Professional Documents
Culture Documents
Its total length including approach spans is 1149 metres and its arch span is 503 metres. The top
of the arch is 134 metres above sea level and the clearance for shipping under the deck is a
spacious 49 metres. The total steelwork weighs 52,800 tonnes, including 39,000 tonnes in the
arch. The 49 metre wide deck makes Sydney Harbour Bridge the widest Longspan Bridge in the
world.
It now carries eight vehicle lanes, two train lines, a footway and a
cycleway.
After inviting worldwide tenders in 1922, the New South Wales
Government received twenty proposals from six companies and on
24 March 1924; the contract (for Australian 4,217,721 pounds 11
shillings and 10 pence!) was let to the English firm Dorman Long
and Co of Middlesbrough.
As Chief Engineer of Sydney Harbour Bridge and Metropolitan Railway Construction from
1912, Dr Bradfield is regarded as the "father" of the Bridge as it was his vision, enthusiasm,
engineering expertise and detailed supervision of all aspects of its construction which brought
Sydney's long held dream into reality.
The contractors, under Director of Construction, Lawrence Ennis, set up two workshops at
Milsons Point on the North Shore. Here, the steel (79% imported from England, 21% from
Australian sources) was fabricated into girders etc.
The foundations for the four main bearings, which carry the full weight of the main span were
dug to a depth of 12.2 metres and filled with special reinforced high-grade concrete laid in
hexagonal formations.
The four impressive, decorative 89 metre high pylons are made of concrete, faced with granite,
quarried near Moruya, where about 250 Australian, Scottish and Italian stonemasons and their
families lived in a temporary settlement. Three ships were specifically built to carry the 18,000
cubic metres of cut, dressed and numbered granite blocks, 300km north to Sydney.
After the approach spans were erected, work began on the main arch. Two half-arches were built
out progressively from each shore, each held back by 128 cables anchored underground through
U-shaped tunnels. Steel members were fabricated in the workshops, placed onto barges, towed
into position on the harbour and lifted up by two 580 tonne electrically operated creeper cranes,
which erected the half-arches before them as they travelled forward.
There was great excitement on 20 August 1930 after the arch was successfully joined at 10pm
the night before. The steel decking was then hung from the arch and was all in place within nine
months, being built from the centre outwards to save time moving the cranes.
As the project neared completion, the last of approximately six million Australian made rivets
were driven through the deck on 21 January 1932. In February 1932 the Bridge was test loaded
using up to 96 steam locomotives placed in various configurations.
The official opening day on Saturday 19 March 1932 was a momentous occasion, drawing
remarkable crowds (estimated between 300,000 and one million people) to the city and around
the harbour foreshores. The NSW Premier, the Hon. John T. Lang, officially declared the Bridge
open. However, the Premier enlivened proceedings when Captain Francis De Groot of the paramilitary group, the New Guard, slashed the ribbon prematurely with his sword, prior to the
official cutting. This incident caused both amusement and dismay on the day and has since
become part of Australian folklore.
If someone else has other nice pictures please let me know so the collection can be further
increased.
503 metres
Width of deck
49 metres
49 metres
Height of Pylons
Bearing Pins
Each of the four pins measures 4.2 metres long and 368
millimetres in diameter
Thrust on bearings
Number of rivets
Approximately 6,000,000
Largest rivet
Longest Hanger
58.8 metres
Shortest Hanger
7.3 metres
Weight of arch
39,000 tonnes
420 millimetres
Paint required
272,000 litres of paint were required to give the Bridge its initial
three coats.
At one time actor and comedian Paul Hogan was a rigger on the bridge before finding
fame and fortune.
In June 1976, the one-billionth vehicle crossed the Sydney Harbour Bridge. The first
500 million crossings took over 33 years while the second 500 million took less than
11 years.
In 1932, the annual average daily traffic volume (in both directions) was about
10,900.
In 1943, with a wartime shortage of vehicles and petrol rationing, there was a drop in
traffic to about 8,600 vehicles a day.
Annual average daily traffic has since grown to:
1950
1960
1970
1980
1987
1989
1991
1992
1995
1996
1997
1998
1999
2000
32,000 vehs/day
76,000 vehs/day
129,000 vehs/day
159,000 vehs/day
180,366 vehs/day
182,024 vehs/day
181,878 vehs/day
138,400 vehs/day
149,391 vehs/day
152,732 vehs/day
155,577 vehs/day
158,392 vehs/day
159,618 vehs/day
161,734 vehs/day (figure high due to equipment problems)
2001
159,597 vehs/day
http://www.sydneyharbourbridge.info/