GAMMON INDIA LIMITED

Job : Chimney Package for 2x600 MW JITPL, Derang, Angul

MAIN ACTIVITIES
Sl. No

Item Description

Unit

Scope of
work

Upto Prev
Achivement

Today's
Achiev.

Cum. Achiev.

270.00

270.00

0.00

270.00

Chimney Shell

Chimney Shell - M40 Grade Concrete

Cum

9737.10

9737.10

0.00

9737.10

Chimney Roof Slab - M40 Grade Concrete

Cum

33.00

33.00

0.00

33.00

Cutting, Bending & fixing of reinforcement steel for


chimney shell (Approx.)

MT

1430.00

1430.00

0.00

1430.00

Supply of MS Plan 10mm thick - Flue Can

MT

865.83

865.83

0.00

865.83

Rolling Flue Can Plates

MT

865.83

865.83

0.00

865.83

Fit up of Flue Can Plates

MT

865.83

865.83

0.00

865.83

Ready for Erection

MT

865.83

865.83

0.00

865.83

Flue Can Lifting

MT

865.83

419.67

0.00

419.67

10

Flue Can Erection

MT

865.83

419.67

0.00

419.67

11

Insulation

MT

865.83

458.17

3.00

461.17

12

Staircase Fabrication

MT

239.00

56.00

0.00

56.00

13

Elevator

No.

1.00

1.00

0.00

1.00

14

Painting external painting

Sqm

18488.00

18488.00

0.00

18488.00

15

Erection of Platform Beams

MT

276.00

276.00

0.00

276.00

Total Qty.
Received

Upto Prev
Recv. Qty.

Today's Recv. Qty

Consumption

Stock at Store
3.27

Remarks : Flue Can Fitup Works in Progress.

SUPPLY OF MATERIALS
S No.

Item Description

8 Dia TMT Bars (MT)

16.87

16.87

0.00

13.60

10 Dia TMT Bars (MT)

5.82

5.82

0.00

4.82

1.00

12 Dia TMT Bars (MT)

258.25

258.25

0.00

245.35

12.90

16 Dia TMT Bars (MT)

638.28

638.28

0.00

632.50

5.78

20 Dia TMT Bars (MT)

187.50

187.50

0.00

185.20

2.30

25 Dia TMT Bars (MT)

460.00

460.00

0.00

457.50

2.50

32 Dia TMT Bars (MT)

868.00

868.00

0.00

864.00

4.00

Cement (MT)

5612.00

5612.00

0.00

5612.00

0.00

10mm MS Flue Plates (MT)

910.00

910.00

0.00

910.00

0.00

10

Paint (Liter)

10000.00

10000.00

0.00

9244.00

756.00

No.

Remarks

PNM
S.No

Staff
Plant Description

S.No

Description

Batching Plant - 30 Cum

Project Manager

Cement Silo

DPM

Transit Mixers

Engineer

Excavator cum Loader JCB

Surveyor

Hydra Crane - 14T

Supervisor

Concrete Hoist

Foreman/slipform operator

DG Set - 125 KVA

Stores

Vibrators

Accounts

Dewatering Pumps

Safety

10

Auto Level

10

11

Total Station

Day Shift

12

Cube Testing Machine

Chimney Misc. Works

13

Concrete Pump

Flue Can Fabrication, Plat form


Fabrication, Staircase
Fabrication & Erection

14

Bar Bending Machine

15

Bar Cutting Machine

16

Plate Bending Machine

17

Lathe Machine

18

Mig. Welding Machine

19

Welding Rectifier

Mechanical/Electrical

20

Winch Power

21

Car / Jeep

Prepared by

(Planning Engineer)

Date:-18/11/2012

Balance

Remarks

0.00

Completed

0.00

Completed

0.00

Completed

0.00

Completed

0.00

Completed

0.00

Completed

0.00

Completed

0.00

Completed

446.16

Work in Process.

446.16

Work in Process.

404.66

Work in Process.

183.00

Work in Process.

0.00

Completed

0.00

Completed

0.00

Completed

Remarks

No.

Remarks

1
1
7
2

3
8
6
4
3

11
Night Shift

No.

12
22

Flue Can Fabrication, Plat form


1 Fabrication, Staircase
Fabrication & Erection

16