You are on page 1of 3

DAILYREPORTFROM SITE

S.No: 02

1.

Date 23.11.2012

Site: M/s Baldev alloys pvt. LTD.


Vwta020,VWHA052,053,054

Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)

Additive mixing de

2.

Details of communications sent to HO


on

Daily report sent.

3.

Details of consignments / materials


received from HO / others

Nil.

4.

Details of payments received from HO /


others

Nil.

5.

Attendance with details


5.1

Staff (VEESONS)

:
MR.M.E.MANIKANDAN(2141)
Mr. DINESH KUMAR.S (1832)

5.2

6.

Contract Workers (Contractor wise)

Important brief feedback about Fabrication


/ Erection / Commissioning (delay with
reference to schedule, major problems
etc.,)

Utkal Engineers:
Boiler: Supervisor:01 IB
03; Riger-03;grinder-01Helper-03(Total=16)

1.contractor man power shortage

2. Radiography film required from con


3.customer side insert plates

4. Milwright fitter req for rotary equipm


5.Sporger header drain drawing

7.

8.

Materials, documents, payments urgently


required from HO with details

Any urgent / important site complaints

1. Utkal engg Contractor payment.


2.refractory contractor

UTKAL Engineering Should be


increasing his manpower.

Site status:

Vwta020 BOILER:
Work started time:08-00AMwork end time: 7-00PM
1) Initial heating and steam inlet piping erection work U/P.
2) PA branch header to spool piece welding work U/P.
3) FD header to Compartment header inlet duct welding work
U/P.

ESP;
1. Collecting electrode to carrier beam pin locking work U/P.
2. Current protection pipe erection work U/P.
VWHA052 Boiler
1. Hp dosing piping HP welding work U/P.
VWHA053 Boiler
1. Evaporator casing welding works U/P.

Prepared by (Name):

M.E.MANIKANDAN

Checked & Approved by (Name) :

M.E.MANIKANDAN

Signature:
Staff No : 2141

Signature:
Staff No. :2141