement of
80mm
544 m
72 The scope of work in the item includes:
73 1. Cost of all materials, labours, equipments and other
incidental charges for execution of this item. Supervision
during installation by the manufacturer is also included.
2. Installation and fixing of expansion joints as per
manufacturers specifications and designs/drawings
approved by the engineer-in-charge including chipping of
concrete, cleaning of concrete from reinforcement bars,
leveling, necessary shuttering, preparation of recess,
placement of Expansion Joint in recess true to line and
level, pre-setting of expansion joint, if necessary,
placement of reinforcement (cost of reinforcement to be
paid separately), filling of recess with concrete of approved
mix, vibrating / compacting, finishing to line and level and
curing etc. (cost of concretingdone in filling the recess
shall be measured and paid in the item of deck slab/
precast segment)
3.Providing Warranty of trouble free performance for
minimum fifteen (15) years and free rectification of defects/
replacement, if any, during this period.
4. Cost of testing of all the materials involved in the
execution of this item as per Quality Assurance Plan
(Quality Assurance Plan to be prepared by the contractor
and duly approved by the Engineer-in-charge).
74 Mode of Measurement :
75 The expansion joints shall be measured in running Metre.
The length payable is the clear carriageway only, though
joints will be provided in the vertical parts of kerbs/ crash
barriers also. Measurement shall be made correct to one
centimeter.
76 14. Designing, providing and laying in position M 35 grade
precast concrete facia panel with form liner finish
(minimum 180 mm thick) for Reinforced Earth Wall using
43/53 grade OPC including TMT Fe 500 D reinforcement
bars, excavating to the required depth, providing "leveling
pad" using M15 grade cement concrete with nominal
reinforcement if required as per design, providing complete
drainage system for disposal of rain water during the
service conditions as well as water added during raising of
embankment, covering external drainage pipes with
precast cover facia, internal perforated drainage pipes
wrapped with geotextile fabric as per approved drawings,
providing geo-textile filter fabric and 600 mm thick filter
media all along the base and sides behind the facia wall,
sealing of joints EPDM pad and geotextile etc. as per
approved drawing, providing and laying in position
galvanised carbon steel strips of approved section and
length and connecting with the precast facia panels as per
the design, anchoring in filled up material with nails etc. as
per approved design, including all materials, labour, lead &
lift, plants, machinery, taxes, royalties complete as per the
directions of the Engineer-in-charge.
7524 Sq.m
77 The scope of work in the item includes :
78 1. Designing and getting the approval for reinforced soil
wall system from Engineer-in-charge and engaging a
specilised agency for execution and supervision of work.
2. Preparing shop drawings for casting the RCC panels as
per approved design with minimum height as 900 mm,
minimum thickness as 180 mm and area of each panel not
less than 1.5 sqm. The coping beam is not permitted and
the top panels shall be cast in the inclined profile as per
approved shop drawings.
3. All initial layout and alignment of reinforced soil wall after
site clearance, for the construction of RE Wall structure
and providing leveling pad including all components like
reinforcing element, etc., dismantling of footpath, planters
etc. if required as per the directions of the Engineer-in-
charge and preparing designs & shop drawings giving
levels etc. The work shall be started only after approval of
the design and shop drawings by Engineer-in-charge.
79 4. Approval of the desired form liner finish, facia patterns
on panels including logo panel with name of clients etc.
from the Engineer-in-charge. Nothing extra shall be
payable for mock ups and trials of the facia panels and
other items.
5. Providing precast facia panel as per approved drawing &
pattern, erecting the panels true to line and level and
galvanised carbon steel strips including connections with
the panel complete as per drawing and direction of
Engineer-in-charge.
6. Filter media with stone crushed aggregates and
geotextile fabric as per drawings at the bed level of the
embankment of reinforced earth structure and behind the
facia panels for proper drainage as per approved drawings
and particular specifications.
80 7. Providing and placing 200 mm dia PVC perforated Pipe
(perforation at top half only) wrapped in geotextile and filled
with filter media, as per drawing for drainage of seepage
water (sub surface drains) from the fill between RS walls.
8. All transportation, erection in position and alignment as
per approved shop drawings to the satisfaction of Engineer-
in-charge.
9. Drainage system for disposal of strom water including
providing vertical drainage pipe on the surface of wall and
covering with precast cover facia complete as per drawing
and direction of Engineer-in-charge.
10. Testing all the materials involved in the execution of the
item as per QAP and specifications including providing the
samples and transporting the same to the testing
laboratory.
11. All incidental labour, materials, equipment and works
required to execute the job as per the directions of
Engineer-in-charge.
12. Providing barricading and all traffic safety requirements
and traffic management during construction as per
direction of Engineer-in-charge and Traffic Police.
81 Mode of Measurement :
82 The wall area shall be measured from top of concrete
levelling pad at base to top of facia panels in square meter
restricted to design area as per approved drawing. All
linear dimensions shall be measured correct to one
centimeter and area calculations shall be correct to two
decimal place in square meter. The cost of backfill (other
than filter media) is not included in this item and shall be
measured and paid for separately in relevent item. No
separate payment for any type of reinforcement shall be
made.
83 15. Providing and fixing in position approved quality
Closed Cell Polystyrene Joint Filler Board (Thermocole) of
24 kg/cum density of 25mm thick sheet for joint filler in
expansion gaps for concrete structures including cutting
,placing in position with bitumastic adhesive as per the
detailed drawings and the instructions of the Engineer in
Charge.
294 Sq.m
84 16. Providing, precasting, transporting, erecting and
placing in position over deck slab, precast crash barriers in
M-40 grade concrete using 43/53 grade O.P.C. having
formliner finish on the outer face and integrating with deck
by providing and laying M-40 grade concrete in cast-in-situ
portion of crash barrier as per approved drawing including
centring and shuttering required, form liner finish, making
joints at evey 9 m in cast in situ portion and sealing with
back up rod & polysulphide sealant, tools, plants and
machineries, leads and lifts etc. all complete as per
approved drawing & direction of the Engineer-in-charge
but excluding the cost of reinforcement which shall be paid
separately under relevant item.
2495 Cu.m
85 The scope of work in item also includes :
86 1. Providing and mixing all ingredient of cement concrete
as per approved mix design including admixture, if any in
approved concrete batching and mixing plant,
transportation to site in transit mixer of adequate capacity,
placement of concrete with appropriate means including
concrete pumps, compacting/ vibrating concrete, finishing
to line and level, curing etc for cast in situ and precast
component of crash barrier.
2. Approval of the facia patterns on crash barrier panels
from the Engineer-in-Charge. Nothing extra shall be
payable for mock ups and trials of the crash barrier except
payment for one approved sample.
3. Making all arrangements for precasting of part portion of
Crash Barrier, handling, rehandling, curing, stacking,
transportation to the site, erection in position with suitable
means, integrating with deck and in situ portion of crash
barrier complete asper approved drawing.
4. Providing shuttering, staging and scaffolding including its
modification, erection and removal in accordance with the
provisions mentioned else where in the tender document
and form liner finish on the outer face of crash barrier.
87 5. Making arrangement and/or fixing/embedding all
necessary fixtures. Cost of fixtures shall be paid for
separately.
6. Fixing/embedding all necessary provisions like HDPE
pipes (2nos. 100mm dia) and conduits of electrical etc.Cost
of HDPE and conduits will be paid separately.
7.cutting groove in cast insitu crash barrier portion
including top width at spacing of 5m centre to centre of size
8mm wide and 25mm deep.
8. Testing all the materials involved in the execution of the
item as per QAP and specifications including providing the
samples and transporting the same to the testing
laboratory.
9. All incidental labour, materials, equipment and works
required to execute the job as per the directions of
Engineer-in-charge.
88 Mode of Measurement :
89 Measurements shall be made for the finished volume of
concrete in Crash Barrier (Cast in situ portion as well as
precast portion) in cum. All linear dimensions shall be
made correct to one centimeter restricted to design
dimensions and volume calculation shall be worked out
naearest to two decimal places in cubic meter. No
deductions shall be made for providing holes in crash
barriers. The reinforcement shall be measured and paid
under relevent item.
90 17. Providing and fixing M40 grade reinforced cement
concrete with 43/53 grade Ordinary Portland Cement in
cast-in-situ crash barriers over the superstructure, bridge
and over the retaining wall as shown in the drawings.
Reinforcement shall be measured and paid separately.
2551 Cum
91 The scope of work in item also includes :
92 1. Providing and mixing all ingredient of cement concrete
as per approved mix design including admixture, if any, in
approved concrete batching and mixing plant,
transportation to site in transit mixer of adequate capacity,
placement of concrete with appropriate means including
concrete pumps, compacting/ vibrating concrete, finishing
to line and level, curing etc for cast in situ crash barrier.
2. Approval of the facia patterns, if any, on crash barrier
panels from the Engineer-in-Charge.
4. Providing shuttering, staging and scaffolding including its
modification, erection and removal in accordance with the
provisions mentioned else where in the tender document.
5. Making arrangement and/or fixing/embedding all
necessary fixtures. Cost of fixtures shall be paid for
separately.
6. Fixing/embedding all necessary provisions like HDPE
pipes (2nos. 100mm dia) and conduits of electrical etc.
Cost of HDPE & conduits will be paid separately.
7.cutting groove in cast insitu crash barrier portion on outer
pheriphery including top width at spacing of 9m centre to
centre of size 8mm wide and 25mm deep.
8. Testing all the materials involved in the execution of the
item as per QAP and specifications including providing the
samples and transporting the same to the testing
laboratory.
9. All incidental labour, materials, equipment and works
required to execute the job as per the directions of
Engineer-in-charge.
93 Mode of Measurement :
94 Measurements shall be made for the finished volume of
concrete in Crash Barrier in cum. All linear dimensions
shall be made correct to one centimeter restricted to
design dimensions and volume calculation shall be worked
out naearest to two decimal places in cubic meter. No
deductions shall be made for providing holes and fixtures in
crash barriers. The reinforcement shall be measured and
paid under relevent item.
95 18. Providing and laying approved quality Polysulphide
Sealant with a movement accommodation of minimum
30% of joint width, and having a minimum tensile strength
of 1.0 MPa suitable for expansion joints (25mm) in crash
barriers etc. including necessary backup rods, bond
breaking tapes, necessary testing and all other items
required to execute the work.
312800 Cu-cm
96 19. Providing and laying Design Mix Reinforced Cement
Concrete of grade M35 with 43/53 grade Ordinary Portland
Cement in cast-in-situ Approach Slabs, Friction Slabs over
the approaches, complete as per drawing excluding the
cost of steel reinforcement.
1191 Cum
97 The scope of work in the item includes :
98 1.Providing and mixing cement concrete with all ingredients
and admixtures (if required), with weigh batching plant,
transportation, placement, finishing and curing of concrete.
2.Providing steel shuttering, staging, and scaffolding,
including its modification if any , erection and removal in
accordance with the provisions mentioned elsewhere in the
tender documents for all leads and lifts with all required
tools and plants.
3. All incidental labour, material, equipments and works
required to execute and complete the job.
4. All arrangements needed to keep the reinforcement bars
in position with due cover blocks of approved quality and
thickness.
5. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
99 Mode of Measurement:
## The measurement shall be made for the finished volume of
concrete (excluding bed concrete which shall be paid
separately) only. The reinforcement shall be measured and
paid under relevant item separately.
## 20. Steel work in built up tubular/ Square Steel section of
Grade E 250 A including cutting, hoisting, fixing in position,
welded, bolted and J-hooks foundation bolts with nuts &
washer, steel shot blasting on external surface using
abrasive charge conforming to SA 2.5 (ISO 8501-1988),
zinc rich epoxy primer and painting with MIO epoxy paint
and Ecrylic polysiloxane paint including special shaped
washers etc. complete. Priming & Painting shall be done as
per technical specification mentioned in the relevent clause
of the agreement complete as per engineer-in-charge,
a. Seamless Type tubes.
131229 Kg
## A) The scope of work for this item includes:
## 1) Design and fabrication of any additional temporary
structure including all types of lifting brackets, supporting
brackets for deck slab casting, which will be required for
transportation and erection in position / launching of
fabricated parts for complete Plate girder in position.
2) Making provisions and Arrangements for required
openings/inserts for fixing lights fixtures and running cable
conduits below or inside the Plate girders at soffit level.
3) All incidental labour, equipments and plants required to
execute and complete the job from fabrication to erection
at final position as per drawings, specifications and
directions of Engineer-in-Charge.
4) All provisions of door openings/cutout in diaphragms or
any other locations for inspection and maintenance
purposes.
5) Cleaning and removal of all spoils, temporary
arrangements for casting of deck slab, and any other
material from the surface of the girder and giving a coat of
final painting as per specifications.
## 6) Safety measures including Barricading during
construction as specified in approved drawings and as
directed by the Engineer-in-Charge.
7) Procurement of all materials from approved
manufacturers and fabricators. Complete methodology for
structural steel works, name of workshop for fabrication
works, testing facilities and procedures etc. to be intimated
for approval of Engineer-in-charge.
8) The provision for temporary bearings/sand jacks for
supporting steel Plate girders during erection.
9) Provision for stability during erection against wind load
or any other type of loading & supporting steel Plate girder
during erection.
10) Connection of the bearing with plate girder including all
provision as per recommendations of bearing supplier.
Cost of bearing shall be paid separately under relevant
item.
## B) Mode of Measurement :
## Measurement shall be only for structural steel which is
erected and is part of permanent structure and paid as per
approved shop drawings. All wastages, temporary works,
jigs, temporary assembly bolts etc. are deemed to be
included in the quoted rates. No allowance or increase in
weight for welding and nuts & bolts etc. will be applicable.
All HSFG nuts, bolts and washers shall be measured and
paid separately under relevant item. Shear studs shall be
measured and paid separately under relevant item.
## 21. Providing and laying in position machine batched,
machine mixed and machine vibrated design mix
reinforced concrete of grade M40 with 43/53 grade
Ordinary Portland Cement in deck slab in superstructure
using 20mm & down stone aggregates and approved
quality sand complete as per approved drawings, designs
and specifications including the necessary tools, plants
and machinery complete but excluding the cost of
reinforcement.
300 Cum
## The scope of work in this item includes :
## 1. Providing and mixing all ingradients of cement concrete
as per approved mix design including admixture, if any in
approved concrete batching and mixing plant, transporation
of concrete to specified location in transit mixer of
adequate capacity, placement of concrete with suitable
means including concrete pump, compacting/ vibrating
concrete, finishing to design line and level and curing etc.
2. Making provisions for installation of expansion joints
over the bridge deck as per approved drawings and as per
manufacturer specifications/ directions of Engineer-in-
charge.
3. Providing shuttering, staging and scaffolding, including
its modifications, erection and removal in accordance with
the provisions mentioned elsewhere in the tender
document.
4. Necessary arrangement to keep the reinforcement in
positioin with suitable cover blocks.
## 5. Cost of Maintenance and protection of existing services
if any which in the opinion of Engineer-in-charge are likely
to be affected by any related activities including temporary
shifting of such services to facilitate construction of deck
slab shall also have to be done, if so required by the
Engineer-in-charge, and the cost for the same shall be
included in the quoted rates.
6. Working for all leads, lifts, heights, labour, material and
equipment etc.
7. Placing the concrete using Boom placer in both Deck
slab and Solid slab in superstructure.
8. Testing all the materials involved in the execution of the
item as per QAP and specifications including providing the
samples and transporting the same to the testing
laboratory.
9. All incidental labour, materials, equipment and works
required to execute the job as per the directions of
Engineer-in-charge.
## 10. Providing barricading and all traffic safety requirements
including management of traffic as direct by Engineer-in-
charge and traffic police.
11. Fixing/ embedding all necessary electrical or other
fixtures (the cost of fixtures shall be paid separately).
## Mode of Measurement :
## The measurements shall be made for the finished volume
of concrete in postion in cubic meter restricted to design
volume as per approved construction drawing. All linear
dimensions shall be measured correct to one centimeter
restricted to design dimension and volume calculations
shall be correct to two decimal place in cubic meter. The
steel reinforcement shall be measured under relevant item.
## 22. Providing and fixing in position Drainage Spouts for
drainage of superstructures complete as per approved
drawings and MORTH Technical Specification 2705 and as
directed by Engineer-in-charge including all incidental
works, labour, materials, staging/scaffolding etc. to
complete the job. The spouts shall be connected with
suitably located runner/downtake pipelines (to be paid
separately under relevant item) to discharge the surface
run-off to drains or any similar arrangement provided at
ground level.
366 Each
## 23. Providing and fixing in position unplasticised Rigid
PVC 160 mm dia (single socket) down take / runner pipe
conforming to IS : 13592 Type A, including jointing with
seal ring conforming to IS : 5382 leaving 10 mm gap for
thermal expansion and fittings conforms to IS-14735,
couplers, Tee with doors, bends including drilling holes for
fixing the clamps with drop pin anchor 8 mm dia, seelant
etc. at all heights complete as per drawings and
instructions of Engineer-in-Charge. (For the measurement
purpose length will be measured in a straight line including
the length of fittings).
2808 m
## 24. Providing and painting with approved quality 2 coats of
Anti Carbonation Coating as per specifications and as
directed by Engineer- in-Charge to unplastered concrete
surface of piers or over any structure, wherever required,
after cleaning the surface of dirt, dust, oil, grease,
efflorescence and applying paint @ of 1 litre for 2.25 sqm.
(150 microns thickness) including scaffolding ,necessary
tools, plants, machinery and all related operations as
required to complete the work as per drawings and
specifications with all leads, lifts and depths.
95761 Sq.m
## 25. Designing, providing and fixing of M.S. Steel frame
work for noise barrier of required height above RCC crash
barrier consisting of mild steeel plates, angles, tubes
(round or square) as per approved drawing including
making holes in the tubes of required size, and bending of
steel tubes, fixing the structure to the base plates of the
crash barrier and welding the different member with
required thickness as per drawing including steel shot
blasting on external surface using abrasive charge
conforming to SA 2.5 (ISO 8501-1988), zinc rich epoxy
primer and painting with MIO epoxy paint and Ecrylic
polysiloxane paint of required colour and shape complete
including working at all height and lifts as per direction of
Engineer-in-Charge. The bottom base plate to be
embeded at the time of casting of crash barrier in proper
position Painting shall be done as per specifications
mentioned in relevant portion of the document. (For the
payment purpose the actual weight of steel members used
in the work will be taken restricting the weight to the
standard weight of each member).
278496 Kg
## 26. Design, supply, fabrication and erection multiwall
Polycarbonate sheet (Bronze-mettalic type) of 6mm thick of
Sebic Lexan, ALCOX system or approved equivalent for
noise barrier with powder coated aluminium profiles, EPDM
gaskets in between, self drilling screws, silicone sealant to
make the structure water tight and using powder coated
aluminium angle size of 25x25x3mm or powder coated
aluminium flat 25x3mm white complete. The sheet is to be
fixed on MS steel frame. The aluminium section will be
bent to the suitable shape, including drilling in MS steel
tubes/plate wherever required complete in all respects as
per drawings and instructions of Engineer-in-charge. The
M.S. Steel frame on which multiwall polycarbonate sheet
will be fixed shall be measured and paid separately.
11606 Sq.m
## 27. Add or deduct for using extra/less quantity of ordinary
portland cement as per the design requirement under
specific condition and as per direction of engineer-in-
charge
100 MT
## 28. Deduct for using Ordinary Portland Cement of grade
43/53 in place of Portland Slag Cement under specific
condition and as per direction of engineer-in-charge.
100 MT
## 29. Providing and installing retro-reflective single sided
overhead signboards comprising of customized modular
PU Epoxy Coated MS angle iron frame work, aluminium
composite panel (ACP) as base board, micro prismatic
retro-reflective sheet and electro cut coloured overlay film.
The horizontal and vertical members of the MS frame
module shall be made of MS angle iron 50x50x5mm in box
shape. No panel size shall be more than one Sqm and
each panel shall be braced diagonally (one way only) with
MS angle iron 50x50x5mm in box shape. The MS frame
module shall have length not more than 3M and multiple
modules shall be connected together with 15mm. dia SS
bolts of 304 grade spaced not more than 300mm center to
center.
468 Sq.m
## The aluminium composite panel (ACP) shall have a
thickness of 4mm with 0.5mm thick skin of aluminium on
both sides. The ACP shall be routed, folded and fixed on
the MS frame with VHB tape. 25mm wide provided
through out the length and breadth of the frame including
riveting at the right angle face of the frame with pop
riveting or with self taping SS screws 5mm. dia spaced not
more than 300mm center to center ensuring that no
riveting is seen on either face of the frame. On the front
face of the ACP, micro prismatic retro-reflective sheet
conforming to Type-IX of ASTM: D 4956-07 shall be
pressure fixed as background sheet (In white colour) which
will be over laid with electro cut transparent film of
approved make and colour to create a desired road sign.
The rear side of the MS frame shall be covered with
balanceing ACP of the same description as mentioned
above and shall be fixed in the similar manner as described
above. The rate shall include all materials, labour,
equipments, fabrication, transportation, erection,
installation and incidentals all complete as per direction of
the Engineer-in-Charge (Structural steel work except MS
angle iron frame work for the sign board shall be paid for
separately under the relevant agreement item).
## 30. Providing and installing retro-reflective single sided
shoulder mounted signboards comprising of customized
modular PU Epoxy Coated MS angle iron frame work,
aluminium composite panel (ACP) as base board, micro
prismatic retro-reflective sheet and electro cut coloured
overlay film. The horizontal and vertical members of the
MS frame module shall be made of MS angle iron section
40x40x5mm. No panel size shall be more than one Sqm
and each panel shall be braced diagonally (one way only)
with MS angle iron 50x50x5mm. The MS frame module
shall have length not more than 3M. The aluminium
composite panel (ACP) shall have a thickness of 4mm with
0.5mm thick skin of aluminium on both sides.
108 Sq.m
## The ACP shall be routed, folded and fixed on the MS frame
with VHB tape. 25mm wide provided throughout the length
and breadth of the frame including riveting at the right
angle face of the frame with pop riveting or with self taping
SS screws 5mm. dia spaced not more than 300mm center
to center on one side of frame ensuring that no riveting is
seen on either face of the frame. On the front face of the
ACP, micro prismatic retro-reflective sheet conforming to
Type-IX of ASTM: D 4956-07 shall be pressure fixed as
background sheet (In white colour) which will be over laid
with electro cut transparent film of approved make and
colour to create a desired Directional signage. The rate
shall include all materials, labour, equipments, fabrication,
transportation, erection, installation and incidentals all
complete as per direction of the Engineer-in-Charge
(Structural steel work except MS angle iron frame work for
the sign board shall be paid for separately under the
relevant agreement item).
## 31. Providing and installing retro-reflective single sided
shoulder mounted signboards comprising of customized
modular PU Epoxy Coated MS angle iron frame work,
aluminium composite panel (ACP) as base board, micro
prismatic retro-reflective sheet and electro cut coloured
overlay film. The horizontal and vertical members of the
MS frame module shall be made of MS angle iron section
35x35x5mm. No panel size shall be more than one Sqm
and each panel shall be braced diagonally (one way only)
with MS angle iron 50x50x5mm. The MS frame module
shall have length not more than 3M. The aluminium
composite panel (ACP) shall have a thickness of 4mm with
0.5mm thick skin of aluminium on both sides.
24 Sq.m
## The ACP shall be routed, folded and fixed on the MS frame
with VHB tape. 25mm wide provided throughout the length
and breadth of the frame including riveting at the right
angle face of the frame with pop riveting or with self taping
SS screws 5mm. dia spaced not more than 300mm center
to center on one side of frame ensuring that no riveting is
seen on either face of the frame. On the front face of the
ACP, micro prismatic retro-reflective sheet conforming to
Type-IX of ASTM: D 4956-07 shall be pressure fixed as
background sheet (In white colour) which will be over laid
with electro cut transparent film of approved make and
colour to create a desired Directional signage. The rate
shall include all materials, labour, equipments, fabrication,
transportation, erection, installation and incidentals all
complete as per direction of the Engineer-in-Charge
(Structural steel work except MS angle iron frame work for
the sign board shall be paid for separately under the
relevant agreement item).
## 32. Dismantling / removing the existing Overhead /
Shoulder Mounted Signage Boards safely from the road,
transportation and storing in safe custody and
transportation back to site and re-installing the same
whenever required including necessary repairs, supplying
and fixing of necessary nuts and bolts, welding etc.,
finishing with Epoxy paint (two or more coats) applied as
per manufacturer's specifications including appropriate
priming coat, preparation of surface etc., with all leads and
lifts, necessary labour, plants and equipments, including all
incidental works all complete as per drawing and Technical
Specifications and directions of Engineer-in-Charge.
Payment of holding down bolts and other missing steel
parts except nuts and bolts shall be made separately under
relevant item. Payment for RCC foundation shall be also
made under relevant items. However no separate payment
for Excavation of earth shall be made.
40 MT
## 33. Providing and installing 4mm thick fiber impregnated
bituminous bridge deck waterproofing membrane of
approved make including necessary primer and adhesive
heating and rolling, overlapping and sealing joints etc.
complete as per specifications and manufacture's
recomendations by approved supplier as per the Direction
of Engineer-in-Charge
47324 Sq.m
## 34. Excavation for roadwork in soil with hydraulic
excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, trimming bottom and side slopes, in
accordance with requirements of lines, grades and cross
sections, and transporting to the embankment location
within all lifts and lead upto 1000m
a) All kinds of soil including building rubbish.
97643 Cum
## The scope of work in the item includes :
## 1. Excavation in laterites shales, sandstones, stone / brick
masonary / RCC / Concrete, footpath, medians, WBM,
WMM, lime concrete, BM, DBM & BC etc.
2. All safety measures during excavation for workers / T &
P against poisonous gases, leachate etc. coming out of
garbage.
3. Cutting of excavation shall be done in stablised slope.
The contractor shall submit Design and drawings for slope
stability in the given strata for approval of Engineer-in-
Charge.
4. Excavation through all types of malba including removal
of all obstructions like boulders, rocks, building rubbish, city
waste etc.
5. Dispolsal of all spoils, dismantled materials, surplus
earth for 1000m lead and lift, and to keep the work area
neat and tidy during the work and thereafter.
6. Cost of pumping / bailing out of water, leachate etc.
including its labour, material and equipments including
running charges.
7. Barricading and all safety requirements as specified in
the tender documents.
8.The item includes all other incidental expenditures for
completing the job as directed by the Engineer-in-Charge.
9. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
## Mode of Measurement :
## Measurement for payment purpose shall be made on
volume basis in cubic metres, volume shall be calculated
by taking levels before excavation and after cutting.
## 35. Excavation for road work in Soil with hydraulic
excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, trimming bottom and side slopes, in
accordance with requirements of lines, grades and cross
sections, and transporting to the embankment location with
all lead upto 1000m. And construction of embankment with
approved materials deposited at site from roadway cutting
and excavation from drain foundation of other structures
graded and compacted to meet requirement of Table 300-
2.
3005 Cum
## The scope of work in the item includes :
## 1. Excavation in laterites shales, sandstones, stone / brick
masonary / RCC / Concrete, footpath, medians, WBM,
WMM, lime concrete, BM, DBM & BC etc.
2. All safety measures during excavation for workers / T &
P against poisonous gases, leachate etc. coming out of
garbage.
3. Cutting of excavation shall be done in stablised slope.
The contractor shall submit Design and drawings for slope
stability in the given strata for approval of Engineer-in-
Charge.
4. Excavation through all types of malba including removal
of all obstructions like boulders, rocks, building rubbish, city
waste etc.
5. Dispolsal of all spoils, dismantled materials, surplus
earth for 1000m lead and lift, and to keep the work area
neat and tidy during the work and thereafter.
6. Cost of pumping / bailing out of water, leachate etc.
including its labour, material and equipments including
running charges.
7. Barricading and all safety requirements as specified in
the tender documents.
8.The item includes all other incidental expenditures for
completing the job as directed by the Engineer-in-Charge.
9. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
## Mode of Measurement :
## Measurement for payment purpose shall be made on
volume basis in cubic metres, volume shall be calculated
by taking levels before excavation and after cutting.
## 36. Construction of embankment with earth obtained from
borrow pits with all lifts and leads, transporting to site,
spreading, grading to required slope, watering and
compacting to meet requirement of table 300-2 of MORTH
with CBR >5 (Also including filling in the approaches
between reinforced earth (RE) wall panels and return walls
as per approved drawings and specifications).
10418 Cum
## The Scope of work in the item includes:
## 1.The item includes the cost of all the operations involved
to complete the job as given under section 305 of MORTH
Specifications including the cost of all materials,
machinery, tools, plants and labour to complete the job as
per approved drawings and as directed by the Engineer in
charge.
2. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
3.The item includes all other incidental expenditures for
completing the job as directed by the Engineer-in-Charge.
4. Barricading and all safety requirements as specified in
the tender documents.
## Mode of Measurement :
## Measurement for payment shall be made for finished items
on sectional area basis in cubic meter, volume being
computed by taking initial and final levels.
## 37. Supply Fly ash and Filling in embankment conforming
to IRC- SP 58 in layers (each layer should not exceed 15
cm), including watering, compacting each layer by rolling/
ramming to meet requirement of table 300-2 of MORTH all
complete as per drawing and direction of Engineer -in -
charge (Also including filling in the approaches between
reinforced earth (RE) wall panels and return walls as per
approved drawings and specifications).
6945 Cum
## The Scope of work in the item includes:
## 1.The item includes the cost of all the operations involved
to complete the job as given under section 305 of MORTH
Specifications including the cost of all materials,
machinery, tools, plants and labour to complete the job as
per approved drawings and as directed by the Engineer in
charge.
2. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
3.The item includes all other incidental expenditures for
completing the job as directed by the Engineer-in-Charge.
4. Barricading and all safety requirements as specified in
the tender documents.
## Mode of Measurement :
## Measurement for payment shall be made for finished items
on sectional area basis in cubic meter, volume being
computed by taking initial and final levels.
## 38. Extra for providing Jamuna Sand in place of fly ash in
above item and mixing the same with fly ash in required
proportion uniformly. Sand brought at site to be stacked on
levelled surface and in measureable position as per the
relevant specification applicable.
1389 Cum
## Mode of Measurement :
## Sand will be measured in stack brought at site in cubic
metre.
## 39. Supply and Filling with Jamuna sand in approaches
between reinfoirced earth wall pannels (conforming to
CPWD Specification) in layers (each layer should not
exceed 20 cm), with watering, rolling and compacting by
rolling/ ramming to achieve 95% density of MDD all
complete as per direction of Engineer -in - charge.
37065 Cum
## 40. Disposal/removal of surples excavated soil, malba,
loading, unloading & stacking if required including disposal
with all leads and lifts (beyond initial lead of 1 Km) on
authorised dumping ground of PWD/MCD etc. as per the
directions of Engineer-in-charge.
97643 Cum
## 41. Preparation and consolidation of sub grade with power
road roller of 8 to 12 tonne capacity after excavating earth
to an average of 22.5 cm depth, dressing to camber and
consolidating with road roller including making good the
undulations etc. and re-rolling the sub grade and disposal
of surplus earth with lead upto 50 metres.
53047 Sq.m
## 42. Providing, laying, spreading and compacting 300 mm
thick Granular Sub Base (GSB) Course in two layers of
150mm thick each, with grade 1 and grade 2 maerials of
CBR not less than 20% and 30% respectively, including
premixing the material with water at OMC in Mechanical
mixing plant, carriage of material at site, spreading in
uniform layers with motor grader on a prepared base,
compacting with power/vibrating road roller of 8 to 10 tonne
capacity to achieve the desired density including all
materials, labours and machinery etc. complete for all
leads and lifts as per specifications and directions of
Engineer-in-charge.
## a) Layer of 150mm thick lower granular cub-base course
with CBR not less than 20% using Grading I (as per table
400-1 of MoRTH Specifications 2001) close graded
materials
10491 Cum
## b) Layer of 150mm thick upper granular cub-base course
with CBR not less than 30% using Grading II (as per table
400-2 of MoRTH Specifications 2001) coarse graded
material granular sub-base materials as per Iten 4.1 of
MoRTH
10491 Cum
## The Scope of work in the item includes:
## 1.The item includes laying of granular sub-base in different
layers
2.The item includes the disposal of earth/spoils from the
site for all leads and lifts as per the directions of the
Engineer-in-charge
3. The item includes the cost of all the operations involved
to complete the job as per MORTH Specifications including
the cost of arrangement of all materials, machinery, Tools
& Plants, manpower of all category as per the directions of
the Engineer-in-charge.
4. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
5. The item includes the submission and approval of the
Job Mix Formula from the Engineer-in-charge.
6. The item includes all other incidental expenditures for
completing the job as directed by the Engineer-in-charge.
7.Providing barricading, all traffic safety requirements and
management of traffic during construction as per direction
of Engineer-in-charge and Traffic Police.
## Mode of Measurement :
## Measurements for payment shall be made for finished item
on volume basis in cubic metres, volume being calculated
by taking levels before laying and finishing Granular Sub-
base layers. The volume of granular sub-base only shall be
measured for payment.
## 43. Providing, laying, spreading and compacting Wet Mix
Macadam (WMM) base course comprising of graded stone
aggregates and granular material conforming to MORTH
Specification (Table 400-11) including pre-mixing the
material with water at OMC in mechanical mixing plant,
carriage of mixed materials by tippers to site, laying and
spreading in uniform layers in base-course on a well
prepared sub-base/base course compacting with power
vibratory roller of 8 to 10 tonne capacity to achieve the
desired density at OMC including all material, labours,
machinery etc. complete for all leads and lifts and as per
the directions of Engineer-in-Charge.
19746 Cum
## The Scope of work in the item includes:
## 1.The item includes the cost of all the operations involved
to complete the job as given under section 406 of MORTH
Specifications including the cost of arrangement of all
materials, machinery, Tools & Plants, manpower of all
categories as per the directions of the Engineer-in-charge.
2. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
3.The item includes all other incidental expenditures for
completing the job as per the directions of the Engineer-in-
charge.
4. The item includes the submission and approval of the
Job Mix Formula from the Engineer-in-charge.
5. Providing barricading, all traffic safety requirements and
management of traffic during construction as per direction
of Engineer-in-charge and Traffic Police.
## Mode of Measurement :
## Measurements for payment shall be made for finished item
on volume basis in cubic meters. Volume being calculated
by taking levels before laying WMM and after the finishing
of WMM.
## 44. Providing and applying Primer Coat with bitumen
emulsion on prepared surface of granular base including
clearing of road surface and spraying primer at the rate of
0.60 kg/sqm using mechanical means
93367 Sq.m
## 45. Providing and applying Tack Coat with bituminous
emulsionusing emulsion pressure distributor at the rate of
0.20 kg per sqm on the prepared bituminous/granular
surface cleaned with mechanical broom.
478517 Sq.m
## 46. Providing and laying bituminous macadam using
crushed stone aggregates of specified grading premixed
with bituminous binder, transported to site by tippers, laid
over a previously prepared surface with paver finisher
equiped with electronic sensor to the required grade, level
and alignment and rolling with smooth wheeled/vibratory
rollers as per specifications to achieve the desired
compaction and density, complete as per specifications
and directions of Engineer-in-Charge.
## 50 to 100 mm average compacted thickness with bitumen
of grade CRMB-60 @3.5% (percentage by weight of total
mix) prepared in Computarised Batch Type Hot Mix Plant
of 100-120 TPH capacity.
5245 Cum
## 47. Providing and laying Dense Bituminous Macadam on
prepared surface with specified graded crushed stone
aggregates including hot mixing of stone aggregates, filler
and bitumen in computerised batch type hot mix plant of
100 - 120 TPH capacity, transporting the mixed material by
tippers to site and laying the mixed material with paver
finisher fitted with electronic sensing device to the required
level and grade and rolling by road rollers, as per MORTH
specifications, to achieve the desired density and
compaction, but excluding the cost of primer/tack coat.
(a) 50 to 100 mm average compacted thickness with
bitumen of grade CRMB-60 @ 5% (percentage by weight
of Total mix) and lime filler @ 2% (percentage by weight of
Aggregate).
9801 Cum
## The Scope of work in the item includes:
## 1.The item includes the cost of all the operations involved
to complete the job as given under sections 507 of MORTH
specifications including the cost of arrangement of all
materials, machinery, Tools & Plants, manpower of all
categories as per the directions of the Engineer-in-charge.
2.The item includes the submission and approval of the
Job Mix Formula from the Engineer-in-charge.
3. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
4.The item includes all other incidental expenditures for
completing the job as per the directions of the Engineer-in-
charge.
5. Providing barricading, all traffic safety requirements and
management of traffic during construction as per direction
of Engineer-in-charge and Traffic Police.
## Mode of Measurement :
## Measurements for payment shall be made for finished item
on volume basis in cubic meters. Volume being computed
by taking levels before laying DBM and after the finishing
of DBM.
## 48. Providing and laying Bituminous Concrete on prepared
surface with specified graded crushed stone aggregates
for wearing course including hot mixing of stone
aggregates, filler and bitumen in computerised batch type
hot mix plant of 100-120 TPH capacity, transporting the
mixed material by tippers to site and laying the mixed
material with paver finisher fitted with electronic sensing
device to the required level and grade and rolling by road
rollers, as per MORTH specifications, to achieve the
desired density and compaction, but excluding the cost of
tack coat.
(a) 40/50mm compacted thickness with bitumen of grade
CRMB-60 @ 5.5% (percentage by weight of Total mix) and
lime filler @ 2% (percentage by weight of Aggregate).
11259 Cum
## The Scope of work in the item includes:
## 1.The item includes the cost of all the operations involved
to complete the job as given under sections 509 of MORTH
Specifications including the cost of arrangement of all
materials, machinery tools and plants, manpower of all
categories as per direction of Engineer-in-Charge.
2.The item includes the submission and approval of the
Job Mix Formula from the Engineer-in-charge.
3. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
4. Providing barricading, all traffic safety requirements and
management of traffic during construction as per direction
of Engineer-in-charge and Traffic Police.
5.The item includes all other incidental expenditures for
completing the job as per the directions of the Engineer-in-
charge.
## Mode of Measurement :
## Measurements for payment shall be made for finished item
on volume basis in cubic meters. Volume being computed
by taking levels before laying BC and after the finishing of
BC.
## 49. Providing and laying Bitumen Mastic wearing course
(as per section 515 of MORTH specifications) with
industrial bitumen of grade 85/25 conforming to IS:702
prepared by using mastic cooker and laid to required level
and slope including providing anti-skid surface with
bitumen precoated fine grained hard stone chipping of
approved size at the rate of 0.005 cum per 10 sqm and at
approximate spacing of 10 centimetres centre to centre in
both directions, pressed into surface protruding 1mm to 4
mm over mastic surface, including cleaning the surface,
removal of debris etc. all complete (Considering bitumen
using 10.2 % as per MORTH specifications). Item also
includes tack coat with bitumen grade VG-10 at the rate of
0.25 kg per sqm.
## a) 25mm thick layer 58982 Sq.m
## b) 40mm thick layer 22800 Sq.m
## The Scope of work in the item includes:
## 1. The item includes the cost of all the operations involved
to complete the job as given under section 515 of MORTH
Specifications including the cost of arrangement of all
materials, machinery tools and plants, manpower of all
categories as per directions of Engineer-in-Charge.
2. The item includes the submission and approval of the
Job Mix Formula from the Engineer-in-charge.
3. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
4.Providing barricading, all traffic safety requirements and
management of traffic during construction as per direction
of Engineer-in-charge and Traffic Police.
5. The item includes all other incidental expenditures for
completing the job as per the directions of the Engineer-in-
charge.
## Mode of Measurement :
## Measurements for payment shall be made for finished item
on square meter basis i.e. multiplying length & breadth
correct to a centimetre.
## 50. Providing and laying Design Mix Plain Cement
Concrete of specified grades using 43/53 grade Ordinary
Portland Cement at all locations with all leads, lifts and
depths including necessary form work, wherever required,
as per direction of Engineer in Charge.
## a) M 10 grade cement concrete 6857 Cum
## b) M 40 grade cement concrete 569 Cum
## The scope of work in the item includes:
## 1. All initial layout and setting out work using total station
survey and including identification and temporary
supporting and protecting of existing services.
2. Disposal of all spoils, dismantled materials, surplus earth
for all leads and lifts, and to keep the work area neat and
tidy during the work and thereafter.
3. Cost of pumping/bailing out of water, including its labour,
material and equipments etc. included in all scope of work.
4. Cost of providing centering and shuttering including its
erection, dismantling and removal for all leads and lifts with
all required tools and plants.
5. Providing and mixing all ingredients including admixtures
if required , with weigh batching plant, transportation,
placement, finishing and curing of concrete.
6. Providing barricading, all traffic safety requirements and
management of traffic during construction as per direction
of Engineer-in-charge and Traffic Police.
7. All incidental labour, materials, equipments and works
required to execute and complete the job as per approved
drawings and specifications.
8. Cost of testing of all materials involved in the execution
of item as per approved QAP and Specifications in internal
/ external laboratory including providing the samples and
transporting to the testing laboratory.
## Mode of Measurement :
## Measurements for payment shall be made on the volume
basis in cubic meters of concrete and the volume shall be
calculated by simple geometrical concepts and formulae
for the finished volume only.
## 51. Providing and Laying Cast-in-situ RCC Drain of grade
M25 with removable precast drain covers at required
interval of required size and thickness including necessary
form work as per drawings and technical specifications
complete. Payment of Excavation, Bed concrete and
Reinforcement shall be paid saparately under relevant
item.
8918 Cum
## The scope of work in the item includes:
## 1. All incidental work required including providing,
placement and removal of shuttering, stated in other parts
of the tender documents.
2. Keeping necessary provision for crossing of electrical /
DJB/ MTNL cables / pipes.
3. Providing and mixing all ingredients and admixtures (if
required) etc. with batching plant, transportation,
placement, finishing and curing as per specifications and
the directions of the Engineer-in-charge.
4. Casting of precast main hole /drain cover at casting yard
of required size and shape. Including placing of
reinforcement lifting hooks etc. in the same as per drawing.
Also includes the cost of transporation of precast cover
from casting yard to site and placing the same in position
(Reinforcement shall be paid separately under relevant
item).
5. All incidental labour, materials and testing, equipment
etc. required to execute and complete the job as per
specifications and as directed by the Engineer-in-Charge.
## Mode of Measurement :
## Measurements for payment shall be made on the volume
basis in cubic meters of concrete and the volume shall be
calculated by simple geometrical concepts and formulae
for the finished volume. No deduction shall be made for the
volume occupied by any fixture provided.
## 52. Providing and laying at or near ground level factory
made Kerb Stone of M-25 grade cement concrete in
position to the required line, level and curvature, jointed
with cement mortar 1:3 (1 cement: 3 coarse sand)
including making joints with or without grooves (thickness
of joints except at sharp curve shall not to more than
5mm), including making drainage opening wherever
required complete etc. as per direction of Engineer-in-
charge (length of finished kerb edging shall be measured
for payment). (Precast C.C. kerb stone shall be approved
by Engineer-in-charge).
808 Cum
## 53. Providing and laying factory made chamfered edge
with CC Paver Block of required strength , thickness, size/
shape made by table vibratory method using PU mould,
laid in required colour and pattern over 50mm thick bed of
compacted fine sand, compacting and proper embedding
through vibratory compaction by using plate vibrator, filling
joints with jamuna sand and cutting of paver blocks as per
size and pattern finishing and sweeping extra sand
complete as per manufacturers specifications and direction
of Engineer-in-Charge. (Item includes Cost of testing of all
materials involved in the execution of item as per approved
QAP and Specifications in internal / external laboratory
including providing the samples and transporting to the
testing laboratory.)a) 60mm thick paver block of M-30
grade cement concrete with approved colour, design and
pattern.
18949 Sq.m
## 54. Providing and laying non pressure R.C.C Pipes with
collars jointed with stiff mixture of cement mortar in the
proportion of 1:2 (1 Cement : 2 fine sand) including testing
of joints etc. complete.
## NP4 pipes(heavy duty)-450 mm dia . 190 m
## NP2 pipes(light duty)-250 mm dia . 696 m
## 55. Constructing brick masonry Road Gully Chamber
45x45x77.5 cm with bricks in cement mortar 1:4 (1 cement
: 4 coarse sand ) with pre-cast R.C.C. vertical/horozontal
grating complete as per standard design with common
burnt clay F.P.S. (non modular) bricks of class designation
7.5 complete as per CPWD specifications.
1013 Each
## 56. Providing and laying cement concrete of grade M 15 in
kerb channel, coping constructiion of energy dissipation
basin at toe of chutes and similar work as per direction of
Engineer-in-charge.
2234 Sq.m
## 57. Brick work with common burnt clay F.P.S. (non
modular) bricks of class designation 7.5 in foundation and
plinth in Cement mortar 1:4 (1 cement : 4 coarse sand).
3208 Cum
## 58. Cement Plaster of mix 1:4 (1 cement: 4 coarse sand)
## (i) 12 mm Thick/15 mm thick 17099 Sq.m
## 59. Providing and applying 2.5 mm thick Road Marking
Strips (retro-reflective) of specified shade/colour for Lane
Marking using hot thermoplastic material by fully/ semi-
automatic paint applicator machine fitted with profile shoe,
glass beads dispenser, propane tank heater and profile
shoe heater, driven by experienced operator on road
surface including cost of material , labour, T&P, cleaning
the road surface of all dirt, scales, oil, grease and foreign
material etc complete as per direction of the Engineer in
charge and applicable specifications. The raw material
used for marking shall conform to BS 3262-1989 part I and
MORT&H specification under section 800 clause 803. Item
to include all incidentals required to complete the job and
cost of testing of materials.
10113 Sq.m
## 60. Boring/drilling bore well of required dia for casing/
strainer pipe, by suitable method prescribed in IS: 2800
(part I), including collecting samples from different strata,
preparing and submitting strata chart/bore log, including
hire & running charges of all equipments, tools, plants &
machineries required for the job, all complete as per
direction of Engineer in-charge, upto 90 metre depth
below ground level.
a) All types of soil - 300mm dia.
155 m
## 61. Supplying, assembling, lowering and fixing in vertical
position in bore well, unplasticized PVC medium well
casing (CM) pipe of required dia, conforming to IS: 12818,
including required hire and labour charges, fittings &
accessories etc. all complete, for all depths, as per
direction of Engineer in-charge.
a) 200 mm nominal size dia.
85 m
## 62. Supplying, assembling, lowering and fixing in vertical
position in bore well unplasticized PVC medium well screen
(RMS) pipes with ribs, conforming to IS: 12818, including
hire & labour charges, fittings & accessories etc. all
complete, for all depths, as per direction of Engineer-in-
charge.
a) 200 mm nominal size dia.
60 m
## 63. Supplying, filling, spreading & leveling stone boulders
of size range 5 cm to 20 cm, in recharge pit, in the required
thickness, for all leads & lifts, all complete as per direction
of Engineer-in-charge.
24 Cum
## 64. Supplying, filling, spreading & leveling gravels of size
range 5 mm to 10 mm including packing in the recharge
pit, over the existing layer of boulders, in required
thickness, for all leads & lifts, all complete as per direction
of Engineer-in-charge.
24 Cum
## 65. Supplying, filling, spreading & leveling coarse sand of
size range 1.5 mm to 2 mm in recharge pit, in required
thickness over gravel layer, for all leads & lifts, all complete
as per direction of Engineer in-charge.
185 Cum
## 66. Providing and fixing suitable size threaded mild steel
cap or spot welded plate to the top of bore well housing /
casing pipe, removable as per requirement, all complete
for bore well of 200 mm dia
10 Each
## 67. Providing and fixing M.S. clamp of required dia to the
top of casing/ housing pipe of tubewell as per IS: 2800
(part I), including necessary bolts & nuts of required size
complete.
a) 200 mm clamp.
10 Each
## 68. Providing and fixing Bail plug/ Bottom plug of required
dia to the bottom of pipe assembly of tubewell as per
IS:2800 (part I).
a) 200 mm dia.
10 Each
## 69. Excavating trenches of required width for pipes,
cables, etc including excavation for sockets, and dressing
of sides, ramming of bottoms, depth upto 1.5 m including
getting out the excavated soil, and then returning the soil
as required, in layers not exceeding 20 cm in depth
including consolidating each deposited layer by ramming,
watering, etc. and disposing of surplus excavated soil as
directed, within a lead of 50 m : All kinds of soil.
a) Pipes, cables etc. exceeding 80 mm dia. but not
exceeding 300 mm dia.
100 m
## 70. Extra for depth beyond 45 cm of brick masonry
chamber :
a) For 455x610 mm size.
2 m
## 71. Providing, hoisting and fixing up to floor five level
precast reinforced cement concrete in lintels, beams and
bressumers, including setting in cement mortar 1:3 (1
cement : 3 coarse sand), cost of required centering and
shuttering but excluding the cost of reinforcement, with
Batch Mixed Cement Concrete M-15 complete all lead and
lift.
21 Cum
## 72. Providing and fixing factory made precast RCC
perforated drain covers, having concrete of strength not
less than M-25, of size 1000 x 450x50 mm, reinforced with
8 mm dia four no longitudinal & 9 nos cross sectional
T.M.T. hoop bars, including providing 50 mm dia
perforations @ 100 to 125 mm c/c, including providing
edge binding with M.S. flats of size 50 mm x 1.6 mm
complete, all as per direction of Engineer-in-charge.
20 Each
## 73. Precasting and placing in position 125 mm dia Bollards
600 mm high of required shape, including providing M.S.
Pipe Sleeve 50 mm dia 300 mm long in the Bollard and
M.S. Pipes 40 mm dia and 450 mm long with
150x150x6mm M.S. plate welded at bottom and embedded
150 mm in cement concrete 1:3:6 (1 Cement : 3 coarse
sand : 6 graded stone aggregate 20 mm nominal size),
including necessary excavation of size 250x250x450 mm
deep for the same in bitumen/concrete pavement at
specified spacing.
206 Each
## 74. Providing and fixing (Red uni-directional 3 Nos. on top
of each nosing at specified locations as per drawings) of
TAT A BP or approved equivalent solar powered roads
studs of self -illuminatin, flashing type having 3 nos. ultra
bright LEDs of Red/Amber colour for uni-directional and 6
nos LEDs for Bi-directional studs, visibility minimum 500
meters, flashing rate 65-75 times per min., with detachable
Ni-MH battery of 1.2 V to give back-up of at least 3-4 days
from fully charged condition, made of Robust aluminium
die-cast housing, having reflector strip in addition to LEDs,
stud capable of withstanding load of fully loaded carriers on
the road, having tampering bottom anchor of minimum
50mm length with at least 6 nos., external anti-twist ribs
projecting out from bottom anchor, waterproof IP65 as per
IS 12063-1987 category -2, tested to perform satisfactory
for minimum 100 hrs, under rapid thermal cycling tests as
per IEC 1215 between -40 to +85 degrees centrigade,
weight minimum 675gm, size 125 x 125 x90 5mm, stud
manufactured indigenously by reputed ISO9001 & ISO
14001 company.
98 Each
## 75. Providing and fixing Glow Studs of size 100 x 20 mm
made of heavy duty body shall be moulded ASA (Acrylic
styrene Acryloretrite) or HIP (High impact polystyrene) or
ABS having electronically welded micro-prismatic lens with
abrasion resistant coating as approved by Engineer in
charge. The glow stud shall support a load of 13635 kg
tested in accordance with ASTM D4280.The slope of retro-
reflective surface shall be 35(+/-5) degrees to base.The
reflective panels on both sides with at least 12 cm of
reflective area up each side.The luminance intensity should
be as per the specification and shall be tested as described
in ASTM 1: 809 as recommended in BS :873 part 4:1973.
The studs shall be fixed to the road surface using the
adhesive conforming to IS, as per procedure
recommended by the manufacturer complete as per
direction of Engineer-in-charge.
7647 Each
## 76. Providing and fixing post Delineators made of ABS
round body fitted with 2 nos 100 mm dia high reflective
reflectors and mounted on MS pipe of 65 mm dia duly
powder coated anti-rust and anti theft steel to be installed
as per direction of Engineer-in-charge.
1328 Each
## 77. Painting with synthetic enamel paint of approved brand
and manufacture of required colour to give an even shade :
## a) Two or more coats on new work over an under coat of
suitable shade with ordinary paint of approved brand and
manufacture or cement primer as per direction of Engineer-
in-Charge.
22687 Sq.m
## b) One or more coats on old work as per direction of
Engineer-in-Charge.
1566 Sq.m
## 78. Construction of Temporary Cabins (Porta cabins) for 3
number office room and one meeting/conference room for
20-25 persons fitted with white board and projector
equipment, at suitable locations as approved by engineer-
in-charge, for the department including the arrangement of
lights, fans, AC, furniture, cub-board and drinking water
etc. for better site supervision including chowkidar/office
boy etc. These porta cabins will be removed and will be
the property of the Contractor after completion of the works
as per the instructions of the Engineer-in-Charge. The
contractor will maintain these porta cabins in good
conditions for the entire period of work without charging
anything extra. (Contractor should quote his rates for hire
and maintenance charges only during construction period).
## (a) Temporary Cabins (Porta Cabins) - 3 nos. (3 x 4.26 x
4.26 = 54.44 sqm with attached toilet)
1 Per Job
## (b) Conference Room 1no. (4.26. x 8.52 = 36.30 sqm. with
attached toilet)
1 Per Job
## 79. Taking out existing CC interlocking paver blocks from
footpath/central verge, including removal of rubbish etc,
disposal of unserviceable material to the dumping ground
and stacking of serviceable material within 50 meters lead
and laying these old cement concrete interlocking paver
blocks in required pattern over 50mm thick bed of
compacted fine sand, compacting and proper embedding
through vibratory compaction by using plate vibrator, filling
joints with jamuna sand and cutting of paver blocks as per
size and pattern finishing and sweeping extra sand
complete as per manufacturers specifications and direction
of Engineer-in-Charge as per direction of Engineer-in-
charge.
15180 Sq.m
## 80. Taking out existing kerb stones of all shape & size
from footpath/central verge, including removal of mortor
etc., disposal of unserviceable material to the dumping
ground and stacking of serviceable material within 50meter
lead as per direction of Enineer-in-charge.
12568 m
## 81. Laying at or near ground level old kerb stones of all
shape and sizes in position to the required line, level and
curvature, jointed with cement mortar 1:3 (1 cement : 3
coarse sand) including making joints with or without
grooves (thickness of joints except at sharp curve shall not
to more than 5mm), including making drainage opening
wherever required complete etc. as per direction of
Engineer-in-charge(Length of finished kerb edging shall be
measured for payment. Old Kerb stones shall be supplied
by the department free of cost)
7262 m
## 82. Dismantling / removing the existing steel railing safely
from the road, transportation and storing in safe custody
and transportation back to site and re-installing the same
whenever required including necessary repairs, supplying
and fixing of necessary nuts and bolts, welding etc.,
finishing with synthetic enamel paint (two or more coats)
applied as per manufacturer's specifications including
preparation of surface etc., with all leads and lifts,
necessary labour, plants and equipments, including all
incidental works all complete as per drawing and Technical
Specifications and directions of Engineer-in-Charge.
Payment of missing steel parts except nuts and bolts shall
be made separately under relevant item. Payment for CC
foundation shall be also made under relevant items.
However no separate payment for making holes for
foundation shall be made.
6530 m
## 83. Desilting of existing drain once or twice in a year as
required i.e. before start of mansoon season including
removal and replacing of manhole covers, removal of silt
malba etc in all conditions by manual or mechanical means
and its disposal for all leads and lifts complete as per
direction of engineer in charge for all drain sizes.
4613 Cum
## 84. Stone work (machine cut edges) for wall lining/coping
etc. (veneer work) upto 10 metre height, backing filled with
a grout of average 12 mm thick cement mortar 1:3 (1
cement : 3 coarse sand) including pointing in white cement
mortar 1:2 (1 white cement : 2 stone dust) with an
admixture of pigment matching the stone shade : (To be
secured to the backing and the sides by means of cramps
and pins which shall be paid for separately) as per direction
of the Engineer-in-Charge.
## Red sand stone/White sand stone - Exposed face machine
cut and table rubbed with rough backing.
9552 Sq.m
## 85. Providing and fixing of manhole cover and frame slab
to required level with new circular manhole 140cm dia with
circular cover of 600mm dia of grade EHD-35
20 Each
## 86. Providing Services of inspection vehicle (suitable for all
weather condition) in good working condition with model
not being older than January 2011, including cost of
petrol/diesel, driver maintenance of car etc. Driver should
be available as and when called including Sunday,
Holidays & late hours. The rate shall include milage of
2500km per month per vehicle with 12 hours per day and
complete as per direction of Engineer-in-Charge.
## (a) Inspection Vehicle - Car 48 per
vechicle
per
month
## (b) Inspection Vehicle - SUV 24 per
vechicle
per
month
## Part B-Schedule of Quantity (Electrical Works)
## SH-I (Street light Poles)
## 1.1 Fabrication, Supply and erection (on existing RCC
pedestal) of flange mounted hot dip galvanized octagonal
pole of 12 Mtr height made from 4 mm thick HT Steel
Plate, having bottom diameter of 200mm and top daimeter
of 100 mm complete with window at height of 2.5 Mtr or as
per direction of Engineer in Charge from the base with
flush cover (Sliding) for cable terminator block etc. and
galvanized base plate of size 310 mmx310mmx20mm/as
required.
The following may be housed in the window provided for
cable termination including their supply and fixing:
6mm thick laminated mounted sheet of suitable size inside
the windoew by providing and welding two no. GI strips of
4mm thickness : 1 No.
A set of 20 amp brass neutrallink, 2 way copper bus bar &
Din channel for two nos. MCB on existing laminated sheet :
1Set
6 amp SP MCB 'B' characterstics : 2 Nos.
4 way 63 Amp heavy duty brass connector : 1 No.
Earth stud welded at suitable height with two nos. washer
& nut : 2 nos.
5 Each
## 1.2 Fabrication, Supply and erection (on existing RCC
pedestal) of flange mounted hot dip galvanized octagonal
pole of 10 Mtr height made from 3 mm thick HT Steel
Plate, having bottom diameter of 185mm and top daimeter
of 75 mm complete with window at height of 2.5 Mtr or as
per direction of Engineer in Charge from the base with
flush cover (Sliding) for cable terminator block etc. and
galvanized base plate of size 290 mmx290mmx16mm/as
required.
The following may be housed in the window provided for
cable termination including their supply and fixing:
6mm thick laminated mounted sheet of suitable size inside
the windoew by providing and welding two no. GI strips of
4mm thickness : 1 No.
A set of 20 amp brass neutrallink, 2 way copper bus bar &
Din channel for two nos. MCB on existing laminated sheet :
1Set
6 amp SP MCB 'B' characterstics : 2 Nos.
4 way 63 Amp heavy duty brass connector : 1 No.
Earth stud welded at suitable height with two nos. washer
& nut : 2 nos.
175 Each
## 1.3 Civil Foundation (Poles)
Providing and laying in position M-20 reinforced cement
foundation of size 750mm (L) x 750mm wide and 1800 mm
deep for 12 Mtr including excavation of earth, providing,
cutting, bending and placing in position, reinforcement of
TMT bars of 12mm dia - 1960 mm long (approx.) - 8 Nos
and reinforcement ring of TMT bar of 8 mm dia - 2800mm
(approx.) - 10 Nos. (with 150mm spacing) as required with
positioning of foundation bolts and foundation will be
placed with laying base concrete : 150 mm thick (1:5:10 i.e.
1 cement: 5 coarse sand : 10 graded stone aggregate
40mm nominal size and providing 75 mm dia (O.D.) DWC
HDPE Pipe for cable entry & exit as required. (Note:- The
Foundation for poles on median shall be done by civil
contactor).
## i) for 12m Pole 67 Each
## 1.4 Providing and laying in position M-20 reinforced
cement foundation of size 600mm (L) x 600mm wide and
1500 mm deep for 10 Mtr including excavation of earth,
providing, cutting, bending and placing in position,
reinforcement of TMT bars of 12mm dia - 1960 mm long
(approx.) - 8 Nos and reinforcement ring of TMT bar of 8
mm dia - 2800mm (approx.) - 10 Nos. (with 150mm
spacing) as required with positioning of foundation bolts
and foundation will be placed with laying base concrete :
150 mm thick (1:5:10 i.e. 1 cement: 5 coarse sand : 10
graded stone aggregate 40mm nominal size and providing
75 mm dia (O.D.) DWC HDPE Pipe for cable entry & exit
as required. (Note:- The Foundation for poles on median
shall be done by civil contactor).
## i) for 10m Pole 175 Each
## 1.5 Foundation Bolts
Supplying and fixing 4 nos. (24mm diax850mm long J type
EN 8 Grade) threaded portion G.I foundation bolts. With
nuts washer, 2 nos. templates (4mm thick, 310mmx310mm
size), making of 4 nosx28mm dia holes with PCD of
320mm for 12 Mtr / 10 Mtr poles. One tem-plate (Top) shall
have a 120mm dia holes at center for cable entry. The
foundation Bolts shall be as per the sketch (Foundation) in
item as required.
242 Per Set
## 1.6 Arm Bracket
Fabrication, supplying and fixing of decorative type
galvanized double arm bracket made out of 127.0 mm dia
x 750 mm long galvanized cap-tube with minimum 1400/
1000 mm long x 60 mm dia pipe galvanized double
overhang bracket on each side with tightening bolt
(Stainless steel) etc as required and as per direction of
Engineer-in-Charge for following.
## i) Minimum 1000mm double Arm Bracket for 10 M Pole on
each side.
175 Each
## ii) Minimum 1400mm Double Arm Bracket for12 M Pole on
each side.
5 Each
## 2. SH-II (Street Light Fixture)
## 2.1 S.I.T.C. Street light fixture of approved make and
quality complete with standard accessories as per technical
specification. It shall have a housing made of LM6 die-cast
Aluminium, a lamp and reflector compartment with IP 66
degree of enclosure protection, a cover made of toughened
glass sealed on to the reflector & control gear
compartment with a removable gear-tray with ballast,
igniter, capacitor etc, mounted on it. The control gear shall
be compatible with the lamp used and the compartment
shall have an enclosure protection of rating IP 54. The
fixture shall be complete with the lamp (SON-T Plus) and
mounted directly on the pole or on an existing/new (new
arm bracket to be paid separately ) arm as required. The
fixture shall be suitable for:
## i) 250 W HPSV Lamp Street light Fixture with 250 W SONT
Plus Lamp.
180 Each
## ii) 400 W HPSV Lamp Street light Fixture with
1xSONT400W lamp.
180 Each
## 2.2 S.I.T.C of Integral flood light luminaire of approved
quality and make with pressure die-cast Aluminium housing
with IP 66 degree of enclosure protection and 150 W
SONT Lamp all complete.
30 Each
## 2.3 S.I.T.C of 2 x 28 Watt weather proof luminarie of
approved make and quality suitable for TL-5 warm white
florosent lamps of high grade polycarbonate housing and
cover etc. as required with 2 Nos 28 Watt TL-5 Lamps.
90 Each
## 3. SH - III (Wiring/Cables)
## 3.1 Supplying and drawing the following sizes of PVC
insulated copper conductor multicore cable in the existing
poles and bracket from cable termination connector to the
fitting alongwith providing suitable Copper lugs connections
as required
## ii) 3 core 2.5 Sq. mm Cable (For 12 Mtr Poles with double
arm bracket of 1400mm each)
5 Per Job
## i) 3 core 2.5 Sq. mm Cable (For 10 Mtr Poles with double
arm bracket of 1000mm each)
175 Per Job
## 3.2 Supply and laying of 1100 Volts grade XLPE cable as
per IS: 7098 (Latest Edition) with standard aluminium
conductor; XLPE insulated, multi-core bunched, armoured
with overall PVC insulation (A2XFY) in the existing
RCC/Hume /HDPE/Metal pipe etc. as required.
## i) For 4 Core x 25 sq. mm A2XFY Cable 11770 m
## ii) For 2 Core x 6 sq. mm A2XFY Cable 1500 m
## 3.3 Cable end Termination
Supplying and making indoor end termination with brass
compression gland and aluminium lugs for following size of
PVC insulated and PVC sheathed / XLPE aluminium
conductor cable of 1.1 KV grade as required.
## i) 4 Core x 25 sq. mm A2XFY Cable 13 Per Set
## ii) 2 Core x 6 sq. mm A2XFY Cable 180 Per Set
## 3.4 Supplying and fixing crimping type aluminium lugs
accessories, consumables and hardware for the following
size of PVC insualted and PVC sheathed/XLPE aluminium
conductor cable.
## i) 1.1 KV 4 core x 25 sqmm XLPE aluminium cable. 500 Per Set
## 3.5 Supplying and laying of 150 mm dia medium class GI
pipe ISI marked , including GI fittings such as socket,
below the road for crossing of electrical cable including
excavation in all type of soils, refilling and dressing of
earth, disposal of unservicable materials etc as required.
250 m
## 3.6 Providing and laying of one number DWC high density
poly ethylene (HDPE) antirodent pipe conforming to IS :
14930 ( Part-II ) complete with necessary fitting for
protection of 1.1 KV grade U.G. cables laid in ground / in
concrete of pole foundation at a depth of 50 cm or as per
directed by Engineer in Charge including excavation,
refilling the trench & disposal of unservicable materials etc.
as required.
a) 90/76 mm dia nominal size.
7183 m
## 3.7 Providing and laying of one number DWC high density
poly ethylene (HDPE) antirodent pipe conforming to IS :
14930 ( Part-II ) complete with necessary fiting for
protection of 1.1 KV grade U.G. cables laid at surface etc.
as required.
a) 90/76 mm dia nominal size.
2700 m
## 3.8 Providing, boring and laying of HDPE pipe of 120 mm
dia confirming to IS 14930, with presure rating of 4
kg.f/Cm2 by trenchless technology with nodding method by
making bore in the horizontal direction across the road as
per the direction of engineer-in-charge with moling
equipment including jointing, cleaning, nodding of pipe
including providing suitable cover on mouth of pipe i/c
excavation of pits of required size of depth 1.2 mtrs. to 2
mtr. refilling etc. as reqd.
200 m
## SH - IV ( EARTHING )
## 4. G.I Earth Pipe Electrode
Earthing with G.I. earth pipe 4.5 metre long, 40 mm dia
including accessories, and providing masonry enclosure
with cover plate having locking arrangement and watering
pipe etc. with charcoal/ coke and salt as required.
12 Per Set
## 4.2 Providing and fixing 6 SWG dia G.I. wire on surface or
in recess for loop earthing along with existing surface/
recessed conduit/submain wiring/ cable as required.
12767 m
## 5. SH - V ( Feeder Pillar )
## 5.1 Fabrication, supplying, installation, connecting, testing
and commissioning of outdoor type cubical feeder piller of
minimum front area 1.5 sq.mtr. and depth not less than
30cm, made out of MS Sheet 2mm thick (14 SWG) duly
campartmentaised having 4 strip busbar of 150 Amp
capacity double door with locking arrangement for
protection from rain, dust vermin, duly fixed on MS angle
iron frame work of size 50mm x 50mm x 6mm with 90 cm
long legs out of which 45 cm duly grouted in cement
concrete 1:2:4 (1 cement,2 sand and 4 stone aggrigate
20cm) and having following accessories mounted inside
the cublical panel i/c connections, inter connections with
aluminium thimbles, earthing with two nos. earth studs duly
painted with one coat of red oxide & two coats of superior
quality enamel paint complete etc. as required.
(i) Feeder Pillar with following accessories:-
a) 100 Amp, 25 KA MCCB - 4 Pole - 1 No.
b) 32 Amp, 16 KA MCCB -4 Pole - 4 Nos (with 100 Amp
frame size)
c) Voltmeter 0-500 volt 96 sqmm flush type with selector
switch - 1 No.
d) Ammeter 0 - 100 Amp 96 sqmm flush type with selector
switch & 100/5 Amp ration CTs - 2 Nos.
e) Indication lamps (RYB) with SP MCB - 3 Nos.
f) 1 No. Digital Astro Timer for ON/OFF of street light poles
with contractor of 110 A, 415 Volt AC rating with 100 Amp.
Auto manual selector switch.
g) Danger Notice Plate - 2 Nos.
h) Separate Compartment should be provided for electrical
supply co. & SCADA system.
5 Each
##
ii) Feeder Pillar with following accessories:-
a) 100 Amp, 25 KA MCCB - 4 Pole - 1 No.
b) 32 Amp, 16 KA MCCB -4 Pole - 4 Nos (with 100 Amp frame
size)
c) 63 Amp, 16 KA MCCB -4 Pole - 2 Nos (with 100 Amp frame
size)
d) Voltmeter 0-500 volt 96 sqmm flush type with selector switch -
1 No.
e) Ammeter 0 - 100 Amp 96 sqmm flush type with selector switch
& 100/5 Amp ration CTs - 2 Nos.
f) Indication lamps (RYB) with SP MCB - 3 Nos.
g) 1 No. Digital Astro Timer for ON/OFF of street light poles with
contractor of 110 A, 415 Volt AC rating with 100 Amp. Auto
manual selector switch.
h) Danger Notice Plate - 2 Nos.
i) Separate Compartment should be provided for electrical supply
co. & SCADA system.
Feeder Pillar with following accessories:-
a) 100 Amp, 25 KA MCCB - 4 Pole - 1 No.
b) 32 Amp, 16 KA MCCB -4 Pole - 4 Nos (with 100 Amp frame
size)
c) 63 Amp, 16 KA MCCB -4 Pole - 2 Nos (with 100 Amp frame
size)
d) Voltmeter 0-500 volt 96 sqmm flush type with selector switch -
1 No.
e) Ammeter 0 - 100 Amp 96 sqmm flush type with selector switch
& 100/5 Amp ration CTs - 2 Nos.
f) Indication lamps (RYB) with SP MCB - 3 Nos.
g) 1 No. Digital Astro Timer for ON/OFF of street light poles with
contractor of 110 A, 415 Volt AC rating with 100 Amp. Auto
manual selector switch.
h) Danger Notice Plate - 2 Nos.
i) Separate Compartment should be provided for electrical supply
1 Each
## 6. SH - VI (ACCESSORIES )
## i) Inspection window cover suitable for existing octagonal
poles including Fixing arrangement and size to be checked
at site as per requirement.
100 Each
## ii) 10 A MCB 50 Each
## iii) choke for 400 Watt HPSV fitting 30 Each
## iv) 400 Watt HPSV Lamps 30 Each
## 7. SH - VII (DISMANTLING AND REFIXING OF POLES
& FIXTURES )
## 7.1 Taking out existing octagonal pole from fondation,
carriage from site to contractor's yard, storage at safe
place, carriage from contractor's yard to site and refixing
on new foundation at site for without any damage including
removal of unservicable/dismental materials. (Foundation &
holding clamps bolts shall be paid seperately).
## i) 12 mtr high octagonal pole with double arm complete in
all respect
67 Each
## 7.2 Dismantelling of existing electrical street light fittings
from exiting Pole of 12 Mtr. Height, carriage from site to
contractor's yard storage at safe place, carriage from
contractor's yard to site and refixing on octagonal poles
with satisfactory operation at site without any damage.
## i) 400 Watt fitting complete in all respect 67 Each
## 7.3 Credit for the dismentaled cable recived from shifting
of existing poles.
## i) 4 Core x 25 sqmm 3222 m
6268409
Total in Figures 0.00
Total in Words Rupees only
1
Figures Words conc reinf HTS SS Exc Backfill
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
RATE In Figures AMOUNT
Rs. P
Tender Inviting Authority: Executive Engineer, Flyover Project Division F-131, PWD
Name of Work: Comprehensive Development of Corridor (Outer Ring Road) between Madhuban Chowk to Mukarba
Contract No: 55/CE/PWD Zone F-1/2012-13
SCHEDULE OF WORKS
0.00 Rupees
only
0.00 26329.06 M35
0.00 Rupees
only
0.00
63
0.00 Rupees
only
0.00
15481
M35
#REF! #REF!
0.00 Rupees
only
0.00
6503
M45
0.00 Rupees
only
0.00
411
M35
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
25775 M60
0.00 Rupees
only
0.00
11522
0.00 Rupees
only
0.00
2062
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
1414.32 M35
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
2495 M40
0.00 Rupees
only
0.00
2551 M40
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
1191 M45
0.00 Rupees
only
0.00
131.229
0.00 Rupees
only
0.00
300 M40
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
278.496
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
97643
0.00 Rupees
only
0.00
3005 3005
0.00 Rupees
only
0.00
10418
0.00 Rupees
only
0.00
6945
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
37065
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
6857 M10
0.00 Rupees
only
0.00
569 M40
0.00 Rupees
only
0.00
8918 M25
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
21 M15
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
0.00 Rupees
only
0.00
98,815 11,522 2,062 473 #REF! #REF!
Conc less pile 72,486
Precast 29,118 3% wastage
Insitu less pile 44,658 1% wastage
pile 28,435 8% wastage
TOTAL 102,212
Conc less pile 72,486
Precast 28,270
Insitu less pile 44,216
pile 26,329
CHECK -
0.00
Rupees only
conc with wastage
28435.384
15635.81
6568.03
415.11
26548.25
1428.4632
2569.85
2576.51
1202.91
303
6925.57
574.69
9007.18
21.21
102,212
RESOURCE CALCULATION FOR PWD FLYOVER :
Sl. No. Item Description Unit
Total
Scope
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24
A Piling :
Piling Monthly Nos. 744 0 0 36 75 75 75 75 75 75 75 75 75 33 0 0 0 0 0 0 0 0 0 0 0
Piling Rig Reqd (Considering 1.5 pile /d/rig) 0 0 1 2 2 2 2 2 2 2 2 2 1 0 0 0 0 0 0 0 0 0 0 0
B Pile Cap :
Pile Cap Casting Monthly Nos. 62 0 0 0 4 5 5 6 6 6 6 6 6 6 6 0 0 0 0 0 0 0 0 0 0
Pile Cap Shutter
(Considering 7 day shutter locking period)
0 0 0 1 1 1 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 0 0 0
C Pier /Pier Cap :
Pier /Pier Cap casting Monthly Nos. 62 0 0 0 1 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 1 0 0 0 0
Pier/ Pier Cap Shutter
(Considering 12 day shutter locking period)
0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 0 0 0 0 0
Milestone Requirement >>>>>>>>>>> 40 380 700
D CASTING : Spine Segment
Spine Segment Nos. BED -1 250 6 12 22 22 22 24 24 22 22 22 22 18 12
Spine Segment Nos. BED -2 242 6 12 22 22 22 22 24 22 22 22 22 18 6
Spine Segment Nos. BED -3 226 6 22 22 22 24 24 22 22 22 22 18
Spine Segment Nos. BED -4 0
Casting /Month Nos. 718 0 0 0 12 30 66 66 66 70 72 66 66 66 66 54 18 0 0 0 0 0 0 0 0
Cum Casting 0 0 0 12 42 108 174 240 310 382 448 514 580 646 700 718 718 718 718 718 718 718 718 718
E Erection : Spine Segment Milestone Requirement >>>>>>>>>>> 20 40 61
A1 - P60 Spans LG-1 61 0 0 0 0 0 3 4 4 4 4 4 4 4 4 4 4 4 4 5 5 0 0 0 0
Erection /Month Spans 61 0 0 0 0 0 3 4 4 4 4 4 4 4 4 4 4 4 4 5 5 0 0 0 0
Cum Erection Spans 0 0 0 0 0 3 7 11 15 19 23 27 31 35 39 43 47 51 56 61 61 61 61 61
Cum Erection (Avg 11.77 nos./span) Nos. 0 0 0 0 0 35 82 129 177 224 271 318 365 412 459 506 553 600 659 718 718 718 718 718
Stacking Requirement 0 0 0 12 42 73 92 111 133 158 177 196 215 234 241 212 165 118 59 0 0 0 0 0
Milestone Requirement >>>>>>>>>>> 50 425 1200 1436
F Casting Cantilever Arm Segment : Nos. 1436 50 50 100 100 100 100 100 120 120 120 120 120 90 90 56
Casting /Month Nos. 0 0 0 50 50 100 100 100 100 100 120 120 120 120 120 90 90 56 0 0 0 0 0 0
CumCasting Nos. 0 0 0 50 100 200 300 400 500 600 720 840 960 1080 1200 1290 1380 1436 1436 1436 1436 1436 1436 1436
Reqd No. of beds / Month
(Considering 3 d Time cycle & 25d work)
Nos. 1436 0 0 0 6 6 12 12 12 12 12 14 14 14 14 14 11 11 7 0 0 0 0 0 0
Milestone Requirement >>>>>>>>>>> 14 34 54 61
G Casting Cantilever Arm Erection : Spans 61 0 0 0 0 0 0 2.5 2.5 2.5 3.75 5 5 5 5 5 5 5 3.75 3.75 2.5 2.5 2.25 0 0
Casting /Month Spans 0 0 0 0 0 0 3 3 3 4 5 5 5 5 5 5 5 4 4 3 3 2 0 0
Cum Erection Spans 0 0 0 0 0 0 3 5 8 11 16 21 26 31 36 41 46 50 54 56 59 61 61 61
Cum Erection in Nos. Nos. 0 0 0 0 0 0 59 118 177 265 383 500 618 736 853 971 1089 1177 1265 1324 1383 1436 1436 1436
1.25 Consd 1.25 span / month /launcher 0 0 0 0 0 0 2 2 2 3 4 4 4 4 4 4 4 3 3 2 2 2 0 0
Stacking Requirement 0 0 0 50 100 200 241 282 323 335 337 340 342 344 347 319 291 259 171 112 53 0 0 0
RESOURCE CALCULATION :
Item Description AREA No. of sets Wt Kg /m2 Total Wt (MT) Rate/MT Amount
PILE CAP 88 2 100 17.6 MT
PIER & PIER CAP -Shutter 145.112 2 130 37.7 MT
PIER & PIER CAP -Staging /Supporting 2 30 MT @15 MT /Set
SPINE SEGMENT - BED 296 3 190 168.7 MT
SPINE SEGMENT - OUTER SIDE 54 3 190 30.8 MT
SPINE SEGMENT - INNER SIDE 181.44 3 200 108.9 MT
CANTILEVER ARMSEGMENT -Shutter 54.15 14 130 98.5 MT
CANTILEVER ARM SEGMENT -Shutter supporting arrangement 14 42.0 MT @3 MT /Set
CANTILEVER ARM SEGMENT -Stacking supporting arrangement 150 375.0 MT @2.5 MT /Set casting yard cost
CRASH BARRIER
Total length = 2.7*4 = 10.8 KM
The entire to be completed in M7 TO M22 = 15 Months
Target per Month = 10800/15 =720m/month
Avg Time cycle for 50mcasting 5d
No. os sets required of 50m= (720/50)*5/25 = 3 Sets of 50m 62.5 3 100 18.8 MT
PRECAST FACIA: CB
Total length = 2.7*4 = 10.8 KM
The entire to be completed in M6 TO M20 = 14 Months
Target per Month = 10800/14 =770m/month
Considering 3mlength of facia 257 nos. / month
Considering 2d time cycle
No. of sets required =257*2/25 =20 Sets 4.5 20 100 9.0 MT
DRAIN SHUTTER :
Total length 2.7KM x 2 = 5.4 km
Target to be completed M2 TO M 15 = 13 Months
Target per Month = 5400/13 = 416m/month
Considering 50m/ 5 day , sets reqd 2Nos. of 50 m 400 2 100 80.0 MT
0 1017 MT
No. of Launcher Reqd >>>
DETAIL PLANNING FOR PWD FLYOVER :
Sections Pier No. Ch from Ch to Length
Pile (1.2m) 0.000 3361.100 3361.10
Pile Cap
Pier & Pier Cap
Spine segment 272
Wing Arm 544
Road Work
Pile (1.2m)
Pile cap
Pier & Pier Cap
Steel Girder Erec
Slab Casting
Misc Work
Road Work
Steel Girder Fabr
Pile (1.2m)
Pile cap
Pier & Pier Cap
Spine segment
Wing Arm
Road Work
Pile (1.2m)
Pile cap
Pier & Pier Cap
Spine segment
Wing Arm
Road Work
Sec-6
Sec-3
A1-P60
Sec-5
Sec-4
Pile (1.2m)
Pile -Cum
Pile cap
Pile cap- Cum
Pier & Pier Cap
Pier & Pier Cap -Cum
Spine segment
Spine segment - Cum
Wing Arm
Wing Arm - Cum
Activities Schedule Per Month
Scope (Item) LG Mkd M1 M2 M3 M4 M5 M6 M7 M8
744 Piling Rig 1+2 36 75 75 75 75 75
62 4 5 5 6 6
62 1 4 4 4 4
61 LG-1 3 4 4
61 CG-1+2+3+4 2.5 2.5
Mobilization
Period
m1 m2 m3 m4 m5 m6 m7 m8
744 36 75 75 75 75 75
0 0 36 111 186 261 336 411
62 0 4 5 5 6 6
0 0 0 4 9 14 20 26
62 0 1 4 4 4 4
0 0 0 1 5 9 13 17
61 0 0 0 3 4 4
0 0 0 0 0 3 7 11
61 0 0 0 0 0 0 3 3
0 0 0 0 0 0 3 5
Key Date - 1
Road Widening(1km) Drain(0.5km)
Piles-132 nos
Pile cap-8 Nos
Pier-5 Nos
casting-40Spine+50 cantilever
Key Date - 2
Road Widening(3km) +Drain(1.5km)
Piles-420 nos
Pile cap-28 Nos
Pier-24 Nos
casting-Spine(380)+Wings(425)
Erection:Spine(20 span)+Wings(14
Span)
Crash Barrier-18 spans casting
RE Wall-25%
M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19
75 75 75 75 33
6 6 6 6 6 6
4 4 4 4 4 4 4 4 4 4 4
4 4 4 4 4 4 4 4 4 4 5
2.5 3.75 5 5 5 5 5 5 5 3.75 3.75
m9 m10 m11 m12 m13 m14 m15 m16 m17 m18 m19
75 75 75 75 33 0 0 0 0 0 0
486 561 636 711 744 744 744 744 744 744 744
6 6 6 6 6 6 0 0 0 0 0
32 38 44 50 56 62 62 62 62 62 62
4 4 4 4 4 4 4 4 4 4 4
21 25 29 33 37 41 45 49 53 57 61
4 4 4 4 4 4 4 4 4 4 5
15 19 23 27 31 35 39 43 47 51 56
3 4 5 5 5 5 5 5 5 4 4
8 11 16 21 26 31 36 41 46 50 54
Date - 2
Road Widening(3km) +Drain(1.5km)
Spine(380)+Wings(425)
Erection:Spine(20 span)+Wings(14
18 spans casting
Key Date - 4
Road Widening+Drain-complete
Piling Complete
Pile cap-complete
Pier-complete
Casting-Spine+Wings (complete)
Erection:Spine(complete)+Wings(54
span)
CB casting-complete+fixing- 50 Span
Key Date - 3
Road Widening+Drain complete
Piling Complete
Pile cap-56 Nos
Pier-48 Nos
Casting
Spine(700nos)+Wings(1200nos)
Erection:
Spine(40span)+Wings(34span)
CB: casting -40 spans + fixing 30spans
RE Wall-100%
M20 M21 M22 M23 M24
744 0
62 0
1 62 0
5 61 0
2.5 2.5 2.25 61 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0.00
0 0
0 0
0 0
0 0
0 0
0 0
0 0
m20 m21 m22 m23 m24
0 0 0 0 0
744 744 744 744 744
0 0 0 0 0
62 62 62 62 62
1 0 0 0 0
62 62 62 62 62
5 0 0 0 0
61 61 61 61 61
3 3 2 0 0
56 59 61 61 61
complete
(complete)
Erection:Spine(complete)+Wings(54
50 Span
Key Date - 5
All work completed
(Including electrical
works)
ENABLING WORKS
Civil works for 3 x 800 MW Gadarawara Power plant, M.P.
Sr.No. POLICY/PROJECT DETAILS RATE Premium
Rs-Lakhs Rs-Lakhs
1 CAR/EAR POLICY
Value of project for all Permanent & Temporary works included
free issue of materials divided as as below:+ free issue material 40,495 Change based on Final value of the Project
CAR - Policy to be taken by client. 40,495 0.496%
TOTALVALUE 40,495 200.86 0.496%
Covers available
a Material Damage with A.O.G perils for 36 months YES
b Fire/Earthquake YES
c Burglary YES
d Strike, Riots, Commotion YES
e Escalation upto 50% of sum insured YES
f Extended Maintenance Period 12 months
g Third Party Liability with Cross upto AOA limit upto Rs.10Cr YES
h Debris Removal upto a limit of Rs.1000L YES
i Owners Surrounding Property 10% of SI YES
l Terrorism Cover - included YES
k offsite storage YES
2 TRANSIT INSURANCE (MARINE & INLAND)
Premium to be considered
Approx value of Plant & Materials 8099 0.07% 5.46 0.013%
0.06% of the value of materials in transit + 12.36% STax
3 PLANT INSURANCE (IMPORTS & INDEGENIOUS)
Premium to be considered
Approx value of plant 4050 0.45% 36 54.60 0.135%
0.40% per annum of the sum insured+12.36% S.Tax Months
4 MOTOR INSURANCE (Incl Comm Vehicle)
Premium to be considered
Approx average value of Plant for total period 500 2.53% 36 37.92 0.094%
2.25% per annum of the value of vehicles + 12.36% STax Months
5 WORKMEN'S COMPENSATION INSURANCE Wages = 5% of Sum Insured
Assumed Wages is 5% 2025 Lakhs 2.8% 56.88 0.140%
Premium to be considered for the whole period
2.5% of wages + 12.36% service tax
TOTAL INSURANCE COST 355.71 0.878%
Civil Works for Godda Power Plant for Jindal Power Ltd - Insurance premium provisions for tender purpose.
As a % of
Quote
Qty. Rate Amt. Qty.
1.0 General
2.0 SHE targets and Goals
3.0 Compliance
4.0 Contractor SHE Policy and Plan
5.0 Designer's role
6.0 Contractor SHE Organisation No Yr
SHE Manager 1 120000 0
Sr. SHE Engineer 3 100000 0
Jr. SHE Engineer 3 800000 0
Safety Steward 2 3 200000 1200000
Sr. SHE (Electrical) Manager 0
Jr. SHE (Electrical) Manager 0 0 800000 0
Sr. SHE (Fire) Engineer 0 1250000 0
Jr. SHE (Fire) Manager 0 800000 0
Occupational Health Officer - MBBS
Doctor with diploma in
industrial/occupational health
24000
2 days per
week
Medical Support Staff - Nurse 0
Medical Support Staff - First Aider 1 3 250000 750000
Environment Manager / Engineer 0 800000 0
Sr. SHE (Traffic) Manager 0
Traffic Marshals
Housekeeping Squad Manager 0
Housekeeping workers
Barricade Manager 0
Total Manpower Cost
Digital Sound Level Meter 1
Digital Lux Meter 1
Laptop Computer 0
Colour Printer 0
Computer (LCD) Projector with screen 0
35 mm camera 1
4 mp digital camera with video 0
4 mp digital still camera 0
Portable loudspeaker
Communication facility like mobile
phone etc.
1
PART - I : SHE MANAGEMENT
Civil work & Steel Structural erection work at Jindal Power Plant- Jharkkhand
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Sl. No. Contents
Requirement and Cost
Manpower Equipment / Material
7.0 Contractor SHE committee
8.0
ID card and first day at work, SHE
orientation training
Training on first aid / CPR to all workers
and staff on first day at work
ID card to all workers (2 per year, 200
workers)
0
SHE handbook (pocketbook) 100
9.0 SHE training
SHE training for managers and
supervisors - 20 topics
SHE training for managers, supervisors
and workers - 25 topics
Training room with chairs, table, board
etc. (projector, laptop considered
separately)
1
10.0 SHE inspection
Half yearly inspection of lifting
machinery, lifting appliances,
equipment and gears by Govt.
approved comopetent person
11.0 SHE audit
External SHE Audit -one per quarter
12.0 SHE communication
Celebration - Safety / Environment /
other days -14, Safety / earth weeks-2,
red cross month-1
Banners
Badges
Prizes and gifts
Miscellaneous expenses on
arrangements
L.S.
Posters
Posters-mega size
Signages-metallic boards
Videos
13.0 SHE submittals to the Employer
14.0 Accident reporting and investigation
15.0 Emergency preparedness plans
16.0 Expects / Agencies for SHE services
TOTAL
17.0 Housekeeping
18.0 Working at Height
Fall protection - safety nets 100
40 NB MS Pipe for railing / barricades 0
6" wide, 1" thk wooden plank / sheet for
toe board
0
19.0 Overhead protection
20.0
Slipping, Tripping, Cutting, Drowning
and Falling Hazards
21.0 Lifting Appliances and Gear
Automatic Safe Load Indicator
22.0 Launching operation
23.0 Construction machinery
Inspection of all construction equipment
by authorized persons / firms approved
by the employer
Provision of reverse horns
24.0 Machine and general area guarding
25.0
Manual lifting and carrying of excessive
weight
26.0 Site electricity
30 mA sensitivity ELCB / RCCB 10
Earthing pits 3
Step down transformer
Low voltage portable electrical hand
tools
Low voltage electrical fixtures
27.0 Lighting
28.0 Hand Tools and Power Tools
Distribution board with Industrial socket
and connectors
4
29.0 Welding, gouging and cutting
Cylinder trolleys 5
Flash back arrestor - set 10
Non-return valve 10
PART - II : SAFETY
30.0 Dangerous and harmful environment
31.0
Fire prevention, protection and fighting
system
Fire extinguishers - 2 Kg, ABC (dry
powder)
6
Fire extinguishers - 2 Kg, CO2 2
Fire extinguishers - 10 Kg, ABC (dry
powder)
0
Fire extinguishers - 9 Kg, CO2 1
Fire extinguishers - 5 Kg, Foam 1
Fire buckets 6
Refilling of fire extinguishers 1
32.0 Corrosive substances
33.0 Demolition
34.0 Excavation and tunnelling
35.0 Work permit system
36.0 Traffice management
Traffic warning signs 0
Other traffic signs 0
Delineators
Traffic cones 10
Safety ribbon 750
Electric blinkers 0
Illuminated traffic control beacons 0
37.0 Work adjacent to live railways
38.0 Batching plant and casting yard layout
39.0 Personal Protective Equipments (PPEs)
Safety helmets 2000
Safety footwear, gumboots 2000
High visibility clothing (jacket) 1000
Fall arrestor 6
Full body harness 50
Goggles 200
Hand gloves 500
Nose mask 350
Ear plugs 50
Welder's apron 10
Electrician's rubber hand gloves 5
40.0 Visitors to site
TOTAL
41.0 Physical fitness of workmen
Medical examination of all workers
PART - III : OCCUPATIONAL HEALTH AND WELFARE
42.0 Medical Facilities
Occupational Health Centre 1
Ambulance van and room (tie-up with
local hospitals)
First aid boxes 3
Consultancy for implementing AIDS
policy
Compensation to 'Peer Educators' 0 0
Fumigation,/spraying of insecticides for
mosquitoes
12
43.0 Noise
Vibration meter 0
44.0 Ventilation and illumination
45.0 Radiation
46.0 Welfare measures for workers=
TOTAL
47.0 Air Quality
Environmental monitoring
PUC check of all vehicles 10
Tractor - tanker for dust suppression 1
Arrangement for wheel washing /
vehicle cleaning
0
48.0 Water Quality
Testing of water for potability 4
49.0
Archaeological and Historical
Preservation
50.0 Landscape and Greenery
51.0 Felling of Trees
52.0 Fly Ash
53.0 Waste
54.0 Hazardous Waste Management
Waste water analysis 4
55.0 Energy Management
TOTAL
TOTAL NON-SALARY- COST
GRAND TOTAL INCl. SALARY
56.0
Charges to be recovered from
contractor for unsafe act or condition
57.0 Stoppage of work
PART - IV : ENVIRONMENTAL MANAGEMENT
PART - V: PENALTY AND AWARDS
58.0 Awards
Appendix 1: Memorandum of
understanding
Appendix 2: SHE Requirement as per
BOCWA, BOCWR, BOCWWCA &
BOCWWCR
Appendix 3: Contents of contractors
SHE plan
Appendix 4: Employer's workplace
policy on HIV/AIDS prevention and
control for
workmen engaged by contractors
General Instruction 1: SHE manpwoer
requirement
General Instruction 2: Qualification
and experience of SHE professionals
General Instruction 3: Minimum
requirements of SHE monitoring and
Audio-visual equipments
General Instruction 4: First day at
work
General Instruction 5: ID card format
General Instruction 6: SHE training
matrix for Managers & Supervisors
General Instruction 7: SHE training
matrix
General Instruction 8: Days to be
observed for creating SHE awareness
General Instruction 9: SHE posters
General Instruction 10: Experts /
Agencies for SHE services
General Instruction 11: Minimum
lighting required
General Instruction 12: Warning
traffic sign
Sample Form 1: Formation of
site SHE committee
Sample Form 2: Minutes of SHE
committee meeting
Total
NOTE: We have not included following:-
1. Cost of MS pipes required to barricade deep excavated pits & work platforms on scaffold
4. Project site will arrange one vehicle to meet any emergency at site.
2. Cost of Wooden planks used for work platforms.
3. Cost of electrical Distribution Boards required at site.
Rate Amt. Qty. Rate Amt.
0
0
0
1200000
0
0
0
0
LS 0
0
750000
0
0
0
0
8000 8000 8000
8000 8000 8000
35000 0
5000 0
25000 0
10000 10000
0 0
0 0
2500 0
6000 6000
PART - I : SHE MANAGEMENT
For 1000 people
Day & Night shift
For 1000 people
Day & Night shift
Civil work & Steel Structural erection work at Jindal Power Plant- Jharkkhand
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Requirement and Cost
Total Amount, Rs. Ramarks
Equipment / Material Consultancy
1000 100 100000 100000
5 0 0
50 5000 5000
30 2000 60000 60000
30 1000 30000 30000
L.S. 50000 50000
2 10000 20000 20000
0 50000 0 0
100 2 200
800 1.25 1000
15000 0 0
25000 1 25000
50 50 2500
200 5 1000
500 5 2500
2000 1 2000
2281200
covered under 6
450 45000 45000
250 0 0
Not considered as
safety items
75 0 0
Catered for by
Mechanical
2500 25000 25000
1250 3750 3750
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
5000 20000 20000
This should form a
part of
electrification of
site
1500 7500 7500
2500 25000 25000
2500 25000 25000
PART - II : SAFETY
2000 12000 12000
3500 7000 7000
3500 0 0
5000 5000 5000
5500 5500 5500
175 1050 1050
L.S. 15000 15000
1250 0 0
1250 0 0
350 0 0
650 6500 6500
3 2250 2250
1550 0 0
1250 0 0
0 0
100 200000 200000
550 1100000 1100000
125 125000 125000
1250 7500 7500
1250 62500 62500
50 10000 10000
35 17500 17500
25 8750 8750
15 750 750
550 5500 5500
225 1125 1125
1744175
250 500 125000 125000
PART - III : OCCUPATIONAL HEALTH AND WELFARE
L.S. 20000 0 20000
1250 3750 3750
2.5 0 0
0
1500 18000 18000
26500 0 0
166750
1 L.S. 50000 50000
150 1500 1500
22500 22500 22500
L.S. 50000 0
0
0
2000 8000
1250 5000 5000
87000
4279125
4279125
PART - IV : ENVIRONMENTAL MANAGEMENT
PART - V: PENALTY AND AWARDS
4279125
4279125 Carried to ONCOST Grand Total
Grand Total
IT
Duration= 3 years
IT INFRASTRUCTURE
Unit Unit Price Total Cost
1) IT hardware consists of: -
Basic file and print servers for authentication 1 150000 150000
No of Desktops required User 5 35000 175000 Exsite
No of Laptops required User 1 53000 53000 Exsite - 2 nos.
Network switches/Hubs 1 15000 15000
Network UPS 1KVA 1 30000 30000
Individual UPS 600 VA User 5 4500 22500
Network Printers 1 50000 50000
DeskJet Printers 6000 0 Account
A3 size DeskJet printer 1 25000 25000
Backup device 1 50000 50000
Plotter (If required) 1 350000 350000 Cost Considered, Only Drwaing printing
2) Software cost consists of: -
Windows Svr Ent 2003 R2 Sngl MVL 1 40000 40000
Basic O/S software for Desktop/Laptop User 6 9000 54000
MS Office User 6 21000 126000
Exchange CAL User 6 6000 36000
Windows CAL User 6 2000 12000
Antivirus software User 6 2200 13200
Project planning software (If required) 0
MS Project 1 22000 22000
Primavera 200000 0
Sure Track 100000 0
AutoCAD 2011 Commercial New SLM 1 100000 100000
Backup management software 1 70000 70000
SQL Svr Standard Edtn 2005 Win32 Sngl MVL 1 40000 40000
SQL CAL 2005 Sngl MVL Device CAL User 1 7000 7000
3) Network cost consists of: -
Structured cabling at projects site User 9 3000 27000
4) Connectivity cost consists of: - Recurring
BSNL MPLS Link
Port Bandwidth 64Kbps
Local Lead Bandwidth 64Kbps
Approximate Local Lead Distance 10Kms
Port Charge Recurring Year 1 105000 105000
Local Lead Charge Recurring Year 1 32652 32652
Modem RAD Recurring Year 1 40000 40000
Installation Change 1 20000 20000
IT person Recurring Year 1 420,000 420,000 extra added
Router 1 60000 60000
Abstract Rs.
Installation cost (Capex) 1,710,548 Rs. Total
Recuuring (annual) cost 434,804 Rs/year
Page 399
IT
Cost Considered, Only Drwaing printing
Page 400
Qty. Rate Amt. Qty. Rate Amt. Qty. Rate Amt.
1.0 General
2.0 SHE targets and Goals
3.0 Compliance
4.0 Contractor SHE Policy and Plan
5.0 Designer's role
30 m
6.0 Contractor SHE Organisation No Yr
Chief SHE Manager 2000000 0
Sr. SHE Manager 600000 0
Jr. SHE Manager 2.5 300000 0
Safety Steward 2.5 146875 0
Sr. SHE (Electrical) Manager 2.5 475000 0
Jr. SHE (Electrical) Manager 2.5 150000 0
Sr. SHE (Fire) Manager 2.5 475000 0
Jr. SHE (Fire) Manager 2.5 0
Occupational Health Officer - MBBS Doctor with
diploma in industrial/occupational health
2.5 175000 0
Medical Support Staff - Nurse 2.5 143750 0
Medical Support Staff - First Aider 2.5 0
Environment Manager 2.5 475000 0
Sr. SHE (Traffic) Manager 2.5 475000 0
Traffic Marshals 2.5 0 0
Housekeeping Squad Manager 2.5 1800000 0
Housekeeping workers 2.5 12500 0
Barricade Manager 2.5 600000 0
Barricade Marshals 2.5 0 0
Labour welfare officer 2.5 0 0
Welfare support staff - clerk 2.5 0 0
Total Manpower Cost
Digital Sound Level Meter 1 15000 15000
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Sl. No. Contents
Requirement and Cost
Manpower Equipment / Material Consultancy
PART - I : SHE MANAGEMENT
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
Qty. Rate Amt. Qty. Rate Amt. Qty. Rate Amt.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Sl. No. Contents
Requirement and Cost
Manpower Equipment / Material Consultancy
Digital Lux Meter 1 15000 15000
Laptop Computer * 35000
Colour Printer * 5000
Computer (LCD) Projector with screen * 25000
35 mm camera * 15000
4 mp digital camera with video * 10000
4 mp digital still camera * 10000
Portable loudspeaker * 2500
Communication facility like mobile phone etc. * 35000
Accident Investigation kit with flashlight etc
7.0 Contractor SHE committee
8.0
ID card and first day at work, SHE orientation
training
Training on first aid / CPR to all workers and
staff on first day at work
300 100 30000
ID card to all workers (2 per year, 1500 workers) 600 5 3000
SHE handbook (pocketbook) 300 50 15000
9.0 SHE training
SHE training for managers and supervisors - 20
topics
100 2000 200000
SHE training for managers, supervisors and
workers - 44 topics
220 1000 220000
Training of vehicle drivers at Central Training
Institute, KSRTC, Bangalore
Training room with chairs, table, board etc.
(projector, laptop considered separately)
1 L.S. 50000
10.0 SHE inspection
Half yearly inspection of lifting machinery, lifting
appliances, equipment and gears by Govt.
approved comopetent person
5 10000 50000
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
Qty. Rate Amt. Qty. Rate Amt. Qty. Rate Amt.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Sl. No. Contents
Requirement and Cost
Manpower Equipment / Material Consultancy
11.0 SHE audit
External SHE Audit -one per quarter 10 50000 500000
12.0 SHE communication
Celebration - Safety / Environment / other days -
14, Safety / earth weeks-2, red cross month-1
Banners 250 0
Badges 1 0
Prizes and gifts 150000 0
Miscellaneous expenses on arrangements L.S. 250000 100000
Posters 50 0
Posters-mega size 200 0
Signages-metallic boards 200 0
Videos 2000 0
13.0 SHE submittals to the Employer
14.0 Accident reporting and investigation
15.0 Emergency preparedness plans
16.0 Expects / Agencies for SHE services
TOTAL
PART - II : SAFETY
17.0 Housekeeping
18.0 Working at Height
Fall protection - safety nets 150 350 52500
40 NB MS Pipe for railing / barricades 1500 250 375000
6" wide, 1" thk wooden plank / sheet for toe
board
300 75 22500
Scissor Lift
Sky Lift
19.0 Overhead protection
20.0
Slipping, Tripping, Cutting, Drowning and Falling
Hazards
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
Qty. Rate Amt. Qty. Rate Amt. Qty. Rate Amt.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Sl. No. Contents
Requirement and Cost
Manpower Equipment / Material Consultancy
21.0 Lifting Appliances and Gear
Automatic Safe Load Indicator
22.0 Launching operation
23.0 Construction machinery
Inspection of all construction equipment by
authorized persons / firms approved by the
employer
Provision of reverse horns
24.0 Machine and general area guarding
25.0 Manual lifting and carrying of excessive weight
26.0 Site electricity
30 mA sensitivity ELCB / RCCB 10 2500 25000
Earthing pits 5 1250 6250
Lightning arrestors 3500 0
Step down transformer 0
Low voltage portable electrical hand tools 0
Low voltage electrical fixtures 0
0
27.0 Lighting 0
0
28.0 Hand Tools and Power Tools 0
0
Distribution board with Industrial socket and
connectors
10 5000 50000
29.0 Welding, gouging and cutting
Cylinder trolleys 5 1500 7500
Flash back arrestor - set 10 2500 25000
Non-return valve 10 2500 25000
30.0 Dangerous and harmful environment
31.0 Fire prevention, protection and fighting system
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
Qty. Rate Amt. Qty. Rate Amt. Qty. Rate Amt.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Sl. No. Contents
Requirement and Cost
Manpower Equipment / Material Consultancy
Fire extinguishers - 2 Kg, ABC (dry powder) 10 2000 20000
Fire extinguishers - 2 Kg, CO2 2 3500 7000
Fire extinguishers - 10 Kg, ABC (dry powder) 1 3500 3500
Fire extinguishers - 9 Kg, CO2 1 5000 5000
Fire extinguishers - 5 Kg, Foam 2 5500 11000
Fire buckets 10 175 1750
Refilling of fire extinguishers 1 L.S. 25000
32.0 Corrosive substances
33.0 Demolition
34.0 Excavation and tunnelling
35.0 Work permit system
36.0 Traffice management
Traffic warning signs 20 1250 25000
Other traffic signs 30 1250 37500
Delineators 75 350 26250
Traffic cones 75 650 48750
Safety ribbon 7500 3 22500
Electric blinkers 5 1550 7750
Illuminated traffic control beacons 10 1250 12500
Tow away vehicle (25 months) 0
37.0 Work adjacent to live railways 0
Safety ribbon 3
38.0 Batching plant and casting yard layout
39.0 Personal Protective Equipments (PPEs)
Safety helmets 400 100 40000
Safety footwear, gumboots 500 350 175000
High visibility clothing (jacket) 500 100 50000
Fall arrestor 10 1250 12500
Full body harness 50 1250 62500
Goggles 50 50 2500
Hand gloves 300 35 10500
Nose mask 300 25 7500
Ear plugs 500 15 7500
Ear muffs 200 125 25000
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
Qty. Rate Amt. Qty. Rate Amt. Qty. Rate Amt.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Sl. No. Contents
Requirement and Cost
Manpower Equipment / Material Consultancy
Welder's apron 10 550 5500
Electrician's rubber hand gloves 10 225 2250
40.0 Visitors to site
TOTAL
41.0 Physical fitness of workmen
Medical examination of all workers 500 650 325000
42.0 Medical Facilities
Occupational Health Centre 1 L.S. 50000 50000
Ambulance van and room (tie-up with local
hospitals)
- - -
First aid boxes 5 1250 6250
Consultancy for implementing AIDS policy 2.5 0
Compensation to 'Peer Educators' 50 2500 125000
Fumigation,/spraying of insecticides for
mosquitoes
28 2500 70000
43.0 Noise
Vibration meter 1 26500 26500
44.0 Ventilation and illumination
Oxygen meter
45.0 Radiation
46.0 Welfare measures for workers=
TOTAL
47 Air Quality
Environmental monitoring 1 L.S. 50000
PUC check of all vehicles 50 150 7500
Tractor - tanker for dust suppression 5 22500 112500
Arrangement for wheel washing / vehicle
cleaning
1 L.S. 50000
48.0 Water Quality
Testing of water for potability 10 1550 15500
49.0 Archaeological and Historical Preservation
PART - III : OCCUPATIONAL HEALTH AND WELFARE
PART - IV : ENVIRONMENTAL MANAGEMENT
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
Qty. Rate Amt. Qty. Rate Amt. Qty. Rate Amt.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Sl. No. Contents
Requirement and Cost
Manpower Equipment / Material Consultancy
50.0 Landscape and Greenery
51.0 Felling of Trees
52.0 Fly Ash
53.0 Waste
54.0 Hazardous Waste Management
Waste water analysis 10 1250 50000
55.0 Energy Management
TOTAL
TOTAL NON-SALARY- COST
GRAND TOTAL INCl. SALARY
PART - V: PENALTY AND AWARDS
57.0 Stoppage of work
58.0 Awards
Appendix 1: Memorandum of understanding
Appendix 2: SHE Requirement as per
BOCWA, BOCWR, BOCWWCA & BOCWWCR
Appendix 3: Contents of contractors SHE
plan
Appendix 4: Employer's workplace policy on
HIV/AIDS prevention and control for
workmen engaged by contractors
General Instruction 1: SHE manpwoer
requirement
General Instruction 2: Qualification and
experience of SHE professionals
General Instruction 3: Minimum
requirements of SHE monitoring and Audio-
visual equipments
General Instruction 4: First day at work
General Instruction 5: ID card format
General Instruction 6: SHE training matrix for
Managers & Supervisors
56.0
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
Qty. Rate Amt. Qty. Rate Amt. Qty. Rate Amt.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Sl. No. Contents
Requirement and Cost
Manpower Equipment / Material Consultancy
General Instruction 7: SHE training matrix
General Instruction 8: Days to be observed
for creating SHE awareness
General Instruction 9: SHE posters
General Instruction 10: Experts / Agencies
for SHE services
General Instruction 11: Minimum lighting
required
General Instruction 12: Warning traffic sign
Sample Form 1: Formation of site SHE
committee
Sample Form 2: Minutes of SHE
committee meeting
Assumptions -
Assumptions -
Average 1000 employees / workers perday
Project Tenure - 30 months
No underground work will be carried out
Cost of goods / services is assumed based on
general experience. The same may vary.
i.e. Charge to Contract
SHE Salary 100% = 0 L considered in org
SHE Requirements 33.29 100% = 33.29 L
Total 33.29 L
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
0 0
0 0
0 1600000
0 800000
0 0
0 1600000
0 0
0 0
0
350000
0 0
0 1000000
0 1600000
0 0
0 1080000
0 30000
0 1500000
0 30000
0
0 15000
0 15000
0 0 0
15000 0
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Total Amount,
Rs.
Ramarks
PART - I : SHE MANAGEMENT
As per
DMRC/SHE/
GI/001/MPR/
281105
As per
DMRC/SHE/
GI/001/MPR/
281105
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Total Amount,
Rs.
Ramarks
15000 0
0 0
0 0
0 0
0 0
0 0
0
0
0
30000
3000
15000
30000
3000
200000
15000 220000
50000
200000
220000
50000
50000
300000
50000
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Total Amount,
Rs.
Ramarks
0
500000 0
0
100000
0
0 0
0 0
0 0
100000
0
0
0
0
1198000
covered under 6
52500
375000
22500
0
0
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Total Amount,
Rs.
Ramarks
0
0
25000
6250
0
0
0
0
0
0
0
0
0
50000
7500
25000
25000
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Total Amount,
Rs.
Ramarks
20000
7000
3500
5000
11000
1750
25000
25000
37500
26250
48750
22500
7750
12500
0
0
0
40000
175000
50000
12500
62500
2500
10500
7500
7500
25000
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Total Amount,
Rs.
Ramarks
5500
2250
1243000.0
325000
50000
6250
0
125000
70000
26500
0
602750
50000
7500
112500
50000
15500
PART - III : OCCUPATIONAL HEALTH AND WELFARE
PART - IV : ENVIRONMENTAL MANAGEMENT
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Total Amount,
Rs.
Ramarks
50000
285,500
3329250
3329250.0
56.0
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
EHS REQUIREMENTS AND CORRESPONDING COST - AN ESTIMATE
Total Amount,
Rs.
Ramarks
`
Contract No: BMR/VIA/EW/R2-1 ITDCem Safety Deptt. \\vboxsrv\conversion_tmp\scratch_2\244006447.xlsx.ms_office.
TENTATIVE CONSTRUCTION PROGRAMME Civil works for 3 x 800 MWGadarawara Power plant, M.P.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 DLP
Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15
1 Letter of Intent
2 Initial Site activity
2.1 Site Hnadover 1 item
2.2 Temporary approach road 1 item
2.3 Casting Yard 1 LS
2.4 Soil Investigation Work 4 B/H
2.5 Mobilization of P&M, set up of office & B/P 1 LS
3 Viaduct
3.1 Pile - 1000 dia - Concrete #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.2 Pile Cap #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.3 Pier #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.4 Crash Barrier #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.5 Portal Girder #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.6 Pier Cap #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.7 Precast Segment
a. Casting #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
b. Erection #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.8 Precast I Beam
a. Casting #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
b. Erection #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.9 Parapet
a. Casting #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
b. Erection #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.10 Rebar #REF! MT #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.11 HT Strand with erection #REF! MT #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.12 Structural Steel #REF! MT #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.13 Ramp Concrete #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.14 CLC Special Span #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.15 Rebar in Special Span #REF! MT #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.10 HT Strands in Special Span #REF! MT #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.12 Misc. work in the Viaduct 1 LS 1 0.20 0.20 0.20 0.20 0.20
4 Stations
4.1 Pile - 1000 dia - Concrete #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4.2 Pile Cap #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4.3 Open Foundation for Piers #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4.4 Crash Barrier #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4.5 Pedestral & Column #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4.6 Other Concrete in stations #REF! Cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4.7 Rebar in Station #REF! MT #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4.8 HT strands in station #REF! MT #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4.9 Finishing items in Station 1 LS 1 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11
Total Rebar #REF! MT #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Total HT Strand #REF! MT #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Structural steel #REF! MT #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Finishing Item 2 LS 2 0 0 0 0 0 0 0 0 0 0 0
Total Concrete (cum) #REF! cum #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Monthly Value of Work(Rs. in Lakhs)
From Cashflow-A sheet to directly in Cashflow sheet
Total Turnover
Projected
32325
Distribution of Cost
1 Direct Materials
Cement 417 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Reinforcement steel & HT strand 481 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Structural steel 37 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Aggregate & sand for concrete 270 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Other materials 1176 1176 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31
2381 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Projected 2381 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2 Enabling works
3 Formwork (shuttering & staging) 335 335 42 42 42 42 42 42 42 42
335 335 42 42 42 42 42 42 42 42
Projected to Match 393 393 49 49 49 49 49 49 49 49
4 Labour Contracts & Sub Contracts
Concrete works #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Rebar & HT Strand work #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Structural Work #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub Contract - Priliminary Work #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub Contract - Piling Work #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub Contract - DSR & NDSR Items #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Total #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Projected to Match 3953 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
ESCALATION % CONSIDERED FOR DIFFERENT COMPONENT
ESCALATION PAYABLE
Materials : Per Annum
Cement 12.0% INR #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Rebar ,Strl Steel 15.0% INR #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Agreegates & boulder 8.0% INR #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Misc 8.0% INR 168 6 6 7 7 7 8 8 9 9 10 10 10 11 11 12 12 13 13
Labour
Supervisory staff 10.0% INR #REF! 0 0 1 1 2 2 2 3 3 3 4 4 4 5 5 6 6 6 7 7 7 7 7 7 #REF! #REF! #REF! #REF! #REF! #REF!
Labour- Operator & Helper 10.0% INR #REF! 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 #REF! #REF! #REF! #REF! #REF! #REF!
Labour Contract & direct labour 10.0% INR #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Contracts : 8.0% INR #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
POL & Power & GTE :
Fuel 10.0% INR #REF! 0 0 1 1 1 2 2 3 3 3 4 4 4 4 3 4 4 4 4 4 4 4 3 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
GTE 8.0% INR #REF! 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
External Hire of Equipment 8.0% INR #REF! 0 0 0 1 1 1 2 2 2 2 3 3 3 3 2 2 3 3 3 3 2 2 2 1 #REF! #REF! #REF! #REF! #REF! #REF!
Total Escalation #REF! L
ESCALATION USING FORMULA GIVEN IN TENDER DOC.
Actual labour 16% L1 212.76 214.52 216.28 218.03 219.79 221.55 223.31 225.07 226.83 228.58 230.34 232.10 233.86 235.62 237.38 239.13 240.89 242.65 244.41 246.17 247.93 249.68 251.44 253.20 254.96 256.72 258.48 260.23 261.99 263.75
Labour component 17% Lo 211
Total Escalation in Labour
Actual cement 6% C1 168.57 170.24 171.91 173.58 175.25 176.91 178.58 180.25 181.92 183.59 185.26 186.93 188.60 190.27 191.94 193.60 195.27 196.94 198.61 200.28 201.95 203.62 205.29 206.96 208.63 210.29 211.96 213.63 215.30 216.97
Cement Component 15% Co 167
Total Escalation in Cement
Actual steel 14% S1 173.95 176.10 178.24 180.39 182.54 184.69 186.83 188.98 191.13 193.28 195.42 197.57 199.72 201.87 204.01 206.16 208.31 210.46 212.60 214.75 216.90 219.05 221.19 223.34 225.49 227.64 229.78 231.93 234.08 236.23
Steel 20% So 172
Total Escalation in Steel
Actual Bitumen B1 44,741 45,111 45,480 45,850 46,220 46,590 46,959 47,329 47,699 48,069 48,438 48,808 49,178 49,548 49,917 50,287 50,657 51,027 51,396 51,766 52,136 52,506 52,875 53,245 53,615 53,985 54,354 54,724 55,094 55,464
Bitumen 5% Bo 44371
Total Escalation in Bitumen
Actual POL (considering fuel for aggregate) 8% F1 48 48 48 49 49 50 50 50 51 51 51 52 52 53 53 53 54 54 55 55 55 56 56 57 57 57 58 58 59 59
POL 5% Fo 47
Total Escalation in POL
P1 134 134 135 136 137 138 139 140 141 142 142 143 144 145 146 147 148 149 150 150 151 152 153 154 155 156 157 157 158 159
Plant & Machinery spares 18% Po 133
Total Escalation in P & m spares
M1 164 165 166 167 169 170 171 172 173 174 175 176 177 178 179 180 182 183 184 185 186 187 188 189 190 191 192 194 195 196
Other Materials 20% Mo 163
Total Escalation in other Material
Total escalation recievable L
ID Description Check Quantity
Page 417 of 430
Tender no: Div 2/044/13 Cumulative>= #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Project :
Monthly>= #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
CASHFLOWSTATEMENT TOTAL Check DLP
Sl.
No.
FTS It.
No.
Description
AMOUNT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
33,295.03
RECEIPTS :
1 MOBILISATION ADVANCE 1664.75 832.38 832.38
2 PLANT ADVANCE - 1664.75 1664.75
3 SECURED ADVANCE 964.16 964
4 MONTHLY R.A. BILLS 32325.27 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
5 RECOVERY OF MOBILISATION ADVANCE -1664.75 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
6 RECOVERY OF PLANT ADVANCE -1664.75 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
7 RECOVERY OF SECURED ADVANCE -964.16 -964
8 RETENTION FROM BILL #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
9 RELEASE OF RETENTION
10 DEDUCTION OF INCOME TAX AT SOURCE -688.53 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
11 CREDIT OF INCOME TAX AT SOURCE 688.53 688.53
12 DEDUCTION OF WC TAX AT SOURCE -646.51 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
13 CREDIT OF WC TAX AT SOURCE 646.51 646.51
MONTHLY RECEIPTS : 32325.27 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 1335.03
PAYMENTS :
1 A.01 STAFF - INDIAN 1218.89 #REF! 9.89 20.36 26.98 32.01 36.28 37.93 37.93 38.19 38.19 38.19 38.19 38.19 38.19 40.65 41.73 41.73 41.73 42.25 42.25 42.25 42.25 40.81 36.73 36.73 #REF! #REF! #REF! #REF! #REF! #REF!
2 A.02 STAFF - EXPAT #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3 A.03 INDIRECT LABOUR 208.86 #REF! 1.70 3.49 4.62 5.48 6.22 6.50 6.50 6.54 6.54 6.54 6.54 6.54 6.54 6.97 7.15 7.15 7.15 7.24 7.24 7.24 7.24 6.99 6.29 6.29 #REF! #REF! #REF! #REF! #REF! #REF!
4 A.04 SITE ESTABLISHMENT 697.78 34.89 139.56 139.56 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21 14.21
5 A.05 INSURANCE 355.71 177.86 177.86
6 A.06 BONDS 183.18 183.18
7 A.07 INTEREST ON ADVANCE #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
8 A.08 BANK CHARGES -458 8.75 3.75 6.88 13.13 18.44 18.44 18.44 18.44 18.44 18.44 23.44 24.06 27.81 29.06 31.56 31.56 31.56 31.56 29.69 29.38 25.00
9 A.09 TAXES 2496.00 2496
10 A.10 DESIGN & PROFESSIONAL SERVICES
11 B.01 LOCAL MATERIALS ( DM )
12 i) CEMENT 417.43 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
13 ii) REBAR & HT Strand 480.68 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
14 iii) STRUCTURAL STEEL 36.64 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
15 iv) BITUMEN
v) AGGREGATES 197.07 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
16 vi) FINE SAND INCL ROYALTY 73.39 73
17 vii) GABION BOX
18 viii) REMAINING OTHERS 1175.54 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31 65.31
19 B.02 IMPORTED MATERIALS
20 B.03 ENABLING WORKS 58.13 58
21 B.04 SHUTTERING & STAGING MATERIAL 335.18 41.90 41.90 41.90 41.90 41.90 41.90 41.90 41.90
22 B.05 LABOUR CONTRACT (PRW) 589.72 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
23 B.06 SUB-CONTRACT 3363.13 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
24 B.07 PLANT
25 i) CAPITAL COST - PLANT ONLY 149.05 24.84 24.84 24.84 24.84 24.84 24.84
26 ii) DEPRICIATION/ INT.HIRE - OLD PLANT 159.92 #REF! 0.02 0.14 3.51 4.09 4.23 5.15 5.24 5.24 5.88 5.88 5.99 5.99 5.99 5.99 5.99 5.99 5.99 5.99 5.99 5.99 5.99 5.33 2.86 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
27 iii) EXTERNAL HIRE CHARGES 711.80 #REF! 0.20 11.50 21.20 26.00 28.40 33.35 34.45 35.65 35.65 35.65 35.65 35.65 33.45 33.45 22.55 22.55 22.55 22.55 22.55 20.15 14.75 14.75 14.75 4.80 #REF! #REF! #REF! #REF! #REF! #REF!
28 iv) PLANT MAINTENANCE 74.37 #REF! 0.01 0.06 1.63 1.90 1.97 2.39 2.44 2.44 2.73 2.73 2.78 2.78 2.78 2.78 2.78 2.78 2.78 2.78 2.78 2.78 2.78 2.48 1.33 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
29 v) WEAR PARTS 65.37 #REF! 0.01 0.06 1.43 1.67 1.73 2.10 2.14 2.14 2.40 2.40 2.45 2.45 2.45 2.45 2.45 2.45 2.45 2.45 2.45 2.45 2.45 2.18 1.17 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
30 vi) RESIDUAL VALUE - NEW PLANT -85.85 -85.85
31 B.08 POL 421.77 #REF! 0.11 5.63 11.96 14.56 15.79 18.63 19.20 19.78 20.09 20.09 20.14 20.14 19.08 19.08 13.81 13.81 13.81 13.81 13.81 12.65 10.03 9.71 8.52 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
32 B.09 PLANT MOB & DE-MOB 50.15 12.54 12.54 12.54 12.54
33 B.10 PLANT LABOUR/OPERATOR 64.08 #REF! 0.01 0.05 1.41 1.64 1.69 2.06 2.10 2.10 2.35 2.35 2.40 2.40 2.40 2.40 2.40 2.40 2.40 2.40 2.40 2.40 2.40 2.13 1.15 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
34 C.01 GTE 323.25 #REF! 0.08 4.32 9.16 11.16 12.10 14.28 14.72 15.16 15.40 15.40 15.44 15.44 14.62 14.62 10.58 10.58 10.58 10.58 10.58 9.69 7.69 7.44 6.53 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
35 C.02 LABOUR CESS 323.25 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
36 C.03 PRICE INFLATION 646.51 647
37 C.04 RISK & BENEFIT COSTS #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
38 C.05 DLP PROVISION 64.65 64.65
39 C.06 PROVISIONAL SUMS
40 C.07 OTHERS (SPECIFY) #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
41 D.01 PROJECT CONTINGENCY 161.63 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
42 D.02 ADDITIONAL CONTINGENCY 646.51 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
43 E TENDER ADJUSTMENT
44 F.01 OVERHEAD -ITD CEM 1293.01 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
MONTHLY PAYMENTS : 30385.75 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! -8.66
MONTHLY SURPLUS ( + ) / DEFICIT ( - ) #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 1344
CUMULATIVE SURPLUS(+)/ DEFICIT(-) 1939.52 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Civil works for 3 x 800 MWGadarawara Power plant, M.P.
DMRC Elevated Packages All amounts in ` Crores
Submit Open bid Submit Open bid Submit Open bid
Packages=> BC21 Jaipur C1 10/27/2010 Jaipur C2 10/27/2010 10/31/2011 CC06 1/13/2012
Client's
Estimate
Bid
amount
%
variation
Client's
Estimate
Bid
amount
% variation Client's
Estimate
Bid
amount
% variation Client's Estimate Bid
amount
% variation
150 215 400
L1 Quote ITD JV 189 #DIV/0! DSC 161 7.3% ITD JV 228 6.0% L&T 380 -5.0%
L2 Quote #DIV/0! NCC 169 12.7% NCC-Jkumar 232 7.9% HCC-JMC 381 -4.8%
L3 Quote #DIV/0! Jkumar 176 17.3% L&T 237 10.2% Afcon 392 -2.0%
L4 Quote #DIV/0! Afcons 189 26.0% DSC 238 10.7% BLK-CRBG 393 -1.8%
L5 Quote #DIV/0! ITD JV 191 27.3% HCC 247 14.9% IJM-NCC 399 -0.3%
L6 Quote #DIV/0! L&T 196 30.7% Lanco 400 0.0%
L7 Quote #DIV/0! HCC 222 48.0% Gammon 402 0.5%
L8 Quote simplex 405 1.3%
L9 Quote Samsung-Soma 419 4.8%
L10 Quote ITD JV 468 17.0%
L11 Quote
L12 Quote
Nos.of Station 5.00 Nil Nil Nil
Total Viaduct Length 7400 m 5682 m 6071m 13158m
Submit Open bid Submit Open bid Submit Open bid Submit
3/12/2012 CC15 4/20/2012 3/14/2012 CC17 4/4/2012 5/9/2012 CC26 6/19/2012 9/26/2012 CC26R
Client's
Estimate
Bid
amount
% variation Client's
Estimate
Bid
amount
% variation Client's
Estimate
Bid
amount
% variation Client's
Estimate
Bid
amount
%
variation
400 255 537 537
Afcons 371 -7.3% L&T 266 4.3% IJM-UEMB JV 529 -1.5% ITD-ITD Cem 332.95 -38.0%
ITD JV 385 -3.8% Afcons 267 4.7% Jkumar-MMS 552 2.8% -100.0%
Unity-Sacyr 398 -0.5% Jkumar-MMS 298 16.9% JMC-CHEC 575 7.1% -100.0%
L&T 406 1.5% JMC-CHEC 313 22.7% Unity-Sacyr 576 7.3% -100.0%
JMC-CHEC 439 9.8% simplex 320 25.5% Afcons 578 7.6% -100.0%
Jkumar-MMS 457 14.3% Gammon 335 31.4% Gammon 596 11.0% -100.0%
IJM-UEMB JV 480 20.0% Simplex 630 17.3% -100.0%
Gammon 499 24.8% L&T 657 22.3% -100.0%
11037.00 11067.00
6.00
7285.00
8.00 8.00

You might also like