Chemical Cleaning of Pre-Boiler System
Chemical Cleaning of Pre-Boiler System
PRE-BOILER SYSTEM
OBJECTIVES
To remove dirt ,oil ,grease etc., from Condensate ,Feed
water, Drip and Extraction steam lines of HP and LP
heaters prior to putting these systems in regular service.
This is to ensure flow of clean condensate and feed water
to the boiler.
CLEANING METHOD
Pre-Mounting Cleaning
STEP- I
The demineralized water is heated upto 700c in the De-aerator
FST.
The Chemical solution prepared in reagent preparation plant is
mixed with the hot water in the De-aerator FST.
CHEMICAL
DEAERATOR
AUX.STEAM
FST
BP
BP
BP
CONDENSERS
CEPS
BP
STEP II
CEPs are charged from water side by opening suction valve
and through proper venting, keeping discharge valve in closed
condition and suction strainer in position.
Flushing started by alternately starting and stopping CEPs and
completing the circulation from CEP discharge to CEP suction
line through recirculation line and condenser.
CHEMICAL
DEAERATOR
AUX.STEAM
FST
BP
BP
BP
CONDENSERS
CEPS
BP
CIRCUIT 1:
Circuit 1A
De-aerator FST TDBFP A booster pump suction line
BP strainers Temporary header connecting the BP
suction lines downstream of the strainers Acid cleaning
pumps Temporary discharge header Temporary lines
to the discharge gate valves of four feed pumps Feed
lines to HPH Bypass line of all HPH HPH bypass
lines Water path of HPH 6,7,8 Feed water line upto
boiler feed control unit Temporary discharge line to the
circulating water line - De-aerator FST.
Circuit 1B
De-aerator FST TDBFP B booster pump suction line
BP strainers Temporary header connecting the BP
suction lines downstream of the strainers Acid cleaning
pumps Temporary discharge header Temporary lines
to the discharge gate valves of four feed pumps Feed
lines to HPH Bypass line of all HPH HPH bypass
lines Water path of HPH 6,7,8 Feed water line upto
boiler feed control unit Temporary discharge line to the
circulating water line - De-aerator FST.
Circuit 1C
De-aerator FST MDBFP booster pump suction line
BP strainers Temporary header connecting the BP
suction lines downstream of the strainers Acid cleaning
pumps Temporary discharge header Temporary lines
to the discharge gate valves of four feed pumps Feed
lines to HPH Bypass line of all HPH HPH bypass
lines Water path of HPH 6,7,8 Feed water line upto
boiler feed control unit Temporary discharge line to the
circulating water line - De-aerator FST.
Circuit 1D
De-aerator FST Booster pump suction line BP
strainers Temporary header connecting the BP suction
lines downstream of the strainers Acid cleaning pumps
Temporary discharge header Temporary lines to the
discharge gate valves of TDBFP A Feed lines to HPH
Bypass line of all HPH HPH bypass lines Water path
of HPH 6,7,8 Feed water line upto boiler feed control
unit Temporary discharge line to the circulating water
line - De-aerator FST.
Circuit 1E
De-aerator FST Booster pump suction line BP
strainers Temporary header connecting the BP suction
lines downstream of the strainers Acid cleaning pumps
Temporary discharge header Temporary lines to the
discharge gate valves of TDBFP B Feed lines to HPH
Bypass line of all HPH HPH bypass lines Water path
of HPH 6,7,8 Feed water line upto boiler feed control
unit Temporary discharge line to the circulating water
line - De-aerator FST.
Circuit 1F
De-aerator FST Booster pump suction line BP
strainers Temporary header connecting the BP suction
lines downstream of the strainers Acid cleaning pumps
Temporary discharge header Temporary lines to the
discharge gate valves of MDBFP A Feed lines to HPH
Bypass line of all HPH HPH bypass lines Water
path of HPH 6,7,8 Feed water line upto boiler feed
control unit Temporary discharge line to the circulating
water line - De-aerator FST.
Circuit 1G
De-aerator FST Booster pump suction line BP
strainers Temporary header connecting the BP suction
lines downstream of the strainers Acid cleaning pumps
Temporary discharge header Temporary lines to the
discharge gate valves of MDBFP B Feed lines to HPH
Bypass line of all HPH HPH bypass lines Water
path of HPH 6,7,8 Feed water line upto boiler feed
control unit Temporary discharge line to the circulating
water line - De-aerator FST.
Circuit 1H
De-aerator FST Booster pump suction line BP
strainers Temporary header connecting the BP suction
lines downstream of the strainers Acid cleaning pumps
Temporary discharge header Temporary lines to the
discharge gate valves of four feed pumps Feed lines to
HPH 50 % bypass line of all HPH Feed water line
upto boiler feed control unit Temporary discharge line
to the circulating water line - De-aerator FST.
Circuit 1I
De-aerator FST Booster pump suction line BP
strainers Temporary header connecting the BP suction
lines downstream of the strainers Acid cleaning pumps
Temporary discharge header Temporary lines to the
discharge gate valves of four feed pumps Feed lines to
HPH 100 % bypass line of all HPH Feed water line
upto boiler feed control unit Temporary discharge line
to the circulating water line - De-aerator FST.
Circuit 1J
De-aerator FST Booster pump suction line BP
strainers Temporary header connecting the BP suction
lines downstream of the strainers Acid cleaning pumps
Temporary discharge header Temporary lines to the
discharge gate valves of four feed pumps Feed lines to
HPH bypass line for 6A,7A,8A Feed water line upto
boiler feed control unit Temporary discharge line to the
circulating water line De-aerator FST.
Circuit 1K
De-aerator FST Booster pump suction line BP
strainers Temporary header connecting the BP suction
lines downstream of the strainers Acid cleaning pumps
Temporary discharge header Temporary lines to the
discharge gate valves of four feed pumps Feed lines to
HPH bypass line for 6B,7B,8B Feed water line upto
boiler feed control unit Temporary discharge line to the
circulating water line De-aerator FST.
Circuit 1E
De-aerator FST Booster pump suction line BP
strainers Temporary header connecting the BP suction
lines downstream of the strainers Acid cleaning pumps
Temporary discharge header Temporary lines to the
discharge gate valves of four feed pumps Feed lines to
HPH Water path of HPH 6A,7A,8A Feed water line
upto boiler feed control unit Temporary discharge line
to the circulating water line De-aerator FST.
Circuit 1L
De-aerator FST Booster pump suction line BP
strainers Temporary header connecting the BP suction
lines downstream of the strainers Acid cleaning pumps
Temporary discharge header Temporary lines to the
discharge gate valves of four feed pumps Feed lines to
HPH Water path of HPH 6B,7B,8B Feed water line
upto boiler feed control unit Temporary discharge line
to the circulating water line De-aerator FST.
CIRCUIT 2:
Circuit 2A
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs line down stream of LPHs Temporary
discharge line to the circulating water system Deaerator FST
Circuit 2B
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Water side of LPHs Line
down stream of LPHs Temporary discharge line to the
circulating water system De-aerator FST
CIRCUIT 3:
Circuit 3A
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs Temporary header for water supply to the HPH
steam space Steam side of HPH 6A HPH discharge
line Temporary discharge line to the circulating water
system De-aerator FST
Circuit 3B
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs Temporary header for water supply to the HPH
steam space Steam side of HPH 6B HPH discharge
line Temporary discharge line to the circulating water
system De-aerator FST
Circuit 3C
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs Temporary header for water supply to the HPH
steam space Steam side of HPH 7A HPH discharge
line Temporary discharge line to the circulating water
system De-aerator FST
Circuit 3D
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs Temporary header for water supply to the HPH
steam space Steam side of HPH 7B HPH discharge
line Temporary discharge line to the circulating water
system De-aerator FST
Circuit 3E
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs Temporary header for water supply to the HPH
steam space Steam side of HPH 8A HPH discharge
line Temporary discharge line to the circulating water
system De-aerator FST
Circuit 3F
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs Temporary header for water supply to the HPH
steam space Steam side of HPH 8B HPH discharge
line Temporary discharge line to the circulating water
system De-aerator FST
CIRCUIT 4:
Circuit 4A
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs Temporary header for water supply to the LPH
steam space Steam side of LPH 1A LPH discharge
line Temporary discharge line to the circulating water
system De-aerator FST
Circuit 4B
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs Temporary header for water supply to the LPH
steam space Steam side of LPH 1B LPH discharge
line Temporary discharge line to the circulating water
system De-aerator FST
Circuit 4C
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs Temporary header for water supply to the LPH
steam space Steam side of LPH 2 LPH discharge
line Temporary discharge line to the circulating water
system De-aerator FST
Circuit 4D
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs Temporary header for water supply to the LPH
steam space Steam side of LPH 3 LPH discharge
line Temporary discharge line to the circulating water
system De-aerator FST
Circuit 4E
Condenser CEP suction lines Acid cleaning pumps
CEP discharge header Condensate line bypassing
LPHs Temporary header for water supply to the LPH
steam space Steam side of LPH 4 LPH discharge
line Temporary discharge line to the circulating water
system De-aerator FST
BP
BP
HPH-6A
HPH-6B
M
M
HPH-7A
HPH-7B
HPH-8A
HPH-8B
TO ECO
I/L
MAIN
CONDENSER - 1
MAIN
CONDENSER - 2
M
M
CEP-3
CEP-2
CEP-1
LPH-1A
LPH-3
LPH-4
LPH-2
M
M
M
M
DRIP /P-B
GSC
DRIP /P-A
LPH-1B
M
CPU
M
BP
BP
HPH-6B
HPH-6A
HPH-7A
HPH-7B
HPH-8A
HPH-8B
MAIN
CONDENSER - 1
MAIN
CONDENSER - 2
CEP-3
CEP-2
CEP-1
M
M
GSC
CPU
M
TO ECO I/L
BP
M
M
BP
MAIN
CONDENSER - 1
MAIN
CONDENSER - 2
CEP-3
CEP-2
CEP-1
LPH-1A
LPH-3
LPH-4
LPH-2
M
M
M
M
M
GSC
LPH-1B
CPU
M
M
BP
M
HPH-6A
BP
HPH-6B
M
M
HPH-7A
HPH-7B
HPH-8A
HPH-8B
TO ECO
I/L
CEP-3
CEP-2
CEP-1
M
M
M
GSC
CPU
M
M
M
MAIN
CONDENSER - 2
M
MAIN
CONDENSER - 1
BP
M
M
BP
MAIN
CONDENSER - 1
MAIN
CONDENSER - 2
CEP-3
CEP-2
CEP-1
LPH-1A
LPH-3
LPH-4
LPH-2
M
M
M
DRIP /P-B
GSC
DRIP /P-A
LPH-1B
M
CPU
M
ACID CLEANING:
Acid cleaning is made using the same four circuits on which
water washing is made. To make closed circuit the de-aerator
is included into the scheme, in which cleaning solution can be
heated if required.
Reagents in liquid form, each by separate pipeline, are
supplied from reagent preparation plant into suction pipeline
of acid cleaning pump.
Minimum Hydrofluoric acid solution temperature is 200C and
optimum temperature is 400 C
Acid cleaning phase duration is 4-8 hours at temperature up to
400C
Hydrofluoric acid cleaning solution concentration is selected
depending on ferric oxide quantity in the circuit to be washed.
PASSIVATION:
Passivation of acid cleaned surface is carried out with
Hydrogen Peroxide solution added with ammonia.
Before passivation the acid cleaned surface is neutralized with
the circulation of ammonia solution.
Passivation is carried out with demineralized water under the
following conditions:
Hydrogen Peroxide concentration is 0.02%.
Ammonia Concentration is upto 0.8%.
Solution temperature is 400C.
Duration 4-6 hours.
Solution flow velocity is 0.3 to 0.5 m/s