The work distribution among various Directors have been issued vide letter
No. CBS/SO dated 19.07.2016. Consequent on promotion and transfer of
Shri Praveen Khorana, Director/B&S/CB-II, the work of Director/B&S/CB-II is
proposed to be looked after by Director/B&S/CB-I and Director/B&S/UTHS as
under:
Director/B&S/CB-I:
Director/B&S/UTHS:
(ii) Co-ordination with CWC, IMD & MOST for analysis of hydro-metrological
data and finalization of flood Estimation Reports for various
zones/subzones, Manual of Railway Affecting Works revision/updation,
collection of gauging/scour data from Zonal Railways, Inspection of gauging
sites, validation studies of flood Estimation Reports for various sub-zones,
other flood related issues, DBR of important bridges.
(iv) Projects:
(a) Use of Remote Sensing and GIS technique in flood estimation:
(IIT/Roorkee and ISRO).
(b) Scour Monitoring: (IIT/Kharagpur)
(Kailash Singh)
ED/Structures
Copy to :
Director/B&S/CB-I Director/B&S/UTHS
ED/STRUCTURES Unit:
Work -
(i) Technical: Design of PSC slabs and PSC Girders, Concrete Bridge code
revision/updation, Launching techniques, Inspection of PSC Bridges with
I&T Unit, Analysis of Arch Bridges, Arch Bridge code revision/updation.
(ii) Administrative: Library, Rajbhasha, ISO.
(iii) Projects: Assessment of efficacy of Arch bridges.
(iv) Any other work assigned from time to time.
(iii) Projects:
ADE - 1. Vacant
Work -
(i) Technical: DBR of Metro Projects, Ballastless track, High Speed
operation.
(ii) Any other work assigned from time to time.
(Kailash Singh)
ED/Structures
Copy to:
(i) ED/B&S
At present, the post of DD/B&F is lying vacant. The work of DD/B&F is therefore be
looked after by ADE/CB-II, till the regular incumbent posted in B&F.
(Praveen Khorana)
Director/B&S/CB-II
Copy to:
At present, the post of DD/B&F is lying vacant. The work of DD/B&F is therefore be
looked after by AIE/CB-I, till the regular incumbent posted in B&F.
(Praveen Khorana)
Director/B&S/CB-II
Copy to:
One post of Director/B&S/UTHS (work charged) has been sanctioned and now
made operational. In view of this distribution of works among Directors will be as under:
Director/B&S/CB-I
Technical:
Standard design of PSC slabs and girders, concrete bridge code, Launching
techniques, Inspection of PSC Bridges with I&T unit, Analysis of Arch Bridges, Arch
Bridge Code etc.
Administrative:
Project:
Director/B&S/CB-II
Technical:
Standard design of bridge sub structure and foundations, RCC slabs, RCC box culverts,
Limited Height Subway, RCC hume pipes, Pipeline crossings, Bridge substructure and
foundation code, Manual on design and construction of well and pile foundation.
Administrative:
B&F Unit
Technical:
Co-ordination with CWC IMD & MOST for analysis of hydro-metrological data and
finalization of Flood Estimation Reports for various zones/subzones, Manual of Railway
Affecting Works, collection of gauging/scour data from Zonal Railways, Inspection of
gauging sites, validation studies of Flood Estimation Reports for various sub-zones,
other flood related issues, DBR of important bridges etc.
Administrative:
Project:
Use of Remote Sensing and GIS in flood estimation with IIT/Roorkee and ISRO.
Scour Monitoring with IIT/Kharagpur.
Director/B&S/UTHS:
Technical:
Presently there is no separate unit, therefore, the items at lower level will be dealt by
respective units.
(H.L.Suthar)
ED/Structures
Copy to:
The work distribution among various Directors have been issued vide letter No.
CBS/SO dated 15.04.2015. At present Director/B&S/CB-I post is lying vacant. The work of
Director/B&S/CB-I is proposed to be looked after by Director/B&S/CB-II and
Director/B&S/UTHS as under:
Director/B&S/CB-II:
In addition to his works, DBS/CB-II will look after the works pertaining to Analysis of arch
bridges, Arch Bridge Code and Administrative work of ISO.
Director/B&S/UTHS:
In addition to his works, DBS/UTHS will look after the technical works of standard design of
PSC slab and girders, concrete bridge code, launching techniques, inspection of PSC
bridges with I&T unit, Temperature Project with Osmania University and Administrative
work of Library and Rajbhasha.
(H.L.Suthar)
ED/Structures
Copy to :
Director/B&S/CB-II Director/B&S/UTHS