The document provides status updates for several vessels:
1. Both main engine heat exchangers on the STI Saturn were recently cleaned and serviced, with port temperatures around 1200C and starboard around 1500C.
2. The Navimar 7 is scheduled for a special survey window from June 21st to September 21st and an extension will be requested in August.
3. Several repairs and services were completed for the STI T1 last week, including gyro annual service, renewal of the power unit, supplying a new EPIRB, and calibration testing.
The document provides status updates for several vessels:
1. Both main engine heat exchangers on the STI Saturn were recently cleaned and serviced, with port temperatures around 1200C and starboard around 1500C.
2. The Navimar 7 is scheduled for a special survey window from June 21st to September 21st and an extension will be requested in August.
3. Several repairs and services were completed for the STI T1 last week, including gyro annual service, renewal of the power unit, supplying a new EPIRB, and calibration testing.
The document provides status updates for several vessels:
1. Both main engine heat exchangers on the STI Saturn were recently cleaned and serviced, with port temperatures around 1200C and starboard around 1500C.
2. The Navimar 7 is scheduled for a special survey window from June 21st to September 21st and an extension will be requested in August.
3. Several repairs and services were completed for the STI T1 last week, including gyro annual service, renewal of the power unit, supplying a new EPIRB, and calibration testing.
last week, found Port- 1200-92c stbd 1500- 85 c under observation. 2. 1 ST Annual Survey-22-jun to 22-dec(GL Class)
Navimar 7 Special Survey window (21-jun to 21 September) BV Class Extension of SS will be request august (next month middle )
STI T1 Last week GYRO Annual service some repairs,power unit renewed,new EPIRB supplied on board tested certificate issued, 15 ppm calibration and test certificate received.
Window SS starting September NK
STI T2 Generator circulation pump repairing done by chief engineer supplied bearings and seal. STBD generator cooler requested ,will be deliver 2 weeks.
Intermediate survey window 17 th June 2014 to dec 2014
Mercury 1.Out board engine ( rescue boat caburator problem),next available entry sharjah will repair. 2.Main engine Thermostat fixing need to next available long stay.
Green ville 15 Greenville 15 new HP laptop supplied and FBB reinstallation carried out, now fbb is working.