Professional Documents
Culture Documents
This is the method statement for construction for the Afon Goedwig micro-hydro
power project. The civil engineering components of the project are an intake weir,
pipeline, powerhouse and outfall.
This method statement includes precautions for in and out of river works with
respect to protection of watercourses and aquatic life.
The following sections detail the outline of works for each component of the
project, followed by the matrix of key hazards with respect to protection of
watercourses on site and the incident response procedure
Construction Schedule
Intake construction is planned for June 2016, historically the driest month for this
area. Plans will be reactive to weather conditions. Works in rivers will be only be
carried out in periods of low flow and concrete pouring will only be carried out in
a stable period of dry weather. In the event of adverse weather predictions all at
risk or dismountable works will be removed from the river and the banks.
1 Site Preparation
1.1 Necessary drawings and documentation are in place for the works.
1.2 Health and safety documentation and provision is in place. Action plans and
materials in place to respond to any incidents involving leaks/breaches/spillages.
1.3 Induction of all contractors on arrival at site including; access, incident and
emergency procedures, health and safety, environmental protection, and
pollution control
1.4 Access routes are established and “no go” zones are marked out
2 Intake Construction
The intake structure is approximately 5m wide and 2m long, made from
approximately 3m3 of reinforced concrete.
A number of impassable falls prevent migrating sea trout reaching further than
approx. 50m upstream of the tailrace area towards the intake.
Fish Protection
It has been agreed with Joel Rees-Jones of NRW on 13/5 that we do not require
to build a fish easement at the intake since there are falls which are impassable
to local brown trout nearby downstream. Hence the proposed measures re fish
and eels are to clear the area by walking through the site several times to
disperse any fish prior to works commencing, and to ensure free downstream
passage at all times.
The weir will be cast with a large open bypass notch around the temporary
bypass pipe. Once all casting work is completed on the weir and all temporary in
river works have been removed, a pre-fabricated plate will be slotted into place in
the bypass notch to complete the weir.
3 Pipeline installation
Pipe route
The section of pipe exiting the intake runs in the riparian zone for approximately
35m and precautions will be taken as for the construction of the intake with
respect to pollution and silt control. Where active drainage lines are crossed by
the pipe route, silt traps will be installed as required.
Measures will be taken to ensure that the pipe route stays isolated from the
stream flow as it leaves the river. Where the pipe trench is temporarily open by
the stream near the intake, sand bags will be used to prevent any possibility of
the stream entering the trench.
The pipe route is adjacent to the existing forestry track for the upper 400m.
After 400m meters the pipe route leaves the forestry road and the remaining
500m will be laid on the surface/shallow buried or covered. For this section the
pipe route is over 50 to 100m away from the river and does not lie on steep cross
slopes falling into the river.
The pipe route does not cross any streams or major drainages.
Pollution control
Trenches will be kept open for a minimum length of time. Open cut trenches will
be fitted with silt traps or silt curtains at all intersections with culverts or other
drainage lines. On sloping ground a section of trench will be left closed every
10m to prevent trenches from becoming drainage lines.
As-dug material will be used to backfill around the pipe. The top soil is very thin
in the area, whilst the subsoil has high clay content, preventing the pipe route
becoming a drain once constructed.
Access to the site is by existing forestry tracks. We will minimize requirements for
vehicles to leave existing tracks. Where vehicle access off of the tracks is
required silt traps will be installed on any drainage lines crossed by the
temporary access routes.
Fish protection
The stretch of stream where the tailrace will be located may occasionally be
accessed by sea trout from the Dulas for spawning for short periods during high
flows (they would have to travel through a 30m long, 3m wide flat bottomed
culvert to get there). We will walk through the works area several times before
starting works. Free upstream and downstream movement by fish and eels will
be maintained during construction of the outfall.
The outfall will be constructed in the following steps during August ‘16:
4.1 Works are isolated from the river by erection of a temporary cofferdam – see
sketch plan below for layout. A small pump will be installed behind the cofferdam
to drain down the area for work. Pumped water will be discharged into the silt
trap erected away from the watercourse.
4.2 The outfall area is excavated down to bedrock or solid ground. Existing
material to be placed to one side for reinstatement
4.3 The floor slab will be cast in concrete
4.4 Once cured, the main outfall structure will be shuttered and cast with
reinforced concrete, around the pipe from the turbine. Wing walls will be
completed, tied into the banks
4.5 River bed reinstated to original level
4.6 Bank and bed scour protection completed using large boulders from
powerhouse excavation
4.7 Outfall screens fitted
4.8 Remove coffer dam and pollution control measures
4.9 Tidy site on conclusion
4.10 Monitor new structures and reinstated grounds
5 Export cable duct installation:
The export cable will be ducted under the stream in August 2016. The duct
carrying the cable will be buried in the existing bed material at a minimum depth
of 500mm below the existing bed level. The bed at the point of crossing is
composed of large shale mudstone. Burial of the duct will be carried out only in
low flow conditions and in a sequence to maintain the unimpeded flow of the
stream during construction. A temporary diversion using sandbags and pipes will
be constructed to divert the flow within the existing channel whilst the duct is
being installed.
Sequence of works for duct installation is as follows;
5.1 Establish temporary diversion of flow within watercourse and
pollution/sediment control measures
5.2 Any pumping required for dewatering of works will be discharged out of the
river channel into silt traps
5.3 Remove material for burial of duct – all removed material is to be stored out
of river and held separate from surrounding material for reinstatement
5.4 Install duct and replace bed material, ensuring reinstatement of bed and
banks to original condition with additional stone as necessary
5.5 Remove temporary flow diversion and demount silt traps/pollution control
measures
5.6 Tidy site on conclusion
5.7 Monitor reinstated grounds for any potential issues
Hazard Mitigation
5.1 Silt making the water turbid and Do not disturb submerged silt beds or
causing damage to aquatic plants and material within the river. Do not allow
fish populations any excavated material to enter into the
river.
5.4 Oil and fuel contaminating soil If an incident occurs and any soils or
other materials are contaminated with
fuel or oil, move them to a suitable
landfill site. Ensure that there is
provision on site for containment of
spills
5.5 Chemicals entering the Consider necessity of any chemicals
watercourse brought onto site, avoid use of all
potentially harmful chemicals and
substitute for non toxic materials and
processes wherever possible.
If necessary for use on site keep
chemicals and oils securely stored.
Ensure any contractors are aware of
correct usage and importance of
avoiding contamination through
careless use, spillage or improper
disposal.
6 Incident Procedure
In the event that the environmental protection measures should fail and an
unforeseen pollution incident should occur, the following procedure is to be
followed:
6.1 Discoverer of incident alerts Construction Manager of nature and magnitude
of the incident
6.2 Construction Manager to reports incident to Natural Resources Wales
immediately in order to inform of potential hazards and to take advice on how to
proceed
6.3 Construction Manager and team to prevent situation from getting any worse
(i.e. stop pollution source if possible)
6.4 If not possible to stop pollution source, Construction Manager and team to
contain situation and minimize damage
6.5 Work not to be recommenced until pollution incident is resolved and all
mitigation measures have been checked and reinstated
6.6 Following any incident; Construction Management team to review site
methods and working practices with NRW