costing for gate culvert, 600mm Dia, 10m long

S/No item Description Qty


1 rebar T16 rebar 2
2 concrete C25 7.1
3 excavation Inclusive of 30m on inlet side and 150m on outlet 172
4 backfilling 10.6
5 formwork 54
6 Hardcore 9
add 20% for profits
Total Amount in KSh
Total
Units Unit rate Amount in KSh
MT 145000 290,000.00
m3 28000 198,800.00
m3 600 103,200.00
m3 300 3,180.00
m2 1200 64,800.00
T 2200 19,800.00
679,780.00
815,736.00
815,736.00
Total