RATE ANALYSIS

Extra Item
Stone Shifting
ITEM DESCRIPTION:
Shifting of the Marble/Granite Stone from inside of the site premises to the Gate No-03 scrap yard. The Item includes the necessary lifting, Shifting and unloading
of the same at the designated place. The Scope includes the incurred transporation and protection of the stone stacking's with the protection sheet. The
measureable area will be each stone size. The Material Cost of the protection will be paid seprately as per actual consumption.Further fencing or barrication will
be paid as per actual.

S.No
B

Description
Granite/Marble Shifting

Working
(4200)/(1300/10.76)

Unit
Sqm

Qty

Rate

Amount

34.76

34.76

As per Attached
Quotation

P& M Char ges


Electricity Charges-3%
Water Charges-2%
Sub Total
Contr actor Over heads & Pr ofit-20%
Sub Total
WCT-4.2%
Gr and Total
Rate Per Sqm

Remarks

1.04
0.70
7.30
43.80
1.86
45.66
46.00