3rd Corrigenda & Addenda of

Schedule of Rates for P.W. (Roads) Directorate 2008-2009


April, 2009

A.

CORRIGENDA OF SCHEDULE OF RATES, P. W. (ROADS) DIRECTORATE 2008-09

(1)

The Table 3.1 2 at Page 172 has been modified as shown below (Cement content column
added) :

TABLE 3.1 2:
Concrete
grade

QUANTITIES OF MATERIALS REQUIRED FOR DESIGN MIX CONCRETE ITEMS


Cement content

Coarse aggregates

M-15

310.00 kg / m3 of concrete

0.9 m3/m3 of concrete

M-20

347.33 kg / m3 of concrete

0.9 m3/m3 of concrete

M-25

403.33 kg / m3 of concrete

0.9 m3/m3 of concrete

M-30

406.67 kg / m3 of concrete

0.9 m3/m3 of concrete

M-35

422.00 kg / m3 of concrete

0.9 m3/m3 of concrete

M-40

430.00 kg / m3 of concrete

0.9 m3/m3 of concrete

M-45

465.00 kg / m3 of concrete

0.9 m3/m3 of concrete

M-50

490.00 kg / m3 of concrete

0.9 m3/m3 of concrete

M-55

529.17 kg / m3 of concrete

0.9 m3/m3 of concrete

Sheet 1 of 2

Remarks

1. The quantities given


in the table are only
for
estimating
purpose. The actual
quantities, however,
shall be ascertained
by
proper
Mix
Design.
2. The
coarse
aggregates may be
assumed to be a
mixture of 22.4 mm &
11.2 mm chips in a
proportion of 60: 40
by volume.

3rd Corrigenda & Addenda of


Schedule of Rates for P.W. (Roads) Directorate 2008-2009
April, 2009
B.

ADDENDA OF SCHEDULE OF RATES, P. W. (ROADS) DIRECTORATE 2008-09

1. The Basic Price of Cement when supplied by the Contractor has been given in Table I 1 of Annexure I,
Page 315 of the Schedule (As shown below) :
TABLE I - 1 : ISSUE RATES OF CEMENT & STEEL MATERIALS
Item
Description of
Issue Rate
Basic Price
No.
Items
(Supplied by
(Supplied by
Department)
Contractor)

Unit

Remarks

1.

Cement :

MT

5500.00

5000.00

6
No change in remarks 1 to 3.
Remaks 4 to be added as
below:

4. The rate of the items


involving use of cement
supplied by the contractor
shall be evaluated as per
Format C.
The remaining part of the Table shall remain unchanged.

2. To add Format C as shown below after Format B in page 317 of the Schedule.
FORMAT C

(Format for analysis of rate of items involving use of cement supplied by contractor.)

Step 1

Rate of item as per relevant section of this Schedule.

Rs. A

Step 2

Deduct cost of cement = 1.1 x (Quantity of cement) x (Issue rate of


cement vide Item no. 1, column 4, Table I 1, Page 315 of this
schedule.).

Rs. B

Note : The quantity of cement shall be as per Section 3 of this schedule of


rates.

Step 3

Add cost of cement supplied by contractor = 1.1 x (Quantity of


cement) x (Basic Price of cement vide Item no. 1, column 5,
Table I 1, Page 315 of this schedule.).

Rs - C

Note : The quantity of cement shall be same as Step 2.

Final rate of item = Rs. A Rs. B + Rs. C =

Sheet 2 of 2