You are on page 1of 4

EXIGO

ITD Cem
DAILY PROGRESS REPORT

Project:

SHUSHRUSHA HOSPITAL AT VIKHROLI

Performing Date:

2/13/2015

Reporting Date:

2/14/2015

Project Details

SUBSTRUCTURE WORK FOR SHUSHRUSHA HOSPITAL AT VIKHROLI

Project Start Date

12/10/2013

Project Completion Date

As per Schedule- 31/03/15

Weather condition

Fair
Brief Summary of Tasks
Cum Compl Upto
BOQ
Prev. Month

Description

Unit

Achieved
for day

This Month Prog.

Cumulative
Progress

Pilling work

Nos

303

303

303

Excavation work

Cum

12364

12364

12364

Concrete (M-25) Grade

Cum

111

111

111

Fabrication of Strutting

MT

229

229

229

Erection of Struting

MT

229

140

140

Caping Beam

Rmt

195

195

195

Drilling & Grouting

Rmt

2347.2

2347

2347

Redrilling for Anchor

Rmt

2226.3

2226

2226

Fixing of Rock Anchor

Nos

425

425

425

Fabrication of Anchor Bar

MT

29

29

29

Grouting for Anchor

Cum

11

11

11

PCC

Cum

475

424

3.50

427

Shuttering work

sqm

10000

4893

510.00

5403

Water Proofing

sqm

3400

2874

20.00

2894

Rienforcement fixing

MT

495

596

0.30

12.00

608

Cum

3725

2355

23.50

125.50

2481

Suncrystal Mix

Kg

1500

3244

Polyalk

Kg

9000

3404

Plum Concrete

Cum

450

327

Dismentling of Pile Cap

Cum

49

49

Chiping

Cum

105

56

Fixing of Anchor Fastener

Nos

254

224

Concrete(M-40 Grade)

10.00

70.50
-

3244

318.00

3722

20.00

347

49

2.50

58

224

Work to be Undertaken On Next day


Pilling work
Excavation work
PCC Work
Concrete work
Strutting work
Caping Beam
Enabling Pile Cap
Drilling & Grouting
Water Proofing
Reinforcement laying
Staging Work
Shuttering work

Completed
Completed
Is in progress

Casting of Ramp Slam in 1st Phase at Rl -3.0 Mtr to +0.0 Lvl (Phase 1)

Is in progress

Casting of 3rd phase slab, at RL-3.0 metre level

Is in progress

Labour Details
Skilled :
Mason:

Completed
Completed
Completed
Completed

Fitter :
Helper :

23
83

HDPE Applicator
Inclined Struting

2
0

EXIGO
Carpenter :
Operator :
Decisions Required (listed in order of priority)

Comments

Prepared by ITD Cem :

For ITD Cem

ITD Cem
18
2

Departmental:
Supervisor:

20
4

Chipper Gang

EXIGO

ROLI

HROLI

Remarks
Complete
Complete
Complete
Complete
Scope reduced
Complete
Complete
Complete
Complete
Complete
Complete
Is in Progress
Is in Progress
Is in Progress
Is in Progress
Is in Progress
Is in Progress
Is in Progress
Is in Progress
Complete
Is in Progress
Complete

ITD Cem

EXIGO

For Exigo

ITD Cem

You might also like