ANDHRA PRADESH POWER GENERATION CORPORATION LIMITED
SRI DAMODARAM SANJEEVAIAH THERMAL POWER STATION
From To Executive Engineer/Civil, M/s Saraswathi-Bhavani JV Construction DivisionI/CCI, Flat No:111,VSS Nandadeep Apartments SDSTPS, Nelatur (V), Next to RTAoffice,Near Suchitra junction Muthukur (M), Nellore (Dt). Medchal Road,Quthbullapur(M) Secunderabad-500067 E-mail: saraswathicon@gmail.com
Sir, Sub:- SDSTPS 2X800MW Ash pond- Laying of ash pipeline including construction of pedestals,formation of embankment and laying of road along pipeline at SDSTPS,Nelaturu(v),Muthukur(M),Nellore(Dt),A.P.- Slow progress of the work - Reg.
Ref :- 1) L.S.Agt No.17/2013-14 of Superintending Engineer/CC-I/SDSTPS 2) Minutes of meeting held in the office of Chief Engineer/Civil/Thermal/APGENCO
***** It is to inform that, as per minutes of meeting held on 23.07.2014 cited reference 2 nd
the firm has to complete the fixing of clamps by 25.07.2014. But, even 50% of the clamps havent been completed so far. And, the firm has also promised to complete the 2 nd cast basalt line and seam less lines in all respects by 31.07.2014. But, it may not be possible to complete it in specified time, as its present progress is too slow. Further, it is also informed that, no concrete works have been taken up since last two weeks. Hence, in this connection it is requested to mobilize the work force and machinery to complete the fixing of clamps and laying of pipe lines immediately , and also complete the pending concrete works for culverts and remaining pedestals as evacuation of ash has already been commenced on 26.07.2014
Yours Faithfully, Sd/-
Executive Engineer/Civil CD-I/CC-I/SDSTPS
Copy submitted to Chief Engineer /const/ SDSTPS / for favor of information Copy submitted to chief Engineer/civil/Thermal projects-1/VS /HYD / for favor of information Copy submitted to superintending Engineer/CCI/SDSTPS for favor of information Copy to Assistant Executive Engineer/ civil/SDSTPS, for favor of taking necessary action.