PROJECT
Sea link project conceived in 1999.
Plagued by PILs Fishermen & Environmentalists
2004 - Work Started.
But drastic changes to 80% of the bridge design.
Cost escalation from Rs. 350 Crore to Rs. 1,306 Crore
to Rs. 1,634 Crore.
MSRDC Project.
Executed by Hindustan Construction Company.
Illumination By Bajaj Electricals for a budget of Rs. 9
Crore.
LOCALE
Build over Mahim Bay
Connects Bandra (suburb) to Worli
(Central Mumbai)
8-Lane wide
Sea-link Length = 5.6 Kilometers
Over the Sea = 3.8 Kilometers
FACT
India's first eight-lane freeway over
the open sea.
Hailed
as
a
modern
engineering marvel.
Indian
connectivity
from
city
to
PROBLEMS PERCEIVED
No solutions figured out for major
traffic snarls at Worli.
Additional Congestion at some
other roads.
Proposed Toll price (Rs. 50 / oneway) may dissuade a few.
Carries
Crosses
Mahim Bay
Locale
Mumbai,Maharashtra,Indi
a
Maintained by
Hindustan Construction
Company
Designer
Seshadri Srinivasan
Design
Cable-stayed,Viaducts
Total length
5.6kilometres (3mi)
Height
126m
Longest span
250m x 2
Clearance below
20m
Construction begin
2000
Construction end
21 April 2009
Opened
30 June 2009
Toll
50 (US$1.11)for one
way
75 (US$1.67)for both
side