Professional Documents
Culture Documents
517526
www.elsevier.comrlocaterautcon
Department of Construction Engineering, National Taiwan Uniersity of Science and Technology, PO Box 90 130, Taipei, Taiwan
b
Ret-Ser Engineering Agency, 207 Sung Chiang Road, Taipei, Taiwan
Accepted 12 September 2000
Abstract
This paper addresses the technological enhancement of the shotcreting robot. The shotcreting robot has an arm with six
degrees of freedoms, which is remotely controlled by an operator. Due to current utilization drawbacks, an improvement
plan has been developed in two stages. First, the control system of the semi-automated robot was improved by reducing the
number of joysticks from six to two, incorporating a real-time computer simulation model enhanced to identify model
feasibility. Second, the robot was enhanced from semi-automated to fully automated. Thus, an automated profile measuring
instrument is used to measure the excavated surface and a simulation model calculates the nozzle path for shotcreting. The
automated shotcreting robot was completed by integrated the graphical model with the robot control system. q 2001 Elsevier
Science B.V. All rights reserved.
Keywords: Shotcreting robot; Computer simulation; Profile measuring instrument; Tunnel construction
1. Introduction
Shotcrete containing coarse aggregate has been
successfully used for many years in mining and
tunnel construction as a primary support and finishing lining. Investigations have showed that lining
rock tunnels with shotcrete combined with other
measures, such as rock bolts, reinforcement mesh, or
light rebar trusses, is more economical and also
minimizes construction hazard under adverse rock
conditions w1,5,6x. Thus, typical shotcrete designs
)
Corresponding author. Tel.: q886-2-2737-6596; fax: q886-22737-6606.
E-mail address: myc@hp.ct.ntust.edu.tw M.-Y. Cheng..
0926-5805r01r$ - see front matter q 2001 Elsevier Science B.V. All rights reserved.
PII: S 0 9 2 6 - 5 8 0 5 0 0 . 0 0 1 0 4 - 7
518
robot may require some adjustments and modifications. The plan and procedures for improving the
prototype robot are described as follows: 1. investigate drawbacks of the current model, 2. propose an
enhancement plan, 3. develop a real-time 3D computer model for graphical simulation and animation,
4. improve the prototype, 5. apply field tests, and
6. employ the animation model for in-house training.
3.1. Current model
The first generation of the shotcreting robot as
shown in Fig. 2. is a multi-joint arm robot with eight
degrees of freedoms. Due to the complexity of operation and control, the robot was modified to the
current model see Fig. 3.. Fig. 4a. shows the
mechanisms of the second-generation spraying arm.
The second generation of the robot arm has six
degrees of freedoms and is remotely controlled by
the operator using a control box with six joysticks
and three buttons. A pivot drive with pedestal forms
the connecting element between the spraying arm
and the carrier vehicle. The motions of the spraying
arm are illustrated in Fig. 4b.. Fig. 4c. shows the
control board of the current model. The pivot drive
controlled by Rod 6 can be rotated 3608 around the
y-axis while the solid arm system controlled by Rod
1 can be rotated 2708 around the z-axis tunnel axis..
In Fig. 4a., the solid arm system consists of three
arms, four joints, and one spraying head. Based on
the z-axis, Arm I is controlled by Rod 2 and can be
519
520
one unit. When Arm I moves 18 in a counter-clockwise direction, Arm II rotates in a clockwise direction by 18 and Arm III rotates simultaneously in a
counter clockwise direction by 18. In terms of the
horizontal direction, Rod A replaces the function of
Rod 1, which can rotate the solid arm 2708 around
the tunnel axis. To reduce the development cost and
risks, a real-time computer simulation model was
developed to identify the feasibility of the proposed
model. The graphically animated model was applied
for in-house training after the improved model was
completed.
In the second stage, the robot was improved from
semi-automated to fully-automated. Within this, an
automated profile measuring instrument is used to
measure the excavated surface. Based on this measurement, the simulation model calculates and identifies the path for the shotcreting nozzle. The coordinates of the path are then fed back to the control
system of the robot. The automated shotcreting robot
was completed by integrating the graphical model
with the robot control system.
3.3. Computer graphical simulation and animation
The main purpose of developing a computer simulation model is to measure the feasibility of the
proposed model before the plan commences. In addi-
Fig. 4. a. Mechanisms of the spraying arm. b. Motions of the spraying arm. c. Original control board. d. Modified control board.
521
Fig. 4 continued ..
model was developed on a SiliconGraphics workstation using ModelGen software to create the 3D
model and PERFORMER software for animation.
The development procedures are described as follows see Fig. 6..
Identify plan objecties: Mechanisms of the arm
motions and control system were first investigated
before improving the model. Second, to achieve the
522
studied. Third, a graphic simulation model was developed to verify the feasibility of the enhancement
plan and also identify any potential problems in
advance.
Establish the simulation model: The hierarchy of
the robot mechanisms was first established and broken down into different levels to create a robot
geometry database. The relationship between different levels is masterrslave based. The higher entity is
the master of the following entities slaves.. As the
master moves, the slave entities also move in relation
to keep the arm as one unit. After identifying the
mechanisms of the solid arm and the relative coordinate for each mechanism, mathematical functions for
each mechanical motion were formulated to assure
movement of the mechanisms as planned.
Deelop the simulation draft: The simulation draft
was developed according to the construction process
in the field. The site environment was established
and relative coordinates between the working spots
523
524
caused by the nozzleman can be reduced to a minimum. By conducting simulations, operators can manipulate the robot for different job-site conditions
and training cost is reduced w11x.
4. Automated shotcreting robot
After completing the first stage of improvement
of the shotcreting robot, the second stage was to
improve the robot from semi-automated to fully-automated. To achieve this objective, an automated
profile measuring instrument was applied to measure
the excavated surface see Fig. 8. w12,1416x. Automated measurement and control are essential to the
development of the automatic shotcreting robot. The
laser measurement instrument was developed by the
Ret-Ser Engineering Agency, the biggest construction company in Taiwan. For each survey point, the
distance is measured twice and the average is calculated. The measurement speed is 25 pointsrmin. The
instrument can be connected with an external computer to display the measured path and the designed
profile as well. The difference in area between the
measured and designed cross sections is integrated.
Thus, the volume of shotcrete can be estimated by
multiplying the area by the width that each spraying
pass covers.
525
Table 1
Field test results
Item
Safety
Hygiene
ControlrWorkability
Learning curve
Rebound Quality.
Shotcreting speed M 2 rmin.
No. of labor
Method
Manual
Prototype robot
Improved robot
Low
Low
Low
Long
25%
0.1424
6
Medium
Medium
Low
Long
14%
0.2712
4
Medium
Medium
Medium
Medium
14%
0.3225
4
High
High
High
Short
9%
0.58
2
526
6. Conclusions
The objectives of this study were achieved by
reducing the number of joysticks for the shotcreting
robot from six to two. According to results of the
field test, the control mechanisms were improved
and the learning curve for training was reduced. A
real-time animated model proved to be very useful
for development of the robot. Through simulation,
operators can test and manipulate the robot for different job-site conditions. The simulation model can
also be used for in-house training as the model is
completed. Moreover, with the development and application of the automated robot, the hazardous and
time-consuming scaling operation can not only be