RAINY SEASON WORKING PLAN SUTT 150 KV Rajamandala

1. PREPARATION.
In doing excavation and foundation, need to be prepared as follows:
The land for the installation of temporary tents and benches for rest of workers
Plastic sheeting 6 x 8 meters
Pole buffer temporary tents
Pallet for placement of cement
The bench for the rest of workers
Hoe
The water pump
Ladder
2. EXCAVATION
Make a border/bouwplank area excavation, so that appropriate excavation foundation
drawing.
Keep gutters around the excavation area, so if the rain water will not flow to excavation
area.

Gutter

Excavation
Area

Excavation done manually because the Tower location that can not be done with the excavator.

Excavations carried out when it did not rain and when to carry out the excavtion, then each
worker was given protective rain (raincoat).
Prepare the pump to drain the water in order to facilitate excavation.
Tools needed to work the rainy season:
Raincoat
plastic sheeting
The water pump
Stairs
The worker
cement mixer
Hoe
Casting.
When the rainy season arrives, the foundry work to do the main thing is the job:
Learn Concrete
Setting Stub
Iron work
Form work for Pad
Casting cement Pad
Form work to Chimney
The work done under the temporary tent/ plastic sheet.

Plastic sheet

Bamboo/woods
Lay down

Ladder
Ladder

Learn Concrete

Pedestal Stub

Excavation Area

Site Mix

After Back fill