You are on page 1of 3

PROJECT NO.

:
WBS NO. : 401
DOCUMENT NO.
XXXX-XX-REQ-XX-XXXX-A4

OWNER
CONTRACTOR
PROJECT NAME
LOCATION

REV. : 1
PAGES:
1 of 12

REQUISITION FOR
STEEL PIPE

: VITOL iNDONESIA
: PT. xxxxxxxxx (PERSERO) TBK
: PROJECT LPG REFRIGRATED TUBAN
: EAST JAVA , JAVA ISLANDS, INDONESIA

REQUISITION
FOR
STEEL PIPE

FOR BID

03/09/2014

0
REV
.

All

Issued for Bid

HPI/ZR

NK

01/07/2014

All

Issued for Bid

HPI/ZR

NK

DATE

PAG
E

DESCRIPTION

PREPD

CHECKED

APPRD

CONTENTS
1 GENERAL................................................................................................................................. 3
2 MATERIALS.............................................................................................................................. 3
3 DOCUMENTATION.................................................................................................................... 3
4 TEST AND INSPECTION...............................................................................................................................4
5 FIELD SERVICE.............................................................................................................................................. 4
6 FIELD PRESERVATION................................................................................................................................ 4
7 SHIPPING AND PACKING INSTRUCTIONS............................................................................4
8 ORDER OF PRECEDENCE....................................................................................................... 4
9 SUB-VENDOR LIST.................................................................................................................. 5
ATTACHMENT-1 SCOPE OF SUPPLY/WORKS...............................................................................6
ATTACHMENT-2 RELATED DOCUMENT..........................................................................................7
ATTACHMENT-3 VENDOR DATA REQUIREMENT (VDR).................................................................8
ATTACHMENT-4 TEST AND INSPECTION.....................................................................................10
ATTACHMENT-5 DEVIATION AND CLARIFICATION LIST.............................................................12