ACCEPTANCE TEST PROCEDURE

IMPROVEMENT
Jan 15

Plan

Design

Preparation

Implement

Maintenance

ATP Activities
ATP Improvement
1. Optic measurement
Optic cleaning
Optic performance test
2. Installation documentation
Measurement capture at
installation system
3. Approval process
Handover process from
construction to maintenance
team
4. As build drawing
Sites layout
Sites equipment
2

Optic Measurement

i.
ii.

Check insertion loss and reflectance of each network


component/event using OTDR
Create PDF certification report for handover pack and
.SOR file for reference.

Optic Cleaning
i.

ii.

iii.

Check all LC feeder connectors are


clean and free from dust, moisture,
contamination and scratches
Check BBU, RRU TX ports are clean
and free from dust, moisture,
contamination and scratches
Create PDF certification report for
handover pack and .SOR file for
reference.

Optic Cleaning
i.

ii.

iii.

Check all LC feeder connectors are clean and


free from dust, moisture, contamination and
scratches
Check BBU, RRU TX ports are clean and free
from dust, moisture, contamination and
scratches
Create PDF certification report for handover
pack and .SOR file for reference.

Installation Documentation

Approval Process
Team maintenance should be confirm and accept all installation item.

As Build Drawing Site Lay Out

As Build Drawing Site Equipment