Structural Works of 4.

2 C & C
Tunnel
: (Box Tunnel and U-section)
Employer
: FAST Consortium LLC.
ArRiyadh Development
Owner
: Authority (ADA)
Consultant
: RAMPED
05/2015 - 03/2016 (12
Term of
Months)
Contract
time extension will be issued
: by the Client
Location and Riyadh/ Kingdom of Saudi
Country
: Arabia
Project

Riyadh Metro Project


Line 4 Tunnel 4.2 is in
progress
Metro tunnel line 4 project which is
undertaken by FAST in KSA's capital city
Riyadh, is in progress. In the project, 25
percent of the scope is completed up to
date .
6 nos of tunnels production was completed In
the first 180 meter long area and activities
are in progress intensely in the 7 nos of
tunnels. Site handover for the remaining
areas is expected from the Client.
During construction, heavy cranes are used
for installation & dismantling of special forms
for roof slab & walls and production is
underway section by section with an average
of 200 workers per month .