Professional Documents
Culture Documents
PROGRAM(UIIDP)
Letter of Call the next least evaluated. bidder
Acceptance
Request NO
Forfeit the bid
Performance security
security
Contract signing
Site Handover
NO
Approve the Revise
submitted
Schedule
YES
Examine & inspect the
construction site
Right of way
Clear the problem as
problem YES immediately as possible
NO
Evaluate the
test result Take appropriate
Rejected measure
UIIDP/023
Accepted
Register Daily activity of the site
YES
Conduct the Temporary Acceptance
Release
50% of the retention money
50% of the Performance security
Use – UIIDP /0 32
Is the sub
project well
rectified & NO
Order in writing to the
competent for
contractor to rectify the
Final
defects as to the satisfaction
Acceptance?
of the client
YES
This _________________________date of ______________ EFY 2013, the site for the construction
of_________________________________________________
_____________________________________________________________has been officially handed
over to (the contractor) _____________________________
The contractor hereinafter, shall be responsible for the damages that occur as a result of his fault,
carelessness or negligence in connection with untimely commencement of the work.
The contractor in addition acknowledges that the completion of the said work shall count as from the date
mentioned above and comply with the terms and conditions of the contract to the satisfaction of the client.
IN WITNESS HERE OF THIS DOCUMENT HAD BEEN SIGNED BY ALL PRESENCE IN THREE
COPIES OF WHICH ONE COPY SHOULD BE DELIVERED TO CLIENT, CONSULTANT (RESIDENT
ENGINEER) AND TO THE CONTRACTOR.
For the Client (Employer) For the Consultant For the Contractor
WITNESSES
1. _______________________________________
2. _______________________________________
3. _______________________________________
Form No-UIIDP/002
URBAN INSTITUTE AND INFRA-STRUCTURE DEVELOPMENT PROGRAM
CONSTRUCTION WORK SCHEDULE
PROJECT_____________________________________________ CONTRACT
NO___________________________________________
EMPLOYER___________________________________________ CONTRACT
TIME__________________________________________
CONTRACTOR________________________________________ COMMENCEMENT
DATE___________________________________
CONSULTANT________________________________________ COMPLETION
DATE________________________________________
CONTRACT Site Hand Over Date_______________________________________
AMOUNT__________________________________
Project Duration in Calendar Days_______________________
4.
PROJECT_____________________________________________ Consultant___________________________________________
EMPLOYER___________________________________________ Contractor___________________________________________
1. Staff
1.1
2. Labor
Force
2.1
PROJECT_____________________________________________ Consultant___________________________________________
EMPLOYER___________________________________________ Contractor___________________________________________
Delivery Week
Staff & Labor Remark
No Unit Quantity
Force Mobilization 1st 2nd 3rd 4th 5th 6th 7th
1 Sand
2 Gravel
3 Stone
4 Cement
5 Reinforcement
Bars
6 HCB
7 Doors & Windows
8 Wood & Steel
9 Glazing
10 Chip wood
11 Zigba Battens
12 Paint
13 Etc
PREPARED BY ________________________________________ APPROVED BY ________________________________________
SIGNATURE___________________________________________ SIGNATURE___________________________________________
Form No-UIIDP/005
URBAN INSTITUTE AND INFRA-STRUCTURE DEVELOPMENT PROGRAM
PROJECT_____________________________________________ Consultant___________________________________________
EMPLOYER___________________________________________ Contractor___________________________________________
Delivery Week
Staff & Labor Remark
No Unit Quantity
Force Mobilization 1st
2nd
3rd
4th
5th
6th
7th
1 Tools
2 Mixer
3 Vibrator
4 Form work- panel
5 Dozer
6 Crane
7 Water Pump
8 Water Tank
9 Others
10 Others
11 Others
12 Others
13 Others
SIGNATURE___________________________________________ SIGNATURE___________________________________________
Form No-UIIDP/006
REGION: _____________________________________________________________________
PROJECT:__________________________ LOCATION__________________
INVESTOR:_________________________ CONTRACT No.______________
CONTRACTOR:_____________________ CONSULTANT:_______________
Site Handover Inspection Certificate
Following an inspection of the site as per the above listed items, the contractor is hereby to take over site
and proceed with the subsequent mobilization and site preparation works.
1. Layout:
- Building _____________________________
- Sewer Lines _____________________________
- Area to be cleared off _____________________________
- Others _____________________________
2. Levels
Following an inspection of the layout and levels of all buildings, Site works. Etc. as the above listed
items permission to proceed with the subsequent excavation/earth works is hereby granted/refused to the
contractor.
Form No-UIIDP/010
Certificate No: __________________
1. Excavation
- Location of Excavation ________________________
- Method of Excavation ________________________
- Type of Excavated material (s): top Soil, root ________________________
- Thickness of Excavated materials _______________________
- Slopes & Levels of Excavated Surfaces _______________________
- Necessary temporary drains provided _______________________
- No Damage to adjacent areas _______________________
2. Placement of Excavated Materials:-
2. Additional Items/Comments
Following an inspection of the quality of Earthworks as per the above listed items permission
of proceed with the subsequent construction / _______________________
__________________________________/ work is hereby granted/ refused to the contractor.
Following an inspection of the quality of concrete work as the above listed items permission to pour
concrete is hereby Granted /Refused to the Contractor.
Supervisor: Name __________________________ Contractor: Name ________
Sign. __________________________ Sign. _________
Date __________________________ Date _________
Form No-UIIDP/014
Certificate No: __________________
1. Component ___________________________
2. Timber Members
Quality ______________________
Shape/Size ______________________
Free from
Decay ___________________________
Insects attack ___________________________
Other damages ___________________________
3. Type Quality of Timber Treatment __________________________
5. Quality/Size of
- Nail ______________________________
- Bolts/Nuts _______________________________
- Glue _______________________________
- Other Joinery _______________________________
6. Shape/Pattern of Timber Work _______________________________
7. Quality of Fabrication _______________________________
8. Quality/Location of Joinery _______________________________
9. Quality of Erection _______________________________
10. Straightness/Deflection of Timber Work _______________________________
11. Additional Items/Comments:
Following an inspection of the quality of Timber work as per the above listed items permission to proceed
with the subsequent construction/ __________________________
1. Ceiling Work
- Quality/Size of Ceiling Material _____________________________
- Fixing of Ceiling Material _____________________________
- Type, color. Quality of Ceiling Painting _____________________________
- Quality, procedure of Ceiling Painting _____________________________
- Cleanliness of Ceiling _____________________________
2. Doors & Windows
- Location of Doors/Windows ______________________________
- Quality of Door/Window Materials ______________________________
- Type of Door/Windows ______________________________
- Direction of Door/Window Swings ______________________________
- Straightness & Plumbing of Door/
Window frames ______________________________
- Quality/fixture of Door & Windows
- Hinges ______________________________
- Locks _______________________________
- Latches _______________________________
- Handles _______________________________
- Protection of Fixed Joinery from Damage _______________________________
3. Additional Items/Comments
Following an inspection of the quality of carpentry Joinery & Glazing work as per the above listed items
permission to proceed with the subsequent construction __________________ _________________
_________________________/ Work is Granted/Refused to the contractor
Roofing & Cladding Work Inspection Certificate- For Item Location _________
1. Roofing work
Type/Quality of Roof Sheet _________________________________
Thickness of Roof Sheet _________________________________
Size/Coating of Steel Hook Bolts/Nuts _________________________________
Lapping of Sheets __________________________________
- End _________________________________
- Side laps length _________________________________
- Direction __________________________________
2. Gutters & Down Pipes
Quality. Size. Thickness. Coating of
- Gutter __________________________________
- Down pipe __________________________________
Quality .Size. Thickness. Spacing. Coating of
- Gutter hangers ________________________________
- Down Pipe Supports ________________________________
Lapping of Down Pipes ________________________________
Quality Coating o gutter Joints Welding ________________________________
3. Additional Items/Comment
Following an inspection of the quality of Roofing and cladding work as per the above listed items
permission to proceed with the subsequent construction /____________________________
_____________________________/ work is Granted/Refused to the Contractor.
1. Plastering work
Location of Plastering ___________________________________
Quality of Plaster
- Material
(Cement, Lime, Sand, Water) ____________________________________
- Mix Proportion ___________________________________
Type of Mechanical Mixer Used ___________________________________
Elapsed Time of Plaster ___________________________________
Cleanliness of Wall ____________________________________
Wetting of Wall Prior to Plastering ____________________________________
Thickness of Plaster ____________________________________
Plumbing & Leveling of Plaster ____________________________________
5. Additional Items/Comments
Following an inspection of the site works as per the above listed items permission to proceed with
the subsequent work is hereby Granted /Refused to the Contractor
2. Right of way
Right of way problem cleared __________________________________________
If cleared when & how __________________________________________
If not cleared what is recommended __________________________________________
3.Environment
Schedule, A B C
If schedule A, full EIA studied ______________________________________________
If schedule B, Partial EIA studied ______________________________________________
What are the mitigation measures proposed for schedule A & B sub projects
a. ______________________________________________________________
b. ______________________________________________________________
c. _______________________________________________________________
d. _______________________________________________________________
a. ______________________________________________________________
b. ______________________________________________________________
c. _______________________________________________________________
5. Additional Items/Comments
Following an inspection of the site works as per the above listed items permission to proceed with
the subsequent work is hereby Granted /Refused to the Contractor
1. Cobblestone Roads
2. Right of way
Right of way problem cleared __________________________________________
If cleared when & how __________________________________________
If not cleared what is recommended __________________________________________
4.Environment
Schedule, A B C
If schedule A, full EIA studied ______________________________________________
If schedule B, Partial EIA studied ______________________________________________
What are the mitigation measures proposed for schedule A & B sub projects
e. ______________________________________________________________
f. ______________________________________________________________
g. _______________________________________________________________
h. _______________________________________________________________
e. ______________________________________________________________
f. _______________________________________________________________
5. Additional Items/Comments
Following an inspection of the site works as per the above listed items permission to proceed with
the subsequent work is hereby Granted /Refused to the Contractor
A. Work Completed_____________________________________________________________________________________________________________
B. Work Under Construction______________________________________________________________________________________________________
Form No-UIIDP/022
Project________________________________________________________________________
Site__________________________________________________________________________
_
Employer______________________________________________________________________
Contractor_____________________________________________________________________
Consultant_____________________________________________________________________
Supervisor
_____________________________________________________________________
TEST ORDER
To (Contractor)
_________________________________________________________________
1. _______________________________________________________________
2. _______________________________________________________________
3. _______________________________________________________________
4. _______________________________________________________________
Approved by______________________________________
Request Date_____________________________________
Note.
1. Representative sample should be taken in consultation with the laboratory personnel assigned to take over
the test. Representatives from the consultant, contractor and client should be available during testing and
sampling.
2. The contractor should distribute copies of the test result to the consultant and the contractor.
Form No-UIIDP/023A
Project________________________________________________________________________
Site__________________________________________________________________________
_
Employer______________________________________________________________________
Contractor_____________________________________________________________________
Consultant_____________________________________________________________________
Testing
Lab_____________________________________________________________________
Testing No_____________________________________________________________________
________________________________________________________________
Specified quality________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
APPROVED BY:____________________________________________
CC:-
To Site Supervisor
To Inspection
Form No-UIIDP/023B
Certificate No: __________________
SITE DIARY
PROJECT: - ____________________________________________________________
SITE:-________________________________________________________________
EMPLOYER: -___________________________________________________________
CONTRACTOR: - ________________________________________________________
CONSULTANT: -________________________________________________________
SUPERVISOR: _ ________________________________________________________
2. Staff on Site
3. Work on progress___________________________________________________
_______________________________________________________________
4. Material on Site_____________________________________________________
5. Equipment on Site___________________________________________________
8. Recommendation____________________________________________________
__________________________________________________________________
REPORT No _________________
MONTH _________________
PROJECT : ______________________________________________
LOCATION : ______________________________________________
EMPLOYER : ______________________________________________
CONSULTANT : ______________________________________________
CONTRACTIOR : _______________________________________________
1. INTRODUCTION & BACKGROUND
2. CONTRACT DATA
B. Advance Guarantee
Pursuant to the special conditions of contract clause ______, the contractor has furnished an advance
security from ______________________________ Bank, in the form of irrevocable unconditional
bank guarantee which is _____% of the contract amount. The guarantee will expire on
________________.
M.CON ADD%
T
A. Sub Structure
Excavation &
Earthwork
Concrete Work
Masonry
B. Super-Structure
Concrete Work
Block Work
Roofing
Carpentry
Joinery
Steel Structure
Metal Work
Finishing
Glazing
Painting
Electrical installation
Sanitary Installation
Site Work
Others
Total
REMARKS
C. Work Completed________________________________________________________________
________________________________________________________________
D. Work Under
Construction_________________________________________________________
________________________________________________________________
4 CONCRETE
A)
B)
C)
D)
5 BLOCKS
A)
B)
6 BRICKS
A)
7 REINFORCEMENT BAR
A)
B)
8 OTHERS
A)
B)
C)
REMARKS:-
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
__________________________________________________________________
MATERIAL SHORTAGE
EQUIPMENT SHORTAGE
CASH SHORTAGE
WETHER CONDITION
EMPLOYER INTERFERANCE
OTHERS
REMARKS:-
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
___________________________________________________________
DESIGN CHANGE
ADDITIONAL WORK
SUSPENSION
MATERIAL CHANGE
RECTIFICATION
OTHERS
REMARKS:-
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_______________________________________________
PROGRESS:- _______________________________________________________
REMARKS _____________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
____________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
______________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
9. EVALUTION MEETING.
1._____________________________________________________________________________
2 .____________________________________________________________________________
3. ____________________________________________________________________________
4. ____________________________________________________________________________
5. ____________________________________________________________________________
6. ____________________________________________________________________________
PROGRESS STATUS
PREVIOUS MONTHS
CURRENT MONTHS
TOTAL TO DATE
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
____________________________________ _____________________________
ENGINEER REPRESENTATIVE PROJECT ENGINEER
___________________________________ _____________________________
DATE DATE
Form No-UIIDP/027
URBAN INSTITUTE AND INFRA-STRUCTURE DEVELOPMENT PROGRAM
WORK ORDER
PROJECT: _______________________________ DATE: ____________________
LOCATION:______________________________ Contract No.________________
INVESTOR: ______________________________ Adm. Region _______________
CONTRACTOR: ___________________________
CONSULTANT: ___________________________
INSTRUCTION
ROUGH SKETCH
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________
_____________________ __________________
___________
Form No-UIIDP/028
URBAN INSTITUTE AND INFRA-STRUCTURE DEVELOPMENT PROGRAM
VARIATION ORDERS NO_________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
Measures taken
________________________________________________________________
_______________________________________________________________
________________________________________________________________
_________________ _____________________
Prepared by Approved by
Copies
A= Materials Unit Cost = A Birr/Unit B=Manpower Unit Cos t= B Birr/Unit C=Equipment Unit Cost = C Birr/Unit
PROJECT: ____________________________________________________________________
LOCATION: ___________________________________________________________________
CLIENT: _____________________________________________________________________
CONTRACTOR: ________________________________________________________________
CONSULTANT: ________________________________________________________________
______________________ _____________________________
Prepared Approved
URBAN INSTITUTE AND INFRA-STRUCTURE DEVELOPMENT PROGRAM
TIME EXTENSION EVALUATION SHEET
PROJECT: ____________________________________________________________________
LOCATION: ___________________________________________________________________
CLIENT: _____________________________________________________________________
CONTRACTOR: ________________________________________________________________
CONSULTANT: ________________________________________________________________
CONTRACT NOR: _______________________________________________________________
______________________ _____________________________
Prepared Approved
Form No-UIIDP/031
URBAN INSTITUTE AND INFRA-STRUCTURE DEVELOPMENT PROGRAM
የክፍያ ምስክር ወረቀት ቁጥር _____________________
አባሪ በሆነው የክፍያ ሰነድ ጥያቄ መሠረት እስከ ዛሬ ድረስ ተቋራጩ የሰራው ሥራና/ያቀረበው ዕቃ ዋጋ
As per the attached Statement the Value of work excited end) or materials Supplied to date
is.___________________________
የገንዘቡ ልክ (ልክ)
Amount (Birr)
ቁ ቀን የገንዘብ ልክ ( ብር)
No. Date Amount (Birr)
የገንዘብ ልክ
1
ተቀናሽ (ብር)
2 Deduction Amount (Birr)
3 1. አስቀድሞ የተከፈለ
4 Previews Payment
5 2. ቅናሽ, Rebate
6
7 3. መያዣ, Reception
8 4. መቀጫ, Penalty
ድምር 5. የቀድሚያ ክፍያ
TOTAL Advice Replacement
6. ሌላ
Others
ድምር TOTAL
የተጣራ ለተቋራጭ የሚከፈል ገንዘብ
Nat Sum due to the Contractor
VAT (15%)
Nat Sum due to the Contractor + VAT
-------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------
ተረጋግጧል / Checked ፀድቋል / Approved
_________________________ ___________________
ሥሪው / Project_________________________________________
ቦታው / Location______________________________________
ድምር / TOTAL
p“b / Rebaate
ጠቅላላ ድምር / GRAND TOTAL
I / we ____________________hereby certify that the above figures are correct and that the total of
work executed to date is birr____________
(________________________________________________________)
ተ.ቁ
No መግለጫ መለኪያ ብዛት / QTY
DESCRIPTION UNIT ነጠላ ድምር ድምር ብር
የውለታው የተሠሪው ዋጋ በከፊል TOTAL
CONT. EXECUTED UNIT SUB- BIRR
PRICE TOTAL
PROJECTE ____________________________________________________________________
D S DESCRIPION T D S DESCRIPTION
T
_____________________ __________________
___________
URBAN INSTITUTE AND INFRA-STRUCTURE DEVELOPMENT PROGRAM
BAR SCHEDULE
Location Bar No. shape Dia. Length No. of Bars Dia. Dia. Dia. Dia. Dia.
Total Length
Weight Kg
Total Weight Kg
_____________________ __________________
___________
Form No-UIIDP/032
URBAN INSTITUTE AND INFRA-STRUCTURE DEVELOPMENT PROGRAM
TEMPORARY ACCEPTANCE
PROJECT : __________________________________________________________________
LOCATION: _________________________________________________________________
CLIENT: ____________________________________________________________________
CONTRACTOR: ______________________________________________________________
2. __________________________________ ” ” _________________________
3. __________________________________ ” ” _________________________
4. __________________________________ ” ” _________________________
5. __________________________________ ” ” _________________________
6. __________________________________ ” ” _________________________
7. _________________________________ ” ” ________________________
Have examined
b. _______________________________
c _______________________________
and have proceed with the ascertainment of the completion and Temporary Acceptance of the above
project on the basis of the following information.
ACCOUNT
DEDUCTIONS
2. Penalty ____________________
3. Rebate ____________________
4. Others ____________________
Retention money ______________ % of the total value of work executed payable on the
Final acceptance
Remarks ___________________________________________________________________
CONCLUSION
The date for acceptance will be _________________________ after thorough investigation of the works
in all it’s excepting invisible and the specifications in an acceptable manner. We, Witnesses thereof we
have written and signed this temporary acceptance of which one copy is be issued to the contractor for all
practical purposes after due approval.
ATTENDING PARTIES
1. ________________________________ ______________________
2. ________________________________ ______________________
3. ________________________________ _______________________
4. ________________________________ _______________________
5. ________________________________ _______________________
6. ________________________________ _______________________
7. ________________________________ _______________________
DATE ________________________________
Form No-UIIDP/033
URBAN INSTITUTE AND INFRA-STRUCTURE DEVELOPMENT PROGRAM
FINAL ACCEPTANCE
PROJECT: ____________________________________________________________________
LOCATION: ___________________________________________________________________
CLIENT: _____________________________________________________________________
CONTRACTOR: ________________________________________________________________
2. __________________________________ ” ” _________________________
3. __________________________________ ” ” _________________________
4. __________________________________ ” ” _________________________
5. __________________________________ ” ” _________________________
6. __________________________________ ” ” _________________________
7. _________________________________ ” ” ________________________
Have examined
d._______________________________________
e. _______________________________________
and have proceed with the ascertainment of good execution and final acceptance of the project on the
basis of the following facts:-
ACCOUNT
DEDUCTIONS
3. Various Deductions
a.___________________________ ______________________
b.___________________________ ______________________
c.___________________________ ______________________
………………………………………………………………………………………
……….)
CONCLUSION
Therefore, we do hereby declare that the work has been executed in the principle of good workmanship
and have accepted the project definitely on behalf of _________________________________________