You are on page 1of 5

Au Price

Au Price
Selling
Selling

1500.00 $/oz
48.23 $/g
6.00 $/oz
0.19 $/g

Cu Price
Cu Price
Selling

3.31 $/lb
7297.23 $/t
80.00 $/t

Mining cost
Mining dilution
Mining recovery

Mining cost adjust.

2.01 $/t
90.00%
100.00%

0 $/t/bench

Rock type 1
Mining CAF
Rehabilitation cost
Processing cost
Addit. Processing Cost
Metal1Rec.
Metal2Rec.

0.001
0.00 $/t
1.60 $/t
0 $/t
90.00%
80.00%

Rock type 2
Mining CAF
Rehabilitation cost
Processing cost
Addit. Processing Cost
Metal1Rec.
Metal2Rec.

0.001
0.00 $/t
1.60 $/t
0 $/t
90.00%
80.00%

Rock type waste


Mining CAF

0.001

MCAF
PCAF

Proceso 1
Recuperacion mina
Leyes

100%
Metal1
Metal2

2.00 g/t
3.0%

Recuperacion
Metal1
90%
Metal2
80%
Revenue = (Price - Selling Cost)*Recuperacion*ley
Metal1
86.4597232
Metal2
173.213424
TOTAL
259.673147
+Min. Recov
259.673147
Procesamiento
Costo
1.6 $/t
Ajustado
1.6

Mining Cost Adjusment Factor


Processing Cost Adjusment Factor

Time
Annual discounting
Average ore output rate
Days
Daily production

10%
250,000.00 t
365.00 d
684.93 t/d

Ultimate Pit
Maximize Cash Flow (LG)
Maximize resources
Use top-down bench discounting for ultimate pit and phases.
Sequencing
Use profit factors
Use price factors
Use mining cost factors
Slopes

All Pit Options


Final pit limits
Ultimate pit
Phase N
OES block N
Maximum pushback number
Pushback boundary adjusments
Minimum distance between pit boundaries
Minimum remmant area in block numbers
Pit boundary correction for smoothness
Pushback bottom bench adjustment
Minimum diameter (mining width)

10

(Make the last pushback equal to final pit limits)