You are on page 1of 3

HANDOVER NOTES

Site / Place of Handover : Handil


Department / Service : CST/OPB/SPS
From :I Gede Andi Dipayadnya
Date / Time : 03rd October 2019
To : Rinaldi
CC : Mr. Handy K.

I. HSE Matters

Cermat : - Safety talk: 12 WP Audit: - Safety Drill: -

II. Main events on the Period

4203282 Modification flexible hose at T-3220


4208886 Modification spool of venting line T-3250
7251730 Repair heat insulation at A-6360, as per ISRS
8467303 Assist FO/INS for removal existing insulation at CSU
8478102 Assist FO/INS for pipe inspection under insulation at PPA
(campaign with another WO)
7251006 Modification pipe support for 6”line WD-1, 4, 5 and 7 at T-990
8478046 Internal inspection at test separator 1-V-1140, MWP. A
4211562 Removal last spool of PK.J-4 for Xmas tree re orientation, SWP-
J, Peciko Field.

III. Work in Progress and Today Activities

 PPA, RTI

4211651 Assist MNP/IS for re-instate FCV-4512, Condensate Transfer Pump


Status: The job will be started today, after lunch by Ajmal’s team due to working on
night shift.

4200182 Repair and reconditioning support of Flare-B


Status: Welding activity for N.22, completed, in progress for touch up painting.
Remaining:
N.15/N.16 Continue for re-fabricate (cutting and grinding activity)
N.17 Continue install stiffner
N.19/N.21 Continue for install bracing and stiffner
N.20 Continue for welding bracing
N.23 Continue for welding stiffner
Note: The job supervised by Mr. Supadiono
8478220 INS-VES-1 FWKO-A /IN-MAJ
Status: Activity re-started on 27th August 2019 and supervised by Mr. Agung BS.
Install scaffolding, completed 3 of 3 ea. Spading activity completed 2 of 4 ea.
Remaining: Postponed, FWKO-A put back on service.
Note: Need for revised operguide due to unable to install 12”#600 rated spade at
12”inlet. Waiting for further confirmation.

 TPA TLA and CSU

7240480 INS_PIP_REP Replacement pipe spool PWT line to jetty and camp
Status:
- Replacement leaking section of PWT line at sheet 2 of 3, done.
- Replacement leaking section of PWT line at sheet 3 of 3, partially done.
Remaining:
- One section of 3”PWT line to jetty at sheet 3 of 3, can not be done due to deep
burried by another pipe. Further assesment and methodological is needed. See
attached drawing for your details.
Note:
Demobilization and housekeping will be done, Today. (after lunch)

IV. High Priority Job to be done in forthcoming days


 PPA RTI
7250366 Replace corroded RTJ gasket
8478221 INS-VES-1-FWKO-B/IN-MAJ
8478025 INS-VES 7-V-2520/IN-MAJ
8478031 INS-VES 7- H-2560/IN-MAJ
8441645 INS-VES 1-E-4250/IN-MAJ (Chiller Gas Train A)
 TLA TPA CSU
4211658 Install spade for automatic sampler removal at OMS (04 oct)
4208846 Re route 2”line from T-3030 to T-3060
7249124 Perform welding for crack repair
7251313 Modification tundish WD no. 5 and WD no. 8, T-990
4208845 Re-route settling tank over flow to T-3060
V. Pending Job and to be solved

Pending Job
7220143 INS-REP 3” oily water warm separator

Awaiting Material

Awaiting Confrmation
7240202 Replace leaking 8”condensate line (DGS)

Awaiting Procedure and OperGuide

Awaiting shutdown and window

Awaiting Study

VI. Miscellaneous Items

- Radio 1464 and HP at the office deck,


- Return to SPS on 17th October 2019

VII. Signature of Leaving Personnel Signature of Incoming Personnel

( I Gede Andi Dipayadnya ) ( RINALDI )

You might also like