You are on page 1of 114

HAZOP STUDY REPORT,

REMEDIATION OF THE FORMER


ORICA VILLAWOOD SITE

Prepared by: Dean Shewring


17 April 2013

Pinnacle Risk Management Pty Limited


ABN 83 098 666 703

PO Box 5024 Elanora Heights


NSW Australia 2101
Telephone: (02) 9913 7284
Facsimile: (02) 9913 7930

Pinnacle Risk Management

HAZOP Study Report, Remediation of the Former


Orica Villawood Site

Disclaimer
This report was prepared by Pinnacle Risk Management Pty Limited (Pinnacle
Risk Management) as an account of work for Orica. The material in it reflects
Pinnacle Risk Managements best judgement in the light of the information
available to it at the time of preparation. However, as Pinnacle Risk
Management cannot control the conditions under which this report may be
used, Pinnacle Risk Management will not be responsible for damages of any
nature resulting from use of or reliance upon this report. Pinnacle Risk
Managements responsibility for advice given is subject to the terms of
engagement with Orica.

Rev

Date

Description

Reviewed By

27/6/12

Draft for Comment

Orica

12/8/12

Orica Comments Included

Orica

13/8/12

Final Issue

16/4/13

Supplementary and Water Treatment Plant


HAZOPs Added

Orica

17/4/13

Final Issue

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

CONTENTS
EXECUTIVE SUMMARY ............................................................................................ I
GLOSSARY ............................................................................................................ II
1

INTRODUCTION .............................................................................................. 1

PROCESS DESCRIPTION AND HAZOP SCOPE .................................................. 2

METHODOLOGY ............................................................................................. 2
3.1

General ............................................................................................. 2

3.2

Meeting Procedures ........................................................................ 3

STUDY TEAM ................................................................................................. 4

DISCUSSION AND CONCLUSIONS ..................................................................... 5

5.1

Analysis of Main Findings .............................................................. 5

5.2

Actions Arising from the HAZOP ................................................... 6

REFERENCES ................................................................................................ 7

LIST OF TABLES
Table 1 HAZOP Team .................................................................................... 4

LIST OF APPENDICES
Appendix 1 - Approval of HAZOP Chair.
Appendix 2 - Process Description
Appendix 3 - HAZOP Drawings
Appendix 4 - HAZOP Guide Words.
Appendix 5 - HAZOP Minutes.

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

EXECUTIVE SUMMARY
Orica is proposing to install and operate a soil processing facility at the former
Orica Villawood site. The Site contains waste byproducts of industrial activities
which ceased in 2000, in particular DDT and its degradation products DDD and
DDE. The contaminants will be separated from the soil and destroyed within
the process.
The Minister for Planning granted development consent for the Project in May,
2012. Project Development Consent Condition 21(b) requires the preparation
of a Hazard and Operability (HAZOP) Study.
Orica requested that Dean Shewring from Pinnacle Risk Management chair the
HAZOP study. This report details the results of the HAZOP study in
accordance with the requirements of the Department of Planning and
Infrastructures HAZOP Guidelines.
The main participants had appropriate experience in the design and operation
of soil processing (or similar) plants. Therefore, the hazards were generally well
known as well as the required control measures to reduce risk to acceptable
levels.
The plant design is an established design with a number of similar plants being
operated throughout the world. Therefore, many of the significant potential
hazardous events and operability problems were already known which reduced
the demand on this study. This included incidents from recently commissioned
plants for Orica and other companies.

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

GLOSSARY
DoPI

Department of Planning and Infrastructure

DTD

Directly-heated Thermal Desorption

ECS

Emission Control System

FSB

Feed Soil Building

HAZOP

Hazard and Operability Study

HIPAP

Hazardous Industry Planning Advisory Paper

PHA

Preliminary Hazard Analysis

P&ID

Piping and Instrumentation Diagram

STA

Soil Treatment Area

VOC

Volatile Organic Compound

ii

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

REPORT
1

INTRODUCTION

Orica is proposing to install and operate a soil processing facility at the former
Orica Villawood site. The Site contains waste byproducts of industrial activities
which ceased in 2000, in particular DDT and its degradation products DDD and
DDE. The contaminants will be separated from the soil and destroyed within
the process.
The Minister for Planning granted development consent for the project in May,
2012.
Development Consent Condition 21(b) specifies the following requirements for
the HAZOP study.
"Prior to Site Establishment, the Proponent shall obtain the
Director-Generals approval of the following study:
b) a Hazard and Operability Study (HAZOP) chaired by an
independent, qualified person or team. The independent person
or team shall be approved by the Director-General. The Study
shall be carried out in accordance with the Department's
publication Hazardous Industry Planning Advisory Paper (HIPAP)
No. 8 - HAZOP Guidelines (Ref 1) and shall include consideration
of measures to prevent any accidental spills of liquids and/ or
liquid wastes on all relevant tanks and equipment used for the
storage and handling of liquids or liquid wastes, including
associated pipes and hoses.
Orica requested that Dean Shewring from Pinnacle Risk Management chair the
required HAZOP study. The approval received from the Department of
Planning and Infrastructure (DoPI) for the chair of this projects HAZOP study is
shown in Appendix 1.
This report details the results of the HAZOP study and is written to meet the
requirements of the Department of Planning and Infrastructures HIPAP Number
8 and Development Consent Condition 21(b).
The HAZOP study on the main contaminant destruction process was detailed in
revisions A to C of this report. Following this study, two additional HAZOPs
were performed. The first additional study reviewed the air compressor for the
evaporative cooler and the pugmill water system. The second additional study
reviewed the waste water treatment plant. The results of these two additional
studies have been added to revision D of this report.
The aim of the HAZOP study is to identify potential hazardous events and
significant operability problems associated with the proposed operations. This

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

aim is inherent for all HAZOP studies. The scope for this study is detailed in
Section 2 of this report.

PROCESS DESCRIPTION AND HAZOP SCOPE

A copy of the detailed process description for the soil treatment plant is supplied
in Appendix 2.
In summary, the feed soil is initially heated in a dryer to remove the volatile
contaminants which are then destroyed in a directly-heated thermal desorption
unit. The resultant product gases are then absorbed within a scrubber. Treated
soil can then be returned to the site.
In the waste water treatment plant, water from various site containments is
processed via settlers, flocculation (including chemical additional and pH
adjustment) and a series of filters to remove the contaminants. The purified
water is discharged to sewer.
Copies of the drawings used in the study which detail the process areas are
supplied in Appendix 3.
As the natural gas supply train to the directly-heated desorption unit will be
compliant to the relevant Australian Standard then the HAZOP just considered
deviations from the design intent associated with natural gas supply (rather than
try to alter an Australian Standard compliant system).

METHODOLOGY

3.1

GENERAL

A HAZOP study is a hazard study which concentrates on how the design will
cope with abnormal conditions, rather than on how it will perform under normal
conditions. The study is comprised of a review of each unit operation,
examining each for possible causes of a wide range of process abnormalities
and their consequences.
HAZOP provides the opportunity for people to think creatively and examine
ways in which hazards or operating problems might arise. To reduce the
chance of missing something, a HAZOP is carried out in a systematic manner,
using guide words to consider each pipeline and each type of hazard in turn.
The study is carried out by a team so that input from all areas of functional
expertise can be provided.
The results of a HAZOP depend heavily upon the experience and attitudes of
the team members and on the leadership style adopted. In this study, the
members of the team had good experience, knowledge and skills and had the
authority to approve the actions decided upon.

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

3.2

MEETING PROCEDURES

The HAZOP study of each section of plant followed the procedure given below:

The process design engineer outlined the broad purpose of the section of
design under study and displayed on the relevant P&IDs on the wall. This
outline included design features, operating conditions, description of fittings
and details of equipment.

Any general questions about the scope and intent of the design were
answered.

The first section or area of the design was highlighted for study, typically an
area where material flows into the plant.

Any general questions about this area were then answered. Minutes may
be generated during this discussion. If so, they have been recorded with the
guide word General Discussion.

The detailed "line by line" study commenced at this point. The HAZOP
leader led the group through the HAZOP guide words. Each guide word is a
prompt, such as "MORE OF OR HIGH FLOW", which identifies a deviation
from normal operating conditions that may lead to a hazardous event or
significant operability problem. This is used to prompt discussion of the
possible causes and effects of flow at an undesirably high rate. If, in the
opinion of the team, the safeguards for the combination of the consequences
and likelihood of a credible event are inadequate then an action is recorded
in the minutes.
For major risk areas the need for action is assessed quantitatively (by
Hazard or Reliability Analysis). For less significant risks the need for action
can be based on experience and judgement. For this study, all actions could
be appropriately addressed by the nominated HAZOP team members /
company.

The main aim of the meeting was to find problems needing solution, rather
than the actual solution. When the group became tied down by trying to
resolve a problem, the issue was minuted as requiring further review outside
the meeting, and the study proceeded.

All changes agreed at the meeting were minuted with some being marked
on the HAZOP master P&IDs.

Note that all actions were recorded in the minutes as well as significant
discussion points which did not result in any actions. The latter were
recorded as a means to record the basis of safety for a potential hazardous
event or operability problem.

The guide words used during the study are listed in Appendix 4.

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

All actions are listed in the HAZOP minutes, contained in Appendix 5. It is


noted that safeguards are only recorded by exception. It is assumed that the
procedures within the Orica safety management system will be used effectively
(as discussed throughout the HAZOP study).
As the purpose of a HAZOP study is to identify, i.e. not necessarily solve,
potential hazardous events and significant operability problems associated with
the process under review, some of the actions require further review post the
study. As a general rule, a HAZOP facilitator allows approximately 5 to 10
minutes to resolve any issues identified during the study. If a solution cannot be
agreed to within this timeframe then the issue is minuted and the study
proceeds.
The reason for this approach is that a positive, open, questioning mindset is
required from the team members. This allows creative brainstorming to identify
possible abnormal plant conditions that may lead to potential hazardous events
and/or significant operability problems. Teams that become tied down trying to
resolve all issues, in particular problems that require further calculations etc,
lose their creativity and hence the basis for the study effectiveness is lost.

STUDY TEAM

The HAZOP study for the project was conducted in a number of sessions from
January to November, 2012.
The main HAZOP team participants had the appropriate level of experience in
design and/or operation of soil processing plants (or similar processes). Table
1 shows the team members who participated in the HAZOP study.
The meetings were led by Dean Shewring with the minutes being recorded by
Peter ODea.
Table 1 HAZOP Team
HAZOP Role

Name

Company

HAZOP Chair

Dean Shewring

Pinnacle Risk Management

HAZOP Secretary

Peter ODea

Orica

Project Management

Peter ODea
Lindsay Killin
Cameron McLean
Richard Giles

Orica
EnviroPacific
EnviroPacific
EnviroPacific

Site Management
Representative

Gwenda Lister

Orica

Process Design and Plant


Operation Representatives

Brett Garton
Bala Kathiravelu
Rudy Maes
Keith Chapman
Tai Truong
Pearce Anderson

EnviroPacific
Orica
Consultant to Chapman Services
Chapman Services
EnviroPacific
EnviroPacific

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

DISCUSSION AND CONCLUSIONS

5.1

ANALYSIS OF MAIN FINDINGS

The HAZOP team assembled for the study was well balanced in terms of
disciplines and experience. The team sizes were generally kept to the required
four to eight people. This increases the ability to achieve a creative
brainstorming workshop to help ensure maximum effectiveness and quality.
The main participants had appropriate experience in the design and operation
of soil processing (or similar) plants. Therefore, the hazards were generally well
known as well as the required control measures to reduce risk to acceptable
levels.
The plant design is an established design with a number of similar plants being
operated throughout the world. Therefore, many of the significant potential
hazardous events and operability problems were already known which reduced
the demand on this study. This included incidents from recently commissioned
plants for Orica and other companies.
Potential hazardous events concerning releases of harmful materials via
gaseous, liquid or solid losses of containment were reviewed during the study.
Assuming the proposed safeguards remain effective then the risk of such
events should be low.
Any significant changes to the HAZOP design should be separately assessed
for new potential hazardous events and operability problems. This is commonly
achieved by utilising a management of change programme within the project
and may require further review using the HAZOP technique.
During the study, industry standard operating procedures were discussed and
included as potential causes for hazardous events and significant operability
problems. Any significant issues identified have been recorded in the HAZOP
minutes for inclusion in the final version of the standard operating procedures
for the Orica facility.
HAZOP studies are, by definition, a qualitative risk assessment. The decisions
made by the HAZOP team members are based on their experience and
knowledge of the type of processing plant under review. If the HAZOP team
members determined the existing control measures were adequate then no
further action is required. Significant points of discussion (generally if significant
consequential impacts are possible) were recorded even though the control
measures were deemed acceptable by the HAZOP team. All issues requiring a
response were included in the HAZOP minutes.

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

5.2

ACTIONS ARISING FROM THE HAZOP

Completed HAZOP actions need to be tracked within the projects HAZOP


action register or equivalent. Regular project meetings should include a review
of the progress of closing-out all of the actions. It is normally the responsibility
of the project manager to ensure that all of the HAZOP actions are completed.
The HAZOP drawings and a record of the completed actions should be retained
with the plant files.

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

Appendix 1

Approval of HAZOP Chair

HAZOP Study Report, Remediation of the Former Orica


Villawood Site

A1.1

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

Appendix 1 Approval of HAZOP Chair.

A1.2

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

Appendix 2

Process Description

HAZOP Study Report, Remediation of the Former Orica


Villawood Site

A2.1

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

Appendix 2 Process Description.

1. Pre-Treatment of Materials
The pre-treatment of excavated materials will be undertaken in two stages. Initially, excavated
material and overlying material may be screened within the Remediation Area compound.
Material required to be treated (in the Directly-heated Thermal Desorption (DTD) Plant) will be
transported to the Feed Soil Building (FSB), where further handling and testing of this material
will take place.
The material will be stockpiled in the FSB using a front end loader before undergoing further
screening and testing for contaminant levels and other characteristics which will be required for
the DTD treatment process. The material will then be blended to achieve a relatively
homogenous feed material prior to being loaded into the feed hopper of the DTD Plant.
Activities within the FSB, including screening and testing will take place 24 hours per day, seven
days per week.

2. Feed Soil Building and Emission Control System


The purpose of the FSB is to control emissions during pre-treatment activities and ensure these
emissions are vented to atmosphere through an Emission Control System (ECS).
The FSB will be constructed of a steel frame with metal sheeting. The building will contain an
approximate seven day working inventory of feed soil plus a sufficient buffer for soil drying and
other pre-treatment activities. This inventory volume is designed to provide adequate storage
capacity to feed the thermal treatment plant during periods when unforeseen conditions
interfere with normal excavation activities.
The FSB will be fitted with an air-lock and automated wheel wash, louvres and an ECS for air
quality control.
The FSB will be equipped with personnel entrances and truck entrances. The truck entrances
will include an air-lock consisting of a small structure internal to the enclosure. The air-lock will
be equipped with two doors. When a truck enters the air-lock, the outer door will open while the
inside door is closed. Once the truck enters the air-lock, the outer door will close, the inner door
will open and the truck will enter the enclosure. The procedure will be reversed when a truck
exits the enclosure.
An ECS will be constructed and operated to preserve air quality within the building and minimise
emissions (dust and organic vapours) to the atmosphere. The ECS will be operated to ensure
the flow of air into the FSB (i.e. air pressure within the FSB will be slightly lower than ambient air
pressure). Conceptually, the ECS will comprise an induced draft fan, duct work system,
particulate control device (dust filters) and a stack.
The air exhausted from the FSB will first pass through a particulate control device to remove
fugitive dust. Dust removed will be collected in enclosed drums or hoppers. When the dust
collection container is taken off-line, the dust will be taken to the Soil Treatment Area (STA) for
treatment.
Air will be exhausted to the atmosphere via a stack. Periodic stack testing will be undertaken in
accordance with license requirements. Permanent analysers will also be installed on the stack to
detect any unacceptable contaminant concentration levels.

A2.2

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

3. Directly-heated Thermal Desorption Plant


The DTD Plant will be located within the STA. After pre-treatment in the FSB, the excavated
materials will be fed into the feed hopper located inside the FSB. The materials will be
transported via a conveyor to the DTD Plant for treatment.
The DTD Plant will operate 24 hours a day, seven days a week with the seventh day typically
scheduled as downtime for maintenance. The nominal maximum rate of treatment through the
DTD Plant is 15 tonnes per hour.
The DTD Plant will have a footprint of approximately 50 m by 25 m. It will be established within
a concrete paved and bunded area having its own internal surface water drainage control
measures. Electrical power to the DTD Plant will be provided by mains power, with a diesel
powered generator used as a back-up. Natural gas sourced from the mains supply, will be used
to fire the heating burners of the plant.
Brief descriptions of typical key unit operations in the process are presented below.
Rotary Dryer
The first step in the DTD treatment process involves the volatilisation or separation of
contaminants from the material in the rotary dryer.
The rotary dryer utilises natural gas as fuel to heat the contaminated material to a temperature
of approximately 350C to 450C.
In a co-current system, the contaminated material enters the rotary dryer at the end where the
burner is located and the combustion gas and treated soil move in the same direction to where
they exit at the opposite end of the dryer.
Contaminants desorb and volatilise as they pass through the dryer. Soil is heated in the first
third of the dryer with most desorption and volatilisation occurring in the next third as
contaminants reach their boiling points.
Once it has passed through the rotary dryer, the heated soil material passes to a pugmill where
it is sprayed with water for cooling and rewetting. The treated material is then transferred to
temporary treated soil stockpiles awaiting validation.
Cyclone
The off-gases flow from the rotary dryer through a cyclone, where large dust particles are
removed, to the thermal oxidiser. The dust from the cyclone is directed to the pugmill where it is
mixed with the treated soil for rewetting and validation.
Thermal Oxidiser
The thermal oxidiser is used to treat the gases produced through the heating of the soil material
in the rotary dryer and would be designed to be Stockholm compliant, i.e. with appropriate
residence time, temperature and turbulence.
The thermal oxidiser operates at a temperature of about 1,000C using natural gas. At this
temperature, the contaminants present in the gas (from the feed material) oxidise or decompose
forming carbon dioxide, water vapour and hydrogen chloride with small amounts of other byproducts such as chlorine and sulphur compounds.

A2.3

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

In order to maintain the correct temperature to maximise destruction efficiency and minimise the
formation of by-products, the thermal oxidiser will be fitted with a sophisticated temperature
control system which will be consistently monitored.
Quench
Once gases have passed through the thermal oxidiser they must be rapidly cooled to minimise
the potential for dioxin formation and allow further treatment before release to the atmosphere
(as required by the Stockholm Convention).
To achieve this, the hot gases are drawn into the quench by an induced draught fan. In the
quench, water is injected to rapidly cool the gases to a temperature which is suitable for further
treatment.
Baghouse
The cooled gas from the quench is combined with steam from the pugmill and drawn into the
baghouse by an induced draught fan. The baghouse contains a series of fabric filters which
remove particulates.
Acid Gas Scrubber
The final step in the treatment process involves the removal of acid gases from the exhaust gas.
The acid gas scrubber consists of a packed tower with a re-circulating caustic solution that
reacts with any hydrogen chloride and chlorine in the exhaust gas to form a salt solution.
Following this, the clean treated gas is vented to the atmosphere via the scrubber stack which
is some 30 m in height.
Treated Soil
Treated soil will be stockpiled adjacent to the STA with drains and bunds provided to manage
runoff. Treated materials stored in this area will undergo validation testing and reclassification.
This is to determine whether the process has been effective and whether or not the materials
are ready for reuse at the Site. Stockpiles will be stabilised with spray grass or other such
treatment and will be wetted when necessary to control dust.
The treated, stockpiled soil will be retained until completion of remediation works at the Site
when it will be transported (by truck) to the Remediation Areas for reinstatement works.

A2.4

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

Appendix 3

HAZOP Drawings

HAZOP Study Report, Remediation of the Former Orica


Villawood Site

A3.1

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

Appendix 3 HAZOP Drawings.

A3.2

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.3

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.4

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.5

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.6

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.7

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.8

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.9

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.10

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.11

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.12

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.13

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.14

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.15

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.16

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.17

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.18

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.19

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.20

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

A3.21

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

Appendix 4

HAZOP Guide Words

HAZOP Study Report, Remediation of the Former Orica


Villawood Site

A4.1

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

Appendix 4 HAZOP Guide Words.


Note that the main headings are shown only. Some main headings included
various sub-prompts as well.
Line-By-Line Guide Words Continuous Fluid Systems

High Level / High Flow

Low Level / Low Flow

Zero Flow / Empty

Reverse Flow

High Pressure
- Venting, relief

Low Pressure
- Venting, relief

High Temperature

Low Temperature

Impurities
- Gaseous, liquid, solid

Change in Concentration or Composition / Two Phase Flow / Reactions

Testing
- Equipment / product

Plant Items
- Operable / maintainable

Electrical

Instruments

A4.2

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

Overview Guide Words

Toxicity

Commissioning

Startup

Shutdown (isolation, purging)

Breakdown (including services failure)

Effluent

Fire and Explosion

Noise / Vibration

Materials of Construction

Quality and Consistency

Output - Reliability and Bottlenecks

Efficiency Losses

Simplicity

A4.3

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

Appendix 5

HAZOP Minutes

HAZOP Study Report, Remediation of the Former Orica


Villawood Site

A5.1

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

Appendix 5 HAZOP Minutes.

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Feed Supply Bin and Conveyors

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10001 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
1.

General
Discussion

Bricks, rubble and


oversized material,
clay etc

Feed interrupted due to


blockages or equipment
damage

No further action required

Belt failure,
maintenance

No need for hopper


screen or clay breaker
as pre-screening. will be
done in the feed soil
building
Will use chemical
resistant belts

2.

General
Discussion

3.

General
Discussion

Chemical (i.e. from


the contaminated
soil) attack on
conveyor belts
Rain

No further action required

Increased moisture
impacts process

Conveyor covers to be
installed

No further action required

4.

High Flow /
High Level

Front end loader


(FEL) overfills
hopper

Spill to the bunded


building floor

DTD operator in contact


with FEL operator, any
spilt soil can be swept
up and reprocessed

Review the need for providing a mirror


or screen in the FEL cabin so the FEL
driver can see the level in the feed
hopper

A5.1

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Feed Supply Bin and Conveyors

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10001 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

No further action required

No further action required

SAFEGUARDS
5.

Low Flow /
Low Level

Soil clumps in
hopper

Potential to fall onto the


belt below (damage)
and possibly cause
blockages

6.

Zero Flow /
Empty

Hopper empty

Only financial keep


burning gas etc

7.

Zero Flow /
Empty

Feeder fails

Hopper full of material.


Confined space entry to
unblock

8.

Zero Flow /
Empty

Feeder fails (as


above)

Hopper full of material.


Confined space entry to
unblock

Steep sided hopper


minimises the risk of
material hold-up on the
hopper walls.
Can adjust the gap
below the hopper during
commissioning
Process controls come
into effect to trip
downstream fired
appliances
Routine checks on belt
feeder during
shutdowns, confined
space risk assessment
Routine checks on belt
feeder during
shutdowns, confined
space risk assessment

A5.2

Preventive maintenance procedures to


emphasise belt feed conveyor checks

BG

Review the need for hatches etc in the


feed bin walls for ease of clearing
material provided they also do not hold
up material

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Feed Supply Bin and Conveyors

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10001 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
9.

Zero Flow /
Empty

Spillage from
conveyors

Clean-up.
Damage to adjacent
equipment

Scrapers prevent return


below belt.
Canopy over conveyors

10.

Zero Flow /
Empty

Friction, e.g. from


wood stuck on belt
etc

Fire hose nearby.


Building vented through
carbon filters

11.

Zero Flow /
Empty

Plant outage

Conveyor belt fire with


toxic products of
combustion potentially
smoke logging the
building
Potential for conveyor
belt fire on restart if
material dries out /
solidifies

12.

Reverse Flow

13.

Impurities

Belt stops on the


inclined conveyor
and runs back due to
soil load
Asbestos cement
sheeting pieces in
the feed

Provide a cover around the slinger


conveyor to prevent any spilt soil
damaging adjacent gas burner and
other equipment
Include in the fire safety study
assessment of belts fires and the risk to
emergency responders from toxic
products of combustion

LK

No further action required

Spillage at bottom
requiring cleaning up

Slinger conveyor can be


run backwards for
material to be collected
in a truck, i.e. to clear
the conveyors
Back stop provided on
the conveyor

No further action required

Exposure to personnel
who contact the treated
soil and maintain the
plant

Will be removed in
accordance will agreed
practices by licensed
contractor

No further action required

A5.3

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Feed Supply Bin and Conveyors

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10001 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

No further action required

Include in the project plan an operability


and maintainability access review to all
equipment items
Risk assessment, including on confined
space entry, required to determine
suitable safeguards for people entering
the feed soil building when the emission
control system fails
No further action required

SAFEGUARDS
14.

Impurities

PPE disposed of via


the process

Possibility of embers
getting to the baghouse
and causing damage to
the filters
Reduced online time

Will be collected and


disposed of as special
waste

15.

Plant Items

16.

Plant Items

Lack of access for


maintenance and
operational checks
Feed soil building
emission control
system out of service

Atmosphere unsuitable
for personnel

Likely to be confined
space entry if the feed
soil building emission
control system fails

17.

Plant Items

Wayward FEL
operation etc

Damage to feed hopper,


conveyors etc

Will provide Jersey


barriers

18.

Electrical

Magnetic field from


tramp metal collector

Impact on people with


pacemakers

Check impact of magnet on implanted


pacemakers and any other critical
electrical devices

A5.4

BG

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Dryer and Cyclone

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10002 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

No further action required

No further action required

No further action required

SAFEGUARDS
19.

General
Discussion (note
the cyclones
remove particles
to 30 microns)

LEL exceeded in the


dryer

Explosion

20.

High Flow /
High Level

Knockout box
blockage

Dryer full of soil


requiring confined space
for cleaning

21.

High Flow /
High Level

High gas flow

Overheating of materials
and hence the potential
for equipment damage

With the soil at


Villawood, the LEL
cannot be exceeded.
Therefore do not need
pop-off damper and
other such provisions
Low soil temperature
and position switches on
the sluice gate or rotary
valve will initiate action
prior to significant
consequential impact
Plant will shut down
from high temperature in
the flue gases (back up
thermocouples
provided).
Steel designed for 650
deg. C

A5.5

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Dryer and Cyclone

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10002 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
22.

Low Flow /
Low Level

Low solid separation


in cyclones from a
plant turndown
Unplanned plant
shutdown

23.

Zero Flow /
Empty

24.

Reverse Flow

Burner continues to
run when the ID fan
stops

25.

High
Temperature

Hot exterior of dryer


and ductwork

Baghouse overloaded

Material sitting hot in the


bottom of the dryer can
deform the dryer drum
High temperature
damage to the dryer or
injury to personnel if
flames are emitted from
the dryer

Burns to personnel

Cyclones designed for


minimum turndown of
the burner
Drum must be able to
turn
Run on of the fan when
shutting down and the
draft from the stack will
initially prevent damage
and the burner flame is
contained within the
dryer, i.e. no potential
for impact on personnel
Personal protection, e.g.
mesh guards or
insulation, will be
provided for surfaces
over 60 deg. C

A5.6

No further action required

Make provisions to turn the drum in


case of plant, including power,
shutdown, e.g. manual jogging
No further action required

No further action required

KC

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Dryer and Cyclone

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10002 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
26.

Plant Items

Dryer flight breakage

Equipment damage

27.

Electrical

Lightning

Instrument damage

28.

Instruments

Routine maintenance
checks and operator
response to noise from
within the dryer

A5.7

No further action required

Review the need for lightning (surge)


protection of the instruments

KC

Ensure redundant pressure transmitters


on the dryer, i.e. separate transmitters
for control and trip actions

KC

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Thermal Oxidiser

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10006 Rev A

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

No further action required

No further action required

No further action required

SAFEGUARDS
29.

General
Discussion

Burner continues to
run when the ID fan
stops

High temperature
damage to the burner or
injury to personnel if
flames are emitted from
the burner

30.

High Flow /
High Level

High feed rate

Thermal oxidiser (TO)


residence time less than
design

31.

High Flow /
High Level

Buildup of slag in
bottom of TO

Shutdown for cleanout

Run on of the fan when


shutting down and the
draft from the stack will
initially prevent damage
and the burner flame is
contained within the
burner, i.e. no potential
for impact on personnel
TO designed for > 2
seconds at maximum
flow plus there is some
extra time in the ducts to
the baghouse
Special burner / inlet
gas design eliminates
creation of sticky
particles and
agglomeration

A5.8

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Thermal Oxidiser

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10006 Rev A

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
32.

Low Pressure

ID fan draws too


much flow

Worst case could


extinguish burner

33.

High
Temperature

Equipment damage

34.

High
Temperature

Too much natural


gas flow due to the
control temperature
transmitter reading
too low
Refractory failure

35.

Low Temperature

Loss of process
control due to the
control temperature
transmitter reading
too high

Fail to achieve
regulatory destruction
temperature

Shell temperature rises


(would probably see
glow on the outside of
the shell)

Burner management
system takes control,
i.e. flameout detector
shuts of the natural gas
flow
TO temperature trips
plus there are also
downstream
temperature controls

No further action required

No further action required

Plant operators will


regularly shoot
measurements with an
infrared gun to detect
hot spots
Thermocouples in series
will pick up temperature
discrepancies.
Calibration instrument
has been purchased

No further action required

No further action required

A5.9

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Thermal Oxidiser

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10006 Rev A

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
36.

Low Temperature

Emergency stop

37.

Plant Items

Flame impingement
on shell opposite
burner

38.

Plant Items

Dust in the TO

Residual material in the


TO cools with potential
to form other
compounds, e.g.
dioxins, furans
Damage to vessel shell

Flame detector does not


see the flame and
hence nuisance trips

Slow cooling allows


plant to be purged of
gases using ID fan

No further action required

Burner entry is longer


than burner flame length
so direct flame
impingement not
expected
Flame sensor is selfchecking and air
purged. System fails
safe

No further action required

No further action required

A5.10

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:
Evaporative Cooler including the Air
/ Water Flows

LEADER:

Dean Shewring

DRAWING:

MINUTES BY:

Peter ODea

No.

Orica, Villawood, DTD Project

C143-PF-96D-DTDU-10007 Rev B

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
39.

General
Discussion

Power failure

40.

General
Discussion

Rapid quenching
does not occur

41.

High Flow /
High Level

False low
temperature reading
at the outlet duct

42.

High Flow /
High Level

Dilution air damper


open when it should
not be

Loss of water flow


leading to high
temperature and hence
damage to equipment,
e.g. the downstream
scrubber
Dioxin formation

Too much water flow


resulting in pooling in
the vessel bottom
causing corrosion
Nothing unsafe just a
change in plant
pressure

Inlet water valve fails


open

Show the inlet water valve on the P&ID


to fail open designate as FO

Design is to quench to
below 200 deg. C in
1 second
Water will evaporate.
Operator is constantly
observing temperature
to the baghouse
Will be detected through
plant pressure controls

No further action required

A5.11

Review the need to install a low


temperature alarm on the existing
downstream thermocouple
No further action required

KC

RM

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:
Evaporative Cooler including the Air
/ Water Flows

LEADER:

Dean Shewring

DRAWING:

MINUTES BY:

Peter ODea

No.

Orica, Villawood, DTD Project

C143-PF-96D-DTDU-10007 Rev B

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
43.

High Flow /
High Level

ECU (emission
control unit) water
pump keeps running
when the
evaporative cooler is
shutdown

Bottom of the
evaporative cooler
floods

44.

Low Flow /
Low Level

Loss of water flow

45.

Low Flow /
Low Level

46.

Reverse Flow

Low air flow, even if


air pressure is
maintained due to
the air nozzle
clogging
Hot gases out the
open dilution
damper??? - no
record of this
happening

High temperature and


hence damage to
equipment, e.g. the
downstream scrubber
Large water particles
created. Inefficient
cooling. Control system
calls for more water
Burns to nearby
personnel

Procedures dictate
pumps to be manually
shut down when the
plant stops.
Water will come out the
dilution air damper and
become visible
Dilution air damper
opens. If control not
regained, plant trips

No further action required

Operator is constantly
observing temperature
to the baghouse and a
low temperature alarm

No further action required

Damper located
sufficiently high to avoid
damage

No further action required

A5.12

Dilution air damper to be as close to the


evaporative cooler outlet duct as
possible for effective cooling

KC

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:
Evaporative Cooler including the Air
/ Water Flows

LEADER:

Dean Shewring

DRAWING:

MINUTES BY:

Peter ODea

No.

Orica, Villawood, DTD Project

C143-PF-96D-DTDU-10007 Rev B

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
47.

Impurities

Oil from the air


compressor

Could send some of the


stack readings high

48.

Change in
Composition or
Concentration /
Two-Phase Flow
/ Reactions
Testing

Poor spray nozzle


atomisation

Pooling in the vessel


bottom causing
corrosion

Bypass valves on the


air or water supply
left open

No serious outcome

49.

The compressor will be


oil-free or have a
coalescing filter
Nozzles can be
withdrawn and tested

Confirm compressor selection and


hence no oil will flow to the evaporative
cooler
No further action required

Bypasses are useful for


maintenance purposes
and are to be retained

No further action required

A5.13

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Baghouse and Dust Screws

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10004 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
50.

Low Flow /
Low Level

Inadequate air
pulsing

Bags become blinded

High differential
pressure alarm

Review the air pulsing duration and


frequency in the detailed design

51.

Zero Flow /
Empty

Dust goes solid and


hence maintenance
access is required

Procedure is to run and


empty the dust screw for
prolonged shutdowns

No further action required

52.

Zero Flow /
Empty

Dust in the bottom of


the baghouse plus
moisture, e.g. during
a shutdown
Backup of dust if a
screw conveyor fails

Dust is held-up in the


system

No further action required

53.

Impurities

Dust screw blocked

No further action required

54.

Plant Items

Torn bags falling


onto the dust screw
in the bottom of the
baghouse
Bag failure

The last screw runs


nd
faster than the 2 last
which runs faster than
dust screw at the
baghouse bottom to
prevent dust being heldup
A grate is provided at
the bottom above the
baghouse dust screw
PM10 analyser and low
differential pressure
alarm

No further action required

Dust not collected

A5.14

RM

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:

Baghouse and Dust Screws

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10004 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
55.

Plant Items

Moisture ingress

Corrosion, e.g. of the


baghouse dust screw
conveyor

Appropriate materials of
construction

A5.15

No further action required

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:
Scrubber (gas stream to
atmosphere) including the Induced Draft Fan

LEADER:

Dean Shewring

DRAWING:

MINUTES BY:

Peter ODea

No.

Orica, Villawood, DTD Project

C143-PF-96D-DTDU-10005 Rev B

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

DONE

No further action required

No further action required

No further action required

SAFEGUARDS
56.

General
Discussion

HCl will be present at


elevated
temperatures
Low plant feed rate

Corrosion and hence


equipment damage

57.

Low Flow /
Low Level

58.

Impurities

Baghouse failure

Solids through to the


scrubber

59.

Plant Items

Stack top silencer


corrosion

Higher risk maintenance


due to work at heights

60.

Plant Items

Stack top silencer


corrosion (as above)

Higher risk maintenance


due to work at heights

Low stack velocity, poor


dispersion

Appropriate materials of
construction will be
provided
The stack top diameter
will be such that the
minimum velocity to
ensure good dispersion
will be maintained at the
design plant turndown
TDS (total dissolved
solids) analyser
provided
Fan is silenced.
Unsure if the stack top
needs to include a
silencer
Fan is silenced.
Unsure if the stack top
needs to include a
silencer

A5.16

Check the need from the noise studies


for a stack top silencer not preferred
as it will be difficult to maintain
If uncertain about the need for a stacktop silencer, make provision for bolting
one on later (including allowance for the
weight)

POD

KC

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Keith Chapman,


Rudy Maes, Cameron McLean, Lindsay Killin, Brett
Garton

SYSTEM:
Scrubber (gas stream to
atmosphere) including the Induced Draft Fan

LEADER:

Dean Shewring

DRAWING:

MINUTES BY:

Peter ODea

No.

Orica, Villawood, DTD Project

C143-PF-96D-DTDU-10005 Rev B

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 23/1/2012

ACTION RECOMMENDED

BY

Provide safety showers with insulated


pipes (to prevent hot water flowing
during high ambient temperatures),
green fluoro light above the shower, a
flow sensor to alarm when a person is
using a shower and procedures for lone
workers

LK

DONE

SAFEGUARDS
61.

Plant Items

Caustic leak

Splashing and corrosive


burns to personnel

Safety showers

A5.17

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Gwenda Lister, Keith Chapman, Rudy Maes,


Lindsay Killin, Brett Garton

SYSTEM:
Feeds

Scrubber Make-up Water Supply

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10005 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 27/1/2012

ACTION RECOMMENDED

BY

DONE

No further action required

No further action required

No further action required

SAFEGUARDS
62.

General
Discussion

Dust carryover from


baghouse

Demister blockage and


hence high scrubber
differential pressure

63.

General
Discussion

Power failure and the


recycle pumps stop

Loss of containment of
acidic gases to
atmosphere

64.

General
Discussion

Failure of the check


valve to the scrubber
quench

Caustic flows back to


the towns water tank

Sprays onto demister,


high differential
pressure alarm across
the scrubber
Emergency power
generator feeds the
scrubber pumps,
analysers installed on
the scrubber stack
The makeup water
supply main block valve
to the scrubber quench
is normally closed and
will only be opened
when the scrubber
recycle pumps are not
operating

A5.18

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Gwenda Lister, Keith Chapman, Rudy Maes,


Lindsay Killin, Brett Garton

SYSTEM:
Feeds

Scrubber Make-up Water Supply

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10005 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 27/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
65.

General
Discussion

66.

General
Discussion

67.

General
Discussion

Review need for the low flow alarm on


the make-up water supply line to the
quench as this will be a nuisance alarm
during normal operation when there is
no flow in this line (i.e. as above, this
line is left isolated when the scrubber
recycle pumps are running)
Check with BK the reason for installing
the flow meter in the make-up water
supply line to the quench given the
operation is manual
Show on the P&ID the sump pump and
its controls

A5.19

RM

POD

KC

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Gwenda Lister, Keith Chapman, Rudy Maes,


Lindsay Killin, Brett Garton

SYSTEM:
Feeds

Scrubber Make-up Water Supply

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10005 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 27/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
68.

High Flow /
High Level

Solenoid valve to the


scrubber sump fails
open

Scrubber sump fills and


then overflows via the
emergency overflow

69.

Zero Flow /
Empty

Solenoid valve to the


demister sprays is
stuck closed

Buildup of solids on the


demister resulting in
high scrubber
differential pressure

70.

Reverse Flow

Acidic gases absorb


back into the makeup water feed lines

Corrosion of the piping


and piping items

Sump high level alarm.


pH meter will detect a
drop in pH.
The emergency
overflow is sized for all
make-up water supply
flows operating together
at maximum rates.
Bunded area if it does
overflow
Scrubber DP high alarm

Appropriate materials of
construction, e.g.
stainless steel or plastic

A5.20

nd

Show on the P&ID the 2 level detector


in the scrubber sump to separate the
control and trip functions

KC

Include in the functional description a


low flow alarm that is only active when
the solenoid valve to demister sprays
should be open (i.e. to avoid a nuisance
alarm when the solenoid is meant to be
closed)
No further action required

RM

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Gwenda Lister, Keith Chapman, Rudy Maes,


Lindsay Killin, Brett Garton

SYSTEM:
Feeds

Scrubber Make-up Water Supply

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10005 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 27/1/2012

ACTION RECOMMENDED

BY

Amend the P&ID to show actual types of


valves: electric or pneumatic actuation

KC

DONE

SAFEGUARDS
71.

Plant Items

Control valves
wrongly selected,
e.g. solenoids for
larger (100 to 150
mm) lines not
appropriate

Loss of plant control

Correct valve selection

A5.21

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Gwenda Lister, Keith Chapman, Rudy Maes,


Lindsay Killin, Brett Garton

SYSTEM:

Scrubber Recycle

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10005 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 27/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
72.

General
Discussion

Scrubber recycle
pump failure

Plant shuts down


(accepted response)

Manual changeover of
pumps

No further action required

73.

High Flow /
High Level

Pump seals fail

Release of 80 C liquid.

Operator regular
inspection and
maintenance as
required

No further action required

pH meter will alarm high


pH

No further action required

Routine manual
sampling of the
scrubber recycle liquid.
pH meter including a
low alarm.
CEMS stack analysers,
e.g. NOx and SOx will
also rise and alarm for
operator response

No further action required

74.

High Flow /
High Level

Overdosing caustic

75.

Low Flow /
Low Level

Underdosing caustic
(e.g. from pH meter
drifting, failure to top
up the caustic IBC)

Slow leak only expected


from these types of
pumps
High pH no significant
consequences identified
Lack of absorption of
acidic gases and hence
atmospheric emission

A5.22

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Gwenda Lister, Keith Chapman, Rudy Maes,


Lindsay Killin, Brett Garton

SYSTEM:

Scrubber Recycle

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10005 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 27/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
76.

Low Flow /
Low Level

Nozzles fall off the


reflux distributor
(screw type which
can unwind)

Inadequate liquid / gas


contact due to
channelling in the
packing

77.

Low Flow /
Low Level

Loss of scrubber flow

Increase in temperature
in the plastic packing
with possible damage

78.

Zero Flow /
Empty

Valve left shut before


the scrubber liquor
analysers

79.

Reverse Flow

Recycle flow goes


back to the caustic
pumps

Analysers do not detect


changes in pH or
conductivity hence the
potential for poor
scrubber performance
Overpressure, loss of
containment at the
caustic IBC

Nozzles to be screwed
in tight and are
replaceable through the
side of the scrubber
column
Correct packing
selection

Operator observes
signals not fluctuating,
analysers in the stack
will alarm
Pressure control valve
in the common delivery
line from the caustic
pumps

A5.23

No further action required

Ensure the scrubber packing can


withstand higher temperatures due to
deviations in the recycle scrubber flow
rate
Include in the functional description flatline detection on the signals from the pH
and conductivity analysers

Review need for a check valve in the


common caustic pump discharge line

RM

RM

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Gwenda Lister, Keith Chapman, Rudy Maes,


Lindsay Killin, Brett Garton

SYSTEM:

Scrubber Recycle

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10005 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 27/1/2012

ACTION RECOMMENDED

BY

DONE

No further action required

No further action required

SAFEGUARDS
80.

High
Temperature

Hot pipelines (i.e.


approximately 80 C)

Burns on contact

81.

Impurities

Blockage in the
scrubber

82.

Change in
Composition or
Concentration /
Two-Phase Flow
/ Reactions
Testing

Iron oxide dust not


collected in
baghouse
Solids buildup in
system

High flow when


taking samples

Splashing

83.

Pipes above 60 deg. C


potentially in contact
with personnel to be
provided with personnel
protection through
insulation, mesh
guarding, signage, etc
Operator checks for
water discolouration

High conductivity but


this is a slow process
and can be controlled
manually

Manual blowdown to control conductivity


is appropriate. Therefore, delete the
actuated blowdown valve and upstream
/ downstream isolation valves
Valves (e.g. gate type)
that can be slowly
cracked open, PPE

A5.24

No further action required

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Gwenda Lister, Keith Chapman, Rudy Maes,


Lindsay Killin, Brett Garton

SYSTEM:

Liquid Feeds to Pugmill

LEADER:

Dean Shewring

MINUTES BY:

Peter ODea

DRAWING: C143-PF-96D-DTDU-10009 &


C143-PF-96D-DTDU-10003 Rev B
No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 27/1/2012

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
84.

General
Discussion

Pump requires
maintenance

The pump discharge


(i.e. after the check
valve) needs to be
flushed for maintenance

85.

General
Discussion

Power failure

Loss of water to the


pugmill dust release in
the area

86.

General
Discussion

Review the need for individual drain


valves on the discharge of each pump
(as per the scrubber recycle pumps) for
maintenance purposes when the other
pump is still operational
Show the flow control valve to the
pugmill as fail open on the P&ID
Hazop suspended until the liquid
balance assessment is carried out on
the liquid feeds to the pugmill.
Preference is to use treated water
instead of Towns Water for sustainability
reasons.
Note: the current design requires
makeup water via the scrubber and
hence excessive caustic usage will
result.
It is expected the liquid feed system
design will change and then the HAZOP
should be performed

A5.25

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

TEAM MEMBERS:

Gwenda Lister, Keith Chapman, Rudy Maes,


Lindsay Killin, Brett Garton

SYSTEM:
Soil to and from the Pugmill
(including the cyclones underflow)

LEADER:

Dean Shewring

DRAWING: C143-PF-96D-DTDU-10002 &


C143-PF-96D-DTDU-10003 Rev B

MINUTES BY:

Peter ODea

No.

Orica, Villawood, DTD Project

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 27/1/2012

ACTION RECOMMENDED

BY

DONE

No further action required

No further action required

SAFEGUARDS
87.

Low Flow /
Low Level

88.

Zero Flow /
Empty

89.

Zero Flow /
Empty

Rock, metal piece,


etc gets into the
pugmill
Screw conveyor
below the cyclones
or rotary valve stops
Loss of water

Baghouse drive
overloads and
equipment damage
High dust flow to the
baghouse
Soil too hot, potential
damage to conveyor
belts, burns, etc.
Potential for a build-up
of solids in the dryer and
hence heat damage to
the dryer

90.

High
Temperature

Loss of water to the


pugmill

Potential for burns from


the hot treated soil

High current detected


shutting down the
pugmill
Pressure measurements
and/or operator will shut
down the plant
High temperature
alarms.
Camera shows high
dust.
Constant operator
attendance.
Operator shuts down
pugmill if it cannot be
controlled
Temperature alarms.
Operator intervention

A5.26

Show on the P&IDs a trip of the dryer if


the pugmill is shut down

RM

Ensure barriers, etc so people cannot


come into contact with hot material

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Gwenda Lister, Keith Chapman, Rudy Maes,


Lindsay Killin, Brett Garton

SYSTEM:

Overview

LEADER:

Dean Shewring

DRAWING:

All Drawings

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 27/1/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
91.

Toxicity

No further issues
identified with the
overview guide
words

No further action required

A5.27

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Caustic IBC and Pumping System

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10011 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
92.

93.

General
Discussion

General
Discussion

Note only:

No further action required

The caustic storage


vessel will be an IBC
manual
changeover via
hoses to a second
IBC about once per
week (with a portable
plastic bund
underneath)
Note only:

No further action required

The pumps will be


diaphragm pumps
with internal pressure
relief, manual
changeover, located
in a bund and a
safety shower nearby

A5.28

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Caustic IBC and Pumping System

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10011 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

PCV 1082C to have a pressure indicator


integral to the valve to allow the
operators to set the pressure on the
regulator and monitor its performance
No further action required

LK

DONE

SAFEGUARDS
94.

General
Discussion

95.

High Flow /
High Level

Overdosing caustic

pH exceeds limit In the


scrubber recycle circuit
no significant
consequences identified

96.

High Flow /
High Level

Loss of containment,
e.g. forklift tynes
puncture the IBC,
hose failure, etc

Potential to cause injury


to personnel

pH meter and alarm (it


is expected to be
reliable in this service
with routine
maintenance)
P10 high pressure
plastic piping, no joints
outside the bunded area

A5.29

No further action required

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Caustic IBC and Pumping System

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10011 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

Determine the maximum temperature


rise and whether there is a detrimental
effect on the scrubber system materials
of construction.

TT

DONE

SAFEGUARDS
97.

High Flow /
High Level

Pumping caustic
when the plant is
shut down

Scrubber sump
overflow.
Temperature rise due to
heat of mixing

High level alarm in the


scrubber sump

Calculate the volume in the scrubber


sump between the normal highest level
and overflow to check that a maximum
3
of 1 m from an IBC will not result in
overflow from the scrubber overflow
pipe.

98.

High Flow /
High Level

Stormwater falling
into the bunded area

Stormwater
management required

Bunded area, sump,


discharge to water
treatment plant

A5.30

Review the need for a hard wired trip to


stop the caustic pump if being run in
manual. Also, review the need for PLC
alarms to indicate that the caustic pump
is left running in manual and hence the
control system trips etc will not be
functional
No further action required

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Caustic IBC and Pumping System

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10011 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
99.

High Flow /
High Level

Pipe breakage, e.g.


mechanical impact

100.

Low Flow /
Low Level

101.

Zero Flow /
Empty

Empty IBC, leaks,


pump not fast
enough
Valves shut, IBC
empty, pump
deadheaded

102.

Reverse Flow

No credible causes
identified given the
safeguards

Caustic leak with the


potential to harm
personnel
Loss of acidic gas
scrubbing
Potential to exceed the
piping system design
pressure for the
deadhead case and
hence result in a loss of
containment of caustic
which could harm
personnel

Strong materials of
construction for the
proposed tubing
pH alarm and interlock,
scrubber stack
analysers and alarms
Internal pressure relief
to be included with the
pump, pH meter and
alarm in the scrubber
recycle circuit

Ensure that the small bore caustic


piping is adequately protected from
mechanical impact
No further action required

Non return valve, PCV


1082C will close when
the caustic pump stops,
suction and discharge
valves for the pump will
also act to prevent
reverse flow

A5.31

LK

No further action required

No further action required

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Caustic IBC and Pumping System

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10011 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
103.

Low Pressure

IBC vent left closed

Suck in the IBC

104.

High
Temperature

Heat of dilution with


caustic and water

No significant
consequences identified

105.

Low Temperature

Standby pump
freezes on cold night

106.

Low Temperature

Pump pressure relief


inlet and outlet lines
freeze

107.

Plant Items

IBC changeover

No caustic flow to the


scrubber when pumps
changed over
Loss of deadhead
protection for the caustic
pump and hence the
potential for a loss of
containment of caustic
which could harm
personnel
Potential incidents
associated with forklift
trucks and hose
disconnection and
reconnection

Procedures and training


for bung removal or
some IBCs have vents
included
Materials adequate for
100 deg. C

No further action required

No further action required

pH alarm and interlock,


scrubber stack
analysers and alarms

Delete the standby pump and piping and


provide a spare pump in store

LK

Review the need for insulation or heat


tracing on the pump pressure relief inlet
and outlet lines

LK

Review the layout for forklift accessibility


as well as the operability of the caustic
hose connections including hose
draining

LK

A5.32

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Towns Water Tank

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10009 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

Thoroughly flush the Towns Water


supply pipe during commissioning to
ensure all residual solids are removed
(plus check quality of gas supply with
respect to solids in the pipeline as well)
Ensure the Towns Water pipe from the
Sydney Water main is large enough to
avoid the need for a booster pump, i.e.
delete the booster pump and fill the
Towns Water tank directly from the
Sydney Water mains supply
Show other consumers of Towns Water
on the drawing, e.g. safety showers,
ablutions, etc. These off-takes are to be
from the supply pipe upstream of the
Towns Water tank for supply quality
reliability (e.g. no process contaminants
due to reverse flow)
Ensure the Towns Water supply line is
away from the project excavation areas

GL

DONE

SAFEGUARDS
108.

General
Discussion

109.

General
Discussion

110.

General
Discussion

111.

High Flow /
High Level

Supply pipe
ruptured, e.g. by
backhoe

Tank fails to fill. No


water flow to the ECU,
pugmill, scrubber, etc

Low pressure and flow


alarms and trips on the
downstream water users

A5.33

LK

LK

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Towns Water Tank

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10009 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

DONE

No further action required

The tank overflow is to be lower than the


water inlet to ensure there the risk of
reverse flow into the Towns Water
supply line to the tank is as low as
possible
No further action required

SAFEGUARDS
112.

Low Flow /
Low Level

113.

Reverse Flow

114.

Impurities

115.

Plant Items

116.

Plant Items

Level control valve


insufficiently open

Frogs, vermin, etc in


tank

Work at heights
when maintaining the
tanks level
transmitter

Tank fails to fill. No


water flow to ECU,
pugmill, scrubber, etc

Blockage of the water


supply pumps inlet
strainers

Potential for falls and


serious injuries

Low pressure and flow


alarms and trips on the
downstream water users

Pump strainer
maintenance and
downstream pressure
and flow alarms

Permit to work system


including controls for fall
prevention

A5.34

Locate the LCV close to the Towns


Water tank roof manhole for ease of
inspection and maintenance
Use a differential pressure transmitter
for tank level measurement (located at
grade) in lieu of an ultrasonic transmitter
on top of tank

LK

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Towns Water Tank

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10009 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
117.

Plant Items

Work at heights
when maintaining the
tanks LCV

Potential for falls and


serious injuries

Permit to work system


including controls for fall
prevention

118.

Instruments

Failure of the sight


glass

Water leaks

Maintenance and
replacement of the sight
glass

A5.35

Review to option for replacing the roof


mounted level control valve to one at
grade (i.e. eliminate the need for a float
valve at the top of the tank and hence
work at heights injuries)
Review type of sight glass level
indication and also the need for a sight
glass for LI1074 to minimise the risk of
leaks

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Towns Water Pumping Systems

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10009 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

The scrubber blowdown (max 20-40


l/min) will go directly to the pugmill from
the discharge side of the scrubber
recycle pumps, not via the pugmill water
supply pumps.

TT

DONE

SAFEGUARDS
119.

General
Discussion

As this line has not been HAZOPed,


perform a formal design change
assessment when the final design
details are known.

120.

General
Discussion

121.

General
Discussion

Therefore, pumps PUI-0907 and 0908


are duty/standby and are the same
design as the other water pumpsets
shown on this P&ID
Review the need to replace the 6 Y-type
strainers with 2 strainers in the common
suction line to all pumpsets (ease of
maintenance)
Add an isolation valve upstream of
PCV1052 (to be consistent with the
other water pumping systems design)

A5.36

TT

TT

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Towns Water Pumping Systems

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10009 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

DONE

No further action required

No further action required

SAFEGUARDS
122.

123.

124.

High Flow /
High Level

Low Flow /
Low Level

Zero Flow /
Empty

Running 2 pumps
simultaneously

Blocked strainers,
valves gagged,
pump problems

Loss of water to the


ECU

No significant
consequences identified

Loss of the required flow


to the ECU, scrubber
and pugmill (as
previously HAZOPed
above)

Duty/standby selector
switch.
Flow controls
downstream will ensure
the users only take what
water they need
Alarms and trips at each
user of the water, e.g.
low pressure or flow.
Critical pumps can be
started manually when
emergency generator
started

Potential for heat


damage to the water
spray nozzles when the
plant is tripped on low
water flow

Confirm that the nozzles are made from


appropriate materials of construction for
high temperature following a plant trip

A5.37

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Towns Water Pumping Systems

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10009 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

As per Plant Items, review the materials


of construction for all equipment
throughout the plant

LK

DONE

SAFEGUARDS
125.

Reverse Flow

Loss of the quench


water pumps to the
scrubber

126.

Reverse Flow

Pumps stops, e.g.


loss of power

127.

Plant Items

Acidic vapours, etc


throughout the plant

128.

Electrical

Power failure

Potential for acidic mist


to absorb into the water
in the supply pipe to the
scrubber and cause
corrosion
Water in the pipes to the
ECU and scrubber flows
back and hence drawing
gases from these
vessels, i.e. corrosion
potential as above
Corrosion of equipment
as above
Loss of critical
equipment

As above, the correct


materials of construction
are to be confirmed

Emergency generator

A5.38

No further action required

Review the materials of construction for


all equipment throughout the plant

LK

Confirm the required items connected to


the emergency power supply

BK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Instrument and Compressed Air

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10010 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
129.

General
Discussion

130.

General
Discussion

131.

General
Discussion

Historical incidents
involving oil filled
compressors running
too hot and hence
cracking the oil

The cracked oil can


leave dust deposits
within the piping system
and hence is an internal
dust explosion hazard

Running the air


compressor within the
design limits, routine oil
sampling and
replacement

A5.39

Review the need for the standby air


compressor, including the need for the
isolation valve on the discharge of
compressor AC-1002. Delete if not
required
The air compressor is to be oil free

LK

Review the final design details from


vendor for the compressor and dryers
(HAZOP assumes desiccant dryer)
including inlet air strainer, check valve to
avoid depressurisation of the air
receiver when the compressors trip, dew
point measurement, weatherproofing to
avoid rain ingress to the compressor
suction, signals to control room,
functional logic, etc

LK

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Instrument and Compressed Air

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10010 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
132.

General
Discussion

133.

General
Discussion

134.

General
Discussion

135.

General
Discussion

A5.40

The maximum air pressure is to be


designed for adequate operation of the
ECU nozzles (possibly 10 barg plus)
Update the air compressor P&ID to
show all air users, e.g. the ECU

LK

Rationalise the number, location and set


pressure for the pressure regulators
(e.g. PCV1079A/B/C appear to be
controlling the same pressure and
hence there is the potential for these
regulators to hunt). For the required
pressure regulators, supply pressure
indication for testing and monitoring
purposes
Make the complete system dry air (i.e.
dry air is required to all users) to avoid
wet air blocking the baghouse filter
bags. This will remove the additional air
receiver, associated equipment and
controls

LK

LK

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

Instrument and Compressed Air

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-DTDU-10010 Rev B

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
136.

High Flow /
High Level

Regulator failure

137.

Zero Flow /
Empty

Loss of power

138.

High Pressure

Compressor
deadheaded

139.

High
Temperature

Heat from 10 bar


pressure requirement

Potential for the


maximum air supply
pressure to be within the
supply pipe to the final
isolation valve at each
air user
No air to users

Confirm that the design is rated for full


air pressure to the final isolation valves
for each air user

Low pressure alarms


and trips

Potential for equipment


damage and possible
failure leading to
missiles, i.e. harm to
people and damage to
equipment
Potential high
temperature damage to
the downstream
equipment

No further action required

Make sure the vendor package has


appropriate safeguards for compressor
deadhead and if a blow off valve /
pressure safety valve is provided then it
should not yield unacceptable noise
levels (e.g. provide a silencer)
Review the maximum compressor
discharge temperature and ensure that
adequate safeguards are included, e.g.
ensure the compressor package has a
cooler

A5.41

LK

LK

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong

SYSTEM:

OVERVIEW

LEADER:

Dean Shewring

DRAWING:

Caustic, Water and Air P&IDs

MINUTES BY:

Peter ODea

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 26/6/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
140.

Commissioning

141.

Commissioning

Foreign objects in
the pipes during
commissioning

Potential to damage
equipment

142.

Commissioning

Potential for dioxin


formation from the
plant

Impact to people and


the business

143.

Commissioning

144.

Materials of
Construction

Potential
incompatibility of the
materials of
construction with the
process materials

Provide high point vents and low point


drains for hydrotesting once the piping
layout drawings are known
Provide temporary cone strainers,
remove sensitive instruments and
valves, etc for line flushing during
commissioning
Incorporate the learnings from the
ATMR plant commissioning especially
re dioxin prevention and control
Provide sufficient process sampling
points between the main plant items to
be able to measure gas composition
and diagnose problems, e.g. levels of
unwanted by-products
Review the compatibility of the chosen
materials of construction, including
gaskets, with the process materials via
the Hazard Study 1 chemicals
compatibility of materials chart

Corrosion and
equipment failure with a
loss of containment

A5.42

LK

LK

TT

LK

BK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong, Peter ODea, Rudy Maes, Keith
Chapman

SYSTEM:

Air Compressor for the Evaporative


Cooler

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-CTCU-10010 (mark-up)

MINUTES BY:

Bala Kathiravelu

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 19/10/12

ACTION RECOMMENDED

BY

The tag numbers on the two air


compressor, e.g. hand switches, need to
be unique. Mark up the P&ID
accordingly
Check the vendor P&ID that high
pressure protection is provided. Also,
review the vendor supply details to
confirm adequate controls and
safeguarding is being provided, e.g.
suction screen and an aftercooler and a
high outlet temperature alarm
Minute 130 (above) regarding the need
for an oil free compressor is to be
reconsidered. If the compressor is not
oil free then provide an oil filter and
confirm the operating temperature is
less than 140 deg C exit the aftercooler

KC

DONE

SAFEGUARDS
145.

General
Discussion

146.

High Pressure

Compressor high
pressure protection
for deadheading

147.

High
Temperature

Operating the oil


flooded compressor
(to be confirmed) at
high temperatures

The compressor is a
screw compressor and
hence the potential for
overpressuring the
discharge piping with
possible failures leading
to missiles
Potential to crack the oil
and lead to a build-up
on the inside of the
pipes which can explode

A5.43

KC

KC

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong, Peter ODea, Rudy Maes, Keith
Chapman

SYSTEM:

Air Compressor for the Evaporative


Cooler

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-CTCU-10010 (mark-up)

MINUTES BY:

Bala Kathiravelu

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 19/10/12

ACTION RECOMMENDED

BY

Install an automatic condensate drain on


the receiver(s?) with an isolation valve
and bypass valve for maintenance

KC

DONE

SAFEGUARDS
148.

Low Temperature

Cooling of the air in


the air receiver

Condensate will form


and build-up within the
air receiver

Manual draining

A5.44

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong, Peter ODea, Rudy Maes, Keith
Chapman

SYSTEM:

Pugmill Water System (pumps 0907


and 0908)

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-CTCU-10009 and 10003


Rev D

MINUTES BY:

Bala Kathiravelu

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 19/10/12

ACTION RECOMMENDED

BY

Following discussion, the scrubber


blowdown is to be sent to the effluent
treatment system. The main issues being:

KC

DONE

SAFEGUARDS
149.

General
Discussion

1. The potential for corrosion in the pugmill


system, e.g. high chlorides levels in a hot,
wet environment or from changes in pH
2. Contamination of the treated soil
3. The historical problems with solids in
the scrubber blowdown causing blockages
(e.g. of the spray nozzles) and settling
(e.g. within tanks), and
4. That the treated water can be rerun and
hence is not a potential loss from plant.
Therefore, Towns Water is to be used for
the pugmill water spray systems. Also,
provide appropriate connections for a
possible future scrubber bleed blowdown
tank (if required) and allow adequate
space in the plot planning

A5.45

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong, Peter ODea, Rudy Maes, Keith
Chapman

SYSTEM:

Pugmill Water System (pumps 0907


and 0908)

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-CTCU-10009 and 10003


Rev D

MINUTES BY:

Bala Kathiravelu

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 19/10/12

ACTION RECOMMENDED

BY

Mark up the P&ID to show individual


isolation supply valves to each pugmill
spray nozzle
Show PCV1052 controlling upstream
pressure as this valve is used for
deadhead protection for the pumps
The Towns Water pumps kickback lines
are to be top entry into the Towns Water
tank (to prevent reverse flow issues
from submerged entries). Therefore
delete the isolation valves at each
kickback line nozzle to the Towns Water
tank and the check valve in the kickback
line for pumps 0907 and 0908
FCV 1019 is to be a modulating valve
and it is to fail last position on loss of air
to the actuator, i.e. show a mushroom
head valve and FLP on the P&ID
Provide an isolation valve on PI 1019B
(consistent with all PIs)

KC

DONE

SAFEGUARDS
150.

General
Discussion

Need to balance flow


to pugmill sprays

151.

General
Discussion

P&ID correction

152.

General
Discussion

P&ID correction

153.

General
Discussion

P&ID correction

154.

General
Discussion

P&ID correction

A5.46

KC

KC

KC

KC

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong, Peter ODea, Rudy Maes, Keith
Chapman

SYSTEM:

Pugmill Water System (pumps 0907


and 0908)

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-CTCU-10009 and 10003


Rev D

MINUTES BY:

Bala Kathiravelu

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 19/10/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
155.

General
Discussion

P&ID correction

156.

High Flow /
High Level

Spray nozzle
unwinding and falling
off

157.

High Flow /
High Level

158.

High
Temperature

The pugmill pump


stops and water
syphons forward
through them to the
pugmill
Note that the
scrubber blowdown
is approximately 80
deg C

Too much water flow to


the pugmill no
significant
consequences identified
Too much water flow to
the pugmill no
significant
consequences identified
Potential for burn
injuries if personnel
contact hot surfaces

A5.47

Delete the line on P&ID 1003 shown as


Cooling Water from Scrubber to the
pugmill sprays (as this was formally
used for return scrubber liquid no
longer required) and also delete PT
1019C and the associated alarms on
this line
Spot weld the spray nozzles onto the
pipes to prevent them from falling off

KC

Include in the functional description the


need to have FVC 1019 & SV 1019
closed when the pugmill pump stops

KC

Provide appropriate personal protection


to avoid burns for the scrubber
blowdown line

LK

KC

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:

Orica, Villawood, DTD Project

TEAM MEMBERS:

Bala Kathiravelu, Gwenda Lister, Lindsay Killin,


Tai Truong, Peter ODea, Rudy Maes, Keith
Chapman

SYSTEM:

Overview - Air Compressor to the


Evaporative Cooler and the Pugmill
Water System

LEADER:

Dean Shewring

DRAWING:

C143-PF-96D-CTCU-10009 and 10003


Rev D, C143-PF-96D-CTCU-10010
(mark-up)

MINUTES BY:

Bala Kathiravelu

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 19/10/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
159.

No further significant hazardous events


or operability problems identified for
these systems using the Overview
guide words

A5.48

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

SYSTEM:

High Capacity Settling Tank

LEADER:

Dean Shewring

DRAWING:

SAS10883-301 Rev A

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Delete the butterfly valve on the clarified


liquid line from the settling tank as this
line is free draining and hence does not
need to be isolated
Mark up the P&IDs to show all line
sizes, e.g. the clarified water line from
the settling tank
Delete the additional diaphragm valve
downstream of the settling tank sump
gate valves. The gate valves are at
ground level (i.e. accessible) and can be
used for isolation for pump flushing etc
instead
Ensure the coagulant pumping system
is within the IBC bunded area to contain
any leaks. Apply this action to all
chemical dosing systems

PA

DONE

SAFEGUARDS
160.

General
Discussion

161.

General
Discussion

162.

General
Discussion

163.

High Flow /
High Level

Losses of
containment from the
coagulant pumping
system

Potential environmental
consequences of
overflow to the ground

System leak checked


prior to operation, the
coagulant IBC is bunded

A5.49

PA

PA

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

SYSTEM:

High Capacity Settling Tank

LEADER:

Dean Shewring

DRAWING:

SAS10883-301 Rev A

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
164.

Zero Flow /
Empty

165.

Reverse Flow

166.

High Pressure

167.

Plant Items

Solids fouling of the


static mixer on the
inlet to the settling
tank

Deadhead of the
sludge pump

Plant downtime for


maintenance

Potential to rupture the


downstream piping
system

Operators to keep the


isolation valves open
during normal operation

A5.50

Delete the static mixer and add the


coagulant upstream in the feed line to
allow sufficient line length for mixing

PA

Confirm that design will prevent reverse


flow of coagulant to the upstream
sources (these upstream sources are to
be shown on the P&ID)
Replace the high pressure instrumented
protection system (i.e. a potential Safety
Instrumented Function to AS61511) with
a suitable mechanical over-pressure
device, e.g. a PRV or kick back line
(Note: consider the implications of
sludge fouling a PRV). Also, note that if
a PRV is installed, it should be installed
immediately downstream of the pump
for the case where the NRV is stuck in
the closed position
Confirm all off-takes from the sludge
lines are horizontal to vertical to prevent
settling and compaction of solids in the
branches

PA

PA

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

SYSTEM:

High Capacity Settling Tank

LEADER:

Dean Shewring

DRAWING:

SAS10883-301 Rev A

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Preference is to not use PVC due to


interaction between solvents and
plasticiser. If used, then the preference
is to use UPVC (i.e. un-plasticised PVC)
Install a timer on the sludge pump to
prevent excessive amounts of water
being flushed to the sedimentation tanks
and also to allow adequate flushing of
sludge pump and lines during pump
operation
Include in the SOPs the need to keep
aboveground pipework open (i.e. not
isolated) to prevent thermal
overpressure from isolated liquid being
heated by the sun
Provide means to allow flushing of the
inlet lines to the settling tank. Treated
water to be used (not potable water due
to the risk of reverse flow and hence
contamination)

PA

DONE

SAFEGUARDS
168.

Plant Items

169.

Plant Items

Operator leaves the


sludge pump running
for too long

Overfilling the
sedimentation tanks

Procedures and training

170.

Plant
I
Items

Isolation of water in
the aboveground
piping

Potential for heating by


the sun and thermal
overpressure, i.e. piping
system failure

Procedures and training

171.

Plant
P
Items

Solids settling in the


feed lines to the
settling tank

Fouling of the feed lines

A5.51

PA

PA

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

SYSTEM:

High Capacity Settling Tank

LEADER:

Dean Shewring

DRAWING:

SAS10883-301 Rev A

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
172.

Plant Items

173.

Instruments

Delete the second isolation valve on


discharge side of the coagulant dosing
pump as it is only isolating a reducer
and double isolation is not required.
Apply this action to all chemical dosing
systems
Provide a diaphragm connection to all
instruments on sludge lines in the plant
to prevent blocking of the impulse lines
from the solids

A5.52

PA

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

SYSTEM:
Feed Tank System including the
Untreated Water Basin
DRAWING:
302 Rev 0
No.

SAS10883 301 Rev A, SAS10883

GUIDE WORDS

POSSIBLE CAUSES

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

LEADER:

Dean Shewring

MINUTES BY:

Lindsay Killin

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Install a flashing light (to be visible from


the DTDU) and/or use a SMS text
warning service to alert the operators of
any unacceptable process conditions
when the plant is unattended
Review the need to overflow the pump
well bund to the adjacent bunded area
given the current containment areas
capacities

PA

Review the need for automating the


break tank recycle valves to lower the
risk of this occurring, e.g. two actuated
valves for flow path determination after
the transfer pump

PA

DONE

SAFEGUARDS
174.

High Flow /
High Level

Rain and the water


treatment plant not
available

Overfilling the untreated


water basin

Procedural control
monitoring water levels

175.

High Flow /
High Level

Draining of both
sedimentation tanks
to the feed tank, e.g.
manual valves
passing or left open

Potential to initially
overflow the feed tank
and then overflow the
pump well bund

Operator to check level


in the feed tank prior to
discharge from the
sedimentation tank.

176.

Zero Flow /
Empty

Operator does not


perform recycle from
the break tank to the
feed tank during start
up

Higher than normal


solids through to the
zeolite filters resulting in
plant recovery impacts
due to the need to
backwash the filters

High level alarms and


trip 2.1 to stop some
feed pumps into the
feed tank
SOPs and training

A5.53

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

SYSTEM:
Feed Tank System including the
Untreated Water Basin
DRAWING:
302 Rev 0
No.

SAS10883 301 Rev A, SAS10883

GUIDE WORDS

POSSIBLE CAUSES

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

LEADER:

Dean Shewring

MINUTES BY:

Lindsay Killin

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Install a screen on the inlet to the raw


water feed pump. Apply this action to all
sump pumps in the plant
Provide means to monitor the water flow
into the mixing tank, e.g. replace the
flow switch with flow meter and a low
flow trip

PA

DONE

SAFEGUARDS
177.

Impurities

178.

Instruments

Foreign objects
entering the untreated water basin
Plant inlet water
flowrate monitoring
for mass balances
and performance
checks

Blockage and/or
damage to the raw
water feed pump

A5.54

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

SYSTEM:
Flocculation Tank and Chemical
Dosing Systems (HAZOPed by Difference)
DRAWING:
No.

SAS10883 302 Rev 0

GUIDE WORDS

POSSIBLE CAUSES

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

LEADER:

Dean Shewring

MINUTES BY:

Lindsay Killin

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Review the possibility of overflowing


from the flocculation tank chamber 1 to
chamber 2 to minimise risk of short
circuiting in the first chamber and hence
inadequate mixing (i.e. use a higher
elevation overflow line)
Markup the P& ID to show the drain
valves on the flocculation tank
chambers
Show both isolation valves on the outlet
of flocculation chamber 2 from the
flocculation tank
Add a flow switch alarm to the water
supply to the proposed safety shower in
case a lone worker requires assistance
when using the safety shower
Utility station to be added to allow wash
down of any spills of flocculant

PA

DONE

SAFEGUARDS
179.

General
Discussion

180.

General
Discussion

181.

General
Discussion

182.

High Flow /
High Level

183.

High Flow /
High Level

Caustic line
breakage through
high pressure /
damage
Loss of containment
of flocculant

Potential to splash a
person and cause a
corrosive burn

System to be leak
checked prior to use,
high pressure tubing to
be used

Slip hazard

A5.55

PA

PA

PA

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

SYSTEM:
Flocculation Tank and Chemical
Dosing Systems (HAZOPed by Difference)
DRAWING:
No.

SAS10883 302 Rev 0

GUIDE WORDS

POSSIBLE CAUSES

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

LEADER:

Dean Shewring

MINUTES BY:

Lindsay Killin

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

As above, preference is to overflow from


the mixing tank (chamber 1) at a high
point which would be ideal for the
flocculant addition point to reduce the
chance of this reverse flow scenario.
Further review required
Ensure the potable water to safety
shower eyewash is protected from
reaching high temperature due to
heating by the sun

PA

Review means to ensure the caustic


does not freeze in the dosing lines

SA

DONE

SAFEGUARDS
184.

Reverse Flow

185.

High
Temperature

186.

Low Temperature

Failure of the
flocculant discharge
non-return valve and
the pump suction
and discharge
(check) valves
Water supply line to
the safety shower /
eyewash heated by
the sun
Cold winter night

Drain the entire


flocculation tank,
including both
chambers, to the
flocculant IBC

Maintenance on the
piping system and
check valves

Hot water from the


safety shower eyewash
with the potential to
render the unit
inoperable
Potential to freeze
caustic (46 to 50%), in
particular, in small bore
lines that have
intermittent flows

A5.56

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

SYSTEM:
Flocculation Tank and Chemical
Dosing Systems (HAZOPed by Difference)
DRAWING:
No.

SAS10883 302 Rev 0

GUIDE WORDS

POSSIBLE CAUSES

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

LEADER:

Dean Shewring

MINUTES BY:

Lindsay Killin

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Perform a risk assessment on the


caustic dosing point for this scenario to
check if additional safety controls are
required, e.g. cowling around the caustic
dosing point

SA

DONE

SAFEGUARDS
187.

Plant Items

Personnel or wildlife
contact with caustic
when splash filling
into the mixing tank

Corrosive burn injuries

Caustic not dosed


during maintenance (the
system is shut down).
Plant will be shutdown
during maintenance of
the pH probe

A5.57

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

SYSTEM:

Lamella Settlers

LEADER:

Dean Shewring

DRAWING:

SAS10883 303 Rev A

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
188.

General
Discussion

Apply the common actions from the


settling tank sludge pump as
appropriate, i.e. actions 7, 8 and 10.

PA

No further significant issues identified

A5.58

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

SYSTEM:
Break Tank / Zeolite Feed Tank
(HAZOPed by Difference) and the Filter Pumping
System, i.e. Filters on-line
DRAWING:
304 Rev A
No.

SAS10883 303 Rev A, SAS10883

GUIDE WORDS

POSSIBLE CAUSES

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

LEADER:

Dean Shewring

MINUTES BY:

Lindsay Killin

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Review the need for having two tanks in


series, i.e. the break tank and the zeolite
feed tank. Can the plant be operated
adequately with only one tank (e.g.
consider sludge fouling the filters at a
higher frequency if only one tank was
used). Delete one tank from the scope
if two are not required
No further action required

PA

Confirm that there are adequate


safeguards to protect against overpressure of the filters as they are
designed for maximum pressure of 250
kPag

PA

DONE

SAFEGUARDS
189.

General
Discussion

190.

General
Discussion

191.

High Pressure

Operator leaves one


or more filter manual
valves in the
incorrect position
during or after a
backwash operation
Zeolite filters outlet
valves shut

Unwanted misdirected
flows, e.g. backwash
water to the GAC feed
tank

SOPs and training


acceptable given the
consequential impacts

Potential to exceed the


design pressure of the
filters from the filter feed
pumps

PSH on filter feed


pumps discharge,
however, its set point is
unknown

A5.59

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

SYSTEM:
Break Tank / Zeolite Feed Tank
(HAZOPed by Difference) and the Filter Pumping
System, i.e. Filters on-line
DRAWING:
304 Rev A
No.

SAS10883 303 Rev A, SAS10883

GUIDE WORDS

POSSIBLE CAUSES

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

LEADER:

Dean Shewring

MINUTES BY:

Lindsay Killin

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Install an analysis point on the common


line to the GAC feed tank to allow the
operators to test the performance of the
zeolite filters

PA

DONE

SAFEGUARDS
192.

Testing

A5.60

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

SYSTEM:

Zeolite Filters Backwashing

LEADER:

Dean Shewring

DRAWING:

SAS10883 304 Rev A

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Install an additional valve downstream


of zeolite filters to isolate the filter
system from the GAC feed tank for
backwashing of the zeolite filters
Provide means to backwash all three
filters when blinded, e.g. install an
additional hose connection on common
backwash inlet to all three filters for
connecting a hose (must consider the
maximum water supply pressure to
ensure this does not exceed the filter
maximum pressure) or install a filter
bypass line to allow backwash with nonfiltered water from the zeolite filter feed
pump
Review the need for the flow switch after
the zeolite feed pumps as the PSH can
be used for filter blockage and
deadhead protection. Delete if not
required

PA

DONE

SAFEGUARDS
193.

General
Discussion

194.

Low Flow /
Low Level

195.

Instruments

All three filters


become blinded

Inability to backwash

A5.61

PA

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

SYSTEM:
GAC Feed Tank System (HAZOPed
by Difference) and GAC Filters
DRAWING:
No.

SAS10883 305 Rev A

GUIDE WORDS

POSSIBLE CAUSES

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

LEADER:

Dean Shewring

MINUTES BY:

Lindsay Killin

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Update the P&ID to show the tank liquid


outlet nozzle isolation valve

PA

DONE

SAFEGUARDS
196.

General
Discussion

197.

General
Discussion

Operator leaves one


or more GAC manual
valves in the
incorrect position

198.

High Flow /
High Level

Two pumps in
operation

199.

High Flow /
High Level

Incorrect valve
alignment

Unwanted misdirected
flows, e.g. non-treated
water to the treated
water basins, or
deadhead of the GAC
feed pump
Potential to carry over
activated carbon to the
downstream treated
water tank and beyond

SOPs and training


acceptable given the
consequential impacts

Potential contaminants
going into the treated
water feed tank and/or
dead head the GAC
feed pump

Testing of the treated


water prior to discharge
to the sewer and the
ability to rerun off-spec
water through the plant

A5.62

No further action required

The stand-by pump is to be removed


from the field and used as a hot spare
(i.e. two pump operation not possible).
Also, include in SOPs the need to only
run one pump at a time in the future to
avoid fluidisation of the GAC if a second
stand-by pump is installed
Include in the SOPs the need for
supervisory checking of valve positions
after a GAC unit valve change / change
over

PA

LK

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

SYSTEM:
GAC Feed Tank System (HAZOPed
by Difference) and GAC Filters
DRAWING:
No.

SAS10883 305 Rev A

GUIDE WORDS

POSSIBLE CAUSES

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

LEADER:

Dean Shewring

MINUTES BY:

Lindsay Killin

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
200.

High Flow /
High Level

GAC purifier feed


pump is larger in size
than the current
pump

201.

Zero Flow /
Empty

GAC feed pump


stops

Increase pumping rate


has potential to fluidise
the carbon bed and
hence the increase risk
of carry-over of GAC
Water in the GAC
purifiers will drain down
to the treated water tank
and form a vacuum in
the upper sections of
the GAC Purifiers. Also,
if the pump check valve
fails, the pressure in the
GACs will be close to a
full vacuum when
draining back to the
GAC feed tank

A5.63

Confirm the new pump will not result in


fluidisation of the GEC purifiers

SA

Confirm that the GAC vessels are


adequately rated for the maximum
vacuum that can be generated

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

SYSTEM:
GAC Feed Tank System (HAZOPed
by Difference) and GAC Filters
DRAWING:
No.

SAS10883 305 Rev A

GUIDE WORDS

POSSIBLE CAUSES

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

LEADER:

Dean Shewring

MINUTES BY:

Lindsay Killin

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Confirm that the maximum design


pressure of the GAC vessels exceeds
the maximum supply pressure from the
new pump. If not, review the need to
replace the existing PRVs with larger
valves
Install a recirculation line from the outlet
of the GACs to the GAC feed tank to
allow GAC recirculation during
downtime
Include in the SOPs the need to rinse
the zeolite filters to the sedimentation
tank via the rinse valves
Determine availability of methods to get
quick turnaround on GAC bed analyses,
or indicator tests while awaiting lab
results

LK

DONE

SAFEGUARDS
202.

High Pressure

New pump feeding


the GACs

Potential to exceed the


maximum design
pressure for the GAC
vessels as this is a
larger duty pump

203.

Impurities

Extended shutdown
(i.e. 4-5 weeks or
more)

Potential for biological


growth on the GAC and
hence deactivation

204.

Impurities

Fines from the initial


flushing of the zeolite
filters

Blinding of the activated


carbon and hence
deactivation (as above)

205.

Testing

A5.64

PA

PA

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

SYSTEM:
GAC Feed Tank System (HAZOPed
by Difference) and GAC Filters
DRAWING:
No.

SAS10883 305 Rev A

GUIDE WORDS

POSSIBLE CAUSES

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Richard Giles, Lindsay Killin

LEADER:

Dean Shewring

MINUTES BY:

Lindsay Killin

CONSEQUENCES

EXISTING

DATE: 29/11/12

ACTION RECOMMENDED

BY

Confirm the mechanical integrity of the


equipment available in the existing parts
of the WTP including the structures (e.g.
stairs and platforms) and the vessels
(e.g. routine pressure vessel inspection
and testing required?)

LK

DONE

SAFEGUARDS
206.

Plant Items

A5.65

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Lindsay Killin

SYSTEM:

Treated Water Basin System

LEADER:

Dean Shewring

DRAWING:

SAS10883 306 Rev A

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 30/11/12

ACTION RECOMMENDED

BY

As the treated water tank and pump are


not required to recover off-spec material
etc then these can be removed from the
design. To prevent draining and hence
forming a vacuum in the GACs when the
GAC feed pump stops install a
motorised solenoid valve on the
common outlet line (close to the GACs)
which is to close the when the GAC feed
pump stops.

PA

DONE

SAFEGUARDS
207.

208.

General
Discussion

Also, include position switches on this


motorised valve to allow interlocking to
pump operation, i.e. prevent pump
operation if the motorised valve is stuck
closed and raise an alarm if this valve is
open when it should be closed. The
valve should fail to the last position
Retain means to recirculate the basins,
e.g. for pH correction. Note: sampling
can be achieved by manually dipping
the basin

General
Discussion

A5.66

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Lindsay Killin

SYSTEM:

Treated Water Basin System

LEADER:

Dean Shewring

DRAWING:

SAS10883 306 Rev A

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 30/11/12

ACTION RECOMMENDED

BY

Change the destination selection valves


in pipes from the basin to ball valves.
Establish a protocol in which Orica and
EPS agree on discharge to the sewer to
minimise the risk of off-spec discharge,
e.g. supervisory checks that the valves
are in the correct position prior to
discharging to the sewer
Change the three basins inlet butterfly
valves to ball valves for improved
reliability of shut-off. These are to be
lockable ball valves to allow full isolation
of basins

PA

Provide means to mitigate the vacuum


that could be formed, e.g. install a vent
(vent could have a non-return valve to
prevent water discharge but allow air in)
or a vacuum breaker

SA

DONE

SAFEGUARDS
209.

High Flow /
High Level

Passing butterfly
valve

Relatively small amount


of off-spec material
could flow to sewer but
probably still on spec in
relation to trade waste
consent

210.

High Flow /
High Level

Putting an on-spec
basin off-spec and
hence having to rerun a
basin back through the
plant prior to discharge

211.

Low Pressure

Off-spec treated
water running to two
basins, e.g. basin
inlet valve passing or
inadvertently left
open
Motorised valve to
treated water basins
closes quickly

Visible inlets to basins


to make sure the
operator can check
visually during
inspections

Potential to form a
vacuum downstream of
the motorised valve and
suck in the poly pipe

A5.67

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Lindsay Killin

SYSTEM:

Sedimentation Tanks

LEADER:

Dean Shewring

DRAWING:

SAS10883 307 Rev A

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 30/11/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
212.

General
Discussion

213.

General
Discussion

Review the option of using bulkabags


under the sedimentation tank drains
instead of the drying beds to improve
ease of handling of sludge
Mark up the P & ID to show the bund
under the sedimentation tanks

A5.68

LK

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Lindsay Killin

SYSTEM:

Sedimentation Tanks

LEADER:

Dean Shewring

DRAWING:

SAS10883 307 Rev A

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 30/11/12

ACTION RECOMMENDED

BY

As an option in the SOPs put the sludge


line from the high capacity settler to only
one of the sedimentation tanks, i.e.
minimise the risk of blocking both tanks
with the higher sludge containing stream

PA

Operation to be reviewed during


commissioning and bulkabags
considered as alternative option to beds
if the beds are blocked too often

LK

DONE

SAFEGUARDS
214.

Zero Flow /
Empty

Sludge caking within


the sludge outlet line

Inability to drain the


sedimentation tank

215.

Zero Flow /
Empty

Fouling of the sand


dryer bed with the
sludge

Inability to drain through


the beds

Lines can be rodded.


Sedimentation tank to
be isolated by the first
outlet valve and the
second outlet valve is to
remain open (to prevent
sludge blockages
between these two
valves). For improved
operation, the
preference is to keep
one tank offline and
hence have the option
to use this standby tank
should the first
tank/lines become
blocked

A5.69

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Lindsay Killin

SYSTEM:

Sedimentation Tanks

LEADER:

Dean Shewring

DRAWING:

SAS10883 307 Rev A

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 30/11/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
216.

Plant Items

217.

Instruments

Personnel exposed
to DDT etc contained
within the sludge

Health impacts on
personnel

SWMS/JSA to be
performed on sludge
handling, e.g. disposal
via the DTDU

No further action required

Position the level switch in each


sedimentation tank for ease of
maintenance access and away from the
sludge inlet to avoid any materials
potentially seizing up the instrument

A5.70

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

PINNACLE RISK MANAGEMENT - HAZOP RECORD SHEET


PROJECT:
Plant

Orica Villawood Water Treatment

TEAM MEMBERS:

Bala Kathiravelu, Peter ODea, Pearce Anderson,


Lindsay Killin

SYSTEM:

Overview

LEADER:

Dean Shewring

DRAWING:

All WTP P&IDs

MINUTES BY:

Lindsay Killin

No.

GUIDE WORDS

POSSIBLE CAUSES

CONSEQUENCES

EXISTING

DATE: 30/11/12

ACTION RECOMMENDED

BY

DONE

SAFEGUARDS
218.

219.

Commissioning

Contamination of the
pressure test / wash
water with existing
contaminants in the
plant

Problems in disposing of
the wash-water

Include in the commissioning plan the


ability to store water used to rinse and
test the plant and equipment for
processing through the plant at a later
date.
Also, avoid using detergents /
dispersants when cleaning. These can
cause future issues with the settling
processes
Review the existing and proposed
materials of construction to ensure that
potential contaminants do not react /
interfere with plant components.
Analysis is also required for the potential
for construction materials being
impregnated by contaminants and
therefore being unsuitable for reuse on
future projects or difficult to dispose of

Materials of
Construction

A5.71

LK

PA

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

Pinnacle Risk Management

REFERENCES

Department of Planning, Hazardous Industry Planning Advisory Paper


N 8 - HAZOP Guidelines, NSW Government, Sydney

Orica Villawood HAZOP Report Rev E.Doc


17 April 2013

You might also like