DAILYREPORTFROM SITE

S.No:45

1.

Date 25.02.2013

Site: M/s Baldev alloys pvt. LTD.


Vwta020,VWHA052,053,054

Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)

Nil.

2.

Details of communications sent to HO


on

Nil.

3.

Details of consignments / materials


received from HO / others

Nil.

4.

Details of payments received from HO /


others

Nil.

5.

Attendance with details


:

MR.M.E.MANIKANDAN(2141)

5.1

Staff (VEESONS)

Mr. DINESH KUMAR.S (1832)

5.2

6.

Contract Workers (Contractor wise)

Important brief feedback about Fabrication


/ Erection / Commissioning (delay with
reference to schedule, major problems
etc.,)

Utkal Engineers:
Boiler: Supervisor:01 IB
06; Riger-05;grinder-0 Helper-07(Total=24)

1.contractor man power shortage

2. Radiography film required from con


3.customer side insert plates

7.

Materials, documents, payments urgently


required from HO with details

8.

Any urgent / important site complaints

UTKAL Engineering Should be


increasing his manpower.
Utkal engineering tools &
tackles Shortage.(welding
machine & cutting set, Grinding
machine)

Site status:

VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM
1)
2)
3)
4)

Roof truss purlin material shifting work u/p.


Temporary supports cutting work u/p.
Non IBR drain piping fit up work u/p.
Air heater casing balance stretch welding completed.

ESP;
1) ESP sealing roof erection work u/p.
2) Field alignment checking work U/P.

Prepared by (Name):

M.E.MANIKANDAN

Checked & Approved by (Name) :

M.E.MANIKANDAN

Signature:

Signature:

Staff No : 2141

Staff No. :2141