ACCOMPLISHMENT FOR BRIDGE

NAME OF PROJECT : IMPROVEMENT & EXECUTION OF BRIDGE ALONG PRINCE TURKI BIN
ABDULAZIZ AL AWAL FROM AL UROBAH ROAD TO UMM AL HAMMAM ROAD IN RIYADH
CONTRACTOR : SHIBH AL-JAZIRA CONTRACTING CO. LTD.

CLIENT : MINISTRY OF MUNICIPAL & RURAL AFFAIRS

Covering the month of :

PROJ. COST :

ITEM
NO.

DESCR IPTION

CONSULTANT : DAR AL RIYADH


269,638,340.40

UNIT

UNIT
COST

BOQ

TO DATE

AMOUNT

REMARKS

Part 1 - Detour Construction


1-1

TRAFFIC DETOUR

1-1-1

Supply and erect NJB in white with red stripes


according to the municipality specs.

L.m.

2,000

2,000

2,000

4,000,000.00

1-1-3

Supply sign board (3 x 2) meter with municipality logo for


(Sorry for the inconvenience and appreciate your cooperation)

No.

12,000

24,000.00

1-1-4

Detour signs

No.

10,000

60

60

600,000.00

PROJECT SIGNS

No.

90,000

90,000.00

1-2

B.O.Q =

4,924,000

TOTAL AMOUNT (PART - 1) =

4,714,000.00

Part 3 - Removal of Obstructions Works


3-1

Removal of sidewalks, curbstone, trees and Palms , conc. Works if


there is w/c may obstruct the works and disposed outside the
project to the approved location by municipality on their
supervision.

m2
B.O.Q =

150

1,194,000

7,000

794

TOTAL AMOUNT (PART - 3) =

119,100.00

119,100.00

Part 4 - Cut & Fill Works


4-1

Soil Excavation

m3
B.O.Q =

30
8,400,000

10,000

2,233

TOTAL AMOUNT (PART - 4) =

66,990.00

66,990.00

Part 5 - Concrete Works for Tunnel


5-1

Blinding concrete 170 Kgs/cm2 under foundation


and approach slab

5-2

Supply 32Mpa and 28Mpa concrete strength after 28 days


crushing cubes. including formworks,approved cement paint and
construction joints.

Bridge Accomplishment.xlsx 16/02/2015

m3

350

Page1 of 2

1,350

66

23,100.00

FM:PJ-003. REV.0

ACCOMPLISHMENT FOR BRIDGE


NAME OF PROJECT : IMPROVEMENT & EXECUTION OF BRIDGE ALONG PRINCE TURKI BIN
ABDULAZIZ AL AWAL FROM AL UROBAH ROAD TO UMM AL HAMMAM ROAD IN RIYADH
CONTRACTOR : SHIBH AL-JAZIRA CONTRACTING CO. LTD.

CLIENT : MINISTRY OF MUNICIPAL & RURAL AFFAIRS

Covering the month of :

PROJ. COST :

ITEM
NO.
5-2-1

DESCR IPTION
Supply concrete 320 Kgs/cm2 for foundation of walls and columns,
the works includes curing and everything.

CONSULTANT : DAR AL RIYADH


269,638,340.40

UNIT

UNIT
COST

BOQ

TO DATE

AMOUNT

m3

700

7,700

974

681,800.00

B.O.Q =

TOTAL AMOUNT (PART - 5) =

20,107,900

REMARKS

704,900.00

Part 6 - Concrete Protection and Expansion Joint


6-1

Waterproofing membrane 2mm, 2 layers for horizontal


with 5cm concrete protection

m2
B.O.Q =

40

7,100

3,204,000

207

TOTAL AMOUNT (PART - 6) =

8,280.00

8,280.00

Part 7 - Reinforcing Steel


7-1

Reinforcing steel as per specification.

Ton
B.O.Q =

4,800

3,000

127

TOTAL AMOUNT (PART - 7) =

15,964,000

609,600.00

609,600.00

Part 18 - NEW ITEMS


5

Grade 35-1.00m. Dia concrete piles

L.m.

2,780

1,520

TOTAL AMOUNT (PART -18) =

Bridge Accomplishment.xlsx 16/02/2015

4,225,600.00

4,225,600.00

TOTAL AMOUNT OF WORK DONE TO DATE (ORIG. ITEMS) =

10,329,370.00

% (PERCENT OF WORK DONE TO DATE)

3.831%

Page2 of 2

Accomplishment
To Date

SAR

FM:PJ-003. REV.0