Handing over notes of Shri. R. Baskaran, proceeding on 47 days leave from
29-06-09.
1. The road map for signaling in SWR for 2009-10 has been clearly defined
after discussion during Sr. DSTE’s meeting on 02-04-09, meeting minutes
issued and may be perused. (Copy enclosed for ready reference).
4. A month wise target for completion of signaling works have been finalised
after taking particulars from Sr. DSTE’s during meeting on 02-04-09.
5. Cable cuts ( both Signalling & Quad) are on the rise, critical sections are
ASK-RRB, b. DWR-KBI, c) UBL-HBS.
Sr. DSTES have been advised to monitor this very closely & take
action to prevent/ immediate restoration when the failure is there.
6. RRB indents: Statement ‘A’ shows the replacement indents required from
all Divisions, DRM’s to be pursued for obtaining the replacement indents.
7. No P.Way plan is pending in the CSTE’s office for clearance. CSE is the
secretary IRSTE chapter/SWR/Hubli. Executive committee meeting
conducted.
R. BASKARAN
CSE/SWR/UBL
C/- CSTE/SWR/UBL
2. SBC Division BYPL (Ex) - DBU section is nominated to CSE on “own your section”
scheme.
4. BYPL goods cabin replacement work is to be carried out with the existing
Signalling plan issued by CSTE/CN. The work is being progressed very slowly by
Sr. DSTE/SBC.
already been given in a month wise programme for the current financial year. For
6. Cable cuts (both Signalling & Quad) are on the rise, Critical sections are ASK-
Sr. DSTES have been advised to monitor this very closely & take action to
8. Taking over of stations from Construction: Many stations have been taken
over from construction even with pending works, , documents are yet to be
9. The documentation of signaling plan, TOC and circuit diagram in SW Rly is not
proper, for most of the stations, may be due to lack of staff and no system
being followed by open line units and Construction units who are executing
office is enclosed for following up. XSTE/Sig/HQ has been instructed to put up
10. The basic document of circuit diagram (bell tested copy) seems to be is missing
for many stations in UBL Division, where open line has carried out signaling
works. Details are yet to be received from Sr. DSTE/UBL. This may be the
11. Construction has not handed over “as made” diagrams, i.e. signalling plan, TOC &
circuit diagrams for most of the stations commissioned in the last 3 to 4 years.
This issue has been taken up with Construction for the past one year, but not
even a single as made document has been submitted to HQ in the last one year.
had more than 100 vital mistakes, which was got corrected after detailed check
up in the field. Since there has been delay in submission to the documents, the
check by open line also before the records are finalized. SSI circuit diagrams
have not been prepared by CSTE/CN & CSTE/Proj for most of the stations. This
12. Pending indents on RRB: Chairman RRB has been constantly pursued for
supplying the papers for the pending indents / replacement indents, details are
13. For the training programme of ESMs CSTE/S.Rly has agreed to conduct the
class room traings at zonal training centre (S&T) /PTJ starting from April 2010,
recently commissioned have got power supply problems due to improper initial
charging of batteries for which a detailed procedure order has been issued to
associate open line staff, which is not being followed by Dy.CSTE/CN/UBL The
same should be pursued with all the construction units for following CSTEs
procedure order.
15. A list of policy circulars issued in the last one year (18 Nos.) is enclosed for
signalling plans. Draft policy is being processed for approval of COM & CSTE.
17. Use of 1000V relays in major yards: Relay voltage at some of the
UCRs/HRs/ECRs and TPRs (where the station is located on one side) is very
critical (less than 20V). This can be improved by providing of 1000 ohms/24V
18. A trial made with 1000 Ohms Relay brought from BZA division has shown
19. UBL Division is having the practice of connecting fuses in the bus bar with 1.5
voltage on some of the relay racks, which can be improved by the order of 3
volts by providing separate wires to relay racks. This has been successfully
& SSE/Sig./BAY successfully. Video cameras are being installd for all SSE/Sig
21. AAC for 2010-11 is required to be finalised by all divisions by March 2010.
Action plan is advised. SBC division has not finalised any imprest stores from
22. Month wise action plan for Improvement of signalling systems for 2010 (Jan to
R. BASKARAN
CSE/SWR/UBL
C/- CSTE/SWR/UBL