Providing & laying in position specified grade of reinforced cement concrete including
mixing, pouring, consolidating & curing but excluding the cost of formwork, finishing
and reinforcements. All up to plinth level. (Nominal Mix) (Lead up to 30.0 M from place
of mixing & Depth of concrete placement up to 3.0 M from plinth level.)
E1 - RCC 1 : 1 : 2 UP TO PLINTH LEVEL
Project / Reference No. / Item Designation
DESCRIPTION
QUANTITY
UNIT
RATE
AMOUNT
M3 )
Foreman
0.05
No.
400
20
Labour (M)
2.0
No.
300
600
Mixer Operator
0.070
No.
350
24.5
Mason
0.17
No.
400
68
Waterman
0.90
No.
250
225
Material:
Aggregate 20 mm & down
0.675
M3
1050
708.75
0.225
M3
915
205.87
Cement
12.2
Bag
300
3660
Coarse Sand
0.45
M3
1120
504
Carriage:
Aggregates
0.90
M3
55
49.5
Cement
0.61
Ton
50
30.5
Sand
0.45
M3
55
24.75
Sub Total:
6120.87
306.04
Water + Electricity
1.5
91.81
12
734.5
10
612.08
7865.3
Rate: Rs / M3
7865.3
Clear
Enter Current Rates for Labour, Material, Taxes etc. & Click Rate Button above.
*** Includes cost of hire & running charges of mixer, vibrator, crane/winch, pump etc.
@ 1.5 % and 0.5 % for scaffolding, testing concrete cubes etc.
SUMMARY
Labour Rs/unit
937.5
Labour
www.agboatwala.com/WEB_SRA/RCC1.htm
Mat+Carr Rs/unit
5183.37
Material + Carr
OTHER Rs/unit
1744.43
OTHER
1/2
10/26/15
11.91 %
Labour Material
65.9 %
18.08 %
22.17 %
www.agboatwala.com/WEB_SRA/RCC1.htm
2/2