HANDOVER NOTES

Site / Place of Handover : Handil


Department / Service : CST/OPB/HDL
From :I Gede Andi Dipayadnya
Date / Time :29 November 2012
To : Agus D.L
CC : Mr. Sentot H./ Mr. Sri Widadi

I. HSE Matters

ALWAYS REMINDER ALL OF THE CREW ABOUT ZERO TOLERANCE CAMPIGN

II. Work In progress and Today Activities


Item. 12714C
Replacement various nozzle at V-585
Status:
- Replacement various flange nozzle, 8 ea
- NDT
Remaining:
- Pre-test and preparation for hydrotest
- Hydrotest, witnessed by MIGAS.
- De spading
- Leak test
- Dismantle scaffolding
Progress reported: %

III. Main Events on the Period.

Item. 12944H
Repair corroded structure at HLB 03 Manifold
Status:
Completed

Item. 12941H
Repair structural and doubler of 8 bracing at HLB-179
Status:
Completed

Item. 12940H
Repair structural and doubler at HLB 02 Manifold
Status:
Completed

Item. 12937H
Repair and doubler structural at HLB-079
Status:
Completed

Item. 12939H
Repair and doubler structural and 20 leg pile at HLB-168
Status:
Completed

Item. 12-1283H
Scaffolding job at KERBAU-1 and install name plate
Status:
Completed

Item. 12117H
Install water filter F-7700 at HV cluster
Status:
- Water filter F-7700 already erected so CPA/MNT can perform their job
- Currently, CPA/MNT performing checking and repairing at several items as per previous
list.
- Once CPA/MNT completed their job, water filter F-7700 will be installed, assisted by: TB.
Megawati 114. This item will be done by Mr. Rudis team.

Item. 12-102C
Assist CPA/INS for internal inspection of V-585
Status:
Completed

IV. High Priority Job to be done in forthcoming days


Coordinate with site planner.

V. Pending Job and to be solved


NIL

VI. Miscellaneous Items

- Contractors team under PT. Meindo, Foreman: Afrizal


- MOP LCT. Logindo Pelican will be valid until 30 NOV 2012

VII. Signature of Leaving Personnel Signature of Incoming Personnel

( I Gede Andi Dipayadnya ) ( Agus DL )