Professional Documents
Culture Documents
Disclaimer
This report was prepared by Pinnacle Risk Management Pty Limited (Pinnacle
Risk Management) as an account of work for Orica. The material in it reflects
Pinnacle Risk Managements best judgement in the light of the information
available to it at the time of preparation. However, as Pinnacle Risk
Management cannot control the conditions under which this report may be
used, Pinnacle Risk Management will not be responsible for damages of any
nature resulting from use of or reliance upon this report. Pinnacle Risk
Managements responsibility for advice given is subject to the terms of
engagement with Orica.
Rev
Date
Description
Reviewed By
27/6/12
Orica
12/8/12
Orica
13/8/12
Final Issue
16/4/13
Orica
17/4/13
Final Issue
CONTENTS
EXECUTIVE SUMMARY ............................................................................................ I
GLOSSARY ............................................................................................................ II
1
INTRODUCTION .............................................................................................. 1
METHODOLOGY ............................................................................................. 2
3.1
General ............................................................................................. 2
3.2
5.1
5.2
REFERENCES ................................................................................................ 7
LIST OF TABLES
Table 1 HAZOP Team .................................................................................... 4
LIST OF APPENDICES
Appendix 1 - Approval of HAZOP Chair.
Appendix 2 - Process Description
Appendix 3 - HAZOP Drawings
Appendix 4 - HAZOP Guide Words.
Appendix 5 - HAZOP Minutes.
EXECUTIVE SUMMARY
Orica is proposing to install and operate a soil processing facility at the former
Orica Villawood site. The Site contains waste byproducts of industrial activities
which ceased in 2000, in particular DDT and its degradation products DDD and
DDE. The contaminants will be separated from the soil and destroyed within
the process.
The Minister for Planning granted development consent for the Project in May,
2012. Project Development Consent Condition 21(b) requires the preparation
of a Hazard and Operability (HAZOP) Study.
Orica requested that Dean Shewring from Pinnacle Risk Management chair the
HAZOP study. This report details the results of the HAZOP study in
accordance with the requirements of the Department of Planning and
Infrastructures HAZOP Guidelines.
The main participants had appropriate experience in the design and operation
of soil processing (or similar) plants. Therefore, the hazards were generally well
known as well as the required control measures to reduce risk to acceptable
levels.
The plant design is an established design with a number of similar plants being
operated throughout the world. Therefore, many of the significant potential
hazardous events and operability problems were already known which reduced
the demand on this study. This included incidents from recently commissioned
plants for Orica and other companies.
GLOSSARY
DoPI
DTD
ECS
FSB
HAZOP
HIPAP
PHA
P&ID
STA
VOC
ii
REPORT
1
INTRODUCTION
Orica is proposing to install and operate a soil processing facility at the former
Orica Villawood site. The Site contains waste byproducts of industrial activities
which ceased in 2000, in particular DDT and its degradation products DDD and
DDE. The contaminants will be separated from the soil and destroyed within
the process.
The Minister for Planning granted development consent for the project in May,
2012.
Development Consent Condition 21(b) specifies the following requirements for
the HAZOP study.
"Prior to Site Establishment, the Proponent shall obtain the
Director-Generals approval of the following study:
b) a Hazard and Operability Study (HAZOP) chaired by an
independent, qualified person or team. The independent person
or team shall be approved by the Director-General. The Study
shall be carried out in accordance with the Department's
publication Hazardous Industry Planning Advisory Paper (HIPAP)
No. 8 - HAZOP Guidelines (Ref 1) and shall include consideration
of measures to prevent any accidental spills of liquids and/ or
liquid wastes on all relevant tanks and equipment used for the
storage and handling of liquids or liquid wastes, including
associated pipes and hoses.
Orica requested that Dean Shewring from Pinnacle Risk Management chair the
required HAZOP study. The approval received from the Department of
Planning and Infrastructure (DoPI) for the chair of this projects HAZOP study is
shown in Appendix 1.
This report details the results of the HAZOP study and is written to meet the
requirements of the Department of Planning and Infrastructures HIPAP Number
8 and Development Consent Condition 21(b).
The HAZOP study on the main contaminant destruction process was detailed in
revisions A to C of this report. Following this study, two additional HAZOPs
were performed. The first additional study reviewed the air compressor for the
evaporative cooler and the pugmill water system. The second additional study
reviewed the waste water treatment plant. The results of these two additional
studies have been added to revision D of this report.
The aim of the HAZOP study is to identify potential hazardous events and
significant operability problems associated with the proposed operations. This
aim is inherent for all HAZOP studies. The scope for this study is detailed in
Section 2 of this report.
A copy of the detailed process description for the soil treatment plant is supplied
in Appendix 2.
In summary, the feed soil is initially heated in a dryer to remove the volatile
contaminants which are then destroyed in a directly-heated thermal desorption
unit. The resultant product gases are then absorbed within a scrubber. Treated
soil can then be returned to the site.
In the waste water treatment plant, water from various site containments is
processed via settlers, flocculation (including chemical additional and pH
adjustment) and a series of filters to remove the contaminants. The purified
water is discharged to sewer.
Copies of the drawings used in the study which detail the process areas are
supplied in Appendix 3.
As the natural gas supply train to the directly-heated desorption unit will be
compliant to the relevant Australian Standard then the HAZOP just considered
deviations from the design intent associated with natural gas supply (rather than
try to alter an Australian Standard compliant system).
METHODOLOGY
3.1
GENERAL
A HAZOP study is a hazard study which concentrates on how the design will
cope with abnormal conditions, rather than on how it will perform under normal
conditions. The study is comprised of a review of each unit operation,
examining each for possible causes of a wide range of process abnormalities
and their consequences.
HAZOP provides the opportunity for people to think creatively and examine
ways in which hazards or operating problems might arise. To reduce the
chance of missing something, a HAZOP is carried out in a systematic manner,
using guide words to consider each pipeline and each type of hazard in turn.
The study is carried out by a team so that input from all areas of functional
expertise can be provided.
The results of a HAZOP depend heavily upon the experience and attitudes of
the team members and on the leadership style adopted. In this study, the
members of the team had good experience, knowledge and skills and had the
authority to approve the actions decided upon.
3.2
MEETING PROCEDURES
The HAZOP study of each section of plant followed the procedure given below:
The process design engineer outlined the broad purpose of the section of
design under study and displayed on the relevant P&IDs on the wall. This
outline included design features, operating conditions, description of fittings
and details of equipment.
Any general questions about the scope and intent of the design were
answered.
The first section or area of the design was highlighted for study, typically an
area where material flows into the plant.
Any general questions about this area were then answered. Minutes may
be generated during this discussion. If so, they have been recorded with the
guide word General Discussion.
The detailed "line by line" study commenced at this point. The HAZOP
leader led the group through the HAZOP guide words. Each guide word is a
prompt, such as "MORE OF OR HIGH FLOW", which identifies a deviation
from normal operating conditions that may lead to a hazardous event or
significant operability problem. This is used to prompt discussion of the
possible causes and effects of flow at an undesirably high rate. If, in the
opinion of the team, the safeguards for the combination of the consequences
and likelihood of a credible event are inadequate then an action is recorded
in the minutes.
For major risk areas the need for action is assessed quantitatively (by
Hazard or Reliability Analysis). For less significant risks the need for action
can be based on experience and judgement. For this study, all actions could
be appropriately addressed by the nominated HAZOP team members /
company.
The main aim of the meeting was to find problems needing solution, rather
than the actual solution. When the group became tied down by trying to
resolve a problem, the issue was minuted as requiring further review outside
the meeting, and the study proceeded.
All changes agreed at the meeting were minuted with some being marked
on the HAZOP master P&IDs.
Note that all actions were recorded in the minutes as well as significant
discussion points which did not result in any actions. The latter were
recorded as a means to record the basis of safety for a potential hazardous
event or operability problem.
The guide words used during the study are listed in Appendix 4.
STUDY TEAM
The HAZOP study for the project was conducted in a number of sessions from
January to November, 2012.
The main HAZOP team participants had the appropriate level of experience in
design and/or operation of soil processing plants (or similar processes). Table
1 shows the team members who participated in the HAZOP study.
The meetings were led by Dean Shewring with the minutes being recorded by
Peter ODea.
Table 1 HAZOP Team
HAZOP Role
Name
Company
HAZOP Chair
Dean Shewring
HAZOP Secretary
Peter ODea
Orica
Project Management
Peter ODea
Lindsay Killin
Cameron McLean
Richard Giles
Orica
EnviroPacific
EnviroPacific
EnviroPacific
Site Management
Representative
Gwenda Lister
Orica
Brett Garton
Bala Kathiravelu
Rudy Maes
Keith Chapman
Tai Truong
Pearce Anderson
EnviroPacific
Orica
Consultant to Chapman Services
Chapman Services
EnviroPacific
EnviroPacific
5.1
The HAZOP team assembled for the study was well balanced in terms of
disciplines and experience. The team sizes were generally kept to the required
four to eight people. This increases the ability to achieve a creative
brainstorming workshop to help ensure maximum effectiveness and quality.
The main participants had appropriate experience in the design and operation
of soil processing (or similar) plants. Therefore, the hazards were generally well
known as well as the required control measures to reduce risk to acceptable
levels.
The plant design is an established design with a number of similar plants being
operated throughout the world. Therefore, many of the significant potential
hazardous events and operability problems were already known which reduced
the demand on this study. This included incidents from recently commissioned
plants for Orica and other companies.
Potential hazardous events concerning releases of harmful materials via
gaseous, liquid or solid losses of containment were reviewed during the study.
Assuming the proposed safeguards remain effective then the risk of such
events should be low.
Any significant changes to the HAZOP design should be separately assessed
for new potential hazardous events and operability problems. This is commonly
achieved by utilising a management of change programme within the project
and may require further review using the HAZOP technique.
During the study, industry standard operating procedures were discussed and
included as potential causes for hazardous events and significant operability
problems. Any significant issues identified have been recorded in the HAZOP
minutes for inclusion in the final version of the standard operating procedures
for the Orica facility.
HAZOP studies are, by definition, a qualitative risk assessment. The decisions
made by the HAZOP team members are based on their experience and
knowledge of the type of processing plant under review. If the HAZOP team
members determined the existing control measures were adequate then no
further action is required. Significant points of discussion (generally if significant
consequential impacts are possible) were recorded even though the control
measures were deemed acceptable by the HAZOP team. All issues requiring a
response were included in the HAZOP minutes.
5.2
Appendix 1
A1.1
A1.2
Appendix 2
Process Description
A2.1
1. Pre-Treatment of Materials
The pre-treatment of excavated materials will be undertaken in two stages. Initially, excavated
material and overlying material may be screened within the Remediation Area compound.
Material required to be treated (in the Directly-heated Thermal Desorption (DTD) Plant) will be
transported to the Feed Soil Building (FSB), where further handling and testing of this material
will take place.
The material will be stockpiled in the FSB using a front end loader before undergoing further
screening and testing for contaminant levels and other characteristics which will be required for
the DTD treatment process. The material will then be blended to achieve a relatively
homogenous feed material prior to being loaded into the feed hopper of the DTD Plant.
Activities within the FSB, including screening and testing will take place 24 hours per day, seven
days per week.
A2.2
A2.3
In order to maintain the correct temperature to maximise destruction efficiency and minimise the
formation of by-products, the thermal oxidiser will be fitted with a sophisticated temperature
control system which will be consistently monitored.
Quench
Once gases have passed through the thermal oxidiser they must be rapidly cooled to minimise
the potential for dioxin formation and allow further treatment before release to the atmosphere
(as required by the Stockholm Convention).
To achieve this, the hot gases are drawn into the quench by an induced draught fan. In the
quench, water is injected to rapidly cool the gases to a temperature which is suitable for further
treatment.
Baghouse
The cooled gas from the quench is combined with steam from the pugmill and drawn into the
baghouse by an induced draught fan. The baghouse contains a series of fabric filters which
remove particulates.
Acid Gas Scrubber
The final step in the treatment process involves the removal of acid gases from the exhaust gas.
The acid gas scrubber consists of a packed tower with a re-circulating caustic solution that
reacts with any hydrogen chloride and chlorine in the exhaust gas to form a salt solution.
Following this, the clean treated gas is vented to the atmosphere via the scrubber stack which
is some 30 m in height.
Treated Soil
Treated soil will be stockpiled adjacent to the STA with drains and bunds provided to manage
runoff. Treated materials stored in this area will undergo validation testing and reclassification.
This is to determine whether the process has been effective and whether or not the materials
are ready for reuse at the Site. Stockpiles will be stabilised with spray grass or other such
treatment and will be wetted when necessary to control dust.
The treated, stockpiled soil will be retained until completion of remediation works at the Site
when it will be transported (by truck) to the Remediation Areas for reinstatement works.
A2.4
Appendix 3
HAZOP Drawings
A3.1
A3.2
A3.3
A3.4
A3.5
A3.6
A3.7
A3.8
A3.9
A3.10
A3.11
A3.12
A3.13
A3.14
A3.15
A3.16
A3.17
A3.18
A3.19
A3.20
A3.21
Appendix 4
A4.1
Reverse Flow
High Pressure
- Venting, relief
Low Pressure
- Venting, relief
High Temperature
Low Temperature
Impurities
- Gaseous, liquid, solid
Testing
- Equipment / product
Plant Items
- Operable / maintainable
Electrical
Instruments
A4.2
Toxicity
Commissioning
Startup
Effluent
Noise / Vibration
Materials of Construction
Efficiency Losses
Simplicity
A4.3
Appendix 5
HAZOP Minutes
A5.1
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10001 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
1.
General
Discussion
Belt failure,
maintenance
2.
General
Discussion
3.
General
Discussion
Increased moisture
impacts process
Conveyor covers to be
installed
4.
High Flow /
High Level
A5.1
LK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10001 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
5.
Low Flow /
Low Level
Soil clumps in
hopper
6.
Zero Flow /
Empty
Hopper empty
7.
Zero Flow /
Empty
Feeder fails
8.
Zero Flow /
Empty
A5.2
BG
LK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10001 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
9.
Zero Flow /
Empty
Spillage from
conveyors
Clean-up.
Damage to adjacent
equipment
10.
Zero Flow /
Empty
11.
Zero Flow /
Empty
Plant outage
12.
Reverse Flow
13.
Impurities
LK
Spillage at bottom
requiring cleaning up
Exposure to personnel
who contact the treated
soil and maintain the
plant
Will be removed in
accordance will agreed
practices by licensed
contractor
A5.3
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10001 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
14.
Impurities
Possibility of embers
getting to the baghouse
and causing damage to
the filters
Reduced online time
15.
Plant Items
16.
Plant Items
Atmosphere unsuitable
for personnel
Likely to be confined
space entry if the feed
soil building emission
control system fails
17.
Plant Items
Wayward FEL
operation etc
18.
Electrical
A5.4
BG
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10002 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
19.
General
Discussion (note
the cyclones
remove particles
to 30 microns)
Explosion
20.
High Flow /
High Level
Knockout box
blockage
21.
High Flow /
High Level
Overheating of materials
and hence the potential
for equipment damage
A5.5
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10002 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
22.
Low Flow /
Low Level
23.
Zero Flow /
Empty
24.
Reverse Flow
Burner continues to
run when the ID fan
stops
25.
High
Temperature
Baghouse overloaded
Burns to personnel
A5.6
KC
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10002 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
26.
Plant Items
Equipment damage
27.
Electrical
Lightning
Instrument damage
28.
Instruments
Routine maintenance
checks and operator
response to noise from
within the dryer
A5.7
KC
KC
TEAM MEMBERS:
SYSTEM:
Thermal Oxidiser
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10006 Rev A
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
29.
General
Discussion
Burner continues to
run when the ID fan
stops
High temperature
damage to the burner or
injury to personnel if
flames are emitted from
the burner
30.
High Flow /
High Level
31.
High Flow /
High Level
Buildup of slag in
bottom of TO
A5.8
TEAM MEMBERS:
SYSTEM:
Thermal Oxidiser
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10006 Rev A
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
32.
Low Pressure
33.
High
Temperature
Equipment damage
34.
High
Temperature
35.
Low Temperature
Loss of process
control due to the
control temperature
transmitter reading
too high
Fail to achieve
regulatory destruction
temperature
Burner management
system takes control,
i.e. flameout detector
shuts of the natural gas
flow
TO temperature trips
plus there are also
downstream
temperature controls
A5.9
TEAM MEMBERS:
SYSTEM:
Thermal Oxidiser
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10006 Rev A
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
36.
Low Temperature
Emergency stop
37.
Plant Items
Flame impingement
on shell opposite
burner
38.
Plant Items
Dust in the TO
A5.10
TEAM MEMBERS:
SYSTEM:
Evaporative Cooler including the Air
/ Water Flows
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Peter ODea
No.
C143-PF-96D-DTDU-10007 Rev B
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
39.
General
Discussion
Power failure
40.
General
Discussion
Rapid quenching
does not occur
41.
High Flow /
High Level
False low
temperature reading
at the outlet duct
42.
High Flow /
High Level
Design is to quench to
below 200 deg. C in
1 second
Water will evaporate.
Operator is constantly
observing temperature
to the baghouse
Will be detected through
plant pressure controls
A5.11
KC
RM
TEAM MEMBERS:
SYSTEM:
Evaporative Cooler including the Air
/ Water Flows
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Peter ODea
No.
C143-PF-96D-DTDU-10007 Rev B
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
43.
High Flow /
High Level
ECU (emission
control unit) water
pump keeps running
when the
evaporative cooler is
shutdown
Bottom of the
evaporative cooler
floods
44.
Low Flow /
Low Level
45.
Low Flow /
Low Level
46.
Reverse Flow
Procedures dictate
pumps to be manually
shut down when the
plant stops.
Water will come out the
dilution air damper and
become visible
Dilution air damper
opens. If control not
regained, plant trips
Operator is constantly
observing temperature
to the baghouse and a
low temperature alarm
Damper located
sufficiently high to avoid
damage
A5.12
KC
TEAM MEMBERS:
SYSTEM:
Evaporative Cooler including the Air
/ Water Flows
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Peter ODea
No.
C143-PF-96D-DTDU-10007 Rev B
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
47.
Impurities
48.
Change in
Composition or
Concentration /
Two-Phase Flow
/ Reactions
Testing
No serious outcome
49.
A5.13
LK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10004 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
50.
Low Flow /
Low Level
Inadequate air
pulsing
High differential
pressure alarm
51.
Zero Flow /
Empty
52.
Zero Flow /
Empty
53.
Impurities
54.
Plant Items
A5.14
RM
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10004 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
55.
Plant Items
Moisture ingress
Appropriate materials of
construction
A5.15
TEAM MEMBERS:
SYSTEM:
Scrubber (gas stream to
atmosphere) including the Induced Draft Fan
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Peter ODea
No.
C143-PF-96D-DTDU-10005 Rev B
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
56.
General
Discussion
57.
Low Flow /
Low Level
58.
Impurities
Baghouse failure
59.
Plant Items
60.
Plant Items
Appropriate materials of
construction will be
provided
The stack top diameter
will be such that the
minimum velocity to
ensure good dispersion
will be maintained at the
design plant turndown
TDS (total dissolved
solids) analyser
provided
Fan is silenced.
Unsure if the stack top
needs to include a
silencer
Fan is silenced.
Unsure if the stack top
needs to include a
silencer
A5.16
POD
KC
TEAM MEMBERS:
SYSTEM:
Scrubber (gas stream to
atmosphere) including the Induced Draft Fan
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Peter ODea
No.
C143-PF-96D-DTDU-10005 Rev B
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 23/1/2012
ACTION RECOMMENDED
BY
LK
DONE
SAFEGUARDS
61.
Plant Items
Caustic leak
Safety showers
A5.17
TEAM MEMBERS:
SYSTEM:
Feeds
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10005 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 27/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
62.
General
Discussion
63.
General
Discussion
Loss of containment of
acidic gases to
atmosphere
64.
General
Discussion
A5.18
TEAM MEMBERS:
SYSTEM:
Feeds
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10005 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 27/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
65.
General
Discussion
66.
General
Discussion
67.
General
Discussion
A5.19
RM
POD
KC
TEAM MEMBERS:
SYSTEM:
Feeds
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10005 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 27/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
68.
High Flow /
High Level
69.
Zero Flow /
Empty
70.
Reverse Flow
Appropriate materials of
construction, e.g.
stainless steel or plastic
A5.20
nd
KC
RM
TEAM MEMBERS:
SYSTEM:
Feeds
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10005 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 27/1/2012
ACTION RECOMMENDED
BY
KC
DONE
SAFEGUARDS
71.
Plant Items
Control valves
wrongly selected,
e.g. solenoids for
larger (100 to 150
mm) lines not
appropriate
A5.21
TEAM MEMBERS:
SYSTEM:
Scrubber Recycle
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10005 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 27/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
72.
General
Discussion
Scrubber recycle
pump failure
Manual changeover of
pumps
73.
High Flow /
High Level
Release of 80 C liquid.
Operator regular
inspection and
maintenance as
required
Routine manual
sampling of the
scrubber recycle liquid.
pH meter including a
low alarm.
CEMS stack analysers,
e.g. NOx and SOx will
also rise and alarm for
operator response
74.
High Flow /
High Level
Overdosing caustic
75.
Low Flow /
Low Level
Underdosing caustic
(e.g. from pH meter
drifting, failure to top
up the caustic IBC)
A5.22
TEAM MEMBERS:
SYSTEM:
Scrubber Recycle
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10005 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 27/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
76.
Low Flow /
Low Level
77.
Low Flow /
Low Level
Increase in temperature
in the plastic packing
with possible damage
78.
Zero Flow /
Empty
79.
Reverse Flow
Nozzles to be screwed
in tight and are
replaceable through the
side of the scrubber
column
Correct packing
selection
Operator observes
signals not fluctuating,
analysers in the stack
will alarm
Pressure control valve
in the common delivery
line from the caustic
pumps
A5.23
RM
RM
TEAM MEMBERS:
SYSTEM:
Scrubber Recycle
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10005 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 27/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
80.
High
Temperature
Burns on contact
81.
Impurities
Blockage in the
scrubber
82.
Change in
Composition or
Concentration /
Two-Phase Flow
/ Reactions
Testing
Splashing
83.
A5.24
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
MINUTES BY:
Peter ODea
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 27/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
84.
General
Discussion
Pump requires
maintenance
85.
General
Discussion
Power failure
86.
General
Discussion
A5.25
TEAM MEMBERS:
SYSTEM:
Soil to and from the Pugmill
(including the cyclones underflow)
LEADER:
Dean Shewring
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 27/1/2012
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
87.
Low Flow /
Low Level
88.
Zero Flow /
Empty
89.
Zero Flow /
Empty
Baghouse drive
overloads and
equipment damage
High dust flow to the
baghouse
Soil too hot, potential
damage to conveyor
belts, burns, etc.
Potential for a build-up
of solids in the dryer and
hence heat damage to
the dryer
90.
High
Temperature
A5.26
RM
LK
TEAM MEMBERS:
SYSTEM:
Overview
LEADER:
Dean Shewring
DRAWING:
All Drawings
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 27/1/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
91.
Toxicity
No further issues
identified with the
overview guide
words
A5.27
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10011 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
92.
93.
General
Discussion
General
Discussion
Note only:
A5.28
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10011 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
LK
DONE
SAFEGUARDS
94.
General
Discussion
95.
High Flow /
High Level
Overdosing caustic
96.
High Flow /
High Level
Loss of containment,
e.g. forklift tynes
puncture the IBC,
hose failure, etc
A5.29
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10011 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
TT
DONE
SAFEGUARDS
97.
High Flow /
High Level
Pumping caustic
when the plant is
shut down
Scrubber sump
overflow.
Temperature rise due to
heat of mixing
98.
High Flow /
High Level
Stormwater falling
into the bunded area
Stormwater
management required
A5.30
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10011 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
99.
High Flow /
High Level
100.
Low Flow /
Low Level
101.
Zero Flow /
Empty
102.
Reverse Flow
No credible causes
identified given the
safeguards
Strong materials of
construction for the
proposed tubing
pH alarm and interlock,
scrubber stack
analysers and alarms
Internal pressure relief
to be included with the
pump, pH meter and
alarm in the scrubber
recycle circuit
A5.31
LK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10011 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
103.
Low Pressure
104.
High
Temperature
No significant
consequences identified
105.
Low Temperature
Standby pump
freezes on cold night
106.
Low Temperature
107.
Plant Items
IBC changeover
LK
LK
LK
A5.32
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10009 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
GL
DONE
SAFEGUARDS
108.
General
Discussion
109.
General
Discussion
110.
General
Discussion
111.
High Flow /
High Level
Supply pipe
ruptured, e.g. by
backhoe
A5.33
LK
LK
LK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10009 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
112.
Low Flow /
Low Level
113.
Reverse Flow
114.
Impurities
115.
Plant Items
116.
Plant Items
Work at heights
when maintaining the
tanks level
transmitter
Pump strainer
maintenance and
downstream pressure
and flow alarms
A5.34
LK
LK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10009 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
117.
Plant Items
Work at heights
when maintaining the
tanks LCV
118.
Instruments
Water leaks
Maintenance and
replacement of the sight
glass
A5.35
LK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10009 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
TT
DONE
SAFEGUARDS
119.
General
Discussion
120.
General
Discussion
121.
General
Discussion
A5.36
TT
TT
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10009 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
122.
123.
124.
High Flow /
High Level
Low Flow /
Low Level
Zero Flow /
Empty
Running 2 pumps
simultaneously
Blocked strainers,
valves gagged,
pump problems
No significant
consequences identified
Duty/standby selector
switch.
Flow controls
downstream will ensure
the users only take what
water they need
Alarms and trips at each
user of the water, e.g.
low pressure or flow.
Critical pumps can be
started manually when
emergency generator
started
A5.37
LK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10009 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
LK
DONE
SAFEGUARDS
125.
Reverse Flow
126.
Reverse Flow
127.
Plant Items
128.
Electrical
Power failure
Emergency generator
A5.38
LK
BK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10010 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
129.
General
Discussion
130.
General
Discussion
131.
General
Discussion
Historical incidents
involving oil filled
compressors running
too hot and hence
cracking the oil
A5.39
LK
LK
LK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10010 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
132.
General
Discussion
133.
General
Discussion
134.
General
Discussion
135.
General
Discussion
A5.40
LK
LK
LK
LK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-DTDU-10010 Rev B
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
136.
High Flow /
High Level
Regulator failure
137.
Zero Flow /
Empty
Loss of power
138.
High Pressure
Compressor
deadheaded
139.
High
Temperature
A5.41
LK
LK
LK
TEAM MEMBERS:
SYSTEM:
OVERVIEW
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Peter ODea
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 26/6/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
140.
Commissioning
141.
Commissioning
Foreign objects in
the pipes during
commissioning
Potential to damage
equipment
142.
Commissioning
143.
Commissioning
144.
Materials of
Construction
Potential
incompatibility of the
materials of
construction with the
process materials
Corrosion and
equipment failure with a
loss of containment
A5.42
LK
LK
TT
LK
BK
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-CTCU-10010 (mark-up)
MINUTES BY:
Bala Kathiravelu
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 19/10/12
ACTION RECOMMENDED
BY
KC
DONE
SAFEGUARDS
145.
General
Discussion
146.
High Pressure
Compressor high
pressure protection
for deadheading
147.
High
Temperature
The compressor is a
screw compressor and
hence the potential for
overpressuring the
discharge piping with
possible failures leading
to missiles
Potential to crack the oil
and lead to a build-up
on the inside of the
pipes which can explode
A5.43
KC
KC
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
C143-PF-96D-CTCU-10010 (mark-up)
MINUTES BY:
Bala Kathiravelu
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 19/10/12
ACTION RECOMMENDED
BY
KC
DONE
SAFEGUARDS
148.
Low Temperature
Manual draining
A5.44
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Bala Kathiravelu
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 19/10/12
ACTION RECOMMENDED
BY
KC
DONE
SAFEGUARDS
149.
General
Discussion
A5.45
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Bala Kathiravelu
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 19/10/12
ACTION RECOMMENDED
BY
KC
DONE
SAFEGUARDS
150.
General
Discussion
151.
General
Discussion
P&ID correction
152.
General
Discussion
P&ID correction
153.
General
Discussion
P&ID correction
154.
General
Discussion
P&ID correction
A5.46
KC
KC
KC
KC
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Bala Kathiravelu
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 19/10/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
155.
General
Discussion
P&ID correction
156.
High Flow /
High Level
Spray nozzle
unwinding and falling
off
157.
High Flow /
High Level
158.
High
Temperature
A5.47
KC
KC
LK
KC
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Bala Kathiravelu
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 19/10/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
159.
A5.48
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
SAS10883-301 Rev A
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
PA
DONE
SAFEGUARDS
160.
General
Discussion
161.
General
Discussion
162.
General
Discussion
163.
High Flow /
High Level
Losses of
containment from the
coagulant pumping
system
Potential environmental
consequences of
overflow to the ground
A5.49
PA
PA
PA
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
SAS10883-301 Rev A
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
164.
Zero Flow /
Empty
165.
Reverse Flow
166.
High Pressure
167.
Plant Items
Deadhead of the
sludge pump
A5.50
PA
PA
PA
PA
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
SAS10883-301 Rev A
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
PA
DONE
SAFEGUARDS
168.
Plant Items
169.
Plant Items
Overfilling the
sedimentation tanks
170.
Plant
I
Items
Isolation of water in
the aboveground
piping
171.
Plant
P
Items
A5.51
PA
PA
PA
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
SAS10883-301 Rev A
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
172.
Plant Items
173.
Instruments
A5.52
PA
PA
SYSTEM:
Feed Tank System including the
Untreated Water Basin
DRAWING:
302 Rev 0
No.
GUIDE WORDS
POSSIBLE CAUSES
TEAM MEMBERS:
LEADER:
Dean Shewring
MINUTES BY:
Lindsay Killin
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
PA
PA
DONE
SAFEGUARDS
174.
High Flow /
High Level
Procedural control
monitoring water levels
175.
High Flow /
High Level
Draining of both
sedimentation tanks
to the feed tank, e.g.
manual valves
passing or left open
Potential to initially
overflow the feed tank
and then overflow the
pump well bund
176.
Zero Flow /
Empty
A5.53
LK
SYSTEM:
Feed Tank System including the
Untreated Water Basin
DRAWING:
302 Rev 0
No.
GUIDE WORDS
POSSIBLE CAUSES
TEAM MEMBERS:
LEADER:
Dean Shewring
MINUTES BY:
Lindsay Killin
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
PA
DONE
SAFEGUARDS
177.
Impurities
178.
Instruments
Foreign objects
entering the untreated water basin
Plant inlet water
flowrate monitoring
for mass balances
and performance
checks
Blockage and/or
damage to the raw
water feed pump
A5.54
PA
SYSTEM:
Flocculation Tank and Chemical
Dosing Systems (HAZOPed by Difference)
DRAWING:
No.
GUIDE WORDS
POSSIBLE CAUSES
TEAM MEMBERS:
LEADER:
Dean Shewring
MINUTES BY:
Lindsay Killin
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
PA
DONE
SAFEGUARDS
179.
General
Discussion
180.
General
Discussion
181.
General
Discussion
182.
High Flow /
High Level
183.
High Flow /
High Level
Caustic line
breakage through
high pressure /
damage
Loss of containment
of flocculant
Potential to splash a
person and cause a
corrosive burn
System to be leak
checked prior to use,
high pressure tubing to
be used
Slip hazard
A5.55
PA
PA
PA
PA
SYSTEM:
Flocculation Tank and Chemical
Dosing Systems (HAZOPed by Difference)
DRAWING:
No.
GUIDE WORDS
POSSIBLE CAUSES
TEAM MEMBERS:
LEADER:
Dean Shewring
MINUTES BY:
Lindsay Killin
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
PA
SA
DONE
SAFEGUARDS
184.
Reverse Flow
185.
High
Temperature
186.
Low Temperature
Failure of the
flocculant discharge
non-return valve and
the pump suction
and discharge
(check) valves
Water supply line to
the safety shower /
eyewash heated by
the sun
Cold winter night
Maintenance on the
piping system and
check valves
A5.56
LK
SYSTEM:
Flocculation Tank and Chemical
Dosing Systems (HAZOPed by Difference)
DRAWING:
No.
GUIDE WORDS
POSSIBLE CAUSES
TEAM MEMBERS:
LEADER:
Dean Shewring
MINUTES BY:
Lindsay Killin
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
SA
DONE
SAFEGUARDS
187.
Plant Items
Personnel or wildlife
contact with caustic
when splash filling
into the mixing tank
A5.57
TEAM MEMBERS:
SYSTEM:
Lamella Settlers
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
188.
General
Discussion
PA
A5.58
SYSTEM:
Break Tank / Zeolite Feed Tank
(HAZOPed by Difference) and the Filter Pumping
System, i.e. Filters on-line
DRAWING:
304 Rev A
No.
GUIDE WORDS
POSSIBLE CAUSES
TEAM MEMBERS:
LEADER:
Dean Shewring
MINUTES BY:
Lindsay Killin
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
PA
PA
DONE
SAFEGUARDS
189.
General
Discussion
190.
General
Discussion
191.
High Pressure
Unwanted misdirected
flows, e.g. backwash
water to the GAC feed
tank
A5.59
SYSTEM:
Break Tank / Zeolite Feed Tank
(HAZOPed by Difference) and the Filter Pumping
System, i.e. Filters on-line
DRAWING:
304 Rev A
No.
GUIDE WORDS
POSSIBLE CAUSES
TEAM MEMBERS:
LEADER:
Dean Shewring
MINUTES BY:
Lindsay Killin
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
PA
DONE
SAFEGUARDS
192.
Testing
A5.60
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
PA
DONE
SAFEGUARDS
193.
General
Discussion
194.
Low Flow /
Low Level
195.
Instruments
Inability to backwash
A5.61
PA
PA
SYSTEM:
GAC Feed Tank System (HAZOPed
by Difference) and GAC Filters
DRAWING:
No.
GUIDE WORDS
POSSIBLE CAUSES
TEAM MEMBERS:
LEADER:
Dean Shewring
MINUTES BY:
Lindsay Killin
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
PA
DONE
SAFEGUARDS
196.
General
Discussion
197.
General
Discussion
198.
High Flow /
High Level
Two pumps in
operation
199.
High Flow /
High Level
Incorrect valve
alignment
Unwanted misdirected
flows, e.g. non-treated
water to the treated
water basins, or
deadhead of the GAC
feed pump
Potential to carry over
activated carbon to the
downstream treated
water tank and beyond
Potential contaminants
going into the treated
water feed tank and/or
dead head the GAC
feed pump
A5.62
PA
LK
SYSTEM:
GAC Feed Tank System (HAZOPed
by Difference) and GAC Filters
DRAWING:
No.
GUIDE WORDS
POSSIBLE CAUSES
TEAM MEMBERS:
LEADER:
Dean Shewring
MINUTES BY:
Lindsay Killin
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
200.
High Flow /
High Level
201.
Zero Flow /
Empty
A5.63
SA
PA
SYSTEM:
GAC Feed Tank System (HAZOPed
by Difference) and GAC Filters
DRAWING:
No.
GUIDE WORDS
POSSIBLE CAUSES
TEAM MEMBERS:
LEADER:
Dean Shewring
MINUTES BY:
Lindsay Killin
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
LK
DONE
SAFEGUARDS
202.
High Pressure
203.
Impurities
Extended shutdown
(i.e. 4-5 weeks or
more)
204.
Impurities
205.
Testing
A5.64
PA
PA
PA
SYSTEM:
GAC Feed Tank System (HAZOPed
by Difference) and GAC Filters
DRAWING:
No.
GUIDE WORDS
POSSIBLE CAUSES
TEAM MEMBERS:
LEADER:
Dean Shewring
MINUTES BY:
Lindsay Killin
CONSEQUENCES
EXISTING
DATE: 29/11/12
ACTION RECOMMENDED
BY
LK
DONE
SAFEGUARDS
206.
Plant Items
A5.65
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 30/11/12
ACTION RECOMMENDED
BY
PA
DONE
SAFEGUARDS
207.
208.
General
Discussion
General
Discussion
A5.66
PA
TEAM MEMBERS:
SYSTEM:
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 30/11/12
ACTION RECOMMENDED
BY
PA
SA
DONE
SAFEGUARDS
209.
High Flow /
High Level
Passing butterfly
valve
210.
High Flow /
High Level
Putting an on-spec
basin off-spec and
hence having to rerun a
basin back through the
plant prior to discharge
211.
Low Pressure
Off-spec treated
water running to two
basins, e.g. basin
inlet valve passing or
inadvertently left
open
Motorised valve to
treated water basins
closes quickly
Potential to form a
vacuum downstream of
the motorised valve and
suck in the poly pipe
A5.67
PA
TEAM MEMBERS:
SYSTEM:
Sedimentation Tanks
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 30/11/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
212.
General
Discussion
213.
General
Discussion
A5.68
LK
PA
TEAM MEMBERS:
SYSTEM:
Sedimentation Tanks
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 30/11/12
ACTION RECOMMENDED
BY
PA
LK
DONE
SAFEGUARDS
214.
Zero Flow /
Empty
215.
Zero Flow /
Empty
A5.69
TEAM MEMBERS:
SYSTEM:
Sedimentation Tanks
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 30/11/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
216.
Plant Items
217.
Instruments
Personnel exposed
to DDT etc contained
within the sludge
Health impacts on
personnel
SWMS/JSA to be
performed on sludge
handling, e.g. disposal
via the DTDU
A5.70
PA
TEAM MEMBERS:
SYSTEM:
Overview
LEADER:
Dean Shewring
DRAWING:
MINUTES BY:
Lindsay Killin
No.
GUIDE WORDS
POSSIBLE CAUSES
CONSEQUENCES
EXISTING
DATE: 30/11/12
ACTION RECOMMENDED
BY
DONE
SAFEGUARDS
218.
219.
Commissioning
Contamination of the
pressure test / wash
water with existing
contaminants in the
plant
Problems in disposing of
the wash-water
Materials of
Construction
A5.71
LK
PA
REFERENCES