HANDOVER NOTES

Site / Place of Handover : Handil


Department / Service : CST/OPS/SOU-HDL
From : Andriadi
Date / Time : 31 Oktober 2006
To : Tommy W
CC : Mr. Bambang S. / Mr. Entjo Sudjana,
Manja Lifa / Ery M / Arief R.

I. HSE Matters
At 29th Oktober 2006, CPM Crew has been demobilized from HY Cluster (Job item
60345/H) due to incomplete equipment check list, such as:
- No ELCB at welding machine.
- Bad Electrical fitting.
- Fire extinguisher was expired
- Bad Chain block condition and color code.
- Bad color coding of compressed cylinder.
- PPE.

II. Work In progress and Today Activities

II. 1. Item 60345/H HY1 Outlet Manifold Replacement

Status :
- Spool 6”-E10-L-30.06 (LP Outlet HY1 Manifold) has been finished.
- Continue welding to replace spool 6”-E10-L-30.07 (MP Outlet HY1 Manifold).
- Spool 6”-E10-L-30.08 (LP Outlet HY1 Manifold) is not done yet.

Crew : Ahmad Yani


LCT : Sinar Harapan Makmur 7
Speed boat : Tanjung Pegah

III. Main Events On the Period.

III.1. Item 60424/H Install temporary platform at HYA

Status : Remaining remove temporary platform.

III.2 Item 60366/H 6"LP Corroded Line Replacement at HL 03/04 MAN.

Status : Completed.

IV. Height Priority Job to be done in forthcoming days


- Nil
V. Pending Job and to be solved

- Nil

VI. Miscellaneous Items

- Nil

VII. Signature of Leaving Personnel Signature of Incoming Personnel

( Andriadi ) ( Tommy W )

“Selamat Bekerja dan Semoga Selalu Dalam Lindungan Allah SWT”