32/33 ME-101 (AMINE FILTER PACKAGE START UP)

IES-5 key for the PLC should be on auto



All KVS should be on auto

Push initialization button from field will start V-108 & V-113 filling.

As V-108 LSH activate P-108 will start in circulation(Water recycling)

Now load 45 kg of cellulose.

Wait until LSH activation on V-113

Now we can start cycle

Give start permissive from DCS (HS-7128)

Keep FV-1774 & FV-1775 on manual with sum of FZI more than 50 %.

Start cycle from Field.

After 20 min sequence will go for filling F-106.

As LSH-2712 on F-106 activate will go on pre coating for 1 hr.

At the end of pre coating cycle will go on filtration.

Set FIC-1774 at SP 115 M3/hr. and FV-1775 at SP 30 M3/hr.





KVS POSITION ON EACH STEP
FILTRATION KV7761,KV7764
AMINE DRAIN KV7766,KV7772
WATER TANK FILLING KV7770 ,KV7760
F106 BACK WASHING KV7768,KV7769,KV7765
PRECOAT TANK V108 FILLING KV7760
WATER RECYCLING KV7773,7767
HOMOGENISATION KV7773,KV7767
FILTER F106 FILLING KV7773,KV7767
RECYCLING(PRE-COATING) KV7762,KV7769,KV7763
FILTER FILLING KV7767,KV7762,KV7763

FAULT ALARMS IN FILTER
PACKAGE
KVS FAULT XA7746
LEVEL SWITCHES FAULT XA7747
P-108 FAULT XA7748
P-116 FAULT XA7749
FM-106 FAULT XA7750