% Completion as of 04.20.14
SBU
PROJECT
Stage
TARGET
ACTUAL
Variance
FINANCIAL ACCOMPLISHMENT
% Completion as of 04.20.14
TARGET
ACTUAL
Variance
PROJECT STATUS
No. of Days
Delayed
(to client)
Count
STATUS
Delays
Original Completion
Date
Revised Completion
Date
RCD presented to
proponent
Driver
Subsequent or
concurrent
DESIGN
Late Start?
BUDGET CONSTRAINT
PERMITS
PROCUREMENT
OPERATIONS
ACTION PLAN
% Completion as of 04.20.14
BELLAVITA
% Completion as of 04.20.14
100.00%
100.00%
0.00%
100.00%
100.00%
0.00%
BELLAVITA
100.00%
100.00%
0.00%
100.00%
100.00%
0.00%
BELLAVITA
100.00%
100.00%
0.00%
100.00%
100.00%
0.00%
95.86%
63.50%
-32.36%
95.86%
63.61%
-32.25%
100.00%
100.00%
0.00%
100.00%
100.00%
100.00%
100.00%
0.00%
100.00%
100.00%
BELLAVITA
BELLAVITA
BELLAVITA
BELLAVITA
BELLAVITA
31-Dec-13
Yes
31-Dec-13
No
31-May-14
EOT Approved
Operations
31-May-13
No
31-May-14
EOT Approved
Permits
30-Oct-14
No
28-Feb-15
EOT Presented
Permits
0.00%
31-Dec-13
Yes
0.00%
31-Dec-13
Yes
Construction
Delays
BELLAVITA
PROJECT STATUS
Construction
BELLAVITA
81
Budget Constraint
Late Start
Construction
BELLAVITA
Fiesta Market
BELLAVITA
Construction
156
Budget Constraint
Legal issues on Boundary still not cleared; Frequent drizzle to rainfall occurrence w/c makes site
unworkable.