Earthwork
C S C Ert C1 - 101 Removal of surface bush, plant, tree and top soil to disposal area 630,000 m2 unit price disposal area shall be located inside the site
C S C Ert C1 - 102 Earth cutting for transition and embankment (V1) 1,737,000 m3 unit price
C S C Ert C1 - 103 Earth cutting, separating and removal of un-used soil to disposal area 996,000 m3 unit price disposal area shall be located outside the site
C S C Ert C1 - 104 Embankment and compacting soil for leveling by usable soil ( from V1 ) 1,563,300 m3 unit price Design elevation : 88 meter
C S C Ert C1 - 105 Embankment and compacting for leveling by using imported soil 173,700 m3 unit price to make suitable soil by mixing with soil from outside
C S C Ert C1 - 106 Removal of boulders for disposal, removal to disposal area 0 m3 unit price
C S C Ert C1 - 107 Removal of boulders and broken down for reusing at site 0 m3 unit price including treatment of remained material for reuse
C S C Ert C1 - 108 Additional excavation for removal of boulders 0 m3 unit price
C S C Ert C1 - 109 Observation system of settlement 2 point --- to be included in relevant items
Slope work
C S C Slp C1 - 201 Slope protection by seed spraying (for cut slope) 37,500 m2 unit price Drain system shall be included in item C1-703
C S C Slp C1 - 202 Slope protection by sod facing (for embankment slope) 21,500 m2 unit price Drain system shall be included in item C1-703
Civil Structures
2 m height retaining wall for protect land slide for 3 x
C S C Str C1 - 501 Concrete Block Retaining walls 400 m unit price
dead end towers
C S C Str C1 - 502 Cable ducts/trenches for electrical wire and OF N/A --- to be included in Material Cost for related equipment
C S C Str C1 - 503 PC (Prestressed Concrete) Piling works Type 1 ( Extra Heavy Equipment ) 6,220 m unit price pile diameter 600 mm
C S C Str C1 - 504 PC (Prestressed Concrete) Piling works Type 2 ( Heavy Equipment ) 4,140 m unit price pile diameter 400 mm
PC (Prestressed Concrete) Piling works Type 3 ( Building, structure water
C S C Str C1 - 505 92,160 m unit price pile diameter 300 mm
tank, etc )
C S C Str C1 - 506 Trial mix test of the concrete grades 1 lot --- to be included in relevant items
C S C Str C1 - 507 Quality control test of the concrete 1 lot --- to be included in relevant items
Road Construction
C S C Rod C1 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 46,333 m2 unit price Refer to Drawing No. P1-CS-PG-01
C S C Rod C1 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 1,693 m2 unit price Refer to Drawing No. P1-CS-RO-01
C S C Rod C1 - 603 Curb and Road Drainage for every road side 17,433 m unit price Refer to Drawing No. P1-CS-RO-01, P1-CS-PG-01
C S C Rod C1 - 604 Upgrading and reinforce permanent access road 5,309 m2 unit price including water pass 6 pipe x 0.5 meter (dia.)
C S C Rod C1 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 5,309 m2 unit price Refer to Drawing No. P1-CS-RO-01
Earthwork
C J C Ert C2 - 101 Removal of surface bush, plant, tree and top soil to disposal area 290,000 m2 unit price disposal area shall be located inside the site
C J C Ert C2 - 102 Earth cutting for transition and embankment (V1) 1,590,000 m3 unit price
C J C Ert C2 - 103 Earth cutting, separating and removal of un-used soil to disposal area 66,000 m3 unit price disposal area shall be located inside the site
C J C Ert C2 - 104 Embankment and compacting soil for leveling by usable soil (V1) 1,585,000 m3 unit price
C J C Ert C2 - 105 Embankment and compacting for leveling by using imported soil 475,000 m3 unit price to make suitable soil by mixing with soil from outside
C J C Ert C2 - 106 Removal of boulders for disposal, removal to disposal area 20 m3 unit price
C J C Ert C2 - 107 Removal of boulders and broken down for reusing at site 140 m3 unit price including treatment of remained material for reuse
C J C Ert C2 - 108 Additional excavation for removal of boulders 420 m3 unit price
C J C Ert C2 - 109 Observation system of settlement 2 point --- to be included in relevant items
C J C Ert C2 - 111 Bench cutting and prepare land of Dead End Towers ( 3 towers ) 6,000 m3 unit price 3 towers ( 40m x 40m land to be flatted )
C J C Ert C2 - 112 Embankment and compacting for leveling for Tower 4,800 m2 unit price 3 towers ( 40m x 40m land to be flatted )
Slope work
C J C Slp C2 - 201 Slope protection by seed spraying (for cut slope) 54,000 m2 unit price Drain system shall be included in item C2-703
C J C Slp C2 - 202 Slope protection by sod facing (for embankment slope) 22,000 m2 unit price Drain system shall be included in item C2-703
Site Finishing
C J C Fin C2 - 301 Earth System for earth grid over the station 62,000 m unit price Mesh Grid by strip cooper (IEEE 80-2000)
C J C Fin C2 - 302 Surface raking after top soil removal 346,500 m2 unit price
C J C Fin C2 - 303 Leveling prior to laying of surface material 346,500 m2 unit price
C J C Fin C2 - 304 Weed killer spreading 235,000 m2 unit price
C J C Fin C2 - 305 Laying and rolling of gravel or crushed stone (thickness 150mm) 235,000 m2 unit price
Civil Structures
2 m height retaining wall for protect deadend tower
C J C Str C2 - 501 Concrete Block Retaining walls 200 m unit price
location
C J C Str C2 - 502 Cable ducts/trenches for electrical wire and OF N/A --- to be included in Material Cost for related equipment
C J C Str C2 - 503 PC (Prestressed Concrete) Piling works Type 1 ( Extra Heavy Equipment ) 2,592 m unit price pile diameter 600 mm
C J C Str C2 - 504 PC (Prestressed Concrete) Piling works Type 2 ( Heavy Equipment ) 3,888 m unit price pile diameter 400 mm
PC (Prestressed Concrete) Piling works Type 3 ( Building, structure water
C J C Str C2 - 505 69,120 m unit price pile diameter 300 mm
tank, etc )
C J C Str C2 - 506 Trial mix test of the concrete grades 1 lot --- to be included in relevant items
C J C Str C2 - 507 Quality control test of the concrete 1 lot --- to be included in relevant items
Road Construction
C J C Rod C2 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 33,751 m2 unit price Refer to Drawing No. P1-CJ-PG-01
C J C Rod C2 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 1,855 m2 unit price Refer to Drawing No. P1-CJ-RO-01
C J C Rod C2 - 603 Curb and Road Drainage for every road side 10,058 m unit price Refer to Drawing No. P1-CJ-RO-01 and P1-CJ-PG-01
C J C Rod C2 - 604 Upgrading and reinforce permanent access road 3,035 m2 unit price including water pass 6 pipe x 1 meter (dia.)
C J C Rod C2 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 3,035 m2 unit price Refer to Drawing No. P1-CJ-RO-01
Earthing System
C S E Ert C3 - 101 Removal of surface bush, plant, tree and top soil to disposal area 96,366 m2 unit price 91,777m2 x 1.05 Refer to Drawing No. P1-ES-CW-01
C S E Ert C3 - 102 Earth cutting for transition and embankment (V1) 45,000 m3 unit price 3 x 75 x 200
C S E Ert C3 - 103 Earth cutting, separating and removal of un-used soil to disposal area 0 m3 unit price disposal area shall be located outside the site
C S E Ert C3 - 104 Embankment and compacting soil for leveling by usable soil (V1) 45,000 m3 unit price
C S E Ert C3 - 105 Embankment and compacting for leveling by using imported soil 0 m3 unit price to make suitable soil by mixing with soil from outside
C S E Ert C3 - 106 Removal of boulders for disposal, removal to disposal area 0 m3 unit price
C S E Ert C3 - 107 Removal of boulders and broken down for reusing at site 0 m3 unit price including treatment of remained material for reuse
C S E Ert C3 - 108 Additional excavation for removal of boulders 0 m3 unit price
C S E Ert C3 - 109 Observation system of settlement 0 point --- to be included in relevant items
C S E Ert C3 - 110 Excavation, installation and Backfilling Earthing System 1 lot fixed price Install Electrode Rod, including material cost
Others
C S E Oth C3 - 401 Topographic survey ( Before & after commencement of works ) 1 lot --- to be included in relevant items
Soil investigation as per Technical Specification ( Drilling : L25m x 4, 8
C S E Oth C3 - 402 100 m unit price
samples)
C S E Oth C3 - 403 Pumping test as per Technical Specification 0 point ---
C S E Oth C3 - 404 Water quality analysis as per Technical Specification 2 point unit price
C S E Oth C3 - 405 Embankment test including soil test N/A point --- not applicable
Road Construction
C S E Rod C3 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 0 m2 unit price
C S E Rod C3 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 440 m 2
unit price Refer to Drawing No. P1-ES-RO-01
C S E Rod C3 - 603 Curb and Road Drainage for every road side 165 m unit price Refer to Drawing No. P1-ES-RO-01
C S E Rod C3 - 604 Upgrading and reinforce permanent access road 0 m unit price
C S E Rod C3 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 0 m unit price Refer to Drawing No. P1-ES-RO-01
C S E Sit C3 - 004 Temporary Security Gate House (15m2) including necessary facilities 1 lot --- to be included in relevant items
C S E Sit C3 - 005 Temporary Employer's site office (200m2) including necessary facilities 1 lot --- to be included in relevant items
Earthing System
C J E Ert C4 - 101 Removal of surface bush, plant, tree and top soil to disposal area 98,335 m2 unit price 93,652m2 x 1.05 Refer to Drawing No. P1-EJ-CW-01
C J E Ert C4 - 102 Earth cutting for transition and embankment (V1) 75,000 m 3
unit price 5 x 75 x 200
C J E Ert C4 - 103 Earth cutting, separating and removal of un-used soil to disposal area 0 m3 unit price disposal area shall be located outside the site
C J E Ert C4 - 104 Embankment and compacting soil for leveling by usable soil (V1) 75,000 m3 unit price
C J E Ert C4 - 105 Embankment and compacting for leveling by using imported soil 0 m3 unit price to make suitable soil by mixing with soil from outside
C J E Ert C4 - 106 Removal of boulders for disposal, removal to disposal area 0 m3 unit price
C J E Ert C4 - 107 Removal of boulders and broken down for reusing at site 0 m3 unit price including treatment of remained material for reuse
C J E Ert C4 - 108 Additional excavation for removal of boulders 0 m3 unit price
C J E Ert C4 - 109 Observation system of settlement 0 point --- to be included in relevant items
C J E Ert C4 - 110 Excavation, installation and Backfilling Earthing System 1 lot fixed price Install Electrode Rod, including material cost
Others
C J E Oth C4 - 401 Topographic survey ( Before & after commencement of works ) 1 lot --- to be included in relevant items
Soil investigation as per Technical Specification ( Drilling : L25m x 4, 8
C J E Oth C4 - 402 100 m unit price
samples)
C J E Oth C4 - 403 Pumping test as per Technical Specification 0 point ---
C J E Oth C4 - 404 Water quality analysis as per Technical Specification 2 point unit price
C J E Oth C4 - 405 Embankment test including soil test N/A point --- not applicable
Road Construction
C J E Rod C4 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 0 m2 unit price
C J E Rod C4 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 241 m2 unit price Refer to Drawing No. P1-EJ-RO-01
C J E Rod C4 - 603 Curb and Road Drainage for every road side 96 m unit price Refer to Drawing No. P1-EJ-RO-01
C J E Rod C4 - 604 Upgrading and reinforce permanent access road 2,443 m2 unit price including water pass 3 pipe x 0.5 meter (dia.)
C J E Rod C4 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 2,443 m2 unit price Refer to Drawing No. P1-EJ-RO-01
Earthwork
C S W Ert C5 - 101 Removial of surface bush, plant, tree and top soil to disposal area 36,000 m2 unit price
C S W Ert C5 - 102 Earth cutting for transition and embankment (V1) 12,000 m3 unit price
C S W Ert C5 - 103 Earth cutting, separating and removal of un-used soil to disposal area 500 m3 unit price including treatment of remained material for reuse
C S W Ert C5 - 104 Embankment and compacting soil for leveling by usable soil (V1) 11,500 m3 unit price
C S W Ert C5 - 105 Embankment and compacting for leveling by using imported soil 17,500 m3 unit price =140x125x1
C S W Ert C5 - 106 Removal of boulders for disposal, removal to disposal area 50 m3 unit price including treatment of remained material for reuse
C S W Ert C5 - 107 Removal of boulders and broken down for reusing at site 50 m3 unit price
C S W Ert C5 - 108 Additional excavation for removal of boulders 50 m3 unit price
C S W Ert C5 - 109 Observation system of settlement 2 point --- to be included in relevant items
Slope work
C S W Slp C5 - 201 Slope protection by seed spraying (for cut slope) with water drain system 800 m2 unit price
Slope protection by sod facing (for embankment slope) with water drain
C S W Slp C5 - 202 900 m2 unit price
system
Site Finishing
C S W Fin C5 - 301 Earth System for earth grid over the station 6,300 m unit price Mesh Grid by strip cooper (IEEE 80-2000)
C S W Fin C5 - 302 Surface raking after top soil removal 8,900 m2 unit price
C S W Fin C5 - 303 Leveling prior to laying of surface material 3,125 m2 unit price
C S W Fin C5 - 304 Weed killer spreading 3,125 m2 unit price
C S W Fin C5 - 305 Laying and rolling of gravel or crushed stone (thickness 150mm) 3,125 m2 unit price
Others
C S W Oth C5 - 401 Topographic survey ( Before & after commencement of works ) 1 lot --- to be included in relevant items
Soil investigation as per Technical Specification ( Drilling : L25m x 6, 12
C S W Oth C5 - 402 150 m unit price
samples)
C S W Oth C5 - 403 Pumping test as per Technical Specification 2 point unit price
C S W Oth C5 - 404 Water quality analysis as per Technical Specification 4 point unit price
C S W Oth C5 - 405 Embankment test including soil test N/A point --- not applicable
Civil Structures
ROAD CONSTRUCTION
C S W Rod C5 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 2,995 m2 unit price Refer to Drawing No. P1-SS-RO-01
C S W Rod C5 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 0 m2 unit price
C S W Rod C5 - 603 Curb and Road Drainage for every road side 774 m unit price Refer to Drawing No. P1-SS-RO-01
C S W Rod C5 - 604 Upgrading and reinforce permanent access road 1,400 m2 unit price including water pass 6 pipe x 0.5 meter (dia.)
C S W Rod C5 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 5,466 m2 unit price Refer to Drawing No. P1-SS-RO-01
Earthwork
C J W Ert C6 - 101 Removial of surface bush, plant, tree and top soil to disposal area 25,849 m2 unit price =(45+113)x140+113x33
C J W Ert C6 - 102 Earth cutting for transition and embankment (V1) 90,000 m3 unit price =100x140x5+100x200x1
C J W Ert C6 - 103 Earth cutting, separating and removal of un-used soil to disposal area 30,000 m3 unit price Screening & Classification of piling material for re-using
C J W Ert C6 - 104 Embankment and compacting soil for leveling by usable soil (V1) 60,000 m3 unit price
C J W Ert C6 - 105 Embankment and compacting for leveling by using imported soil 10,000 m3 unit price =100x200x1
C J W Ert C6 - 106 Removal of boulders for disposal, removal to disposal area 50 m3 unit price including treatment of remained material for reuse
C J W Ert C6 - 107 Removal of boulders and broken down for reusing at site 1,000 m3 unit price
C J W Ert C6 - 108 Additional excavation for removal of boulders 50 m3 unit price
C J W Ert C6 - 109 Observation system of settlement 2 point --- to be included in relevant items
Slope work
C J W Slp C6 - 201 Slope protection by seed spraying (for cut slope) with water drain system 0 m2 unit price
Slope protection by masonry stone (for embankment slope) with water drain
C J W Slp C6 - 202 2,700 m2 unit price Masonry retaining wall by using stone at site
system
Site Finishing
C J W Fin C6 - 301 Earth System for earth grid over the station 6,300 m unit price Mesh Grid by strip cooper (IEEE 80-2000)
C J W Fin C6 - 302 Surface raking after top soil removal 8,900 m2 unit price
C J W Fin C6 - 303 Leveling prior to laying of surface material 3,125 m2 unit price
C J W Fin C6 - 304 Weed killer spreading 3,125 m2 unit price
C J W Fin C6 - 305 Laying and rolling of gravel or crushed stone (thickness 150mm) 3,125 m2 unit price
Civil Structures
C J W Str C6 - 501 Concrete Block Retaining walls 150 m unit price 2 m height retaining wall for protect land slide
C J W Str C6 - 502 Cable ducts/trenches for electrical wire and OF N/A --- to be included in Material Cost for related equipment
Road Construction
C J W Rod C6 - 601 Concrete Road (inside site) including "Curbs and Channels (Precast)" 3,819 m2 unit price Refer to Drawing No. P1-SJ-RO-01
C J W Rod C6 - 602 Asphalt Road (inside site) including "Curbs and Channels (Precast)" 0 m2 unit price
C J W Rod C6 - 603 Curb and Road Drainage for every road side 969 m unit price Refer to Drawing No. P1-SJ-RO-01
C J W Rod C6 - 604 Upgrading and reinforce permanent access road 200 m2 unit price
C J W Rod C6 - 605 Finishing up permanent access road including "Curbs and Channels (Precast)" 1,852 m2 unit price Refer to Drawing No. P1-SJ-RO-01
Other Works
C C A Sit CA - a01 Temporary works for construction 1 lot to be included in relevant items
C C A Sit CA - a02 Stock yards, repair shop and warehouse for construction purpose 1 lot to be included in relevant items
C C A Sit CA - a03 Notice board at every station 1 lot to be included in relevant items
Base Camp
Code
C - Civil Works
1 Sumatra Muara Enim Converter Station
3 Sumatra Lubai Electrode station
5 Sumatra Ketapang Cable Switching Station
7 Sumatra Muara Enim 275kV Substation
9 Sumatra OPGW Repeater Station
0 Java OPGW Repeater Station
2 Java X-Bogor Converter Station
4 Java Lebak Electrode Station
6 Java Salira Cable Switching Station
8 Java X-Bogor 150kV Substation
A All station
100 Earthwork
200 Slope work
300 Site Finishing
400 Survey and Testing
500 Civil Structures
600 Road Construction
700 Drainage and Water Supply System
800 Fencing and Gate
900 Building Works
000 Site Setting Out and Temporary Works
a00 Other works
b00 Base Camp