You are on page 1of 7

BOQ Civil 1/7

PT. PLN (Persero)

Quantity of Materials Supply & Installation Works (Bill of Quantity)


Java- Sumatra Interconnection Transmission Line Project
Package 1 : 500 kV AC/DC Converter Stations and Substations
Quantities for Bidding Purpose only, Quantities shall be adjusted to meet actual requirement during construction.
Payment
Items No. Code Description Quantity Unit Remarks
Adjustment

Schedule No.4: Installation and Other Services

Muara Enim Converter Station in Sumatra

Earthwork
C S C Ert C1 - 101 Removal of surface bush, plant, tree and top soil to disposal area 630,000 m2 unit price disposal area shall be located inside the site
C S C Ert C1 - 102 Earth cutting for transition and embankment (V1) 1,737,000 m3 unit price
C S C Ert C1 - 103 Earth cutting, separating and removal of un-used soil to disposal area 996,000 m3 unit price disposal area shall be located outside the site
C S C Ert C1 - 104 Embankment and compacting soil for leveling by usable soil ( from V1 ) 1,563,300 m3 unit price Design elevation : 88 meter
C S C Ert C1 - 105 Embankment and compacting for leveling by using imported soil 173,700 m3 unit price to make suitable soil by mixing with soil from outside
C S C Ert C1 - 106 Removal of boulders for disposal, removal to disposal area 0 m3 unit price
C S C Ert C1 - 107 Removal of boulders and broken down for reusing at site 0 m3 unit price including treatment of remained material for reuse
C S C Ert C1 - 108 Additional excavation for removal of boulders 0 m3 unit price
C S C Ert C1 - 109 Observation system of settlement 2 point --- to be included in relevant items

Slope work
C S C Slp C1 - 201 Slope protection by seed spraying (for cut slope) 37,500 m2 unit price Drain system shall be included in item C1-703
C S C Slp C1 - 202 Slope protection by sod facing (for embankment slope) 21,500 m2 unit price Drain system shall be included in item C1-703

Site Finishing 374,500


C S C Fin C1 - 301 Earth System (earth grid) over the station 62,000 m unit price Mesh Grid by strip cooper (IEEE 80-2000)
C S C Fin C1 - 302 Surface raking after top soil removal 430,000 m2 unit price
C S C Fin C1 - 303 Leveling prior to laying of surface material 430,000 m2 unit price
C S C Fin C1 - 304 Weed killer spreading 345,000 m2 unit price
C S C Fin C1 - 305 Laying and rolling of gravel or crushed stone (thickness 150mm) 345,000 m2 unit price

Survey and Testing


C S C Oth C1 - 401 Topographic survey ( Before & after commencement of works ) 1 lot --- to be included in relevant items
Soil investigation as per Technical Specification ( Drilling : L25m x 24, 48
C S C Oth C1 - 402 600 m unit price
samples)
C S C Oth C1 - 403 Pumping test as per Technical Specification 2 point unit price
C S C Oth C1 - 404 Water quality analysis as per Technical Specification 8 point unit price
C S C Oth C1 - 405 Embankment test including soil test 2 point --- to be included in relevant items

Civil Structures
2 m height retaining wall for protect land slide for 3 x
C S C Str C1 - 501 Concrete Block Retaining walls 400 m unit price
dead end towers
C S C Str C1 - 502 Cable ducts/trenches for electrical wire and OF N/A --- to be included in Material Cost for related equipment
C S C Str C1 - 503 PC (Prestressed Concrete) Piling works Type 1 ( Extra Heavy Equipment ) 6,220 m unit price pile diameter 600 mm
C S C Str C1 - 504 PC (Prestressed Concrete) Piling works Type 2 ( Heavy Equipment ) 4,140 m unit price pile diameter 400 mm
PC (Prestressed Concrete) Piling works Type 3 ( Building, structure water
C S C Str C1 - 505 92,160 m unit price pile diameter 300 mm
tank, etc )
C S C Str C1 - 506 Trial mix test of the concrete grades 1 lot --- to be included in relevant items
C S C Str C1 - 507 Quality control test of the concrete 1 lot --- to be included in relevant items

Road Construction
C S C Rod C1 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 46,333 m2 unit price Refer to Drawing No. P1-CS-PG-01
C S C Rod C1 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 1,693 m2 unit price Refer to Drawing No. P1-CS-RO-01
C S C Rod C1 - 603 Curb and Road Drainage for every road side 17,433 m unit price Refer to Drawing No. P1-CS-RO-01, P1-CS-PG-01
C S C Rod C1 - 604 Upgrading and reinforce permanent access road 5,309 m2 unit price including water pass 6 pipe x 0.5 meter (dia.)
C S C Rod C1 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 5,309 m2 unit price Refer to Drawing No. P1-CS-RO-01

Drainage and Water Supply System


C S C Dsy C1 - 701 Blind Drain Dia 300 mm 2,000 m unit price Drain system for water flow by the original river
C S C Dsy C1 - 702 Blind Drain Dia 1000 mm 0 m unit price Drain system for water flow by the original river
Drainage system for slope protection, horizontal & vertical trench with drain
C S C Dsy C1 - 703 5,000 m unit price Including water pits, similar to X-Bogor
box
C S C Dsy C1 - 704 Reservoir E and F with water gate to flush out sedimentation 30,000 m3 unit price E : 5,000m3, F : 25,000m3
C S C Dsy C1 - 705 Concrete 0pen channel drainage system around Station boundary 3,100 m unit price W2.0m x L3100m with 15 water pits ( 3m x 3m )
Similar to Drawing " Civil Work X-Bogor CS Drainage
C S C Dsy C1 - 706 Drainage pipe system for station area (connect to French drainage system) 1 lot fixed price
System (4)"
C S C Dsy C1 - 707 Water storage tank (2000m3 each) 2 set fixed price Refer to Drawing No. P1-CS-DW-03
C S C Dsy C1 - 708 Water Supply System 1 lot fixed price Refer to Drawing No. P1-CS-DW-03
Refer to Drawing No. P1-CS-DW-05 ( in Price Sch,
C S C Dsy C1 - 709 Fire Fighting System 1 lot fixed price
No1 )
C S C Dsy C1 - 710 Deep Well 1 lot fixed price Refer to Drawing No. P1-CS-DW-03
C S C Dsy C1 - 711 Oil drain and Oil Pit system for transformers 1 lot fixed price
C S C Dsy C1 - 712 Water Supply System test --- --- to be included in relevant items
C S C Dsy C1 - 713 Fire Fighting System test --- --- to be included in relevant items

Fencing and Gate


C S C Fec C1 - 801 Concrete panel fence ( for land boundary ) 4,035 m unit price Refer to Drawing No. P1-CS-FG-01
C S C Fec C1 - 802 Mesh fence ( for station boundary ) 2,954 m unit price Refer to Drawing No. P1-CS-FG-01
C S C Fec C1 - 803 Entrance main gate 1 lot fixed price Refer to Drawing No. P1-CS-FG-01
C S C Fec C1 - 804 BRC Protection fence and gate (for equipment boundary) 2,480 m unit price 10xNR, 10xACF, 2xDCF, 10xDC switchgear

Building Works, Outdoor Lighting, Security System & Finishing


C S C Bil C1 - 901 Guard house 1 lot fixed price
C S C Bil C1 - 902 Warehouse for DC station 1 lot fixed price
C S C Bil C1 - 903 Water pump house 2 set fixed price
C S C Bil C1 - 904 Fire pump house 2 set fixed price
C S C Bil C1 - 905 Emergency generator house 1 lot fixed price
C S C Bil C1 - 906 Converter valve hall 1 lot fixed price Including High and Low for two (2) Polar
C S C Bil C1 - 907 Main Control Building for HVDC 1 lot fixed price
C S C Bil C1 - 908 Administration building 1 lot fixed price
C S C Bil C1 - 909 Laboratory and training building 1 lot fixed price
C S C Bil C1 - 910 High Voltage Testing Building 1 lot fixed price
C S C Bil C1 - 911 Garage house 1 lot fixed price "5 cars and 1 truck" for one house
C S C Bil C1 - 912 20kv switchgear building 1 lot fixed price including 275kV
C S C Bil C1 - 913 Bay control house 6 set unit price

Package 1 : Java - Sumatra Interconnection Transmission Line Project


500kV AC/DC Converter Stations and Substations JICA ODA Loan No. IP-556
BOQ Civil 2/7
PT. PLN (Persero)
Payment
Items No. Code Description Quantity Unit Remarks
Adjustment
C S C Bil C1 - 914 Control Building for 275 kV 1 lot fixed price
C S C Bil C1 - 915 Ware house for 275kV 1 lot fixed price
C S C Bil C1 - 916 Emergency generator house for 275 kV side 1 lot fixed price
C S C Bil C1 - 917 Workshop for 275kV 1 lot fixed price
C S C Bil C1 - 920 Outdoor Lighting 1 lot fixed price Refer to Drawing No. P1-CS-OL-01
C S C Bil C1 - 921 Paving in station 408 m2 unit price Refer to Drawing No. P1-CS-PG-01
C S C Bil C1 - 922 Parking and facilities 413 m2 unit price Refer to Drawing No. P1-CS-PG-01
C S C Bil C1 - 923 Gardening and Landcaping 26,294 m2 unit price Refer to Drawing No. P1-CS-PG-01
C S C Bil C1 - 924 Gravel in station 0 m2 unit price to be included in item C1-305
C S C Bil C1 925 Security System 1 lot fixed price Refer to Drawing No. P1-CS-SS-01

Site Setting Out and Temporary Works


C S C Sit C1 - 001 Reinforcement, repair and expansion of transportation road, bridge, etc 1 lot fixed price
C S C Sit C1 - 002 Removal and recover the obstructive structure in transportation road 1 lot fixed price
C S C Sit C1 - 003 Batching plant for concrete work 1 lot --- to be included in relevant items
C S C Sit C1 - 004 Temporary Security Gate House (15m2) including necessary facilities 1 lot --- to be included in relevant items
C S C Sit C1 - 005 Temporary Employer's site office (200m2) including necessary facilities 1 lot --- to be included in relevant items
C S C Sit C1 - 006 Temporary road (Penetration Macadam Road, width: 6m) 1 lot --- Contractor's responsible

X-Bogor Converter Station in Java

Earthwork
C J C Ert C2 - 101 Removal of surface bush, plant, tree and top soil to disposal area 290,000 m2 unit price disposal area shall be located inside the site
C J C Ert C2 - 102 Earth cutting for transition and embankment (V1) 1,590,000 m3 unit price
C J C Ert C2 - 103 Earth cutting, separating and removal of un-used soil to disposal area 66,000 m3 unit price disposal area shall be located inside the site
C J C Ert C2 - 104 Embankment and compacting soil for leveling by usable soil (V1) 1,585,000 m3 unit price
C J C Ert C2 - 105 Embankment and compacting for leveling by using imported soil 475,000 m3 unit price to make suitable soil by mixing with soil from outside
C J C Ert C2 - 106 Removal of boulders for disposal, removal to disposal area 20 m3 unit price
C J C Ert C2 - 107 Removal of boulders and broken down for reusing at site 140 m3 unit price including treatment of remained material for reuse
C J C Ert C2 - 108 Additional excavation for removal of boulders 420 m3 unit price
C J C Ert C2 - 109 Observation system of settlement 2 point --- to be included in relevant items
C J C Ert C2 - 111 Bench cutting and prepare land of Dead End Towers ( 3 towers ) 6,000 m3 unit price 3 towers ( 40m x 40m land to be flatted )
C J C Ert C2 - 112 Embankment and compacting for leveling for Tower 4,800 m2 unit price 3 towers ( 40m x 40m land to be flatted )

Slope work
C J C Slp C2 - 201 Slope protection by seed spraying (for cut slope) 54,000 m2 unit price Drain system shall be included in item C2-703
C J C Slp C2 - 202 Slope protection by sod facing (for embankment slope) 22,000 m2 unit price Drain system shall be included in item C2-703

Site Finishing
C J C Fin C2 - 301 Earth System for earth grid over the station 62,000 m unit price Mesh Grid by strip cooper (IEEE 80-2000)
C J C Fin C2 - 302 Surface raking after top soil removal 346,500 m2 unit price
C J C Fin C2 - 303 Leveling prior to laying of surface material 346,500 m2 unit price
C J C Fin C2 - 304 Weed killer spreading 235,000 m2 unit price
C J C Fin C2 - 305 Laying and rolling of gravel or crushed stone (thickness 150mm) 235,000 m2 unit price

Survey and Testing


C J C Oth C2 - 401 Topographic survey ( Before & after commencement of works ) 1 lot --- to be included in relevant items
Soil investigation as per Technical Specification ( Drilling : L25m x 24, 48
C J C Oth C2 - 402 600 m unit price
samples)
C J C Oth C2 - 403 Pumping test as per Technical Specification 2 point unit price
C J C Oth C2 - 404 Water quality analysis as per Technical Specification 8 point unit price
C J C Oth C2 - 405 Embankment test including soil test 2 point --- to be included in relevant items

Civil Structures
2 m height retaining wall for protect deadend tower
C J C Str C2 - 501 Concrete Block Retaining walls 200 m unit price
location
C J C Str C2 - 502 Cable ducts/trenches for electrical wire and OF N/A --- to be included in Material Cost for related equipment
C J C Str C2 - 503 PC (Prestressed Concrete) Piling works Type 1 ( Extra Heavy Equipment ) 2,592 m unit price pile diameter 600 mm
C J C Str C2 - 504 PC (Prestressed Concrete) Piling works Type 2 ( Heavy Equipment ) 3,888 m unit price pile diameter 400 mm
PC (Prestressed Concrete) Piling works Type 3 ( Building, structure water
C J C Str C2 - 505 69,120 m unit price pile diameter 300 mm
tank, etc )
C J C Str C2 - 506 Trial mix test of the concrete grades 1 lot --- to be included in relevant items
C J C Str C2 - 507 Quality control test of the concrete 1 lot --- to be included in relevant items

Road Construction
C J C Rod C2 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 33,751 m2 unit price Refer to Drawing No. P1-CJ-PG-01
C J C Rod C2 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 1,855 m2 unit price Refer to Drawing No. P1-CJ-RO-01
C J C Rod C2 - 603 Curb and Road Drainage for every road side 10,058 m unit price Refer to Drawing No. P1-CJ-RO-01 and P1-CJ-PG-01
C J C Rod C2 - 604 Upgrading and reinforce permanent access road 3,035 m2 unit price including water pass 6 pipe x 1 meter (dia.)
C J C Rod C2 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 3,035 m2 unit price Refer to Drawing No. P1-CJ-RO-01

Drainage and Water Supply System


C J C Dsy C2 - 701 Blind Drain Dia 300 mm 5,000 m unit price Drain system for water flow by the original river
C J C Dsy C2 - 702 Blind Drain Dia 1000 mm 2,000 m unit price Drain system for water flow by the original river
Drainage system for slope protection, horizontal & vertical trench with drain
C J C Dsy C2 - 703 8,000 m unit price Including water pits as shown in the drawings
box
A : 11,950m2 (43,048m3), B : 3,200m2 (14,030m3),
C J C Dsy C2 - 704 Reservoir A, B, C and D with water gate to flush out sedimentation 119,774 unit price
C : 10,800m2, (57,830m3), D : 1,800m2 ( 4,836m3)
W2.0m x L200m, W2.5m x L600m, W3.0m x L1500m
C J C Dsy C2 - 705 Concrete 0pen channel drainage system around Station boundary 2,300 m unit price
with 6 pits ( 4m x 4m x 4m )
refer to Drawing " Civil Work X-Bogor CS Drainage
C J C Dsy C2 - 706 Drainage pipe system for station area (connect to French drainage system) 1 lot fixed price
System (4)"
C J C Dsy C2 - 707 Water storage tank (2000m3 each) 2 set fixed price Refer to Drawing No. P1-CJ-DW-03
C J C Dsy C2 - 708 Water Supply System 1 lot fixed price Refer to Drawing No. P1-CJ-DW-03
C J C Dsy C2 - 709 Fire Fighting System 1 lot fixed price Refer to Drawing No. P1-CJ-DW-05
C J C Dsy C2 - 710 Deep Well 1 lot fixed price Refer to Drawing No. P1-CJ-DW-03
C J C Dsy C2 - 711 Oil drain and Oil Pit system for transformers 1 lot fixed price
C J C Dsy C2 - 712 Water Supply System test --- --- to be included in relevant items
C J C Dsy C2 - 713 Fire Fighting System test --- --- to be included in relevant items

Fencing and Gate


C J C Fec C2 - 801 Concrete panel fence ( for land boundary ) 2,972 m unit price Refer to Drawing No. P1-CJ-FG-01
C J C Fec C2 - 802 Mesh fence ( for station boundary ) 2,414 m unit price Refer to Drawing No. P1-CJ-FG-01
C J C Fec C2 - 803 Entrance main gate 1 lot fixed price Refer to Drawing No. P1-CJ-FG-01
C J C Fec C2 - 804 BRC Protection fence and gate (for equipment boundary) 2,480 m unit price 10xNR, 10xACF, 2xDCF, 10xDC switchgear

Package 1 : Java - Sumatra Interconnection Transmission Line Project


500kV AC/DC Converter Stations and Substations JICA ODA Loan No. IP-556
BOQ Civil 3/7
PT. PLN (Persero)
Payment
Items No. Code Description Quantity Unit Remarks
Adjustment

Building Works, Outdoor Lighting, Security System & Finishing


C J C Bil C2 - 901 Guard house 1 lot fixed price
C J C Bil C2 - 902 Warehouse for DC station 1 lot fixed price
C J C Bil C2 - 903 Water pump house 2 set fixed price
C J C Bil C2 - 904 Fire pump house 2 set fixed price
C J C Bil C2 - 905 Emergency generator house 1 lot fixed price
C J C Bil C2 - 906 Converter valve hall 1 lot fixed price Including High and Low for two (2) Polar
C J C Bil C2 - 907 Main Control Building for HVDC 1 lot fixed price
C J C Bil C2 - 908 Administration building 1 lot fixed price
C J C Bil C2 - 909 Laboratory and training building 1 lot fixed price
C J C Bil C2 - 910 High Voltage Testing Building 1 lot fixed price
C J C Bil C2 - 911 Garage house 1 lot fixed price 5 car house and 1 truck house
C J C Bil C2 - 912 20kv switchgear building 1 lot fixed price including 150kV
C J C Bil C2 - 913 Bay control house 6 set unit price
C J C Bil C2 - 914 Control Building for 150 kV 1 lot fixed price
C J C Bil C2 - 915 Ware house for 275kV 1 lot fixed price
C J C Bil C2 - 916 Emergency generator house for 275 kV side 1 lot fixed price
C J C Bil C2 - 917 Workshop for 275kV 1 lot fixed price
C J C Bil C2 - 920 Outdoor Lighting 1 lot fixed price Refer to Drawing No. P1-CJ-OL-01
C J C Bil C2 - 921 Paving in station 797 m2 unit price Refer to Drawing No. P1-CJ-PG-01
C J C Bil C2 - 922 Parking and facilities 413 m2 unit price Refer to Drawing No. P1-CJ-PG-01
C J C Bil C2 - 923 Gardening and Landcaping 47,692 m2 unit price Refer to Drawing No. P1-CJ-PG-01
C J C Bil C2 - 924 Gravel in station 0 m2 unit price to be included in item C2-305
C J C Bil C2 - 925 Security System 1 lot fixed price Refer to Drawing No. P1-CJ-SS-01

SITE SETTING OUT and TEMPORARY WORK


C J C Sit C2 - 001 Reinforcement, repair and expansion of transportation road, bridge, etc 1 lot fixed price
C J C Sit C2 - 002 Removal and recover the obstructive structure in transportation road 1 lot fixed price
C J C Sit C2 - 003 Batching plant for concrete work 1 lot --- to be included in relevant items
C J C Sit C2 - 004 Temporary Security Gate House (15m2) including necessary facilities 1 lot --- to be included in relevant items
C J C Sit C2 - 005 Temporary Employer's site office (200m2) including necessary facilities 1 lot --- to be included in relevant items
C J C Sit C2 - 006 Temporary road (Penetration Macadam Road, width: 6m) 1 lot --- Contractor's responsible

Lubai Electrode Station in Sumatra

Earthing System
C S E Ert C3 - 101 Removal of surface bush, plant, tree and top soil to disposal area 96,366 m2 unit price 91,777m2 x 1.05 Refer to Drawing No. P1-ES-CW-01
C S E Ert C3 - 102 Earth cutting for transition and embankment (V1) 45,000 m3 unit price 3 x 75 x 200
C S E Ert C3 - 103 Earth cutting, separating and removal of un-used soil to disposal area 0 m3 unit price disposal area shall be located outside the site
C S E Ert C3 - 104 Embankment and compacting soil for leveling by usable soil (V1) 45,000 m3 unit price
C S E Ert C3 - 105 Embankment and compacting for leveling by using imported soil 0 m3 unit price to make suitable soil by mixing with soil from outside
C S E Ert C3 - 106 Removal of boulders for disposal, removal to disposal area 0 m3 unit price
C S E Ert C3 - 107 Removal of boulders and broken down for reusing at site 0 m3 unit price including treatment of remained material for reuse
C S E Ert C3 - 108 Additional excavation for removal of boulders 0 m3 unit price
C S E Ert C3 - 109 Observation system of settlement 0 point --- to be included in relevant items
C S E Ert C3 - 110 Excavation, installation and Backfilling Earthing System 1 lot fixed price Install Electrode Rod, including material cost

Others
C S E Oth C3 - 401 Topographic survey ( Before & after commencement of works ) 1 lot --- to be included in relevant items
Soil investigation as per Technical Specification ( Drilling : L25m x 4, 8
C S E Oth C3 - 402 100 m unit price
samples)
C S E Oth C3 - 403 Pumping test as per Technical Specification 0 point ---
C S E Oth C3 - 404 Water quality analysis as per Technical Specification 2 point unit price
C S E Oth C3 - 405 Embankment test including soil test N/A point --- not applicable

Road Construction
C S E Rod C3 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 0 m2 unit price
C S E Rod C3 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 440 m 2
unit price Refer to Drawing No. P1-ES-RO-01
C S E Rod C3 - 603 Curb and Road Drainage for every road side 165 m unit price Refer to Drawing No. P1-ES-RO-01
C S E Rod C3 - 604 Upgrading and reinforce permanent access road 0 m unit price
C S E Rod C3 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 0 m unit price Refer to Drawing No. P1-ES-RO-01

Drainage and Water Supply System


C S E Ert C3 - 705 Concrete 0pen channel drainage system around Station boundary 1 lot fixed price Refer to drawing
C S E Ert C3 - 714 Primary Drainage 1,831 m unit price Refer to Drawing No. P1-ES-DW-01
C S E Ert C3 - 715 Secondary Drainage 130 m unit price Refer to Drawing No. P1-ES-DW-01

Fencing and Gate


C S E Fec C3 - 801 Concrete panel fence ( for land boundary ) 1,548 m unit price Refer to Drawing No. P1-ES-FG-01
C S E Fec C3 - 802 Mesh fence ( for station boundary ) 0 m unit price
C S E Fec C3 - 803 Entrance main gate 1 lot fixed price Refer to Drawing No. P1-ES-FG-01
C S E Fec C3 - 804 BRC Protection fence and gate (for equipment boundary) 100 m unit price Refer to Drawing No. P1-EL-BL-01

Building Works, Outdoor Lighting, Security System & Finishing


C S E Bil C3 - 901 Guard house 1 lot fixed price
C S E Bil C3 - 902 Chamberhouse for switching Electrode 1 lot fixed price
C S E Bil C3 - 903 Water pump house --- --- Including in the cost of Guardhouse
C S E Bil C3 - 920 Outdoor Lighting 1 lot fixed price Refer to Drawing No. P1-EL-OL-01
C S E Bil C3 - 921 Paving in station 0 m2 unit price Refer to Drawing No. P1-EL-PG-01
C S E Bil C3 - 922 Parking and facilities 66 m2 unit price Refer to Drawing No. P1-EL-PG-01
C S E Bil C3 - 923 Gardening and Landcaping 71 m2 unit price Refer to Drawing No. P1-EL-PG-01
C S E Bil C3 - 924 Gravel in station 217 m2 unit price Refer to Drawing No. P1-EL-PG-01
C S E Bil C3 - 925 Security System (CCTV only) 1 lot fixed price Refer to Drawing No. P1-EL-BL-01 & P1-EL-BL-02

Site Setting out and Temporary Works


C S E Sit C3 - 001 Reinforcement, repair and expansion of transportation road, bridge, etc 1 lot fixed price
C S E Sit C3 - 002 Removal and recover the obstructive structure in transportation road 1 lot fixed price

C S E Sit C3 - 004 Temporary Security Gate House (15m2) including necessary facilities 1 lot --- to be included in relevant items
C S E Sit C3 - 005 Temporary Employer's site office (200m2) including necessary facilities 1 lot --- to be included in relevant items

Package 1 : Java - Sumatra Interconnection Transmission Line Project


500kV AC/DC Converter Stations and Substations JICA ODA Loan No. IP-556
BOQ Civil 4/7
PT. PLN (Persero)
Payment
Items No. Code Description Quantity Unit Remarks
Adjustment
Lebak Electrode Station in Java

Earthing System
C J E Ert C4 - 101 Removal of surface bush, plant, tree and top soil to disposal area 98,335 m2 unit price 93,652m2 x 1.05 Refer to Drawing No. P1-EJ-CW-01
C J E Ert C4 - 102 Earth cutting for transition and embankment (V1) 75,000 m 3
unit price 5 x 75 x 200
C J E Ert C4 - 103 Earth cutting, separating and removal of un-used soil to disposal area 0 m3 unit price disposal area shall be located outside the site
C J E Ert C4 - 104 Embankment and compacting soil for leveling by usable soil (V1) 75,000 m3 unit price
C J E Ert C4 - 105 Embankment and compacting for leveling by using imported soil 0 m3 unit price to make suitable soil by mixing with soil from outside
C J E Ert C4 - 106 Removal of boulders for disposal, removal to disposal area 0 m3 unit price
C J E Ert C4 - 107 Removal of boulders and broken down for reusing at site 0 m3 unit price including treatment of remained material for reuse
C J E Ert C4 - 108 Additional excavation for removal of boulders 0 m3 unit price
C J E Ert C4 - 109 Observation system of settlement 0 point --- to be included in relevant items
C J E Ert C4 - 110 Excavation, installation and Backfilling Earthing System 1 lot fixed price Install Electrode Rod, including material cost

Others
C J E Oth C4 - 401 Topographic survey ( Before & after commencement of works ) 1 lot --- to be included in relevant items
Soil investigation as per Technical Specification ( Drilling : L25m x 4, 8
C J E Oth C4 - 402 100 m unit price
samples)
C J E Oth C4 - 403 Pumping test as per Technical Specification 0 point ---
C J E Oth C4 - 404 Water quality analysis as per Technical Specification 2 point unit price
C J E Oth C4 - 405 Embankment test including soil test N/A point --- not applicable

Road Construction
C J E Rod C4 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 0 m2 unit price
C J E Rod C4 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 241 m2 unit price Refer to Drawing No. P1-EJ-RO-01
C J E Rod C4 - 603 Curb and Road Drainage for every road side 96 m unit price Refer to Drawing No. P1-EJ-RO-01
C J E Rod C4 - 604 Upgrading and reinforce permanent access road 2,443 m2 unit price including water pass 3 pipe x 0.5 meter (dia.)
C J E Rod C4 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 2,443 m2 unit price Refer to Drawing No. P1-EJ-RO-01

Drainage and Water Supply System


C J E Ert C4 - 701 Blind Drain Dia 300 mm 500 m unit price Drain system for water flow by the original river
C J E Ert C4 - 702 Blind Drain Dia 1000 mm 200 m unit price Drain system for water flow by the original river
Drainage system for slope protection, horizontal & vertical trench with drain
C J E Ert C4 - 703 1,000 m unit price Including water pits as shown in the drawings
box
C J E Ert C4 - 705 Concrete 0pen channel drainage system around Station boundary 1 lot fixed price
C J E Ert C4 - 714 Primary Drainage 2,009 m unit price Refer to Drawing No. P1-EJ-DW-01
C J E Ert C4 - 715 Secondary Drainage 118 m unit price Refer to Drawing No. P1-EJ-DW-01

Fencing and Gate


C J E Fec C4 - 801 Concrete panel fence ( for land boundary ) 1,551 m unit price Refer to Drawing No. P1-EJ-FG-01
C J E Fec C4 - 802 Mesh fence ( for station boundary ) 0 m unit price
C J E Fec C4 - 803 Entrance main gate 1 lot fixed price Refer to Drawing No. P1-EJ-FG-01
C J E Fec C4 - 804 BRC Protection fence and gate (for equipment boundary) 100 m unit price Refer to Drawing No. P1-EL-BL-01

Building Works, Outdoor Lighting, Security System & Finishing


C J E Bil C4 - 901 Guard house 1 lot fixed price
C J E Bil C4 - 902 Chamberhouse for switching Electrode 1 lot fixed price
C J E Bil C4 - 903 Water pump house --- --- Including in the cost of Guardhouse
C J E Bil C4 - 920 Outdoor Lighting 1 lot fixed price Refer to Drawing No. P1-EL-OL-01
C J E Bil C4 - 921 Paving in station 66 m2 unit price Refer to Drawing No. P1-EL-PG-01
C J E Bil C4 - 924 Gravel in station 71 m2 unit price Refer to Drawing No. P1-EL-PG-01
C J E Bil C4 - 923 Gardening and Landcaping 217 m2 unit price Refer to Drawing No. P1-EL-PG-01
C J E Bil C4 - 925 Security System (CCTV only) 1 lot fixed price Refer to Drawing No. P1-EL-BL-01 & P1-EL-BL-02

Site Setting out and Temporary Works


C J E Sit C4 - 001 Reinforcement, repair and expansion of transportation road, bridge, etc 1 lot fixed price
C J E Sit C4 - 002 Removal and recover the obstructive structure in transportation road 1 lot fixed price
C J E Sit C4 - 004 Temporary Security Gate House (15m2) including necessary facilities 1 lot --- to be included in relevant items
C J E Sit C4 - 005 Temporary Employer's site office (200m2) including necessary facilities 1 lot --- to be included in relevant items

Ketapang Switching Station in Sumatra

Earthwork
C S W Ert C5 - 101 Removial of surface bush, plant, tree and top soil to disposal area 36,000 m2 unit price
C S W Ert C5 - 102 Earth cutting for transition and embankment (V1) 12,000 m3 unit price
C S W Ert C5 - 103 Earth cutting, separating and removal of un-used soil to disposal area 500 m3 unit price including treatment of remained material for reuse
C S W Ert C5 - 104 Embankment and compacting soil for leveling by usable soil (V1) 11,500 m3 unit price
C S W Ert C5 - 105 Embankment and compacting for leveling by using imported soil 17,500 m3 unit price =140x125x1
C S W Ert C5 - 106 Removal of boulders for disposal, removal to disposal area 50 m3 unit price including treatment of remained material for reuse
C S W Ert C5 - 107 Removal of boulders and broken down for reusing at site 50 m3 unit price
C S W Ert C5 - 108 Additional excavation for removal of boulders 50 m3 unit price
C S W Ert C5 - 109 Observation system of settlement 2 point --- to be included in relevant items

Slope work
C S W Slp C5 - 201 Slope protection by seed spraying (for cut slope) with water drain system 800 m2 unit price
Slope protection by sod facing (for embankment slope) with water drain
C S W Slp C5 - 202 900 m2 unit price
system

Site Finishing
C S W Fin C5 - 301 Earth System for earth grid over the station 6,300 m unit price Mesh Grid by strip cooper (IEEE 80-2000)
C S W Fin C5 - 302 Surface raking after top soil removal 8,900 m2 unit price
C S W Fin C5 - 303 Leveling prior to laying of surface material 3,125 m2 unit price
C S W Fin C5 - 304 Weed killer spreading 3,125 m2 unit price
C S W Fin C5 - 305 Laying and rolling of gravel or crushed stone (thickness 150mm) 3,125 m2 unit price

Others
C S W Oth C5 - 401 Topographic survey ( Before & after commencement of works ) 1 lot --- to be included in relevant items
Soil investigation as per Technical Specification ( Drilling : L25m x 6, 12
C S W Oth C5 - 402 150 m unit price
samples)
C S W Oth C5 - 403 Pumping test as per Technical Specification 2 point unit price
C S W Oth C5 - 404 Water quality analysis as per Technical Specification 4 point unit price
C S W Oth C5 - 405 Embankment test including soil test N/A point --- not applicable

Civil Structures

Package 1 : Java - Sumatra Interconnection Transmission Line Project


500kV AC/DC Converter Stations and Substations JICA ODA Loan No. IP-556
BOQ Civil 5/7
PT. PLN (Persero)
Payment
Items No. Code Description Quantity Unit Remarks
Adjustment
C S W Str C5 - 501 Concrete Block Retaining walls 150 m unit price 2 m height retaining wall for protect land slide
C S W Str C5 - 502 Cable ducts/trenches for electrical wire and OF N/A --- to be included in Material Cost for related equipment
C S W Str C5 - 503 PC (Prestressed Concrete) Piling works Type 1 ( Extra Heavy Equipment ) --- ---
C S W Str C5 - 504 PC (Prestressed Concrete) Piling works Type 2 ( Heavy Equipment ) --- ---
PC (Prestressed Concrete) Piling works Type 3 ( Building, structure water
C S W Str C5 - 505 4,536 m unit price
tank, etc )
C S W Str C5 - 506 Trial mix test of the concrete grades 1 lot --- to be included in relevant items
C S W Str C5 - 507 Quality control test of the concrete 1 lot --- to be included in relevant items

ROAD CONSTRUCTION
C S W Rod C5 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 2,995 m2 unit price Refer to Drawing No. P1-SS-RO-01
C S W Rod C5 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 0 m2 unit price
C S W Rod C5 - 603 Curb and Road Drainage for every road side 774 m unit price Refer to Drawing No. P1-SS-RO-01
C S W Rod C5 - 604 Upgrading and reinforce permanent access road 1,400 m2 unit price including water pass 6 pipe x 0.5 meter (dia.)
C S W Rod C5 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 5,466 m2 unit price Refer to Drawing No. P1-SS-RO-01

Drainage and Water Supply System


C S W Dsy C5 - 701 Blind Drain Dia 300 mm 200 m unit price Drain system for water flow by the original river
C S W Dsy C5 - 702 Blind Drain Dia 1000 mm --- --- Drain system for water flow by the original river
Drainage system for slope protection, horizontal & vertical trench with drain
C S W Dsy C5 - 703 400 m unit price Including water pits
box
C S W Dsy C5 - 704 Reservoir --- ---
C S W Dsy C5 - 705 Concrete 0pen channel drainage system around Station boundary 200 m unit price W2.0m x L200m with water pits
C S W Dsy C5 - 706 Drainage pipe system for station area (connect to French drainage system) 1 lot fixed price Φ500 185m, Φ700 120m, Φ1,000 70m
C S W Dsy C5 - 714 Primary Drainage 280 m unit price Refer to Drawing No. P1-SS-DW-01
C S W Dsy C5 - 715 Secondary Drainage 114 m unit price Refer to Drawing No. P1-SS-DW-01
C S W Dsy C5 - 716 Tertiary Drainage 482 m unit price Refer to Drawing No. P1-SS-DW-01
C S W Dsy C5 - 707 Water storage tank (120m3) 1 set fixed price Refer to Drawing No. P1-SW-BL-03
C S W Dsy C5 - 708 Water Supply System 1 lot fixed price Refer to Drawing No. P1-SW-DW-02
C S W Dsy C5 - 709 Fire Fighting System 1 lot fixed price Refer to Drawing No. P1-SW-DW-03
C S W Dsy C5 - 710 Deep Well 1 lot fixed price Refer to Drawing No. P1-SW-DW-02
C S W Dsy C5 - 711 Oil drain and Oil Pit system for transformers 1 lot fixed price
C S W Dsy C5 - 712 Water Supply System test --- --- to be included in relevant items
C S W Dsy C5 - 713 Fire Fighting System test --- --- to be included in relevant items

Fencing and Gate


C S W Fec C5 - 801 Concrete panel fence ( for land boundary ) 2,532 m unit price Refer to Drawing No. P1-SS-FG-01
C S W Fec C5 - 802 Mesh fence ( for station boundary ) 893 m unit price Refer to Drawing No. P1-SS-FG-01
C S W Fec C5 - 803 Entrance main gate 1 lot fixed price Refer to Drawing No. P1-SS-FG-01
C S W Fec C5 - 804 Protection fence and gate --- ---

Building Works, Outdoor Lighting, Security System & Finishing


C S W Bil C5 - 901 Guard house 1 lot fixed price
C S W Bil C5 - 902 Warehouse 1 lot fixed price
C S W Bil C5 - 904 Fire pump house 1 lot fixed price
C S W Bil C5 - 905 Emergency generator house 1 lot fixed price
C S W Bil C5 - 907 Main Control Building 1 lot fixed price Including gantry tower and Cable Trench Entrance
C S W Bil C5 - 918 Building for Cable Switching 1 lot fixed price
C S W Bil C5 - 919 Building Oil facility for Submarine Cable 1 lot fixed price
C S W Bil C5 - 920 Outdoor Lighting 1 lot fixed price Refer to Drawing No. P1-SS-OL-01
C S W Bil C5 - 922 Parking and facilities 120 m2 unit price Refer to Drawing No. P1-SS-PG-01
C S W Bil C5 - 923 Gardening and Landcaping 13,341 m2 unit price Refer to Drawing No. P1-SS-PG-01
C S W Bil C5 - 924 Gravel in station 0 m2 unit price to be included in item C5-305
C S W Bil C5 - 925 Security System 1 lot fixed price Refer to Drawing No. P1-SS-SS-01

Site Setting out and Temporary Works


C S W Sit C5 - 001 Reinforcement, repair and expansion of transportation road, bridge, etc 1 lot fixed price
C S W Sit C5 - 002 Removal and recover the obstructive structure in transportation road 1 lot fixed price
C S W Sit C5 - 003 Batching plant for concrete work 1 lot --- to be included in relevant items
C S W Sit C5 - 004 Temporary Security Gate House (15m2) including necessary facilities 1 lot --- to be included in relevant items
C S W Sit C5 - 005 Temporary Employer's site office (200m2) including necessary facilities 1 lot --- to be included in relevant items

Salira Switching Station in Java

Earthwork
C J W Ert C6 - 101 Removial of surface bush, plant, tree and top soil to disposal area 25,849 m2 unit price =(45+113)x140+113x33
C J W Ert C6 - 102 Earth cutting for transition and embankment (V1) 90,000 m3 unit price =100x140x5+100x200x1
C J W Ert C6 - 103 Earth cutting, separating and removal of un-used soil to disposal area 30,000 m3 unit price Screening & Classification of piling material for re-using
C J W Ert C6 - 104 Embankment and compacting soil for leveling by usable soil (V1) 60,000 m3 unit price
C J W Ert C6 - 105 Embankment and compacting for leveling by using imported soil 10,000 m3 unit price =100x200x1
C J W Ert C6 - 106 Removal of boulders for disposal, removal to disposal area 50 m3 unit price including treatment of remained material for reuse
C J W Ert C6 - 107 Removal of boulders and broken down for reusing at site 1,000 m3 unit price
C J W Ert C6 - 108 Additional excavation for removal of boulders 50 m3 unit price
C J W Ert C6 - 109 Observation system of settlement 2 point --- to be included in relevant items

Slope work
C J W Slp C6 - 201 Slope protection by seed spraying (for cut slope) with water drain system 0 m2 unit price
Slope protection by masonry stone (for embankment slope) with water drain
C J W Slp C6 - 202 2,700 m2 unit price Masonry retaining wall by using stone at site
system

Site Finishing
C J W Fin C6 - 301 Earth System for earth grid over the station 6,300 m unit price Mesh Grid by strip cooper (IEEE 80-2000)
C J W Fin C6 - 302 Surface raking after top soil removal 8,900 m2 unit price
C J W Fin C6 - 303 Leveling prior to laying of surface material 3,125 m2 unit price
C J W Fin C6 - 304 Weed killer spreading 3,125 m2 unit price
C J W Fin C6 - 305 Laying and rolling of gravel or crushed stone (thickness 150mm) 3,125 m2 unit price

Survey and Testing


C J W Oth C6 - 401 Topographic survey ( Before & after commencement of works ) 1 lot --- to be included in relevant items
Soil investigation as per Technical Specification ( Drilling : L25m x 6, 12
C J W Oth C6 - 402 150 m unit price
samples)
C J W Oth C6 - 403 Pumping test as per Technical Specification 2 point unit price
C J W Oth C6 - 404 Water quality analysis as per Technical Specification 4 point unit price
C J W Oth C6 - 405 Embankment test including soil test N/A point --- not applicable

Civil Structures
C J W Str C6 - 501 Concrete Block Retaining walls 150 m unit price 2 m height retaining wall for protect land slide
C J W Str C6 - 502 Cable ducts/trenches for electrical wire and OF N/A --- to be included in Material Cost for related equipment

Package 1 : Java - Sumatra Interconnection Transmission Line Project


500kV AC/DC Converter Stations and Substations JICA ODA Loan No. IP-556
BOQ Civil 6/7
PT. PLN (Persero)
Payment
Items No. Code Description Quantity Unit Remarks
Adjustment
C J W Str C6 - 503 PC (Prestressed Concrete) Piling works Type 1 ( Extra Heavy Equipment ) --- ---
C J W Str C6 - 504 PC (Prestressed Concrete) Piling works Type 2 ( Heavy Equipment ) --- ---
PC (Prestressed Concrete) Piling works Type 3 ( Building, structure water
C J W Str C6 - 505 3,780 m unit price
tank, etc )
C J W Str C6 - 506 Trial mix test of the concrete grades 1 lot --- to be included in relevant items
C J W Str C6 - 507 Quality control test of the concrete 1 lot --- to be included in relevant items

Road Construction
C J W Rod C6 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 3,819 m2 unit price Refer to Drawing No. P1-SJ-RO-01
C J W Rod C6 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 0 m2 unit price
C J W Rod C6 - 603 Curb and Road Drainage for every road side 969 m unit price Refer to Drawing No. P1-SJ-RO-01
C J W Rod C6 - 604 Upgrading and reinforce permanent access road 200 m2 unit price
C J W Rod C6 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 1,852 m2 unit price Refer to Drawing No. P1-SJ-RO-01

C J W Dsy C6 - 701 Blind Drain Dia 300 mm --- ---


C J W Dsy C6 - 702 Blind Drain Dia 1000 mm --- ---
Drainage system for slope protection, horizontal & vertical trench with drain
C J W Dsy C6 - 703 --- ---
box
C J W Dsy C6 - 704 Reservoir --- ---
including underground trench and water pit x 1 (see
C J W Dsy C6 - 705 Concrete 0pen channel drainage system around Station boundary north side 200 m unit price
drawing)
C J W Dsy C6 - 706 Drainage pipe system for station area (connect to French drainage system) 1 lot fixed price Φ500 185m, Φ700 120m, Φ1,000 70m
C J W Dsy C6 - 714 Primary Drainage 90 m unit price Refer to Drawing No. P1-SJ-DW-01
C J W Dsy C6 - 715 Secondary Drainage 286 m unit price Refer to Drawing No. P1-SJ-DW-01
C J W Dsy C6 - 716 Tertiary Drainage 365 m unit price Refer to Drawing No. P1-SJ-DW-01
C J W Dsy C6 - 717 Diversion Channel 190 m unit price Refer to Drawing No. P1-SJ-DW-01
C J W Dsy C6 - 707 Water storage tank (120m3) 1 set fixed price Refer to Drawing No. P1-SW-BL-03
C J W Dsy C6 - 708 Water Supply System 1 lot fixed price Refer to Drawing No. P1-SW-DW-02
C J W Dsy C6 - 709 Fire Fighting System 1 lot fixed price Refer to Drawing No. P1-SW-DW-03
C J W Dsy C6 - 710 Deep Well 1 lot fixed price Refer to Drawing No. P1-SW-DW-02
C J W Dsy C6 - 711 Oil drain and Oil Pit system for transformers 1 lot fixed price
C J W Dsy C6 - 712 Water Supply System test --- --- to be included in relevant items
C J W Dsy C6 - 713 Fire Fighting System test --- --- to be included in relevant items

Fencing and Gate


C J W Fec C6 - 801 Concrete panel fence ( for land boundary ) 1,285 m unit price Refer to Drawing No. P1-SJ-FG-01
C J W Fec C6 - 802 Mesh fence ( for station boundary ) 927 m unit price Refer to Drawing No. P1-SJ-FG-01
C J W Fec C6 - 803 Entrance main gate 1 lot fixed price Refer to Drawing No. P1-SJ-FG-01
C J W Fec C6 - 804 Protection fence and gate --- ---

Building Works, Outdoor Lighting, Security System & Finishing


C J W Bil C6 - 901 Guard house 1 lot fixed price
C J W Bil C6 - 902 Warehouse 1 lot fixed price
C J W Bil C6 - 904 Fire pump house 1 lot fixed price
C J W Bil C6 - 905 Emergency generator house 1 lot fixed price
C J W Bil C6 - 907 Main Control Building 1 lot fixed price Including gantry tower and Cable Trench Entrance
C J W Bil C6 - 918 Building for Cable Switching 1 lot fixed price
C J W Bil C6 - 919 Building Oil facility for Submarine Cable 1 lot fixed price
C J W Bil C6 - 920 Outdoor Lighting 1 lot fixed price Refer to Drawing No. P1-SJ-OL-01
C J W Bil C6 - 922 Parking and facilities 150 m2 unit price Refer to Drawing No. P1-SJ-PG-01
C J W Bil C6 - 923 Gardening and Landcaping 10,894 m2 unit price Refer to Drawing No. P1-SJ-PG-01
C J W Bil C6 - 924 Gravel in station 0 m2 unit price to be included in item C6-305
C J W Bil C6 - 925 Security System 1 lot fixed price Refer to Drawing No. P1-SS-SS-01

Site Setting out and Temporary Works


C J W Sit C6 - 001 Reinforcement, repair and expansion of transportation road, bridge, etc 1 lot fixed price
C J W Sit C6 - 002 Removal and recover the obstructive structure in transportation road 1 lot fixed price
C J W Sit C6 - 003 Batching plant for concrete work 1 lot --- to be included in relevant items
C J W Sit C6 - 004 Temporary Security Gate House (15m2) including necessary facilities 1 lot --- to be included in relevant items
C J W Sit C6 - 005 Temporary Employer's site office (200m2) including necessary facilities 1 lot --- to be included in relevant items

Other Works

C C A Sit CA - a01 Temporary works for construction 1 lot to be included in relevant items
C C A Sit CA - a02 Stock yards, repair shop and warehouse for construction purpose 1 lot to be included in relevant items
C C A Sit CA - a03 Notice board at every station 1 lot to be included in relevant items

Base Camp

C S C Bca C1 - b01 Project Office 1 set Refer to Drawing No. P1-CO-BC-01


C S C Bca C1 - b02 Guard House 1 set Refer to Drawing No. P1-CO-BC-02
C S C Bca C1 - b03 Facility Depot 1 set Refer to Drawing No. P1-CO-BC-03
C S C Bca C1 - b04 Canteen 1 set Refer to Drawing No. P1-CO-BC-04
C S C Bca C1 - b05 Masjid 1 set Refer to Drawing No. P1-CO-BC-05
C S C Bca C1 - b06 Lodging House Type I 1 set Refer to Drawing No. P1-CO-BC-06
C S C Bca C1 - b07 Lodging House Type II 1 set Refer to Drawing No. P1-CO-BC-07
C S C Bca C1 - b08 Guest House 2 set Refer to Drawing No. P1-CO-BC-08
C S C Bca C1 - b09 House Type 70 4 set Refer to Drawing No. P1-CO-BC-09
C S C Bca C1 - b10 House Type 90 2 set Refer to Drawing No. P1-CO-BC-10
C S C Bca C1 - b11 Badminton Court & Toilet 1 lot Refer to Drawing No. P1-CO-BC-11
C S C Bca C1 - b12 Tennis & Futsal Court 1 lot Refer to Drawing No. P1-CO-BC-12
C S C Bca C1 - b13 Main Gate & Fence 1 lot Refer to Drawing No. P1-CO-BC-13
C S C Bca C1 - b14 Concrete Road & Drainage 1 lot Refer to Drawing No. P1-CO-BC-14
C S C Bca C1 - b15 Paving, Parking & Landscaping 1 lot Refer to Drawing No. P1-CO-BC-15
C S C Bca C1 - b16 Outdoor Lighting Plan 1 lot Refer to Drawing No. P1-CO-BC-16

C J C Bca C2 - b01 Project Office 1 set Refer to Drawing No. P1-CO-BC-01


C J C Bca C2 - b02 Guard House 1 set Refer to Drawing No. P1-CO-BC-02
C J C Bca C2 - b03 Facility Depot 1 set Refer to Drawing No. P1-CO-BC-03
C J C Bca C2 - b04 Canteen 1 set Refer to Drawing No. P1-CO-BC-04
C J C Bca C2 - b05 Masjid 1 set Refer to Drawing No. P1-CO-BC-05
C J C Bca C2 - b06 Lodging House Type I 1 set Refer to Drawing No. P1-CO-BC-06
C J C Bca C2 - b07 Lodging House Type II 1 set Refer to Drawing No. P1-CO-BC-07
C J C Bca C2 - b08 Guest House 2 set Refer to Drawing No. P1-CO-BC-08

Package 1 : Java - Sumatra Interconnection Transmission Line Project


500kV AC/DC Converter Stations and Substations JICA ODA Loan No. IP-556
BOQ Civil 7/7
PT. PLN (Persero)
Payment
Items No. Code Description Quantity Unit Remarks
Adjustment
C J C Bca C2 - b09 House Type 70 4 set Refer to Drawing No. P1-CO-BC-09
C J C Bca C2 - b10 House Type 90 2 set Refer to Drawing No. P1-CO-BC-10
C J C Bca C2 - b11 Badminton Court & Toilet 1 lot Refer to Drawing No. P1-CO-BC-11
C J C Bca C2 - b12 Tennis & Futsal Court 1 lot Refer to Drawing No. P1-CO-BC-12
C J C Bca C2 - b13 Main Gate & Fence 1 lot Refer to Drawing No. P1-CO-BC-13
C J C Bca C2 - b14 Concrete Road & Drainage 1 lot Refer to Drawing No. P1-CO-BC-14
C J C Bca C2 - b15 Paving, Parking & Landscaping 1 lot Refer to Drawing No. P1-CO-BC-15
C J C Bca C2 - b16 Outdoor Lighting Plan 1 lot Refer to Drawing No. P1-CO-BC-16

Code
C - Civil Works
1 Sumatra Muara Enim Converter Station
3 Sumatra Lubai Electrode station
5 Sumatra Ketapang Cable Switching Station
7 Sumatra Muara Enim 275kV Substation
9 Sumatra OPGW Repeater Station
0 Java OPGW Repeater Station
2 Java X-Bogor Converter Station
4 Java Lebak Electrode Station
6 Java Salira Cable Switching Station
8 Java X-Bogor 150kV Substation
A All station
100 Earthwork
200 Slope work
300 Site Finishing
400 Survey and Testing
500 Civil Structures
600 Road Construction
700 Drainage and Water Supply System
800 Fencing and Gate
900 Building Works
000 Site Setting Out and Temporary Works
a00 Other works
b00 Base Camp

Package 1 : Java - Sumatra Interconnection Transmission Line Project


500kV AC/DC Converter Stations and Substations JICA ODA Loan No. IP-556

You might also like