Professional Documents
Culture Documents
Resenting Arned Alue: Successfully
Resenting Arned Alue: Successfully
Earned ct Review
Value
Report
Projec
t/
Tasks
Totals
Successfully
for Pro
ject
Oct obe
Summa
ry
2002
Nov em
ber
Task 1
Decem
Task 1-A
Presenting
Earned Value
Progra
m Revie
w
ber
Budget
Task 1-B
Task 2
Budget
Spendin
$4,000.0
0
$3,000.0
0
$2,000.0
0
$1,000.0
0
$0.00
$321.74
$200.00
$483.33
t/
Projec
Tasks
March
Ap
May
$109.29
Bu
BCWP
ACWP
Value
ing E
BCWS Spend
dge t
$300
.00
$2, 500
.00
$2, 000
Task 2
Task 3
Task 4
BCWP
.00
$1, 500
BCWS
ACWP
$400
.00
$1, 000
$350
0
$500.0
Task 5
$456
$725
$550
$189
$159
$107
$0. 00
BCWS
BCWP
t
Budge
ACWP
Sum mar
$140
$175
$128
$250
$200
$100
$200
$564
$211
$223
$168
$150
Incomple
Earned Value has been used since the 1960s by the Department of Defense as a central
part of the C/SCSC (Cost/Schedule Control Systems Criteria). Recently, the DOD
revised the 35 criteria contained in the C/SCSC and produced the 32 criteria for EVMS
(Earned Value Management Systems).
$61
30. 6%
Review
CPI abo
te Task
d Task
These criteria have since been accepted by the American National Standards Institute/
Electronic Industry Association as a new standard, called ANSI/EIA 748. Now, EVM
is being used in a wider variety of government contracts, and is spreading through the
private sector as a valuable tool for project managers.
63. 6%
$64
ve 1.3
1.24
2.82
$364
$22
Program
Stat us
Com plete
52. 6%
1.09
0.80
($35)
$108
77. 8%
1.00
1.00
$0
$12
55. 8%
1.00
0.86
($50)
$0
100.0%
$400
$400
$400
$400
Task 1
$350
$300
1.15
1.27
$431
$0
100.0%
$300
SPI
CPI
CV
$267
67. 4%
48.6%
69.7%
CMPLT
$2, 005
$1, 575
$1, 740
$2, 975
.00
$3, 000
ABC
Project
Task 7
66.7%
$100.00
Contrac
ts review:
11-30-02
Sign Off:
______
______ SV
_____
PRCNT
Total
t
Budge
74.4%
64.4%
$200.00
$243.94
Review
mance
2002
Perfor
ril
80.4%
$186.05
$836.56
$225.00
$350.00
78.6%
$500.00
$725.00
Task 6
$235.71
$175.00
$1,300.0
0
Value
78.3%
$200.00
$350.00
$250.00
Task 2-B
64.2%
$743.50
$400.00
Task 2-C
PRCNT
CMPLT
$2,585.6
2
$725.00
$300.00
Task 2-A
Status
BCW
Ear ned P
Value
$1,375.0
0
$950.00
Task 1-C
Ear ned
ACWP
Spe ndi
ng
$4,025.0
0
$111
$23
$18
1.12
2.11
1.12
1.12
1.40
1.57
CPI from
1 to 1.3
w1
CPI belo
Successfully
page 2
Example:
April
May
$3,000.00
Budget-at-Completion
$2,500.00
$2,000.00
$1,500.00
Planned
Value = $1000
$1,000.00
Actual
Costs = $1000
$500.00
2002
March
April
May
$0.00
$3,000.00
Budget
AC
$2,500.00
Actual
Costs = $1000
Planned
Value = $1000
$2,000.00
Figure 1
$1,500.00
$1,000.00
Earned
Value = $750
$500.00
$0.00
EV
Budget
AC
Figure 2
From this example, we can see that EVM expands on the two-dimensional analysis
Has this project spent more or less money than planned? by adding the third
dimension What did we get for the money we spent?
Successfully
page 3
Building Blocks of
Earned Value Analysis
In addition to more accurate project status assessment, EVM makes it easy for a project
manager to analyze both schedule and cost performance in a variety of ways. Using a
limited set of basic task information, it is possible not only to determine how a project
has been performing, but to predict future performance trends as well.
Basis for Earned Value Analysis:
Contract Review
Earned Value Report
Project /
Tasks
Totals for Project
2002
October
November
BAC
AC
December
%
Complete
$4,025.0
$1,375.00
63.7%
$950.0
$725.00
78.3%
Task 1-A
$300.0
$200.00
78.6%
Task 1-B
$400.0
$350.00
80.4%
Task 1-C
$250.0
$175.00
74.4%
Task 1
$4,000.00
Once these three measurements have been established, the following calculations can be
performed:
Earned Value (EV) = BAC x Percent Complete. The budgeted cost of completed
work as of the current date.
Planned Value (PV) = The point along the time-phased budget that crosses the
current date. Shows the budgeted cost of scheduled work as of the current date.
Successfully
page 4
Building Blocks of
Earned Value Analysis
Project /
Tasks
October
November
December
BAC
64%
$4,025
$1,375
$2,564
$2,780
78%
$950
$725
$743
$783
Task 1-A
79%
$300
$200
$236
$246
Task 1-B
80%
$400
$350
$322
$339
Task 1-C
74%
$250
$175
$186
$198
10
11
12
13
14
November
December
$4,000.00
BAC
DATE
LINE
$3,500.00
$3,000.00
PV
$2,500.00
EV
$2,000.00
$1,500.00
$1,000.00
AC
$500.00
$0.00
Earned Value
Budget
Actual Costs
Planned Value
Summary
Program Review
Status
Successfully
page 5
Performance Indices
and Variance
Once Earned Value and Planned Value are known, they can then be used to determine
schedule and cost variance, and calculate performance efciency.
October
December
January
$3,500.00
$3,000.00
Schedule
Variance (SV)
$2,500.00
$2,000.00
Cost
Variance (CV)
$1,500.00
$1,000.00
$500.00
$0.00
Planned Value
Earned Value
BAC
Actual Costs
Figure 6
Successfully
page 6
Performance Indices
and Variance
Performance Review
Tasks
2004
BAC
March
April
May
CPI
SPI
Project A
$850
$270
$335
$250
1.08
0.81
Task 1
$350
$195
$260
$150
1.30
0.75
Task 2
$500
$75
$75
$100
0.75
1.00
Figure 7
Successfully
page 7
Forecasting Future
Performance Trends
The Schedule Performance and Cost Performance Indices not only monitor current
project performance, they can also be used to predict future performance trends.
To-Complete Performance Index (TCPI) = (BAC-EV) / (BAC-AC).
Indicates the CPI required throughout the remainder of the project to stay within
the stated budget.
Estimate at Completion (EAC) = AC + ((BAC-EV)/CPI). A forecast of total
costs that will be accrued by project completion based on past cost performance
trends.
Variance at Completion (VAC) = EAC BAC. The difference between the new
Estimate at Completion and the original Budget at Completion.
Performance Review
Tasks
BAC
EAC
2004
VAC
March
Project A
$2,975.0
2,355.70
-619.30
Task 1
$300.0
350.00
50.00
Task 2
$400.0
440.00
40.00
April
AC
EV
TCPI
CPI
May
$3,000.00
$1,615.00
$2,004.73
0.71
1.24
$350.00
$300.00
0.00
0.86
$440.00
$400.00
0.00
0.91
$175.00
$139.53
1.47
0.80
$200.00
$563.89
0.31
2.82
$1,000.00
$100.00
$210.53
0.63
2.11
$500.00
$200.00
$222.73
0.85
1.11
$150.00
$168.06
0.95
1.12
$2,500.00
$2,000.00
Task 3
$250.0
313.09
63.09
$1,500.00
Task 4
$725.0
257.13
-467.87
Task 5
$400.0
189.80
-210.20
Task 6
$350.0
314.66
-35.34
Task 7
$550.0
491.02
-58.98
$0.00
Planned Value
Earned Value
Budget
Actual Costs
Successfully
page 8
Tasks
March
Project A
April
May
3/10
5/8
Total
Budget
$2,975.0
Task 1
$300.0
Task 2
$400.0
Task 3
(2)
(1)
$250.0
Task 4
$725.0
Task 5
$400.0
(3)
Task 6
Task 7
$350.0
$550.0
Status
Incomplete Task
Completed Task
Started Task
Successfully
page 9
Tasks
Project A
%
Comp.
2004
March
April
59% 3/10
May
5/8
Total
Budget
AC
$2,975.00
$1,575.00
(5)
Task 1
100%
$300.00
$350.00
Task 2
100%
$400.00
$400.00
Task 3
51%
$250.00
$175.00
Task 4
78%
$725.00
$200.00
Task 5
47%
$400.00
$100.00
Task 6
73%
$350.00
$200.00
Task 7
14%
$550.00
$150.00
(4)
Status
Incomplete Task
Completed Task
Started Task
Successfully
page 10
2004
October
December
March
Project ABC
3/11
Task 1
Total
Budget
$2,975.0
$300.0
ACWP
Spending
BCWS
$1,739.90
$300.00
Contract Review
Task 2
Earned Value
Task 3
Budget
Task 4
Spending
$400.0
$350.00
$400.00
$400.00
$127.91
$175.00
October
BCWP
E Value
$4,025.0
$2,585.62
$950.0
$300.0
$743.50
$235.71
$400.0
$321.74
$250.0
$1,300.0
$186.05
$836.56
$725.0
SV
$225.0
PRCNT
CMPLT
$483.33
CV
CPI
$109.29
$350.0
67.4%$1,775.0
$264.85
$243.94
$429.74
$1,005.56 1.27
$550.0
$300.00 Final 100.0%
$0.00
$800.0
Review
$425.0
$400.00
100.0%
$0.00
$358.14
($50.00)
0.86
$480.00
$167.42
$0.00
1.00
$2,004.73
Project /
$3,000.00
$250.0
Tasks
$139.53
SPI
1.15
1.00
1.00
2004
55.8%
$11.62 ($35.47)
0.80
November
December
$1,500.00
1.09
$4,000.00
$456.48
$200.00
$563.89
77.8%
$107.41
$363.89
2.82
$189.47
$100.00
$210.53
52.6%
$21.06
$110.53
2.11 $3,500.00
1.11
1.24
$400.0
Summary
Task 1-A
Task 6
Program Review
$350.0
$159.09
$200.00
$222.73
Status
63.6%
$63.64
$22.73
1.11
Task 1-B
Task 7
$3,000.00
$550.0
$3,000.00
$2,000.00
$1,000.00
$0.00
AC
EV
$4,025.0
$1,375.00
$2,563.59
63.7%
$950.0
$725.00
$743.50
78.3%
$300.0
$200.00
$235.71
78.6%
$400.0
$350.00
$321.74
80.4%
74.4%
1.40
$106.94
$150.00
$168.06
30.6%
$61.12
$18.06
1.12
1.57
Task 1-C
PV
EV
BAC
AC
BAC
$0.00
Task 1
Task 5
$1,575.00
Earned
Value
Budget
November
$250.0
$175.00
$186.05
$1,300.0
$500.00
$836.56
64.4%
$725.0
$200.00
$483.33
66.7%
$225.0
$100.00
$109.29
48.6%
$350.0
$200.00
$243.94
69.7%
$1,775.0
$150.00
$983.53
55.4%
$550.0
$150.00
$358.14
65.1%
$800.0
$0.00
$480.00
60.0%
$0.00
$145.39
34.2%
$2,500.00
Task 2
Summary
Status
Task 2-A
Task 2-B
$2,000.00
Completed Task
Task 2-C
Incomplete Task
Program Review
CPI below 1
Task 3
Task 3-A
$1,000.00
$500.00
Task 3-B
Final
Review
Task 3-C
Earned Value
Budget
Spending
$0.00
$425.0
Summary
Program Review
Status
Successfully
page 11
2005
March
Project ABC
BAC
April
May
PRCNT
CMPLT
$1,809
$1,575.0
$2,005
67.4%
Budget $2,500.00
$300
$300
$350.0
$300
100.0%
$2,000.00
$400
$400
$400.0
$400
100.0%
$1,500.00
$250
$134
$175.0
$140
55.8%
$1,000.00
$725
$483
$200.0
$564
77.8%
$400
$200
$100.0
$211
52.6%
$350
$170
$200.0
$223
63.6%
PV
Task 3
AC
Spending
Task 4
Earned
Value
$2,975
Task 2
Earned Value
Actual
Costs
5/8 $3,000.00
3/10
Task 1
Planned
Value
Task 5
$500.00
Task 6
$0.00
PV
EV
BAC
AC
Status
Incomplete Task
Completed Task
Started Task
Successfully
2005
Schedule Variance = EV - PV
Cost Performance Index = EV / AC
May
Total
Budget
5/8
$2,975.00
Task 1
Task 2
Cost Variance = EV - AC
Schedule Performance Index = EV / PV
Actual
Costs
Earned
Value
$1,808.97
$1,575.00
$2,004.73
67.4%
$195.77
$429.74
1.27
1.11
$300.00
$300.00
$350.00
$300.00
100.0%
$0.00
($50.00)
0.86
1.00
$400.00
$400.00
$400.00
$400.00
100.0%
$0.00
$0.00
1.00
1.00
Task 3
$250.00
$133.72
$175.00
$139.53
55.8%
$5.81
($35.47)
0.80
1.04
Task 4
$725.00
$483.33
$200.00
$563.89
77.8%
$80.56
$363.89
2.82
1.17
Task 5
$400.00
$200.00
$100.00
$210.53
52.6%
$10.53
$110.53
2.11
1.05
Task 6
$350.00
$169.70
$200.00
$222.73
63.6%
$53.03
$22.73
1.11
1.31
$550.00
$122.22
$150.00
$168.06
30.6%
$45.84
$18.06
1.12
1.38
March
Project ABC
April
3/10
Task 7
PV
EV
BAC
AC
Planned
Value
page 12
PRCNT
CMPLT
SV
CV
CPI
SPI
$3,000.00
Summary
Status
Completed Task
Incomplete Task
Program Review
CPI below 1
$2,000.00
$1,000.00
$0.00
SV
CV
$500.00
$350.00
$200.00
$50.00
($100.00)
Contract Review
Summary
Program Review
2005
October
November
Budget
December
Actual
Costs
Status
Earned
Value
PRCNT
CMPLT
$4,025.00
$1,375.00
$2,585.62
64.2%
$950.00
$725.00
$743.50
78.3%
Task 1-A
$300.00
$200.00
$235.71
78.6%
Task 1-B
$400.00
$350.00
$321.74
80.4%
Task 1-C
$250.00
$175.00
$186.05
74.4%
$1,300.00
$500.00
$836.56
64.4%
Task 2-A
$725.00
$200.00
$483.33
66.7%
Task 2-B
$225.00
$100.00
$109.29
48.6%
Task 2-C
$350.00
$200.00
$243.94
69.7%
$1,775.00
$150.00
$1,005.56
56.7%
$550.00
$150.00
$358.14
65.1%
$800.00
$0.00
$480.00
60.0%
$425.00
$0.00
$167.42
39.4%
Task 1
Task 2
Task 3
Task 3-A
Task 3-B
Final
Review
Task 3-C
Earned Value
Budget
Spending
$4,000.00
$3,000.00
$2,000.00
$1,000.00
$0.00
Successfully
Performance Review
Project/
Tasks
2005
March
April
Total
Budget
May
$3,000.00
Project ABC
Budget
$2,500.00
Task 1
Task 2
Planned
Value
page 13
Cost Variance = EV - AC
Schedule Performance Index = EV / PV
Actual
Costs
Earned
Value
PRCNT
CMPLT
SV
CV
CPI
SPI
$2,975.0
$1,808.97
$1,575.00
$2,004.73
67.4%
$195.77
$429.74
1.27
1.11
$300.0
$300.00
$350.00
$300.00
100.0%
$0.00
($50.00)
0.86
1.00
$400.0
$400.00
$400.00
$400.00
100.0%
$0.00
$0.00
1.00
1.00
$250.0
$133.72
$175.00
$139.53
55.8%
$5.81
($35.47)
0.80
1.04
$725.0
$483.33
$200.00
$563.89
77.8%
$80.56
$363.89
2.82
1.17
$400.0
$200.00
$100.00
$210.53
52.6%
$10.53
$110.53
2.11
1.05
$350.0
$169.70
$200.00
$222.73
63.6%
$53.03
$22.73
1.11
1.31
$550.0
$122.22
$150.00
$168.06
30.6%
$45.84
$18.06
1.12
1.38
$2,000.00
Earned Value
Task 3
Planned Value
$1,500.00
Task 4
Actual Cost
$1,000.00
Task 5
Task 6
$500.00
Task 7
$0.00
PV
EV
BAC
AC
Summary
Status
Program Review
Completed Task
Incomplete Task
CPI below 1
Copyright 2005 KIDASA Software, Inc. All rights reserved. www.kidasa.com. This publication may be distributed freely, as long as it is distributed in its entirety.