Professional Documents
Culture Documents
Technical Specification
Technical Specification
1
2
3
4
5
6
7
8
Vitrified tiles
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
Drip Seal
GI pipe Sealant
Pipe clamp & supports
Clean Out Plug
GM / Forged Brass Ball Valves
Wafer Type Check Valve
Butterfly Valve
Air Release Valve
Ball Float Valve
MH / Water Tank Plastic Steps
Insulation for Hot Water Pipes
Water Tanks
SFRC MH cover & frame and gratings
49
50
51
52
53
54
55
56
57
58
59
60
61
Paver Tiles
TECHNICAL SPECIFICATIONS
FOR
CIVIL AND OTHER ALLIED WORKS
CONTENTS
Sub-Head No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
Content / Description
-----------------REFERENCE STANDARDS
EARTH WORK
ANTI-TERMITE TREATMENT
SAND FILLING
STONE FILLING
UPVC PIPE
PEA GRAVEL
PLAIN AND REINFORCED CONCRETE WORK
STEEL REINFORCEMENT
FORM WORK
STRUCTURAL STEEL WORK
ALUMINIUM DOORS, WINDOWS & VENTILATORS
FLOORING AND PAVING
PLASTERING
WHITE WASHING AND CEMENT PAINTING
IS: 248
IS: 383
IS: 419
IS: 427
IS: 432
IS: 456
IS: 459
IS: 515
IS: 730
IS: 800
IS: 814
Covered electrodes for manual metal arc welding of carbon and carbon
manganese steel.
IS: 815
IS: 816
IS: 817
IS: 883
IS: 1038
IS:1079
IS: 1081
Code of practice for fixing and glazing of metal (steel and aluminium)
doors, windows and ventilators.
IS: 1161
IS: 1285
Wrought aluminium and aluminium alloy extruded round tube and hollow
sections.
IS: 1361
IS: 1363
IS: 1367
IS: 1566
IS: 1786
High strength deformed steel bars and wires for concrete reinforcement.
IS: 2062
IS: 2116
IS: 2212
IS: 2386
IS: 2553
IS: 2835
IS: 3007
IS: 4021
IS:- 4923
IS: 4925
IS: 5410
Cement Paint.
IS: 6477
IS: 7318
IS: 10262
welding
of
IS: 2720(PART- XXVIII) - Determination of dry density of soil, in-place, by the Sand
Replacement Method
IS: 2720(PART- XXIX)
Cutter Method
IS: 2076
IS: 4985
IS: 14294
IS: 14324
3.0
EARTHWORK
3.1
EXCAVATION
3.1.1
3.1.2.
Surface dressing shall be carried out on the entire area occupied by the
buildings including plinth protection as directed without any extra cost.
The depths of excavation shown on the drawings are the depths after
surface dressing.
3.1.3
3.1.4
Black cotton soil, and other expansive or unsuitable soil excavated shall
not be used for filling in foundations, and plinths of buildings or in other
structures including manholes, septic tanks etc., and shall be disposed
off within the contract area marked on the drawings, as directed, levelled
and neatly dressed.
3.1.5
the sides of trenches from caving in or collapsing. The extent and type of
timbering and shoring shall be as directed by the Owner.
3.1.6
3.1.7
3.1.8
3.1.9
3.1.10
3.1.11
3.1.12
3.1.13
3.1.14
4.0
4.1
SCOPE
This specification specifies the requirement for the chemical treatment of
soils for the protection of buildings and plant buildings from attack by
subterranean termites. This includes usages of anti-termite chemicals,
CODE OF PRACTICES
4.2.1
The following Indian Standard Code of Practices of latest edition only shall
be followed and wherever references of the same has been taken, it shall
be of latest edition only :
IS : 6313
(Part- I)
(Part- II)
(Part-III)
IS : 8944
IS : 4015
(Part- I)
(Part-II)
4.3
TERMINOLOGY
4.3.1
4.3.2
4.3.3
4.3.4
4.4
SITE PREPARATION
4.4.1
The trees, stumps, logs or roots shall be removed from the building or
plant building site area to reduce the hazards from subterranean termites.
Similarly, the sub-floor area shall be kept free from all debris. In order to
ensure uniform distribution of the treating solution and to assist
penetration, the following site preparation may be necessary.
a.
On clays and other heavy soils where penetration is likely to be slow and
on sloping sites where run off of the treating solution is likely to occur, the
surface of the soil shall be scarified to a depth of at least 75 mm.
b.
c.
All sub-floor levelling and grading shall be completed. All cutting, trenches
and excavations shall be completed with back-filling in place. Borrowed
fill must be free from organic debris and shall be well compacted.
d.
All concrete form work, levelling pegs, timber off cuts and other builders
debris shall be removed from the area to be treated.
4.5
CHEMICALS
4.5.1
Chlorpyriphos emulsified concentrate 1% concentration, toxic to subterraineean termites, shall be use to check termite infestation in the soil.
This is useful in the treatment of new building / plant building sites and
shall also be used to eradicate existing infestation in building and plant
buildings and to prevent reinfestation. The above chemical emulsion is
required to be dispersed uniformed in the soil so as to form an effective
chemical barrier.
4.5.2
4.5.3
4.5.4
4.6
4.6.1
4.6.2
Soil treatment shall start when foundation trenches and pits are ready to
take bed concrete / levelling course in foundations. Laying of bed
concrete / levelling course should start when the chemical emulsion has
been absorbed by the soil and the surface is quite dry. In the event of
water logging of foundation pit, the water shall be pumped out and the
chemical emulsion shall be applied when the soil is absorbent. The
treatment shall not be carried out during rains or soil is wet. The treatment
to the surface of earth filling within the plinth shall also be done in the
same manner laying the sub-grade for flooring.
4.6.3
The treated soil barrier shall not be disturbed. If , for the some reasons,
the treated soil barriers are disturbed, immediate step shall be taken to
restore the continuity and completeness of the barrier system.
4.6.4
4.6.4.1
a.
The bottom surface and the sides (upto a height of 300 mm ) of the
excavations made for masonry foundation and basements shall be treated
with the chemical at the rate 5.0 litres per square metre surface area.
b.
After the masonry foundation and the retaining wall of the basements
come up the back fill in the immediate contact with the foundation
structure shall be treated at the rate of 7.5 litres per square metre of the
vertical surface of the sub-structure of each side. If water is used for
ramming the earth fill, the chemical treatment shall be carried out after the
ramming operation is done by rodding the earth at 150 mm centres close
to the wall surface and spraying the chemicals with the above doses.
4.6.4.2
4.6.4.3
4.6.4.4
b.
4.6.4.6
Top surface of the consolidated earth over which the apron is to be laid
shall be treated with chemical emulsion at the rate of 5.0 litres per square
metre of the surface. If consolidated earth does not allow the emulsion to
seep through, holes upto 50 to 75 mm deep at 150 mm centres both ways
shall be made with 12 mm diameter mild steel rod on the surface to
facilitate saturation of the soil with chemical emulsion.
4.6.4.7
4.6.4.8
4.6.5.
Measurements
All dimensions shall be measured correct to a cm. The measurements for
all the operations described above shall be plinth area of the building or
plant building in square-metres at floor 1 level (Ground floor). Nothing
extra shall be measured for payment.
4.7
4.7.1
4.7.2
4.7.2.1
a.
The soil in contact with the external wall of the building/plant building shall
be treated with chemical emulsion at the rate of 7.5 litres per square-meter
of vertical surface of the sub-structure for each side. To facilitate this
treatment, trenches shall be excavated with help of a shovel exposing
the wall surfaces upto a depth of 500 mm and holes 150 mm apart shall
be made with an iron rod close to the wall face and the same shall be
extended from the bottom of the trench to the top of the footing of the
foundation or upto a depth at least 500 mm. Half the total quantity of the
chemical emulsion shall be poured into these holes and the rest shall be
sprayed on the back filled earth as it is return on to the trench, directing
the spray against the wall surface.
b.
c.
4.7.2.2
In case of RCC framed structure, the soil (back-fill earth) in contact with
the column sides and plinth beams along the external perimeter of the
building / plant building shall be treated with chemical emulsion at the rate
of 7.5 litres per square metre of the vertical surfaces of the structures. To
facilitate this treatment, trenches shall be excavated with the help of a
shovel exposing the sides of the column and plinth beams upto a depth of
500 mm or upto the bottom of the plinth beam, if this level is less than 500
mm. The chemical emulsion shall be sprayed on the back-fill earth as it is
returned into the trench, directing the spray against the concrete surfaces
of the beams or columns as the case may be.
Treatment of Soil Under Floors.
Chemical treatment shall be done by drilling 12 mm diameter holes at the
junction of the floor and walls along the cracks on the floors and along the
construction joints at the interval of 300 mm to reach soil below. Chemical
emulsion shall be squirted into these holes using a hand operated
pressure pump to soak the soil below until refusal or upto a maximum of
1.0 litre per hole. The hole shall then be sealed properly with cement
mortar 1 : 2 ( 1 cement : 2 coarse sand) finished to match the existing
floors. The above cement mortar applied shall be cured for atlas 10 days
as per the direction of Engineer-in-Charge.
4.7.2.3
4.7.2.4
4.7.3
Measurements
All dimensions shall be measured correct to a cm. The measurement shall
be made of the surface actually provided with anti-termite treatment.
b.
c.
d.
4.8
4.9
SAFETY PRECAUTIONS
a.
b.
c.
The concentrates are oil solutions and will cause fire hazard owing to the
use of petroleum solvents. Flames shall not be allowed during mixing.
d.
5.0
5.1
FILLING
Back filling of excavations in trenches, foundations and elsewhere shall
consist of one of the following materials approved by Owner.
i.
Soil
ii.
Sand
iii.
Moorum
iv.
Hard-core
v.
Stone / gravel.
All back filling materials shall be approved by the Owner /Consultant.
5.1.1
Soil filling - Soil material shall be free from rubbish, roots, hard lumps
and any other foreign organic material. Filling shall be done in regular
horizontal layers each not exceeding 20 cm. Depth.
5.1.2
5.1.3
Back filling around pipes in the trench shall be done after hydrotesting is
done.
5.1.4
Back filling around liquid retaining structures shall be done only after
leakage testing is completed and approval of Owner is obtained.
5.1.5
Sand filling - Sand shall be coarse, clean, strong, free from dust, organic
and foreign matter and shall be approved by the owner / consultant.
The filling shall be done in layers not exceeding 20 cm in thickness
including consolidating and dressing each deposited layer by flooding with
water, compacting with Mechanical contractor and properly consolidated.
The density to be achieved for each layer shall not be less than 90% of
the density obtained in the laboratory. The compaction should be tested
as per I.S. 2720 (Part 28 & 29). Care shall be taken to see that the
compaction equipment does not hit or come too close to the Bullet so as
to cause any damage to it.
The top and slope surface of consolidated sand filling shall be dressed to
required level, slope, lives and grades and shall be protected from
damage and maintained till the works are completed in all respects.
Sand filling shall not be covered till the Engineer-in-charge inspects the
job, satisfied and approved.
5.1.6
5.1.7
Stone pitching - The size of pitching stone shall not be less than 15 cm
in either direction. It should be sound, durable, free from dust, other
impurities, weathering, salt, alkali and adherent coatings. Stone shall be
laid in proper line, slope and set with cement mortar 1 : 6 (1 cement : 6
coarse sand) including cement mortar pointing 1 : 3 (1 cement : 3 fine
sand) after racking out of joints upto 12 mm depth and shall be cured
properly as per direction of Engineer-in-charge.
6.0
7.0
Pea Gravel - Pea gravel shall be clean, strong, free from dust, organic and
foreign matter and its size shall remain same as it exists on other side of
mound. It shall be approved by the client before laying.
Pea gravel of 150 mm (min) thick, after hand packing, shall be laid all
round and all along UPVC perforated drainage pipe as per drawing and
as per direction of Engineer-in-charge.
The thickness of gravel layer shall remain same as it exists on the other
sides of mound. Care shall be taken so that filled-up sand cannot enter
into the perforated pipe.
The contractor shall guarantee that the pea gravel layer shall remain in
position, level and thickness as specified in the drawing for at least one
year after commissioning. It shall be the responsibility of the contractor to
replace the gravel layer if it is damaged during guarantee period.
8.0
8.1
8.1.1
MATERIALS
Cement : Any of the following cements may be used as required.
IS - 269
IS - 455
IS - 6909
IS - 8041
IS - 8112
8.1.2
8.1.3
IS - 12330
IS - 12269
Water : Water used for mixing and curing concrete and mortar shall
conform to the requirements as laid down in clause 4.3 of IS: 456. Seawater shall not be used for concrete work.
Aggregates : Coarse and fine aggregates for cement concrete plain
and reinforced shall conform to the requirements of IS : 383 and / or IS :
515. Before using, the aggregates shall be tested as per IS : 2386.
Coarse aggregate: Coarse aggregate for all cement concrete work shall
be broken or crushed hard stone, black trap stone obtained from
approved quarries or gravel.
Sand : Fine aggregate for concrete work shall be coarse sand from
approved sources. Grading of coarse sand shall be within grading
zones I, II or III laid down in IS : 383, table-4. If required the aggregates
(both fine and coarse) shall have to be thoroughly washed and graded as
per direction of Owner.
8.2
MIXING
All cement concrete plain or reinforced shall be machine mixed. Mixing
by hand may be employed where quantity of concrete involved is small,
with the specific prior permission of the Owner , 10 % extra cement shall
be added in case of hand mixing as stipulated in IS - 456.
8.3
8.4
LAYING
Concreting shall be commenced only after the Owner has inspected and
passed the sub-base / base or the centering, shuttering and
reinforcement. Concrete in slab, beams, columns, footings etc., shall be
laid gently in layers not exceeding 15 cm and shall be properly
consolidated by means of approved mechanical vibrators.
8.5
CURING
a.
After the concrete has begun to harden, it shall be protected with moist
gunny bags, sand or any other material approved by the Owner
/Consultant against quick drying. After 24 hours of laying concrete, the
surface shall be cured by flooding with water or by covering with wet
absorbent materials for 7 days as per the direction of Owner.
b.
Approved curing compounds may be used in lieu of moist curing with the
permission of the Owner /Consultant. Such compounds shall be applied
to all exposed surfaces of the concrete as soon as possible after the
concrete has set. No extra payment shall be made for the same.
8.6
GRADES OF CONCRETE
8.6.1
1.
2.
3
4.
5.
6.
M - 7.5
M - 10
M - 15
M - 20
M - 25
M - 30
( 75 Kg / cm2 )
( 100 Kg / cm2 )
( 150 Kg / cm2 )
( 200 Kg / cm2 )
( 250 Kg / cm2 )
( 300 Kg / cm2 )
8.6.2
8.6.3
M-7.5 grades of concrete may be used for lean concrete bases and
simple foundation for masonry walls.
8.6.4
A sieve analysis test of aggregates shall be carried out as and when the
source of supply is charge without extra charge notwithstanding the
mandatory test required to be carried out as per CPWD Specification.
8.6.5
8.7
8.7.1
All concrete work (P.C.C. / R.C.C.) shall be with nominal mix concrete
unless specified otherwise. The proportions of materials used for
concrete of grades M-5, M-7.5, M-10, M-15 and M-20 shall be as per the
following table.
Proportions for Nominal Mix of Concrete
Grade
of
Concrete
Total Quantity of
Dry Aggregate by
Mass per 50 Kg of
Cement (as sum of
Fine and Coarse
Proportion of Fine
Aggregate to
Coarse
aggregate
Quantity of water
per
50 Kg of cement
M- 5
Aggregates). In Kg.
Max.
800
M-7.5
625
M - 10
M - 15
M 20
480
350
250
M- 25
( by Mass )
Maximum in Liters.
Generally 1.2
subject to an upper
limit of 1 : 1.5 and
a lower limit of 1: 2
.5
60
45
-do-do-do-
34
32
30
-do-
Notes : 1. The proportions of the fine aggregates should be adjusted from upper
limit to lower limit progressively as the grading of the fine aggregates
become finer and the maximum size of coarse aggregate becomes
larger. Graded coarse aggregate as per IS: 383 may be used.
2.
3.
8.7.2
The cement content of the mix specified for any nominal mix shall be
proportionately increased if the quantity of water in a mix has to be
increased to overcome the difficulties of placement and compaction, so
that water-cement ratio is not exceeded. In case of vibrated concrete, the
limits specified, above may suitably be reduced to avoid segregation.
8.7.3
8.8.
TESTING OF CONCRETE
8.8.1
8.8.2
A slump test shall be taken at each mixer at least once in every fifty
batches mixed. Any batch for which a slump test is being made shall not
be transferred to the place of laying until the slump test has been
completed. Any batch which gives a slump in excess of that described at
the time of preliminary tests shall be rejected and removed from the site.
8.8.3
8.8.4
If a test for particular work does not meet the specified requirements, the
Owner
in his absolute discretion may accept the work at a
correspondingly reduced rate provided the average strength at 28 days is
not less than 85% of the specified strength.
8.8.5
If the results are poorer than 85% of the specified strength, the Owner
may order further testing of any kind as may be deemed necessary in his
opinion, including load tests. The load tests shall be carried on the
portion of the structure involving concrete represented by the
unsatisfactory works test and such other adjoining elements of a building
as the Owner may decide.
If the results of the load tests are not satisfactory, the Contractor shall at
his own cost undertake remedial measures including dismantling and
reconstruction according to the directions and to the satisfaction of the
Owner / Consultant. If the load test is successful, the Owner/ Consultant
may
exercise his judgement before accepting or rejecting the work and shall
still have the power to apply a reduction in rate as herein stated before,
in case the work in question is accepted.
8.9
PROPORTIONING
Mixes of cement concrete shall be as ordered. Where the concrete is
specified by grade, it shall be prepared by mixing cement, sand and
coarse aggregate by weight as per mix design. In case the concrete is
specified as volumetric mix, then dry volume batching shall be done,
making proper allowances for dampness in aggregate and bulking in
sand. Equivalent volume batching for concrete specified by grade may
however be allowed by the Owner at his discretion.
9.0
STEEL REINFORCEMENT
9.1
9.2
i.
ii .
iii .
iv .
v.
TMT bars.
iii. The thickness of weld bead should be 0.2 x diameter of bar and the
length of the longitudinal bead required shall be 10 x diameter of bar,
however, the maximum length of continuous bead shall be limited
to 5 x diameter of bar with intermediate gap. When welding is done
on both sides bead length shall be 5 x diameter of bar on each side.
iv. Stripper at closer spacing shall be provided in the lap welded joints as
directed by Owner
9.3
10.0
FORM WORK
10.1
The shuttering or form work shall conform to the shape, lines and
dimension as shown on the drawings and be so constructed as to remain
sufficiently rigid during placing and compacting of the concrete and shall
be sufficiently tight to prevent loss of liquid from the concrete. The
surface that becomes exposed on the removal of forms shall be
examined by Owner or his authorised representative before any defects
are made good. Work that has sagged or bulged out or contains honey
combing, shall be rejected. All shuttering shall be plywood or steel
shuttering.
10.2
11.0
11.1
STRUCTURAL STEEL
All structural steel used in construction within the purview of this contract
shall comply with one of the following Bureau of Indian Standard
Specifications, whichever is appropriate or as specified.
IS: 2062
11.2
IS: 1079
IS: 1161
Tubular Sections.
IS: 4923
SMITHY WORKS
All smithy work shall be accurately made as shown in the drawings and
shall be clean and sound. The metal shall not be burnt or injured in any
way.
11.3
FABRICATION
Fabrication of steel structure shall be carried out in conformity with the
best modern practices and with due regard to speed with economy in
fabrication and erection and shall conform to IS: 800. All members shall
be so fabricated as to assemble the members accurately on site and
erect them in correct positions. Before despatch to site the components
shall be assembled at shop and any defect found shall be rectified. All
members shall be free from kind, twist, buckle, bend, open joints etc.,
and shall be rectified before erecting in position. Failure in this respect
will subject the defective members to rejection.
11.4
WELDING
11.4.1
11.4.2
The step back method of welding shall be adopted for continuous runs.
Members which offer greater resistance to compression shall be welded
first. The work shall be securely held in position by means of tack weld,
clamps or jig before commencing of welding work so as to prevent
relative movement due to distortion or other cause. All welds with blow
holes, slag-intrusion and other defects must be removed from each run
before another run is super imposed and also from the final run. Any
defects in the work shall be rectified by the Contractor at his own
expense. Bends, twists or distortion caused in any member due to faulty
workmanship and method adopted during welding or in transit will be
rejected and will have to be replaced / rectified by the Contractor at his
own expense. According to the size of electrodes used, the Contractor is
expected to adjust the current rating in the welding generators.
11.5
The Owner /Consultant reserves the right to have test done at any time
for any welding and the cost of the test shall be borne by the Contractor.
11.6
11.7
11.8
Electrodes: Electrodes used for welding shall comply with IS: 814 or
IS: 815 or any specification provided to the Contractor from time to time.
No electrodes remaining in open containers for more than 72 hours shall
be used.
11.9
11.10
b)
11.11
Every portion work shall have its erection mark or number stencilled on
the member for guidance in erection and bear all necessary marks of
erections as directed by the Owner.
11.12
two coats of primer and two coats of paints as per painting specification
attached in this enquiry.
11.13
The Owner or his authorised representative shall have free access at all
reasonable time to all places where the work is being carried out, and
shall be provided by the Contractor at his own expenses all necessary
facilities for inspection during fabrication and erection. The Owner or his
authorised representative shall be at liberty to reject the work in whole or
in part if the workmanship or materials do not conform to the terms of the
specifications mentioned herein. The Contractor shall remove, replace or
alter any part of the work as ordered by the Owner or his authorised
representative.
12.0
12.1
SCOPE
This specification shall be used in non coastal area.
Surface Preparation
The surfaces to be painted shall be sand blasted to Sa - 2.5 as per
Swedish Standard SIS 05 - 59 - 00. Air used for sand blasting must be
dry and oil free. Sand used for sand blasting shall be good quality river
sand suitable for achieving the required surface finish. For optimum
results pressure of sand blasting gun should be maintained at around 7.0
kg/cm2 and maximum height of profile should be kept around 50 microns.
Sand blasted surfaces must be coated with primer within 4 hrs. In dry
climate. Moreover it is not advisable to carry out sand blasting when
humidity exceeds 85% (R.H).
12.1.1
a.
b.
12.1.2
12.1.3
All the surfaces must be sand blasted and 2 coats of prime plus 1 coat of
finish paint applied in the shop before the same are shifted to site for
erection. All the members must be suitably match marked for facilitating
proper assembly.
After erection is over all surfaces shall be washed up as follows :
a.
b.
12.1.4
a.
Primer and paint shall be compatible to each other and should be from
the same manufacturer.
b.
c.
Colour shade for each coat of primer and finish paint must be different
to identify the coats without any ambiguity.
Shade for the final finish coat shall be decided by Owner at site.
All painting materials must be accompanied by manufactures test
certificates. However, if Owner has any doubt regarding quality of
materials, he shall have the right to direct Contractor to get the doubtful
material tested or and provide ( by the Contractor ) testing agencies for
which no extra payment shall be made to the Contractor and the
charges shall deemed to be covered in the unit rates quoted for
fabrication and erection of structural work.
DFT for paint shall be measured on at least 20 points and mean DFT
shall not vary by more than 10% than specified in DFT. Instrument for
measurement of DFT shall be arranged and provided by Contractor at
his cost. Thickness of each coat shall also be checked regularly to
ensure uniformity in DFT.
12.1.5
Measurement
Structural work so painted shall be measured on MT basis. The weight
for this item shall be taken from any of the following documents in the
following order of priority:
i.
ii.
12.1.6
12.1.7
must be
CO
DE
ASIAN
G&N
SHALIMAR
J&N
BERGER
BOMBAY
P1
APCODUR
- EPOXY
ZINC
CHROME
PRIMER
AMERCOAT71
EPIGARD-4
ZINC
CHROMAT
E PRIMER
EPILAC ZINC
CHROMATE
PRIMER
EPILUX-4
ZINC
CHROMATE
PRIMER
PENTA-DUR
PRIMER
1532
ASIOCHLO
R HB
ZINC
PHOSPHAT
E PRIMER
NEROLAC
PHOSPHAT
E PRIMER
CHLOROKOTE ZINC
PHOSPHAT
E PRIMER
JENSOLAC
CR PRIMER
LINSOL HB
ZINC
PHOSPHATE
PRIMER
KANGAROD HB ZINC
PHOSPHAT
E OR
HEMPATEX
PRIMER
1632
APCODUR
CF 692
NEROLAC
TWO COMP
EPOXY
EPIGARD
XL FINISH
EPILAC 974
ENAMEL
EPILUX - 4
ENAMEL
PENTADUR
ENAMEL
5534
P2
FP
1
GRAY
FP
2
ASIOCHLO
R CF
NEROLAC
CR
CHLOROK
OTE
625
PAINT
FINISH
12.2
JENSOLAC
CHLORINATE
D RUBBER
PAINT
LINSOL
CHLORINATE
D RUBBER
PAINT
PENTACHLOR GP
ENAMEL
5638
SCOPE
This specification shall be used for the painting of structural steel in
coastal area in saline atmosphere.
12.2.1
SURFACE PREPARATION
Surface preparation for all items to be painted shall be done by sand
blasting to SA 2.5 as per Swedish Specification SIS 05-59-00. Air used
for sand blasting must be dry and oil free. Sand used for sand blasting
must be of good quality river sand suitable for achieving required surface
finish. For optimum results, pressure at sand blasting gun should be
maintained at around 7 kg/cm2 and maximum height of profile should be
kept around 50 microns. Sand blasted surface must be coated with
primer within 2 hrs. In dry climate. Moreover it is not advisable to carry
out sand blasting when humidity exceeds 50% RH.
12.2.2
a.
i.
ii.
IP1 - One coat of Epoxy MIO having DFT of 70 microns per coat.
iii.
FP1 - One coat of finish epoxy paint using two pack Polyamide cured
epoxy having DFT of 40 microns per coat.
iv.
12.2.3
a.
b.
i.
ii.
iii.
c.
d.
e.
f.
g.
h.
i.
Mode of application for other primers and paints except ethyl silicate
inorganic zinc primer shall be strictly as per recommendation of paint
manufacturer.
J.
k.
Number of coat & DFT per coat must be strictly followed as indicated in
the specification above and if the desired DFT is not achieved in the
specified number of coat, Contractor shall be required to apply extra
coat (s) to achieve desired DFT without any additional cost to Owner /
Consultant. It may be noted here that multi-coat is not allowed for ethyl
silicate inorganic zinc primer and therefore extreme care is to be taken
for assuring desired DFT in single coat. Unless it is not practical to do
so, colour shades for primer, intermediate coat and finish paints must be
different to identify each coat without any ambiguity.
l.
DFT for painting shall be measured on at least 20 points and mean DFT
shall not vary by more than 10% of the specified DFT. Reliable and
calibrated instrument for measurement of DFT shall be arranged and
provided by Contractor at his cost at site.
Sand blasting, painting work being a specialised job, must be carried out
through approved agencies only. List of approved agencies is as
indicated below :
n.
12.2.4
CODE
ITEM
P1
ETHYL
SLILICATE
INORGANIC
ZINC
PRIMER
IP1
EPOXY
70
70
MIO
FP1
TWO PACK
POLYAMIDE
CURED
EPOXY
40
ASIAN
G&N
SHALIMAR
J&N
BERGER
BOMBAY
APCOSIL
DYMET -
TUFFKOTE
ZINC
HEAPELS
601
COTE - 9
ZILICATE
J&N
INORGANIC
ZINC
SILICATE
PRIMER
ANODE
GALVOSIL
APCODUR
AMER
COAT
MIO
385
APCODUR
NEROLAC
CF-692
TWO
COMP
304
1570
EPIGUARD
EPILAC HB
EPILUX-4
HB MIO
MIO
HB MIO
EPIGUARD
EPILAC
EPILUX-4
XL
974
ENAMEL
PENTADUR
HB MIO
4567
PENTADUR
ENAMEL
5534
EPOXY
FP2
ALIPHATIC
ACRYLIC
POLYURETHANE
PAINT
40
APCOTHANE
AMERCOAT
674
450 GL
SHALITHANE
JN 992
BERGA-
PENTO-
PU FINISH
THANE
THANE
PAINT
ENAMEL
4513
13.0
13.1
14.0
14.1
14.1.1
The area to be paved shall be divided into suitable panels. Form work
shall be provided. The boarding / battens shall be fixed in position with
their toe at proper level, giving slope where required. Alternatively base
concrete may be deposited in the whole area at a stretch.
14.1.2
Before placing the base concrete the sub-base shall be properly wetted
and rammed. The concrete of the specified mix shall then be deposited
between the forms where provided, thoroughly tamped and the surface
finished level with the top edge of the forms. The surface of base
concrete shall be spread uniformly. The surface shall be finished rough
to provide adequate bond for the topping. Two or three hours after
concrete has been laid the surface shall be brushed with wire brush to
remove any scum or latinate and swept clean so that coarse aggregate is
exposed.
14.2
14.2.1
14.2.2
The forms shall be fixed over the base concrete dividing into suitable
panels. Where glass dividing strips are provided, thickness of glass
dividing strips shall be 4 mm or as indicated. Before placing the concrete
topping, neat cement slurry at the rate of 2 Kg/Sq.m. shall be then
thoroughly brushed into the base concrete just ahead of the finish. The
topping shall then be laid, thoroughly compacted by using screed
board/plate vibrator. The surface floated with a wooden float to a fair and
even surface shall be left for some time till moisture disappears from it.
Junctions with skirting / dado on wall surfaces shall be rounded off using
cement mortar 1:2. Curing shall be carried out for a minimum of 7 days.
15.0
PLASTERING
15.1
15.2
15.3
Cement mortar shall be of the mix as indicated in the items and shall be
mixed as specified in the CPWD Specifications.
15.4
15.5
15.6
15.7
15.8
15.9
16.0
16.1
White Washing
16.1.1
16.1.2
White wash shall be prepared from lime slaked at site and mixed and
stirred with 5 litres of water for 1 Kg. of unslaked lime to make a thin
cream. The cream shall be screened through a clean,coarse cloth and
suitable adhesive such as DDL or equivalent as per manufacturer
specification shall be added. About 1.3 Kg of sodium chloride in hot
water shall also be added for every 10 Kg. Of lime for making the coat
hard and rule resistant. Indigo shall also be mixed @ 3 gm/Kg of lime.
Each coat shall be allowed to dry before next coat is applied. When dry
the wash should show no sign of cracking, One coat consists of
application with brushes in horizontal stroke followed by vertical stroke.
16.2
Cement Painting
16.2.1
Cement paint: Cement paint shall comply with IS: 5410 specification for
cement paint of colour as required.
16.2.2
16.2.3
3.1
3.2
Scope: Scope of this Manual is to define the procedure for Quality Assurance &
Quality Control for construction activities.
3.3
3.4
General:
3.4.1 The contractor shall be required to produce samples of all materials sufficiently in
advance to obtain approval of the EngineerinCharge. Subsequently the materials to
be used in the actual execution of the work shall strictly conform to the quality of
samples approved. In case of variation, such materials shall be liable to rejection.
3.4.2 All the materials used in the work shall comply with the requirement of Engineerin
Chargeand shall pass all the tests and analysis required by him as per particular
specifications as applicable or such recognized specifications as acceptable to the
EngineerinCharge.
3.4.3
3.4.4
The contractor shall at his cost, make all arrangement and shall provide such
facilities as may be require for collecting, preparing and forwarding the required
number of samples for tests and for analysis at such time and to such places, as
directed by NRL. Nothing
extra shall be paid for the above and including the cost
of material to be tested.
3.4.5 The necessary tests shall be conducted in the laborator ies approved by the NRL. The
testing charges, if any, shall be borne by the contractor.
3.4.6 The contractor or his Lead Quality Officer shall associate in collection, preparation,
forwarding and testing of such samples. In case he or his authorized representative
is not present or does not associate himself, the results of such tests and
consequences
thereon shall be binding on the contractor.
3.4.7 The contractor shall give a performance test of the entire installations as per
standard
specifications before the work is finally accepted and nothing extra
whatsoever shall be payable to the contractor for the test.
3.4.8 Contractor arrange for various construction material tests as per details provided in
AnnexureXI. The tests mentioned in this list are indicative only. Some more tests
may be required to be done from time to time, during the progress of work.
Contractor shall arrange for such tests at field or laboratories at no extra cost.
3.4.9 Contractor has to maintain and regularly update the following machine printed site
registers, formats of which are enclosed in AnnexureXII. These registers shall be
updated and submitted to NRL for further checking.
a) Material Issue & Stock Register (for materials issued by NRL)
b) Site Measurement Register
c) Site Instruction Register
d) Site inspection Register
e) Cube Test Register
f) Equipment Deployment Record
g) Material Test Register
3.4.10 Hindrance Register: This register shall be kept in custody of NRL. Hindrance, if any,
shall be reported in person by the contractor or his representative maximum
within the next
day of hindrance. In case of failure in reporting within the next day of
hindrance, the same shall not be recorded by NRL.
3.5
Inspection & Test Plan
General Note:
The enclosed ITPs shall be followed for the work to be performed by the contractor. The
provisions indicated for stage wise inspection by Engineerincharge are the minimum and
the Engineerincharge may decide to increase Witness points. Activities for which ITPs
are not given, contractor has to develop and get the same approved by Engineerincharge
well before start of the work.
Contractor has to carry our 100% examination of all activities.
Legend:
WC
: 100 % Examination by Contractor.
W
: Witness Point
: An activity which requires witnessing by Engineerincharge / NRL when the
activity is performed after proper notification has been provided.
Rm
: Random / Surveillance Inspection by Engineerincharge.
: Monitoring of making observation to verify whether or not material/ item or
services conform to specified requirement. Surveillance activities may include audit,
inspection, witness of testing, review of quality documents & records, Personnel
qualification etc.
Note : Responsibility of execution of the inspection / testing is with the contractor.
Engineerincharge / NRL only
verifies examination of testing done by the contractor at
important stages.
Abbreviations:
AFC
: Approved For Construction
BM
: Bench Mark
PCC
: Plain Cement Concrete
RCC
WBM
PVC
OMC
FGL
GL
PL
Responsibility
Contractor
NRL
WC
WC
WC
WC
Rm
Rm
W
Rm
Rm
WC
WC
WC
WC
W
W
Rm
W
WC
WC
WC
WC
WC
W
Rm
W
Rm
W
WC
WC
WC
WC
WC
WC
Rm
W
W
Rm
Rm
Rm
WC
WC
WC
WC
W
W
Rm
W
WC
WC
WC
WC
WC
WC
Rm
Rm
Rm
Rm
Rm
Rm
WC
WC
WC
Rm
Rm
Rm
7.4
Top level / Thickness of PCC
7.5
Curing
8.0 REINFORCED CEMENT CONCRETE
8.1
Material Tests
Material Inspection, Layout & Surface preparation
8.2
8.3
Design Mix
8.4
Form work/ Water stoppers/ Cover
8.5
Reinforcement
8.6
Mix proportion, W/C ratio, Slump test
8.7
Inserts, Foundation bolts, templates
8.8
Pour card (format attached)
8.9
Concreting, compaction, test cubes
8.10
Curing
8.11
Testing of cubes
9.0 BRICK WORK
9.1
Layout
9.2
Material tests
9.3
Soaking of bricks
9.4
Thickness of joints/ bond/ closers
9.5
Line, level, plumb
9.6
Raking out joints, Keys in brick work, if any
9.7
Curing
10.0 PLASTERING
10.1
Scaffolding
10.2
Mix proportion
10.3
Hacking, cleaning of surface, removing of loose
particles
10.4
Watering of surface prior to plastering
10.5
Thickness of plaster, plumb, even surface
10.6
Grooves, opening etc.
10.7
Curing
11.0 STRUCTURAL STEEL (During fabrication)
11.1
Material test
11.2
Fabrication drawings
11.3
Welders performance qualification
11.4
Welding machines, tools, tackles
11.5
Filler material, baking of electrodes, sequence of
welding, interpass cleaning
11.6
Surface cleaning, application of primer, paint
11.7
Checking as per drawing
12.0 STRUCTURAL STEEL (During Erection)
12.1
Safety of workmen, scaffolds
12.2
Final coat of paint
13.0 PAINTING WORKS
13.1
Colour brand/ shade
13.2
Material inspection
13.3
Surface cleaning & preparation
13.4
Application
14.0 ROOFING SHEETS
14.1
Material as per specification check
14.2
Type of hooks J/ L or self tapping screws
14.3
Layout & level of truss/ purlin
14.4
Lapping
WC
WC
Rm
Rm
WC
WC
WC
WC
WC
WC
WC
WC
WC
WC
WC
W
Rm
W
Rm
Rm
Rm
W
W
Rm
Rm
W
WC
WC
WC
WC
WC
WC
WC
Rm
W
Rm
Rm
Rm
Rm
Rm
WC
WC
WC
Rm
Rm
Rm
WC
WC
WC
WC
Rm
Rm
Rm
Rm
WC
WC
WC
WC
WC
W
W
Rm
Rm
Rm
WC
WC
W
W
WC
WC
W
Rm
WC
WC
WC
WC
W
W
Rm
Rm
WC
WC
WC
WC
W
Rm
Rm
Rm
14.5
Fixing of hooks, washers/ self tapping screws
14.6
Wind ties
14.7
Barge boards (is any)
15.0 TILES FLOORING/ SKIRTING/ WALL TILES
15.1
Material inspection
15.2
Base surface preparation
WC
WC
WC
Rm
Rm
Rm
WC
WC
W
Rm
15.3
Layout/ pattern
15.4
Level/ slope in floor
15.5
Base plaster mix
15.6
Soaking of tiles in water
15.7
Cutting of tiles as per design & room layout
15.8
Finishing & cleaning
16.0 CEMENT CONCRETE FLOORING/ SKIRTING
16.1
Base surface preparation
16.2
Layout/ pattern
16.3
Glass strips, (if any)
16.4
Level/ slope in floor
16.5
Thickness of floor
16.6
Concrete mix
16.7
Curing
17.0 INER-LOCKING PAVER BLOCKS
17.1
Material inspection
17.2
Layout/ Pattern
17.2
Base preparation
17.4
Sand filling compaction, thickness
17.5
Laying & Fixing
18.0 TERRAZO FLOORING
18.1
Material inspection
18.2
Base surface preparation
18.3
Mix proportions & laying
18.4
Curing
18.5
Polishing
19.0 KOTA STONE/ MARBLE/ GRANITE FLOORING
19.1 Material inspection
19.2 Base surface preparation
19.3 Base plaster mix
19.4 Layout & Fixing
19.5 Polishing
20.0 INTERNAL PLUMBING
20.1 Material inspection
20.2 Layout
20.3 Painting of pipes (if any)
20.4 Installation testing
20.5 Sanitary fixtures & fittings
20.6 Sunken slab treatment
21.0 EXTERNAL PLUMBING
21.1 Material inspection
21.2 Layout
21.3 Painting of pipes (if any)
21.4 Bed concrete of pipes
21.5 Hooking up with manhole/ septic tank
21.6 Road crossings, if any
21.7 Installation testing
WC
WC
WC
WC
WC
WC
Rm
W
Rm
Rm
Rm
Rm
WC
WC
WC
WC
WC
WC
WC
Rm
Rm
Rm
W
Rm
Rm
Rm
WC
WC
WC
WC
WC
W
Rm
Rm
Rm
Rm
WC
WC
WC
WC
WC
W
Rm
Rm
Rm
Rm
WC
WC
WC
WC
WC
W
Rm
Rm
Rm
Rm
WC
WC
WC
WC
WC
WC
W
Rm
Rm
W
W
W
WC
WC
WC
WC
WC
WC
WC
W
Rm
Rm
Rm
Rm
Rm
W
WC
WC
WC
W
W
Rm
WC
WC
WC
WC
WC
W
Rm
Rm
Rm
Rm
WC
WC
WC
W
Rm
Rm
WC
WC
WC
WC
WC
WC
WC
WC
Rm
Rm
Rm
Rm
Rm
Rm
Rm
Rm
WC
WC
WC
W
Rm
Rm
WC
WC
WC
WC
WC
WC
W
W
Rm
W
Rm
Rm
WC
WC
WC
WC
WC
Rm
Rm
Rm
Rm
W
WC
WC
WC
WC
WC
Rm
Rm
Rm
W
Rm
WC
Rm
In
nspection Test
T
Plan (contd.)(
:
SL No.
POUR CA
ARD FOR CON
NCRETE WOR
RKS
ork
Name of wo
Name of the Contractor
Work Ordeer No.
INSPECTIONS
1
APP
PROX. QUANTITY OF CONCRETE TO BE POURED
GRA
ADE OF CONCRET
TE
CEM
MENT QUANTITY REQUIRED
QUA
ALITY AND SOURCE OF WATER
QUA
ALITY OF COARSE
E AGGREGATE
A. CLEANLIN
NESS
B. GRADATIO
ON
C. CRUSHING
G STRENGTH
7
ALITY OF FINE AG
GGREGATE
QUA
A. SILT CONT
TENT
B. GRADATIO
ON
TAILS OF REINFORCEMENTS
DET
A. DIA. OF MA
AIN BARS
B. DIA. OF ST
TIRRUPS
C. C/C DIST. OF
O BARS
D. C/C DIST OF
O STIRRUPS
E. LAPS (Noss)
F. CHAIRS (N
Nos)
G. COVERAGE
E CHECK
FOR
RM WORK
A. SURFACE CONDITION
C
B. CLEAN & WELL
W
OILED
C. ALIGNMEN
NT
D. SUPPORT TO FROMWORK / RIGIDITY
E. WATERTIG
GHTNESS
10
PRO
OPOSED FINISH LEVEL
11
CUB
BE SAMPLES TO BE
B TAKEN
12
MAC
CHINERIED DEPL
LOYED
NO.S
13
TIME OF POURING
:
14
SLUMP
15
16
TOT
TAL NUMBER OF WORKERS
W
SKIL
LLED
:
UNSK
KILLED
WO
ORKING CONDITION
OBSERVATIONS FO
OUND
DURING CASTIN
NG
S
SIGN.
OF NRL
SL.
NO.
1
2
3
4
5
6
7
8
9
10
DESCRIPTION
1
Mass of core cutter (gm)
Mass of core cutter + wet soil (gm)
Volume of core cutter (cc)
Bulk density (gm/cc)
Mass of wet soil (gm)
Mass of oven dried soil (gm)
Moisture content (%)
Dry density = BD/ (1+MC/100), (gm/cc)
Lab control density (gm/cc)
% of compaction
NRL
ANNEXURE X
List of Laboratory Equipments
A. For Building & Road works:
1. Sieves as per IS 4601962
(i) IS Sieves 450mm internal dia., of sizes 100mm, 80mm, 63mm, 50mm, 40mm,
25mm, 20mm, 12.5mm, 10mm, 6.3mm, 4.75mm, complete with lid and pan.
(ii) IS Sieves 200mm internal dia. (brass frame), consisting of 2.36mm, 1.18mm,
600 microns, 425 microns, 300 microns, 212 microns, 150 microns, 90 microns, 75
microns,
with lid and pan.
2. Sieve shaker capable of 200mm and 300mm dia. Sieves, manually operated with
timing switch assembly.
3. Ovens electrically operated, thermostatically controlled upto 110 C sensitivity
1C.
4. Equipment for slump test Slump cone, steel plate, tamping rod, steel scale, scoop.
5. Cube moulds 150cm X 150cm X 150 cm 50 no.s
6. 100 tonnes compression testing machine, electricallycum manually operated.
7. Graduated measuring cylinders 200ml. capacity
8. Balances
(i) 7 kg. to 10 kg. capacity, semiself indicating type accuracy 10 gm.
(ii) 500 gm. Capacity, semiself indicating type accuracy 1hm.
(iii) Pan balance 5 kg. capacity accuracy 10 gms.
(iv) Chemical balance, 100 gm capacity accuracy 0.1 gm
9. Aggregate Crushing strength apparatus
10. Aggregate Impact value appartaus
11. Los Angeles Test apparatus
12. Rapid Moisture meter
13. Core cutter apparatus
14. Temperature gun, Temperature Range 0 to 750F
15. Theodolite
16. Dumpy Level with staffs
17. Electrical moisture meter for timber
18. Digital Elcometer (0125 microns for steel & 0100 microns for non ferrous base
with
accuracy of 1 micron)
B. Miscellaneous:
1. Vernier Callipers
2. Steel measuring tapes
3. Rebound hammer for testing concrete
Material
(2)
Water
Coarse
Aggregates
Sl. No.
(1)
Bulk Density
Specific Gravity
Surface moisture
Particle size
Percentage of
soft or deleterious material
(i) pH Value
Tests (3)
IS: 2386
Appendix B
IS 3025
Test procedure
(4)
F or L
Field
(F)/
Laborat
10 cum
50 cum
As per
requireme
nt
Minm.
Qty. for
testing
50 cum or part
thereof and on each
change of source.
Frequency (7)
ANNEXURE XI
Material Tests
Material
(2)
Sand
Concrete
Timber
Sl. No.
(1)
4.
5.
Appendix D
Bulking of Sand
Appendix G
Appendix H
Appendix M
Slump test
Cube test
Moisture Content
Appendix B
Appendix C
Silt Content
Particle size
distribution
Appendix A
Test
procedure
(4)
Organic Impurities
Tests (3)
F/L
F/ L
F or L
Field (F)/
Laboratory (L)
(5)
1 cum
20 cum
20 cum
40 cum
Frequency (7)
Appendix I
Test
procedure
(4)
WBM
9.
Gradation,
Abrasion & Impact
value, Flakiness &
Elongation
Gradation, Density
of Compacted layer
Granular
Sub base
8.
F/L
F/L
IS 2386,
MORST &H
Field (F)/
Laboratory
(L) (5)
IS 2720,
MORST& H
IS: 2202/
Appendix N
Appendix L
Efflorescence
End Immersion
Test
Knife test
Adhesion test
Appendix K
Water Absorption
Dimensional test
Flush Door
Bricks
6.
Tests (3)
7.
Material
(2)
Sl. No.
(1)
NA
NA
Frequency (7)
Annexure XII
Register Formats
a) Material Issue & Stock Register (for materials issued by NRL)
Page No:
Brief Item
Item
Description
Executed on
Signature
Rate of
Consumed
Material
Consumption
Qty.
Requisition
Details
No.
Date
Qty.
Contractor
Page No:
work:
Contractor:
W.O No.:
Date of Measurement:
Sl.
Item
Item description(in
No.
No.
Unit
D/ H
No.
Qty.
Remarks
NRL
Page No:
Contractor:
W.O No.:
Date
Signature &
Accepted by
Complied by
Cross checked by
Name (NRL)
(contractor)
contractor on
Page No:
Contractor:
W.O No.:
Sl.
Item / Activity
No.
offered for
Location
Offered by
Inspected &
Next
(contractor)
accepted by
activity
Inspection
Remarks
(NRL)
(Page No.)
Name of work:
Contractor:
W.O No.:
Sl.No.
Date
Equipment
Deployment
Reference gate
Signature
Details
Date
pass
Contractor
Purpose
NRL
SL.
NO.
GRD. OF
CONCRE
TE
LO
CA
TI
ON
OF
CO
NC
RE
TE
DA
TE
OF
PO
URI
NG
CUBE
MAR
K
STR
ENG
TH
AV
G.
ST
RE
NG
TH
CONT
RACT
OR
SIGN.
DAT
E
(TES
TED
)
TO
TA
L
LO
AD
ST
RE
NG
TH
AV
G.
ST
RE
NG
TH
CO
NTR
ACT
OR
SIG
N
NR
L
SIG
N
TOTA
L
LOA
D
NRL
SIG
N
DAT
E
(TES
TED
)
Name of work:
Contractor:
W.O No.:
Sl.
No.
Material
description
Frequency
of test as
per
BIS/
contract
Lot size/
Qty.
(from
which
sample is
taken)
Sample
taken
on
Date of
testing
Refer
ence
Doc.
Status of
test
results
Contractor
Signature
NR
L
Remarks
Page No:
Name of work:
Contractor:
W.O No.:
APPENDIX A
TEST FOR ORGANIC IMPURITIES
The aggregate must also be checked for organic impurities such as decayed vegetation
humus, coal dust etc.
What is called the colour test is reliable indicator of the presence of harmful
organic matter in aggregate, except in the area where there are deposits of lignite.
Fill a 350 ml clear glass medicine bottle upto 70 ml mark with a 3% solution of
caustic soda or sodium hydroxide. The sand is next added gradually until the volume
measured by the sandy layer is 125 ml. The volume is then made upto 200 ml by
addition of more of solution. The bottle is then stoppered and shaken vigorously and
allowed to stand for 24 hours. At the end of this period, the colour of the liquid will
indicate whether the sand contains a dangerous amount of matter. A colourless liquid
indicates a clean sand free from organic matter. A straw coloured solution indicates some
organic matter but not enough to be seriously objectionable. Darker colour means
that the sand contains injurious amounts and should not be used unless it is washed,
and a retest shows that it is satisfactory.
Add 2.5 ml of two per cent solution of tannic acid in 10 per cent alcohol, to 97.5 ml of
three per cent sodium hydroxide solution. Place in a 350 ml bottle, fix the stopper, shake
vigorously and allow to stand for 24 hours before comparison with the solution above
the sand.
Note: A three per cent solution of caustic soda is made by dissolving 3 g of sodium
hydroxide in 100 ml of water, preferably distilled. The solution should be kept in a glass
of bottle tightly closed with a rubber stopper. Handling sodium hydroxide with moist
hands may result in serious burns. Care should be taken not to spill the solution for it is
highly injurious to clothing, leather, and other materials.
APPENDIX B
TEST FOR PARTICLE SIZE (SIEVE ANALYSIS)
Apparatus: Perforated plate sieves as per IS designation should be used.
The balance or scale shall be such that it is readable and accurate to 0.1 per cent of
the weight of the test sample.
Sample: The weight of sample available shall not be less than the weight given in the
table below. The sample of sieving shall be prepared from the larger sample either by
quartering or by means of a sample divider.
TABLE SHOWING MINIMUM WEIGHTS FOR SAMPLING
Maximum size present in
substantial
proportions
(mm)
10
4.75
2.36
Test Procedure: The sample shall be brought to an airdry condition before weighing
and sieving. This may be achieved either by drying at room temperature or by heating
at a temperature of 100 degree to 110 degree centigrade. The air dry sample shall be
weighed and sieved successively on the appropriate sieves starting with the largest. Care
shall be taken to ensure that the sieves are clean before use.
Each sieve shall be shaken separately over a clean tray until not more than a trace
passes, but in any case for a period of not less than two minutes. The shaking shall be
done with a varied motion, backwards and forwards, left to right, circular clockwise and
anticlockwise, and with frequent jarring, so that the material is kept moving over the
sieve surface in frequently changing directions. Materials shall not be forced through the
sieve by hand pressure, but on sieves coarser than 20 mm, placing of particles is
permitted, Lumps of fine material, if present may be broken by gentle pressure with
fingers against the side of the sieve. Light brushing of underside of the sieve with a soft
brush may be used to clear the sieve openings.
Light brushing with a fine camel hair brush may be used on the 150 micron IS sieve
to prevent segregation of powder and blinding of apertures. Stiff or worn out brushes
shall not be used for this purpose and pressure shall not be applied to the surface of
the sieve to force particles through the mesh.
On completion of sieving the material retained on each sieve, together with any
material cleaned from the mesh, shall be weighed.
Reporting of Results: The results shall be calculated and reported as:
(a) The cumulative percentage by weight of the total sample passing each of the
sieves, to the nearest whole number:
Or
(b) The percentage by weight of the total sample passing one sieve and retained on the
next smaller sieve, to the nearest 0.1 percent.
In order that the sieves shall not be overloaded, care must be taken to ensure
that the maximum sieve loads shown in Table (below) are not exceeded at the
completion of sieving.
4.5
3.5
2.5
2.0
1.5
1.0
0.75
0.50
0.30
APPENDIX C
TEST FOR SILT CONTENT
The sand shall not contain more than 8% of silt as determined by field test with
measuring cylinder. The method of determining silt contents by field test is given below:
A sample of sand to be tested shall be placed without drying in a 200 ml
measuring cylinder. The volume of the sample shall be such that it fills the cylinder upto
100 ml mark.
Clean water shall be added upto 150 ml mark. Dissolve a little salt in the water in
the proportion one tea spoon to half a litre. The mixture shall be shaken vigorously,
the last few shakes being sidewise direction to level off the sand and the contents
allowed to settle for three hours.
The height of the silt visible as settled layer above the sand shall be expressed as a
percentage of the height of sand below. The sand containing more than the above
allowable percentage of silt, shall be washed so as to bring the silt contents within
allowable limits.
APPENDIX D
BULKING OF FINE AGGREGATES/SAND (FIELD METHODS)
Two methods are suggested for determining the bulking of sand/fine aggregate. The
procedure may be suitably varied, if necessary. Both depend on the fact that the
volume of inundated sand/fine aggregate is the same if the sand/fine aggregate were
dry.
Method -1: Put sufficient quantity of sand loosely into a container until it is about two
third full. Level off the top of the sand and push a steel rule vertically down through
the sand at the middle to bottom, measure the height. Suppose this is X cm.
Empty the sand out of the container into another container where none of it is lost.
Half fill the first container with water. Put back about half the sand and rod it with a steel
rod, about 6 mm in diameter, so that its volume is reduced to a minimum. Then add
the remainder and level the top surface of the inundated sand. Measure its depth at
the middle with the steel rule. Suppose this is Y cm.
The percentage of bulking of the sand due to moisture shall be calculated from the
formula: Percentage bulking = (X/Y 1) X 100
Method-2: In a 250 ml measuring cylinder, pour the damp sand, consolidate it by
staking until it reached the 200 ml mark.
Then fill the cylinder with the water and stir the sand well (the water shall be
sufficient to submerge the sand completely). It will be seen that the sand surface is
now below its original level. Suppose the surface is at the mark of Yml, the percentage of
bulking of sand due to moisture shall be calculated from the formula.
Percentage bulking= (200/Y 1) x 100
APPENDIX E
TEST FOR SURFACE MOISTURE
Take a sample of wet aggregate and weigh it (A). Then place it in a frying pan and gently
apply heat, meanwhile stirring with a glass rod until the surface moisture disappears.
This is apparent when the aggregate loses its shining wet appearance and becomes
dull, or when it just attains a free funning condition. The saturated surface dry
material is then weighed (B). Continue the heating thereafter until the moisture is
evaporated and weigh the dry sample (C). The surface moisture is then calculated as
follows:
Surface moisture
= 100 x A B
C
It is expressed as a percentage of dry aggregate.
APPENDIX F
DETERMINATION OF TEN PER CENT FINE VALUE
Apparatus: The apparatus for the standard test shall consist of the following:
(a) A 15 cm diameter openended steel cylinder, with plunger and baseplate, as
shown in Fig. in the end of this appendix. The surfaces in contact with the
aggregate shall be machined and case hardened or otherwise treated so as to
have a diamond (VH) pyramid hardness number of not less than 650 VH.
(b) A straight metal tamping rod of circular crosssection 16 mm in diameter and 45
to 60 cm long, rounded at one end.
(c) A balance of capacity 3 Kg, readable and accurate to one gram. (d) I.S. Sieve of
sizes 12.5, 10 and 2.36 mm.
(d) A compression testing machine capable of applying a load of 50 tonnes and
which can be operated to give a uniform rate of loading so that the maximum load
in any test is reached in 10 minutes. This load may vary from 0.5 to 50 tonnes.
(e) For measuring the sample, a cylindrical metal measure of sufficient rigidity to
retain its form under rough usage and of the following internal dimensions:
Diameter
11.5 cm
Height
18.0 cm
(f) Means of measuring the reduction in the distance between the plates of the
testing machine to the nearest one millimeter during the test (for example, dial
gauge).
Test Sample: Material for the test shall consist of aggregate passing a 12.5 mm I.S. Sieve
and retained on a 10 mm I.S. Sieve. The aggregate shall be tested in a surface dry
condition. If dries by heating the period of drying shall not exceed four hours, the
temperature shall be 100C to 110C and the aggregate shall be cooled to room
temperature before testing.
The quantity of aggregate shall be such that the depth of material in the cylinder,
after tamping as described below, shall be 10 cm.
The weight of material comprising the test sample shall be determined (weight
A) and the same weight of sample shall be taken for the repeat test.
Note: About 6.5 kg of natural aggregate is required to provide the two test samples.
Less of light weight aggregate is required.
The measuring cylinder is filled in three layers of approximately equal depth with
aggregate passing a 12.5 mm I.S. Sieve and retained on 10 mm I.S. Sieve. Each layer is
subjected to 25 strokes from the tamping rod (16 mm dia and 45 to 60 cm long) rounded
to one end, care being taken in case of weak materials not to break the particles. The
surface of the aggregate shall be carefully leveled and the plunger inserted so that it
rests horizontally on this surface.
Test Procedure: The apparatus, with the test sample and plunger in position, shall then
be placed in the compression testing machine. The load shall be applied at a uniform
rate so as to cause a total penetration of a plunger in 10 minutes of about: 15.0 mm
for rounded or partially rounded aggregates (for example uncrushed gravel) 20 mm
for nominal crushed aggregate & 24 mm for honey combed aggregate (for example
expanded shales and slags). These figures may be varied according to the extent of
the rounding or honey combing.
After reaching the required maximum penetration, the load shall be released
and the whole of the material removed from the cylinder and sieved on a 2.36 mm I.S.
Sieve. The fines passing the sieve shall be weighed, and this weight expressed as a
percentage of the weight of the test sample. Normally, this percentage will fall within
the range 7.5 to 12.5, but if it does not, a further test shall be made at a load adjusted
appropriately, to bring the percentage fines within the range of 7.5 to 12.5.
A repeat test shall be made at the load that gives as percentage fines within the range 7.5
to 12.5.
Calculations: The mean percentage fines from the two tests at this load shall be used in
the following formula to calculate the load required to give 10 percentage fines. Load
required for 10 percent fines =
Where X = Load in tonnes and 14 X Y + 4
Y= mean percentage fines from two test at X tonnes load.
Reporting of Results: The load required to produce 10 percent fines shall be
reported to the nearest whole number for loads of 10 tonnes or more, the nearest 0.5
tonne for loads of less than 10 tonnes.
The value expressed to the nearest 0.5 tonne should be as follows:
(a) For normal concrete, not less than 5 tonnes.
(b) For wearing surfaces, not less than 10 tonnes.
(c) For granolithic concrete, not less than 15 tonnes.
100 to 150
20
25
6.3
130 to 140
152.0.5
K 16All
200 to
dim ensions
in230
m illim etres K 16
APPENDIX G
SLUMP TEST
Apparatus: Mould shall consist of a metal frustum of cone having the following internal
dimensions:
Bottom diameter..20 cm
Top diameter10 cm
Height30 cm
The mould shall be of a metal other than brass and aluminium of at least 1.6 mm (or
16 BG) thickness. The top and bottom shall be open and at right angles to the axis of the
cone. The mould shall have a smooth internal surface. It shall be provided with suitable
foot pieces and handles to facilitate lifting it from the moulded concrete test specimen in a
vertical direction as required by the test. A mould provided with a suitable guide attachment
may be used.
Tamping rod shall be of steel or other suitable material 16 mm in diameter 60 mm long and
rounded at one end.
Procedure: The internal surface of the mould shall be thoroughly cleaned and free form
superfluous moisture and any set concrete before commencing the test. The mould shall be
placed on a smooth horizontal, rigid and non-absorbent surface viz. leveled metal plate. The
operator shall hold the mould firmly in place while it is being filled with test specimen of
concrete. The mould shall be filled in four layers, each approximately one quarter of height
of mould. Each layer shall be tamped with twenty five strikes of the rounded end of the
tamping rod. The strokes shall be distributed in a uniform manner over the cross section of
the mould and for the second and subsequent layers shall penetrate into the under- lying layer.
The bottom layer shall be tamped through out its depth. After the top layer has been rodded,
the concrete shall
be struck off level with trowel or the tamping rod, so that the mould is exactly filled. Any
mortar which shall leak out between the mould and the base plate shall be cleaned away.
The mould shall be removed from the concrete immediately after filling by raising it slowly
and carefully in a vertical direction. The moulded concrete shall then be allowed to
subside and the slump shall be measured immediately by determining the difference
between the height of the mould and that of the highest point of specimen.
The above operations shall be carried out at a place free from vibration or shock, and
within a period of two minutes after sampling.
Result: The slump shall be recorded in terms of millimeters of subsidence of the specimen
during the test. Any slump specimen which collapses or shears off laterally give incorrect
result. If this occurs, the test shall be repeated with another sample.
The slump test shall not be used for very dry mixes as the results obtained are
APPENDIX H
CUBE TEST FOR COMPRESSIVE STRENGTH OF CONCRETE - MANDATORY
LAB TEST
H-0 One sample (consisting of six cubes 15x15x15 cm shall be taken for every 20 cum or part
thereof concrete work ignoring any part less than 5cum or as often as considered necessary
by the Engineer- in-Charge. The test of concrete cubes shall be carried out in
accordance with the procedure as described below. A register of cubes shall be maintained
at the site of work in Appendix C. The casting of cubes, concrete used for cubes and all other
incidental charge, such are curing, carriage to the testing laboratory shall be borne by the
contractors. The testing fee for the cubes, if any, shall be borne by the department.
H-1 Test Procedure
H-1.1 Mould
The mould shall be of size 15 cmx15 cmx15 cm for the maximum nominal size of
aggregate not exceeding 40 mm. For concrete with aggregate size more than 40 mm size of
mould shall be specified by the Engineer-in-charge, keeping in view the fact that the length of
size of mould should be about four times the size of aggregate.
The moulds for test specimens shall be made of non-absorbent material and shall be
substantially strong enough to hold their form during the moulding of test specimens. They
shall not vary from the standard dimensions by more than one percent. The moulds shall be
so constructed that there is no leakage of water from the test specimen during moulding. All
the cube moulds for particular site should, prior to use, be checked for accuracy in dimensions
and geometric form and such test should at least be made once a year.
Each mould shall be provided with a base plate having a plane surface and made of nonabsorbent material. This plate shall be large enough in diameter to support the moulds
properly without leakage. Glass plates not less than 6.5mm thick or plain metal not less than
12mm thick shall be used for this purpose. A similar plate shall be provided for covering the
top surface of the test specimen when moulded.
Note: Satisfactory moulds can be made from machine or steel castings, rolled metal
plates or galvanized.
H-1.2 Sample of Concrete
Sample of concrete for test specimen shall be taken at the mixer or in the case of ready
mixed concrete from the transportation vehicle discharge or as directed by Engineer-inCharge. Such samples shall be obtained by repeatedly passing a scoop or pail through the
discharge stream of concrete. The sampling operation should be spread over evenly to the
entire discharging operation. The samples thus obtained shall be transported to the place of
moulding of the specimen to counteract segregation. The concrete shall be mixed with a
shovel until it is uniform in appearance. The location in the work of the batch of concrete
this sampled shall be noted for further reference. In case of paving concrete, samples shall be
taken from the batch immediately after deposition of the sub grade. At least five samples
shall be taken from different portion of the pile and these samples shall be thoroughly
mixed before being used to form the test specimen.
The sampling shall be spread as evenly as possible throughout the day. When wide changes
occur during concreting, additional sample shall be taken if so desired by the Engineer-inCharge.
H-1.3 Preparation of Test Specimens
The interior surfaces of the mould and base plate shall be lightly oiled before the concrete is
placed in the mould. The samples of concrete obtained as described under the test
specimen shall be immediately moulded by one of the following methods as indicated below:When the job concrete is compacted by manual methods, the test specimen shall be
moulded by placing the fresh concrete in the mould in three layers, each approximately one
third of the volume of the mould. In placing each scoopful of concrete the scoop shall be
moved around the top edge do the mould as the concrete there sided from it, in order to ensure
a uniform distribution of concrete within the mould. Each layer shall be rodded 35 times with
16 mm rod, 60 cm in length, bullet pointed at the lower end. The strokes shall be
distributed in uniform manner over the cross section of the mould and shall penetrate
into underlying layer. The bottom layer shall be rodded through its depth. After the top
layer has been rodded, the surface of the concrete shall be struck off with a trowel and
covered with a glass plate at least 6.5 mm thick or a machined plate. The whole process of
moulding shall be carried out in such a manner as to preclude the change of the water
cement ratio of the concrete, by loss of water either by leakage from the bottom or over flow
from the top of the mould.
When the job concrete is placed by vibration and the consistency of the concrete is such
that the test specimens cannot be properly moulded by hand rolling as described above, the
specimens shall be vibrated to give a compaction corresponding to that of the job concrete.
The fresh concrete shall be placed in mould in two layers, each approximately half the
volume of the mould. In placing each scoopful of concrete the scoop shall be moved around
the top edge of the mould as the concrete there slides from it, in order to ensure a
symmetrical distribution of concrete within the mould. Either internal or external vibrators
may be used. The vibration of each layer shall not be continued longer than is necessary
to secure the required density. Internal vibrators shall only be used when the concrete is
required to be compacted in layers. In compacting the first layer, the vibrators shall not be
allowed to rest on the bottom of the mould. In placing the concrete for top extent that there
will be no mortar loss during vibrations. After vibrating the second layer enough concrete
shall be added to bring level above the top of the mould. The surface of the concrete shall
then the struck off with a trowel and covered with a glass or steel plate as specified above.
The whole process of moulding shall be carried out in such a manner as to preclude the
alteration of water-cement ratio of the concrete by loss of water, either by leakage for the
bottom or over flow from the top of the mould.
H-1.4 Curing and Storage of Test Specimen
In order to ensure reasonably uniform temperature and moisture conditions during the
first 24 hours for curing the specimen and to protect them from damage, moulds shall be
covered with wet straw or gunny sacking and placed a storage box so constructed and
kept on the work site that its air temperature when containing concrete specimens shall
remain 22C to 33C. Other suitable means which provide such a temperature and moisture
conditions may be used.
Note:- It is suggested that the storage box be made of 25 mm dressed tongued and grooved
timber, well braced with battens to avoid warping. The box should be well painted inside
and outside and should be provided with a hinged cover and padlock.
The test specimen shall be removed from the moulds at the end of 24 hours and stored
in a moist condition at a temperature within 24C to 30C until the time of test. If storage
in water is desired, a saturated lime solution shall be used.
H-1.5 Testing
The specimens shall be tested in accordance with procedure as described below:
(a) The tests shall be made at an age of concrete corresponding to that for which the strengths
are specified.
(b) Compression tests shall be made immediately upon removal of the concrete test
specimen from the curing room i.e. the test specimen shall be loaded in damp
condition. The dimensions of the test specimens shall be measured in mm accurate to 0.5
mm.
(c) The metal bearing plates of the testing machine shall be placed in contact with the
ends of the test specimens. Cushioning materials shall not be used. In the case of cubes,
the test specimen shall be placed in the machine in such a manner that the load is
applied to sides of the specimens as cast. An adjustable bearing block shall be used
to transmit the load to the test specimen. The size of the bearing block shall be the
same or slightly larger than that of test specimen. The upper or lower section of the
bearing block shall be kept in motion as the head of the testing machine is brought to a
bearing on the test specimen.
(d) The load shall be applied axially without shock at the rate of approximately 140
per sq.cm. per minute. The total load indicated by the testing machine at failure of
specimen shall be recorded and the unit compressive strength is calculated in kg
sq. cm. using the area computed from the measured dimension of the
specimen. The type of failure and Appearance of the concrete shall be noted.
kg.
test
per
test
APPEND
DIX I
T
TEST
FOR DIMENSION
D
AL TOLERA
ANCE
Procedure
P
A the blisters, loose particles of claay and smalll projection
All
ns shall be reemoved from
m the
su
urface of brricks. Each specimen of 20 briicks shall then
t
be arrranged up
pon a
leevel surfacee successiv
vely as indiccated in Figg. A, B and C below in contact
c
with
h each
other and in straight line. The overaall length off the assemb
bled bricks (20 Nos) sh
hall be
m
measured
wiith a steel taape sufficien
ntly long to measure the whole row
w at one streetch.
T
Tolerance
T actual dimensions
The
d
of bricks when
w
tested
d as descriibed in A2 shall be within
w
th
he followingg limits perr 20 bricks.
Modular Briicks
M
Length 3720 to 3880 mm
m (3800 80
8 mm)
W
Width
1760 to 1840 mm
m (1800 40
4 mm)
H
Height
1760 to 1840 mm
m (1800 40
4 mm) forr 90 mm higgh brick
760 to 840 mm (800
(
40 mm)
m for 40 mm high brrick
N
Non-Modula
ar Bricks
For class 10
Length (4520
0 to 4680) mm
m (4600 80 mm)
W
Width
(2240 to 2160) mm (2200 40 mm)
H
Height
(1440
0 to 1360) mm
m (1400 40 mm) fo
or 70 mm high
h
bricks
(640 to 560) mm
m (600 40
0 mm) for 30 mm high bricks
For other cla
asses
Length (4320
0 to 4680) mm
m
W
Width
(2130
0 to 2310) mm
m
H
Height
(1340
0 to 1460) mm
m for 70 mm
m high brricks
(840 to 920) mm
m for 44 mm
m high brick
ks
C
Criteria
for Conformitty
A lot shall be consideered conforrming to the
t
requireements of dimensionss and
to
olerances iff all the gro
oups of bricks are testeed to meet the
t specified requirem
ments.
A' Measuremeent of Length
'A
APPENDIX J
TEST FOR COMPRESSIVE STRENGTH
Specimen
Five whole bricks shall be taken from the samples as specimens for this test. Length
and width of each specimen shall be measured correct to 1 mm.
Apparatus
The apparatus consists of compression testing machine, the compression plate of which
shall have a ball seating in the form of portion of a sphere the centre of which shall
coincide with the centre of the plate.
Procedure
(a) Pre-conditioning: The specimen shall be immersed in the water for 24 hours at 25
to 29C. Any surplus moisture shall be allowed to drain at room temperature. The
frog of the bricks should be filled flush with mortar 1:3 (1 cement : 3 clean
coarse sand of grade 3 mm and down) and shall be kept under damp jute bags
for 24 hours, after that these shall be immersed in clean water for three days.
After removal from water, the bricks shall be wiped out of any traces of moisture.
(b) Actual Testing: Specimen shall be placed with flat faces horizontal and mortar filled
face upward between three 3 ply plywood sheets each of thickness 3 mm and
carefully centred between plates of the testing machine. Plaster of Paris can also
be used in place of plywood sheets to ensure a uniform surface.
Load shall be applied carefully axially at uniform rate of 14 N/mm2 per minute till
the failure of the specimen occurs.
Reporting the Test Results
The compressive strength of each specimen shall be calculated in N/mm2 as under :
Compressive Strength =
In case the compressive strength of any individual brick tested exceeds the upper
limit of the average compressive strength specified for the corresponding class of brick,
the same shall be limited to the upper limit of the class specified in 6.1.2 for the
purpose of calculating the average compressive strength. Compressive strength of all the
individual bricks comprising the sample shall be averaged and reported.
Criteria for Conformity
A lot shall be considered having satisfied the requirements of average compressive
strength if the average compressive strength specified in 6.1.2 for the corresponding class
of brick tested is not below the minimum average compressive strength specified for the
corresponding class of bricks by more than 20 per cent.
APPENDIX K
TEST FOR WATER ABSORPTION
No. of Specimen
Five whole bricks shall be taken from samples as specimen for this test.
Apparatus
A balance required for this test shall be sensitive to weigh 0.1 percent of the weight of the
specimen.
Procedure
(a) Pre-conditioning: The specimen shall be allowed to dry in a ventilated oven at a
110C to 115C till it attains a substantially constant weight. If the specimen is
known to be relatively dry, this would be accomplished in 48 hours, if the
specimen is wet, several additional hours may be required to attain a constant
weight. It shall be allowed to cool at room temperature. In a ventilated room,
properly separated bricks will require four hours for cooling, unless electric fan
passes air over them continuously in which case two hours may suffice.
The cooled specimen shall be weigh (W1) a warm specimen shall not be used for
this purpose.
(b) Actual Testing: Specimen shall be completely dried before immersion in the
water. It shall be kept in clean water at a temperature of 27C 2C for 24 hours.
Specimen shall be wiped out of the traces of water with a damp cloth after
removing from the water and then shall be weighed within three minutes after
removing from water (W2).
Reporting the Test Results
The water absorption of each specimen shall be calculated as follows and the average of
five tests shall be reported.
Water Absorption W2 W1 x 100
W1
Criteria for Conformity
A lot shall be considered having satisfied the requirements of water absorption if the
average water absorption is not more than 20% by weight.
APPENDIX L
TEST FOR EFFLORESCENCE
No. of Specimen
Five whole bricks shall be taken as specimen for this test.
Apparatus
Apparatus required for this test shall be a shallow flat bottom dish containing distilled
water.
Procedure (actual testing)
The brick shall be placed vertically in the dish with 2.5 cm immersed in the water. The
room shall be warm (18C to 30C) and well ventilated. The bricks should not be removed
until it absorbs whole water. When the whole water is absorbed and the brick appears to
be dry, place a similar quantity of water in that dish and allow it to evaporate as before.
The brick shall be examined after the second evaporation.
Reporting the Test Results
The rating to efflorescence in ascending order shall be reported as NIL, SLIGHT,
MODERATE, HEAVY or SERIOUS in accordance with the following :
(a) NIL: When there is no perceptible deposit of efflorescence.
(b) SLIGHT: When not more than 10 per cent of the area of the brick is covered with a
thin deposit of salts.
(c) MODERATE: When there is heavier deposit and covering upto 50% of the area
of the brick surface but unaccompanied by powdering or flaking of the surface.
(d) HEAVY: When there is a heavy deposit of salts covering 50% or more of the
brick surface but unaccompanied by powdering or flaking of the surface.
(e) SERIOUS: When there is heavy deposit of salts, accompanied powdering and/or
flaking of the surface and tending to increase in the repeated wetting of the
specimen.
Criteria for Conformity
A lot be considered having satisfied the requirements of efflorescence if for 4 out of the
specimen of 5 bricks, the rating of efflorescence is not beyond Moderate.